Project Merged
Project Merged
Project Merged
A PROJECT REPORT ON
SUBMITTED BY
VINOD KUMAR REDDY D 3VC16CV120
VISHWANATH 3VC17CV095
ARPITHA D B 3VC17CV013
S M BHAVANI 3VC17CV072
H S SAGAR 3VC18CV411
UNDER THE GUIDANCE OF
Mrs.Pushpalatha R Gadag
Assistant professor
Dept of civil Engineering
RYMEC, Ballari
CERTIFICATE
This is to certify that Project work entitled “ANALYSIS AND DESIGN OF HOSTEL
BUILDING BY USING E-TABS” has been successfully carried out by VINOD KUMAR
REDDY D with USN: 3VC16CV120, VISHWANATH with USN: 3VC17CV095 and
ARPITHA D B with USN: 3VC17CV013, S M BHAVANI with USN: 3VC17CV072,
H S SAGAR with USN: 3VC18CV411, in the partial fulfillment for the award of degree of
Bachelor of Engineering in Civil Engineering from visvesvaraya Technologies University
Belegavi, during the academic year 2017-18. It is certified that all corrections/ suggestions
indicated for internal assessment have been incorporated in the report, the project report has
been approved as it satisfies the requirements in respect of project work prescribed for the
Bachelor of Engineering Degree.
Any achievement big or small should have catalyst and a constant encouragement and
advice of valuable and noble minds for our efforts to bring out this project work.
The satisfaction that accompanies the successful culmination of any task would be
incomplete without mentioning those who made it possible because success is the epitome of
hard work, determination, concentration and dedication.
In our society ‘GURU’ is the most important person who educates us about the
various facts of life. Hence we would like to express our deep sense of gratitude to our
beloved and respected principal Dr. T Hanumantha Reddy, who is the source of
information for all the students and who has encouraged us in whatever way that e can do
best.
Our sincere thanks goes to our beloved Head of the Department of Civil
Engineering, Dr. H.M.Mallikarjuna, who has extended his whole hearted support for the
successful completion of the project.
We are greatly indebted to our Project Guide Asst. Prof. Pushpalatha R Gadag for
his help in understanding the concept of project and their effort for all round growth and
development of an individual.
ABSTRACT
The present work deals with the analysis, design and of hostel
building by using e-tabs by using most economical beam to
column method. The dead load &live loads are applied and the
design for beams, columns, footing is obtained from Etabs with
its new features surpassed its predecessors with its data sharing.
Our main aim is to complete a hostel building and to ensure that
the structure is safe and economical against gravity loading
conditions and to fulfill the function for which the structures
have been built for. For the design of the structure, the dead
load and live load are considered. The analysis and design of the
structure done by using software package ETABS.
The results of analysis are used to verify the fitness of structure
for use. Computer software’s are also being used for the
calculation of forces, bending moment, stress, strain &
deformation or deflection for a complex structural system.
SUBJECT : ANALYSIS, DESIGN AND ESTIMATION OF HOSTEL BUILDING BY ETABS
2. Structural Analysis-1
4. Structural Analysis-2
5. Geotechnical Engineering-1
8. Geotechnical Engineering-2
C0413.2 To carry out manual analysis and design calculations based on the required criteria
C0413.3 To carry out design and prepare drawings using relevant computer software( excel-
spread sheet, auto CAD, ETAB’s
C0413.4 To produce presentable report containing executive summary, introduction, task
distribution, concepts, design calculation, conclusions etc.,
Subject Course outcomes Bloom’s level
Code:
10CV8 At the end of the course, students will be able to:
C0414.1 Identify and explain planning, spacing of columns as per Knowledge,
codal provisions Understand
(L1,L2)
C0414.2 Describe and explain analysis and manual design calculations Knowledge,
based on the required criteria using relevant codes Understand
(L1,L2)
C0414.3 Investigate and compare the analysis, design and prepare Knowledge,
drawings using relevant computer software Understand
(L4,L6)
At the end of the course, students will have: At the end of the course students will be able to
a) An ability to apply the knowledge of mathematics, science, engineering Identify the importance and understand the
fundamentals, (PO1).
