Out of 15 questions, you answered 7 correctly with a final grade of 47%
Chapter 12
7 correct (47%)
Quizzes
Multiple Choice Quiz 8 incorrect (53%)
More Resources 0 unanswered (0%)
Chapter Outline
Glossary Your Results:
Study Outline
PowerPoint Presentation
The correct answer for each question is indicated by a .
C) available-to-promise items.
D) disaggregated items.
E) pegged items.
2 CORRECT If lot-for-lot ordering is used, then planned order releases will be equal to:
A) gross requirements.
D) net requirements.
3 CORRECT Which of the following is not a direct input into MRP?
B) bills of materials
D) inventory records
4 MRP is primarily used in this setting:
INCORRECT
A) job shop
B) continuous
C) batch
5 Which of these describes lot sizing? Determining:
INCORRECT
A) planned order releases
B) net requirements
C) when to order
novella.mhhe.com/sites/0078024102/student_view0/chapter12/multiple_choice_quiz.html 1/3
7/29/2021 Multiple Choice Quiz
D) how much to order
6 CORRECT In MRP, planned order receipts must always equal:
A) scheduled receipts.
C) net requirements
D) gross requirements.
7 CORRECT Which is true about scheduled receipts?
A) They are orders previously placed, and not yet completed or received.
B) master schedule.
C) bill of materials.
B) order releases
C) changes
D) exceptions
10 Low-level coding refers to:
INCORRECT
A) having low-level employees input product codes into computer data banks.
B) structuring a bill of materials so that multiple occurrences of an item coincide with the lowest level at which the item occurs.
B) scheduled receipts
C) projected on hand
D) gross requirements
12 Closed-loop MRP relates most closely to:
CORRECT
A) capacity planning.
B) ERP.
C) scheduled receipts.
novella.mhhe.com/sites/0078024102/student_view0/chapter12/multiple_choice_quiz.html 2/3
7/29/2021 Multiple Choice Quiz
A) minimize variable cost.
B) use scheduled receipts only when necessary.
B) gross requirements; 5
C) net requirements; 4
D) gross requirements; 4
15 Product Alpha consists of two units of component X and four units of component Y. Component X consists of four units of component Y and two units of component Z.
INCORRECT Component Y's lead time is two weeks, there are no units of component Y on hand, and there are no scheduled receipts for component Y. There are 400 units of
component X on hand. Neither X nor Y go into any other item or subcomponent. If 100 units of Alpha are to be produced beginning in week 4, then __________ units
of component Y will need to be begun in week __________.
A) 400; 3
B) 1,200; 1
C) 800; 3
D) 400; 2
My Instructor: HTML
My TA: HTML
Other: HTML
To learn more about the book this website supports, please visit its Information Center.
Copyright
2021
McGraw-Hill Global Education Holdings, LLC. All rights reserved.
Any use is subject to the
Terms of Use and Privacy Center | Report Piracy
novella.mhhe.com/sites/0078024102/student_view0/chapter12/multiple_choice_quiz.html 3/3