Fault Analysis On Distribution Feeders With High Penetration of PV Systems
Fault Analysis On Distribution Feeders With High Penetration of PV Systems
3, AUGUST 2013
Authorized licensed use limited to: UNIVERSIDADE FEDERAL DE ENGENHARIA DE ITAJUBA. Downloaded on April 27,2021 at 21:42:28 UTC from IEEE Xplore. Restrictions apply.
HOOSHYAR AND BARAN: FAULT ANALYSIS ON DISTRIBUTION FEEDERS WITH HIGH PENETRATION OF PV SYSTEMS 2891
TABLE I
PROTECTION SCHEME FOR A PV SYSTEM
Authorized licensed use limited to: UNIVERSIDADE FEDERAL DE ENGENHARIA DE ITAJUBA. Downloaded on April 27,2021 at 21:42:28 UTC from IEEE Xplore. Restrictions apply.
2892 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 28, NO. 3, AUGUST 2013
the PVs identified. The algorithm then updates the node voltages
and branch currents by repeating the calculations done at the
first step. This loop is repeated until the PV protection does not
disconnect any more PVs.
Finally, note that, if the PV system protection is not IEEE 929
compliant, then this particular protection scheme should be used
in the PV protection simulation part of the analysis.
B. Test Results
To evaluate the performance of the proposed method on a
green hub, an actual 22-kV distribution system serving mostly
residential loads in a suburb of Raleigh, NC, is considered as
the test case in this study. The feeder has three-phase primary
with several single-phase underground cables tapped off from
the main circuit to feed the customers within the same neigh-
borhood. For this study, this system is simulated using PSCAD
in order to get detailed time-domain simulations and to use them
for comparison with the proposed method. Since it was not prac-
tical to include all of the loads and PV systems individually in
the simulation, the loads and the PV systems on the single-phase
laterals served off the main line sections have been aggregated
Fig. 5. Proposed fault analysis algorithm for a green hub.
as one lumped load and PV system as shown in Fig. 6. Hence,
the simulated system is a three phase circuit with unbalanced
loads and PVs represented on a phase basis. We will refer to
hence their protection schemes will start counting to disconnect this sample feeder as the green hub.
the PVs in 2 s (120 cycles). PV6 on the other hand will ride The PV system is simulated by adopting a typical model,
through the fault as its terminal voltage is higher than 0.88 pu. which uses average models for the converters, and includes
However, after PV1–PV3 are disconnected at 0.1 s, the maximum power point tracking [11]. Fig. 7 shows the –
system voltage will decrease further due to increased fault cur- curve of the adopted PV system model obtained from the
rent from the substation, as shown on the figure; and this in turn simulation results. As shown in the figure, the PV system in-
will cause PV4 to be disconnected faster at 0.2 s and PV6 to be verter operates under two modes of operation: constant power
disconnected at 2.1 s as well. and constant current. Figs. 8 and 9 compare the results from
Finally, note that, as a result of PVs disconnecting at different the proposed method with the results obtained from PSCAD
times on the feeder, the fault current will be varying, as the simulations.
fault current profiles on Fig. 4 clearly shows. Hence, in order The fault currents given are the fault currents through the
to be able to determine such a fault current profile on a feeder, feeder circuit breaker under single-phase and three-phase faults.
we need to extend conventional fault analysis method by incor- As the figures show, the method calculates the current levels and
porating both the – characteristics and protection schemes the time instants at which the current level changes.
for PVs. Section III introduces the proposed scheme for this Fault currents are calculated for faults at four different nodes
purpose. (4, 8, 10, and 13) and with varying fault resistance. These re-
sults show that the proposed method estimates are very close to
III. FAULT ANALYSIS METHOD FOR GREEN HUB the ones from simulations. The maximum difference between
the current magnitudes calculated by the proposed method and
A. Algorithm for Fault Analysis obtained from the simulations is 6.16%.
Fig. 5 shows the proposed algorithm for the fault analysis
method for a green hub. As the figure shows, the fault is assumed IV. ESTIMATING OVERCURRENT RELAY TRIP TIME
to occur at , and then the algorithm first calculates the As illustrated in Section III, the fault current varies in the
node voltages ( ) and branch current during the first period green hub, and therefore it becomes more challenging to esti-
after the fault where all PVs respond to the fault and contribute mate the time taken for an overcurrent relay, which will see this
to the fault. Since PV current injection depends on its terminal fault, to trip. We developed a method for this purpose.
voltage, an iterative procedure is needed to obtain the solution, Since electromechanical relays and digital relays respond to
as the figure illustrates. The PV model indicated in the figure is the varying fault currents differently, we need to consider both
the controlled current model developed in the previous section. cases.