objectives, history to construct a structural
b) An ability to apply reasoning informed by contextual knowledge to asses health, building.
safety, legal and cultural issues and the consequent responsibilities relevant to the
professional engineering practice .(PO6)
a) An ability to apply knowledge of mathematics, basic science and engineering Understand the importance of functions,
fundamentals. (PO1)
advantages and disadvantages of ETABS.
b) An ability to apply reasoning informed by contextual knowledge to asses health, safety,
legal and cultural issues and the consequent responsibilities relevant to the professional
engineering practice .(PO6)
a) An ability to apply reasoning informed by contextual knowledge to asses health, Creating the technical document and
safety, legal and cultural issues and the consequent responsibilities relevant to the
communicate to the society.
professional engineering practice .(PO6)
CO1: Identify the importance and understand the objectives of a structural building.
The CO1 stated above is mapped with the Engineering Knowledge (PO1) which reflects the application of engineering fundamentals. The
CO1 reflects use of Engineering Fundamentals and include complex Engineering conditions. Hence correlation between CO1-PO1 is low.
(PO1-(1))
The CO1 stated above is mapped with the engineer and society(PO6) which apply reasoning informed by the contextual knowledge to asses
health, safety and does not correlate with social and cultural issues. Hence correlation between CO1-PO6 is moderate. (PO6-(1))
The CO2 stated above is mapped with the Engineering Knowledge (PO1) which reflects the application of engineering fundamentals. The
CO2 reflects use of Engineering Fundamentals and include complex Engineering conditions. Hence correlation between CO2-PO1 is
moderate. (PO1-(2))
Does CO2 reflect intended measurement from PO6?
The CO2 stated above is mapped with the engineer and society(PO6) which apply reasoning informed by the contextual knowledge to asses
health, safety and does not correlate with social and cultural issues. Hence correlation between CO2-PO6 is moderate. (PO6-(2))
The CO2 stated above is mapped with the communication (PO10) which Communicate effectively on complex engineering activities with the
engineering community and with society at large and receive clear instructions. Hence correlation between CO2-PO10 is moderate. (PO10-
(2))
CO3: Identify and analyze the construction and functions of structural building.
The CO3 stated above is mapped with the Engineering Knowledge (PO1) which reflects the application engineering fundamentals. However
the CO3 does not reflect much use of complex Engineering conditions. Hence correlation between CO3-PO1 is moderate. (PO1-(3))
The CO3 stated above is mapped with the engineer and society (PO6)which apply reasoning informed by the contextual knowledge to asses
health, safety and does correlate with social and cultural issues. Hence correlation between CO3-PO6 is high. (PO6-(3))
CO4: Create technical document and communicate to the society.
The CO4 stated above is mapped with the engineer and society (PO6)which apply reasoning informed by the contextual knowledge to asses
health, safety and does not correlate with social and cultural issues. Hence correlation between CO4-PO6 is moderate. (PO6-(4))
The CO4 stated above is mapped with the communication (PO10) which Communicate effectively on complex engineering activities with the
engineering community)= and with society at large and receive clear instructions. Hence correlation between CO4-PO10 is moderate. (PO10-
(4))
PROGRAM OUTCOMES (POs)
1. Engineering knowledge: Apply the knowledge of science, mathematics, engineering fundamentals, and engineering specialization to solution
of complex engineering problems.
2. Problem analysis: Identify , formulate , review, research, literature and analyze complex engineering problem reaching substant iated
conclusion using first principle of mathematics , natural sciences and engineering sciences .
3. Design / development of solutions: Design solution for complex engineering problems and design system components or processes that meet
the specified needs with appropriate considerations for public health, safety and the cultural, societal and environmental consideration.
4. Conduct investigations of complex problems: Use research-based knowledge and research methods including design of experiments, analysis
and interpretation of data and synthesis of the information to provide valid conclusions.
5. Modern tool usage: create ,select and apply appropriate techniques, resources and modern engineering and IT tools including predict; Apply
reasoning informed by the contextual knowledge to assess societal, health , safety, legal and cultural issues and the consequent responsibilities
relevant to the professional engineering practice ones and modeling to complex engineering activities with an understanding of the limitations.