In the next step, response of the PV protection is emulated in
order to determine the PVs that will be disconnected by their A. Electromechanical Relays
protection system and how long it will take for the protection Fig. 10 depicts the contacts movement of an electromechan-
system to disconnect them. Once this time is identified, the ical for the case that the current changes from to at sec-
algorithm increments the simulation time by and disconnects onds, and and are the angular distances that have been
Authorized licensed use limited to: UNIVERSIDADE FEDERAL DE ENGENHARIA DE ITAJUBA. Downloaded on April 27,2021 at 21:42:28 UTC from IEEE Xplore. Restrictions apply.
HOOSHYAR AND BARAN: FAULT ANALYSIS ON DISTRIBUTION FEEDERS WITH HIGH PENETRATION OF PV SYSTEMS 2893
Fig. 6. Test feeder—a sample green hub (circles indicate the nodes where the faults have been simulated).
where can be obtained from the relay time–current curve. Following the same logic, the following equation gives the
Now, by equating (1) with (3), we can get an estimate of the relay trip time if the fault current changes times from to
trip time as at to :
(4) (7)
Authorized licensed use limited to: UNIVERSIDADE FEDERAL DE ENGENHARIA DE ITAJUBA. Downloaded on April 27,2021 at 21:42:28 UTC from IEEE Xplore. Restrictions apply.
2894 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 28, NO. 3, AUGUST 2013
Fig. 8. Breaker current for single phase faults on the sample distribution feeder (green hub).
Fig. 9. Breaker current for three phase faults on the sample distribution feeder (green hub).
Authorized licensed use limited to: UNIVERSIDADE FEDERAL DE ENGENHARIA DE ITAJUBA. Downloaded on April 27,2021 at 21:42:28 UTC from IEEE Xplore. Restrictions apply.
HOOSHYAR AND BARAN: FAULT ANALYSIS ON DISTRIBUTION FEEDERS WITH HIGH PENETRATION OF PV SYSTEMS 2895
Fig. 15. Breaker relay trip times for three-phase faults on the sample distribu-
tion feeder (green hub).
Finally, note that these two methods are needed for investi-
gating protection issues on a PV dominated system. The pro-
Fig. 12. Digital overcurrent relay operation when the fault current changes. posed methods will show: 1) if the protection devices on the
feeder operate properly, or there are coordination issues, and
2) if the feeder protection devices coordinate well with the PV
protection systems. For example, the coordination between the
breaker and the recloser in the sample feeder can be evaluated
by checking the breaker and the recloser trip times for a fault
occurring right after the recloser. If there are issues identified
through these methods, they can then be addressed by revising
protection schemes, usually on the feeder side. An example of
such a study is given in [4]. Note that, for the case considered,
the single-phase faults are cleared faster than the three-phase
faults, due mainly to more sensitive pickup settings of ground
relays.
V. CONCLUSION
This paper shows that the fault current profile on a PV-dom-
inated distribution feeder is considerably different than that of
a conventional feeder with only loads. Both the fault current
contribution from PV systems and the voltage-based protection
Fig. 13. Method to calculate the relay trip time of an overcurrent relay.
schemes they employ contribute to the variation of fault current.
The paper proposes new method that extends the conventional
short-circuit analysis methods and provides an estimate of the
fault current profiles. The simulation-based test results indicate
that the method provides quite accurate estimate.
The paper also proposes a method which takes this varying
fault current a protection relay will see and estimates the time it
will take for the relay to operate. Test results for this procedure
show that the method reproduces the relay operating time quite
accurately.
Given that PV penetration on distribution level will increase
in near future, the proposed methods are much needed tools for
a practicing engineer in assessing the impact of PV penetration
on system protection and developing mitigating strategies, such
as revising relay settings for relay coordination.