6. The engineer and society: Apply the reasoning informed by contextual knowledge to assess societal, health, safety, legal and cultural issues
and the consequent responsibilities relevant to the professional engineering practice.
7. Environment and sustainability: Understand the impacts of professional engineering solutions in societal and environmental context, and
demonstrate the knowledge of, and need for sustainable development.
8. Ethics: Apply ethical principle and commit to professional ethics and responsibilities and norms of engineering practice.
9. Individual and team work: Function effectively as an individual and as a member or leader in diverse teams and in multidisciplinary settings.
10. Communication: communicate effectively on complex engineering activities with engineering community and with society at large such as,
being able to comprehend and write effective reports and design documentation, make effective presentation and give and receive clear
instructions.
11. Project management and finance: Demonstrate the knowledge and understanding of engineering and management principles and in multi
disciplinary environments.
12. Life -long learning: recognize the need for , and have presentation and ability to engage in independent and life-long learning in the
broadcast context of technological change.
CO-PO Mapping
PO
PSO1
PSO2
PSO3
PO10
PO11
PO12
PO1
PO2
PO3
PO4
PO5
PO6
PO7
PO8
PO9
CO
CO414.1 3
1 2 1
CO414.2
1 2 1 3
CO414.3 3
1 2
CO414.4 3
2 1
Average
1 2 1 3 1
CONTENTS
1. INTRODUCTION 01-27
3. SLABS 47-63
4. BEAMS 64-75
5. COLUMNS 76-82
6. FOOTINGS 83-99
7. STAIRCASE 100-103
8. ESTIMATION 114-148
9. CONCLUSION 149-149
The following symbols has been used in our project and its meaning is clearly mentioned respective
to it:
A - Area
Dt - Thickness of a flange
DL - Dead Load
EL - Earthquake load
e - Eccentricity
fd - Design strength
K - Stiffness of member
Ld - Development length
l1 - Span in the direction in which moments are determined, centre to centre of supports
M - Bending moment
m - Modular ratio
n - Number of samples
r - Radius
T - Torsional moment
T - Wall Thickness
V - Shear force
W - Total load
WL - Wind Load
Z - Modulus of section
z - Lever arm
- Angel or Ratio
- Diameter of bar
CHAPTER 1
INTRODUCTION
1.1 GENERAL:
The best way to ensure this safety is to design the structure according to the
relevant codes of practice and construct the structure according to accepted practice.
Civil engineers will be called upon to carry out design of structures to be constructed as
well as analyze (or review) structure already constructed, they should be familiar with
the current codes and methods of analysis and design.
The structural design is a science and an art, with economy and elegance. A
durable structure is one, which can safely carry the forces and can serve the desired
function satisfactorily during its service life span without collapse under the most
probable loads.
The objective of structural design is to plan a structure, which meets the basic
requirements of structural design are as follows:
Serviceability
Safety
Strength
Durability
Economy
Aesthetic beauty
Feasibility, practicability and acceptability
Methods of construction.
Computer programming.
An engineer is required to know the different types of materials used for structures
and their structural properties. A structural engineer should be in accordance with the
rules, regulations and provisions of design codes, which reflect the current viewpoint
acceptable to the engineering community at large and which are based on available
knowledge. The codes are either of national character or are those of official bodies like
Railways, Road Congress, Public Works Department, Municipal Corporation, or of
professional organizations. (The designs in this project work are based on IS 456-2000).
This stage also involves information necessary from the client. The information required
is as follows:
Functions of a structure
Resources available
Importance of the structure and aesthetic requirements
Expected life
Probability of extension in future
Relative weight-age between time, economy, resources, importance and so on.
STAGE II: This stage involves determination of external loads action on the structure
and design loads.
STAGE III: It involves analysis of the structure for the determination of internal
member forces (like bending moment and shear forces) in the members and behavior of
structures under the action of these forces.
STAGE IV: This stage involves the determination of member dimension, quantities
and detailing of reinforcement to resist the design forces. This stage forms the core and
substance of design.
There are three design philosophies which have been used for the design of
reinforced concrete structure i.e., working stress method, ultimate load method and
limit state method.
At present the IS 456 recommends the use of limit state method of design.
However it has also retained the working stress method of design.
IS 456 – 2000 uses a factor of safety equal to 3 on the 28 days cube strength to
obtain the permissible compressive stress in bending in concrete and equal to 1.78 on the
yield strength of steel in tension to obtain the permissible tensile in reinforcement. The
idealized stress and strain diagram is shown below:
This method uses load factor to increase the working load to obtain ultimate loads and
includes the non-linear behavior of concrete. Structure is designed to resist the desired
ultimate loads. Whitney’s ultimate theory is based on the assumption that the ultimate
strain in concrete is 0.3% and the compressive stress at the extreme fiber of the section
corresponds to this strain. The idealized stress and strain diagrams are shown below:
Limit state design has originated from ultimate or plastic design. The object of
design based on the limit state concept is to achieve an acceptable probability that a
structure will not become unserviceable in its life time for the use for which it is intended,
that is, it will not reach a limit state. A structure with appropriate degrees of reliability
should be able to withstand safely all loads that are liable to act on it throughout its life
and it should also satisfy the serviceability requirement, such as, limitations on deflection
and cracking. Further, it should be to maintain the required structural integrity during and
after accidents such as fires, explosions and local failure. In other words, all relevant limit
states must be considered in design to ensure an adequate degree of safety and
serviceability. The most important of these limit states which must be examined in design
are as follows.
This state corresponds to the maximum load carrying. Violation of collapse limit
state implies failure in the sense that a clearly limit state of structural usefulness has been
exceeded. However, it does not mean a complete collapse. This limit may correspond to
Flexure
Compression
Shear
Torsion
Deflection
Cracking
Vibration
SECTION 1 - GENERAL:
This section of the revision deals with only the scope, references, terminologies
and symbols in the code.
Most of the changes that have been made are in section 2 of the code. The revised
code has incorporated many changes to give importance to durability of concrete
structures, which of late has been neglected at the expense of much importance on
strength. The following are the important changes:
Recognition of the all the three grades of OPC cements along with other types of
cements [Clause 5.1 of IS 456(2000)].
Enumeration of allowable mineral admixtures (Clause 5.2) and the approval of the
practice of chemical admixtures (Clause 5.5).
The method of testing water for concreting has been described and permissible
limits of chlorides and sulphates given (Clause 5.4 and Table 1).
Characteristic strength has been defined as the minimum yield or 0.2% proof
stress (Clause 5.6.3).
The value of modulus of elasticity of concrete is specified to be taken as follows
Ec = 5000 √𝑓𝑐𝑘 (in N/mm2) (Clause 6.2.3).
The minimum strength of concrete for structural purpose is specified as M20, with
minimum cement content include in admixtures of 300 kg/m3 and maximum water
cement ratio of 0.55 (Clause 6.12 and Table 5). Grade up to M80 has been
included in the code (Table 2). The maximum cement content not including
mineral admixtures has been specified as of 450 kg/m3(Clause 8.2.4.2).
The text on the main clauses in section 3 remains more or less the same as the
earlier version. However, as already pointed out, the one-digit forward shift of clause
numbers as well as the changes in table and figure numbers is the main difference
between the two versions in this section. The main changes are following:
Basis for design (clause 18). The status of working stress method without using
load factor as an alternative method has been discontinued. Limit state method
should normally make designs, and working stress method is to be used only when
the former method is not applicable. For example, carrying out serviceability limit
state of deflection, cracking, etc.
Factor for stability against overturning against dead load should be 1.2 or 0.9
depending on its action and that for imposed load 1.4. The lateral sway due to
transient loads should be H/500 (Clause 20).
Fire resistance requirements are important additions to the code in this section.
Minimum dimensional requirements for slabs, beams, columns and walls as well
as minimum cover requirements for different fire ratings have been specified
(Clause 21 and Table 16A).
Effective length of cantilevers has been defined (Clause 22.2.6).
Bending moment co-efficient at midpoint of interior spans has been increased
from 1/24 to 1/16 to bring its value to ¾ the value at the support (Table 12).
The curves for the modification factor for tension reinforcement for checking
deflection requirements of beams and slabs have been changed to represent the
actual steel stress at service loads instead of the old curves based on types of steel
and allowable stresses.