Fig. 14. Breaker relay trip times for single-phase faults on the sample distribu-
tion feeder (green hub).
REFERENCES
[1] J. Keller, B. Kroposki, R. Bravo, and S. Robles, “Fault current contribu-
breaker relay for single-phase and three-phase faults. The max- tion from single-phase PV inverters,” in Proc. 37th IEEE Photovoltaic
imum difference is 5.97%. Specialists Conf., Jun. 19–24, 2011, pp. 1822–1826.
Authorized licensed use limited to: UNIVERSIDADE FEDERAL DE ENGENHARIA DE ITAJUBA. Downloaded on April 27,2021 at 21:42:28 UTC from IEEE Xplore. Restrictions apply.
2896 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 28, NO. 3, AUGUST 2013
[2] T. S. Sidhu and D. Bejmert, “Short-circuit current contribution from [13] S. E. Zocholl, “Testing dynamic characteristics of overcurrent relays,”
large scale PV power plant in the context of distribution power system in Proc. 20th Annu. Western Protective Relay Conf. , Spokane, WA,
protection performance,” in Proc. IET Conf. Renewable Power Gener- Oct. 1993, pp. 350–355.
ation RPG, Sep. 6–8, 2011, pp. 1–6.
[3] J. Gao, W. Hu, Z. Shi, and B. Tang, “Research of effect on distribution
network with penetration of photovoltaic system,” in Proc. 45th Int.
Universities Power Eng. Conf., 2010, pp. 1–4.
[4] M. E. Baran, H. Hooshyar, Z. Shen, and A. Huang, “Accommodating
high PV penetration on distribution feeders,” IEEE Trans. Smart Grid, Hossein Hooshyar (S’12) received the Ph.D. degree
vol. 3, no. 2, pp. 1039–1046, Jun. 2012. from the North Carolina State University, Raleigh, in
[5] R. A. Walling, R. Saint, R. C. Dugan, J. Burke, and L. A. Kojovic, 2011.
“Summary of distributed resources impact on power delivery systems,” Since then, he has been with the Electric Power
IEEE Trans. Power Del., vol. 23, no. 3, pp. 1636–1644, Jul. 2008. Engineering Group, Luleå University of Technology,
[6] F. Soudi, D. Shirmohammadi, and C. S. Cheng, “A distribution short Skellefteå, Sweden, as a Postdoctoral Fellow. His
circuit analysis approach using hybrid compensation method,” IEEE research interest includes digital simulation of
Trans. Power Syst., vol. 10, no. 4, pp. 2053–2059, Nov. 1995. power systems and integration of renewable energy
[7] D. Y. Wang, Z. Zabar, and D. Czarkowski, “Load flow based distri- resources.
bution system short-circuit algorithm incorporating distributed syn-
chronous generators,” in Proc. IEEE Int. Symp. Circuits Syst., May
21–24, 2006, pp. 1–4.
[8] M. E. Baran and I. El-Markaby, “Fault analysis on distribution feeders
with distributed generators,” IEEE Trans. Power Syst., vol. 20, no. 4,
pp. 1757–1764, Nov. 2005. Mesut E. Baran (S’85–M’88–SM’05–F’11) re-
[9] Draft Guide to Conducting Distribution Impact Studies for Distributed ceived the Ph.D. degree from the University of
Resource Interconnection, IEEE.7/D4.0, . California, Berkeley, in 1988.
[10] IEEE Recommended Practice for Utility Interface of Photovoltaic (PV) He is currently a Professor with North Carolina
Systems, IEEE 929, 2000. State University, Raleigh. His current research in-
[11] Model Available on the Website of ECEE Department at the University terests include distribution and transmission system
of Colorado at Boulder [Online]. Available: http://ecee.colorado.edu/ analysis and control, integration of renewable
~ecen2060/matlab.html energy resources, and utility applications of power
[12] S. H. Horowitz and A. G. Phadke, Power System Relaying, 3rd ed. electronics-based devices.
New York: Wiley, 2008.
Authorized licensed use limited to: UNIVERSIDADE FEDERAL DE ENGENHARIA DE ITAJUBA. Downloaded on April 27,2021 at 21:42:28 UTC from IEEE Xplore. Restrictions apply.