The method for adjusting differences in support moments obtained in restrained
slabs by Table of co-efficient for Two-way slabs has been described (Clause
24.4.1).
The concept of determining effective length of columns by ‘stability index’
defined in Annexure E has been introduced (Clause 25.2)
When considering biaxial bending, it has been specified that it is sufficient to
ensure that eccentricity exceed the minimum about only one axis at a time (Clause
25.4).
The main changes in section 4 are the addition topics, the one digit forward shift
of the clause numbers of the old version of the code and the changes in the numbers of the
figures continue in this section also.
A new clause on design of reinforced concrete corbels has been added (Clause
28).
Mention has been made of precast joists and filler block construction (clause
30.8).
The clauses regarding design of plain concrete walls have modified to include
design of walls in horizontal shear also (Clause 32).
The concept of minimum reinforcement and nominal reinforcement for concrete
sections of thickness greater than 1 m has been added (Clause 34.5).
No major changes have been made in the contents of the various clauses of this
section. However, the one digit forward shift in clause numbers as well as changes in
table and figure numbers have been carried out to this section also. The following are the
main changes introduced in IS 456 (2000) section 5.
For limit state of cracking guidance regarding width of cracks allowed in different
environments have been specified (Clause 35.3.2).
The design shear strength for tension reinforcement values equal or less than
0.15% has been the increased shear strength close to the supports and rules
regarding detailing of steel close to the support (Clause 40.5).
The general approach to design of reinforced concrete members in torsion has
been explained in detail (Clause 41.1).
A new clause on deflection of flexural members has been added (Clause 42).
Formulae for calculation of deflections have been presented in Annexure C.
A new clause on cracking of flexural members has been added. (Flexural
members is defined as one subjected axial load < 0.2 fck Ac) (Clause 43). The
formulae for crack width calculations are given in Annexure F.
Limit state design should ensure that the structure would be safe as regards the
various limit state conditions, in its expected periods of existence. Hence the limit state
method of design is also known in American terminology as strength and serviceability
method of design.
The two major limit state conditions to be satisfied namely, the ultimate limit state
and the serviceability state, are again classified into major limit state, which is given in
various clauses in IS 456(2000).
The usual practice of design of concrete structure by limit state principle consists
in taking of each of the above conditions and providing for them separately so that the
structure is safe under all the limit states of strength and stability.
The design should provide for all the above limit state conditions; each of these
conditions is carried out as described now.
The ultimate strength of structure or member should allow an expected load. For
this purpose, the structure should be designed by the accepted ultimate load theory to
carry the specified overload. This may be in - flexure, compression, shear, torsion or
tension.
The structure should be fit for its environment. The cover for steel as well as
cement content and water cement ratio of the concrete that is provided in structure should
be satisfying environmental conditions.
The deflection of the structure under service load condition should be within
allowable limits. This can be done by two methods.
(i) Empirical method: Since the most important empirical factor that controls
deflections is span /depth ratio, limiting the span-depth ratio as specified by
codes can control deflection.
(ii) Theoretical method: Deflection can also be calculated by theoretical methods
and controlled by suitable dimensioning of the structure.
The structure should not develop cracks of more than allowable width under
service load condition. This can be taken care of by employing two methods:
(i) Empirical method: By strictly following the empirical bar detailing rules as
specified in the codes.
This condition is met by observing the empirical and rules are given in codes for
designing and detailing the vertical, peripheral and internal ties in the structure.
Structures have to carry Dead and Live loads. The maximum working load that
the structure has to withstand and for which it is to be designed is called characteristic
load. Thus there are characteristic dead loads and characteristic live loads. Thus the
strength that one can be safely assume for the materials (Steel and Concrete) are called
their characteristic strength.
For safe of simplicity, it may be assumed that the variation of these loads and
strength follows normal distribution law so that the laws of statistics can be applied to
them. As the design load should be more than the average load obtained from statistics we
have.
Even though the design loads has to be calculated statistically as indicated above,
research for determining actual loading on structure has not yet yielded adequate data to
enable one to calculate theoretical values of variations for arriving at the actual loading on
a structure. Loads that have been successfully used so far in elastic design procedures are
at present accepted as the characteristic loads. The specified values to be used are laid
down in IS 875.
Having obtained the characteristic loads and characteristic strength, the design
loads and design strength are obtained by the concept of partial safety factor. Partial
safety factor are applied both to loads on the structure and to strength of materials. These
factors are now explained:
(γf):
The load to be used for ultimate strengths design is also termed as factored loads.
In IS Codes the symbol DL is used for Dead load, LL for Live load, WL for wind load
and EL for Earthquake loads. It may be noted that the use of partially safety factor for
load simple means that for calculation of the ultimate load for design, the characteristic
load has to be multiplied by the partial safety factor denoted by the symbol. This may be
regarded as the overload factor for which the structure has to be designed. Thus the load
obtained by multiplying the characteristic load by partial safety factor is called factored
load, and is given by
It is extremely important to remember that in limit state design, the design load is
different from that used in elastic design. It is factored loads, and not characteristic loads,
which are used for calculations of reactions, bending moments, and shear forces. The
partial safety factors are to be used for elastic (working stress) design.
It may be noted that by adopting a partial safety of 1.5, both for dead and live
loads, the value of moment, and shear force etc. to be used is limit state design by IS code
is 1.5 times the moment, shear, etc. that would have been used for elastic(working stress)
design.
Theoretically, the partial safety factors should be different fir the two types of
loads. The British Code BS 8110 uses a factor of 1.4 for DL and 1.6 for LL for strength
considerations. It is only for convenience of using the same structural analysis for both
elastic design and limit state design that IS recommends the same partial safety factor for
dead and live loads. Thus in IS 456 the factored load, shear, moment etc. in limit state
design will be 1.5 times the value used for elastic design.
Sl
Load combination Ultimate limit state Serviceability limit state
no
1 Dead and Imposed 1.5 DL + 1.5 LL DL + LL
Dead and Wind
(i) Dead load
contributes to 0.9 DL + 1.5 WL DL + WL
2 stability
1.5 DL + 1.5 WL DL + WL
(ii) Dead load assists
overturning
1.2 DL +1.2 LL + 1.2
3 Dead, Imposed and Wind DL +0.8 LL +0.8 WL
WL
The grade strength of concrete is the characteristic strength of concrete and the
guaranteed yield strength of steel is the characteristic strength of steel. Calculation to
arrive at the characteristic material strength of materials by using statistical theory takes
into account only the variation of strength between the test specimens. It should be
clearly noted that the above procedure does not allow for the possible variation between
the strength of the test specimen and the material in the structure will be taken separately
by a factor 0.67. The relation gives the concept of partial safety factor for material
strength due to variations in strength between samples.
Characteristic Strength
Design Strength =
Partial Safety Factor(𝛾𝑚 )
This simply means that the strength to be used for design should be reduced value
of the characteristic strength by the factor denoted by partial safety factor for the material.
The recommended values for these partial safety factors are given in the table:
It should be clearly understood that the partial safety factors used in limit state
design are different from the factors of safety used in elastic design. The values
recommended for factors of safety in elastic design are usually 3 over the cube strength of
concrete for bending compression and 1.8 over the yield strength for steel stresses. Thus
in designing by working stress method, one works at stress levels well below the failure
strength of concrete and steel. It should also be remembered that the tables and formulae
derived for limit state design and those used in Design Aids SP 16 are derived with values
of γm already incorporated in them. Hence, unlike the partial safety factor for load, these
partial safety factors for material strengths need not be considered in routine design in
these formulae, chart and tables.
0.0035. Codes differ with respect to the strain εco at which the strength becomes
constant. In IS it is taken as a constant value of 0.002. The IS curve simplifies the
distance at which the parabola ends and the rectangle begins. It value can be deduced as
follows: if ‘x’ is taken as the depth of the neutral axis corresponding to the strain 0.0035,
the distance from the origin for the strain is given by:
0.002
X1 = X (distance of neutral axis) = 0.57x
0.0035
Thus the parabola extends to a distance (0.57 x) and the rectangle for the distance
0.43x.
The short term, static modulus for concrete E c, is assumed by IS code 456(2000)
clause 6.2.3.1 as
Ec = 5000√𝑓𝑐𝑘 (N/mm2)
In most calculations this value has to be modified for creep and other long-term
effects.
In order to distinguish between the concrete as tested in a cube and the concrete
that exists in the structure (size effect), it is assumed that the concrete in the structure
develops strength of only 0.67 times the strength of the cube. Hence the theoretical stress-
strain curve of the concrete in the design of the structures is correspondingly reduced by
the factor 0.67, as indicated in the fig. in addition to the above and explained earlier, a
partial safety factor of 1.5 is applied on the concrete in the structure so that the design
stress-strain curve for concrete in a structure as shown in fig. (Fig. 21, IS 456, clause
38.1)
1.12.2 STEEL:
Steel are designated by its yield stress fy. Thus Fe 415 means steel with yield
stress of 415 N/mm2. Usually its ultimate or failure stress will be more than 1.25 fy.
The stress-strain curve for steel according to IS 456, clause 38.1 is assumed to
depend on the type of steel. Mild steel bar (fy= 250 N/mm2) is assumed to have a stress-
strain curve as shown in fig. and cold worked deformed bar (Fe 415) a stress-strain curve
as shown in fig. the stress-strain curves for steel, both in tension and in compression in
the structure, are assumed to be the same as obtained in the tension test. As the yield
strength of IS grade steel has a minimum guarantee yield strength, the partial safety factor
to be used for steel strength need not be as large as that for concrete. The partial safety
factor recommended of steel is 1.15, and this is to apply to the stress-strain curve as
shown in fig. it should be noted that for the cold worked deformed bars, the factor 1.15 is
applied to points on the stress-strain curve from 0.8fy to fy only. The value of Es is
assumed as 200 KN/mm2 for all types of steels.
Concepts of characteristic strengths and characteristic loads are used for design
for strength. Separate partial safety factors for strength and loads are also introduced. The
design strengths of steel and concrete are taken as the characteristics strength divided by
their respective partial safety factors for strengths. Similarly, the factored load to be
resisted by the structure is taken as the product of the characteristic load and the partial
safety factor for loads. The stress-strain curve for concrete and steel are assumed to be of
fixed shape, for convenience in mathematical computation.
1.14 LOADS:
Forces or other actions that result from the weight of building materials, occupants
and their possession, environment effects, differential movement and restrained
dimensional changes.
The dead load in an building comprise the weight of all walls, partitions, floors,
and roofs and includes the weight of all other super imposed loads, which are
permanently attached to the structure. For such loads, which do not change their position
and so not vary in magnitude, and where self-weight of the structure is unknown,
preliminary section may be assumed by the design engineer using experience, thumb
rules and the formulae available.
Department Of Civil Engineering, RYMEC Ballari 2020-21 Page 21
ANALYSIS, DESIGN AND ESTIMATION OF HOSTEL BUILDING BY ETABS
On completion of design, total dead load is computed and compared with dead
load assumed for design and revised, if necessary.
of 1.5kN/m2 is considered.
Live load comprises of those loads whose position or magnitude or both may
change. Live load is expressed as a uniformly distributed static load. In our country,
floors of various types of building have been categorized into different classes and live
loads corresponding to them have been specified in the code IS: 875-1987 part II.
Floor loads:
All rooms and kitchen = 2kN/m2
Toilets and bath rooms = 2kN/m2
Corridor, passage, staircase, balconies = 3kN/m2
Roof load = 1.5kN/m2
1.16 OBJECTIVES
• Analysis of structure.
The execution of project had begun in the month of May 2021 and is scheduled to end on
Agust 2022.The drafting of floor plans are dealt by the architect Vinay H S from the
Office of Swathi Infrastructure, Patel Nagar, Hosapete -583 201 Every floor plan
(Ref Dr-2) is identical or typical in nature except for the Ground floor. The building is
provided with open dog legged staircase to have enough access to all the floors. This
project is so planned to occupy around 100 students with all daily facilities.
The soil sample from the project site is tested and it possesses to have a safe bearing
capacity of 185 kN/m2 for which the foundation design is to be done. The structural
(Ref Dr-4, 5 & 6).Also the columns are provided in view of not having any practical
obstruction.
The design loads and the design forces in members are determined i.e., the loads coming
from slab and walls are calculated
For this system (RCC Structural framework consisting beams and columns) analysis is to
be performed for gravity loads/vertical load and lateral loads (Earthquake force), the
results obtained from the analysis is tabulated and the maximum values at critical sections
are recorded
The recorded values are designed for limit state and the member sizes and reinforcement
are calculated.
Finally the structural drawings (Ref Dr- 6, 7, 8, 9, 10, 11) are prepared pertaining to the
finalized design
D = 450mm
D = 450mm
( ly-lx )
lx/2 lx/2
The Loads on beams supporting solid slabs spanning in two directions at right angles and
supporting uniform distributed loads may be assumed to be in accordance with the above
shown fig. The shaded trapezoidal load to be carried by beam AB and the shaded
triangular load to be carried by beam BC.
lx/2
Q = ( qlx2 )/4
= [( qlx2 )/4] / lx kN
qe = qlx/4 kN/m.
lx/2
Q = [qlylx/2 – qlx2/4] kN
= ( 3 - 0.45) =2.55m
= 11.2 kN/m.
CHAPTER 2
The present day framed structures are of great importance since they isolate the
structural and walls seen just as partitions to avoid natural elements and for privacy. The
load is taken fully by an interconnected frame work of beams and columns.
Such framed structures have a very high degree of indeterminacy, and without
accurate analysis, the prediction of behavior of such a structure becomes impossible.
In general for any structure, analysis and design are necessary. Experience without
modern methods of design leads to the construction of structure, which are over safe or
under safe with degree of safety unknown. The design calculations guarantee adequate
safety consistent with economy against the structure being rendered unfit for service
owing to cracking, deflection and failure. Hence, modern method as analysis and design
leads to level of which various forces moments etc. in the members of a known, with
various forces known approximate cross section of different members can be chosen.
The slope deflection method was first proposed by Prof. G.A. Maney in 1915 as a
general method for analysis of indeterminate beams and frames. In this method, if the
slopes at the ends and the relative displacement of the ends are known, the moment at the
ends can be found in terms of slopes, deflection, stiffness and length of members. This
involves the formation of a number of simultaneous equations depending upon the degree
of redundancy of frames / beam. The solution of these equations is tedious when done by
hand especially when the number of equations is more and can be termed as almost
impossible when it is very large. Even if a computer is used for the solution of equations
the memory capacity of the computer is a limiting factor in solving the equations. This
method was widely used till Prof. Hardy Cross introduced moment distribution method in
1930. This method being simple to understand and having scientific and systematic
approach over shadowed the slope deflection method. This leads to the performance of
moment distribution method and discouraging the use of slope deflection method. The
method is an improvement over the slope deflection method by fact that the answer are
obtained to the desired accuracy without explicitly writing down the equations. This
method though easy to understand and execute is prone to errors. It needs the formation
of moment distribution tables and systematic calculation. Any errors committed in the
computational scheme in either carried over moments or distributed moments, if
undetected will be carried over. This is a major drawback as compared to Kani’s method
where such errors are automatically rectified.
In the moment distribution method the analysis of sway frame is very laborious
and time consuming as it requires the analysis of the frame twice-once for no sway and
once for sway requiring two moment distribution table and computations are lengthy. The
lengthy process of this method is very much evident in the solution of multistory, multi-
bay frame both in terms of time and amount of paper. Since errors cannot be easily
detected and removed when the computational scheme is very large this method is usually
not preferred as there are better methods for analysis of such frames. This method is most
suitable for analysis of continuous beams only though it is applicable to all types of
frames and beams.
The column analogy method which was also proposed by Prof. Hardy Cross is
most useful for the analysis of beams with fixed supports or rigid frames up to third
degree of redundancy. The special feature of this method is that the members many be of
uniform moment of inertia throughout their length or may be varying. This method is
Department Of Civil Engineering, RYMEC Ballari 2020-21 Page 29
ANALYSIS, DESIGN AND ESTIMATION OF HOSTEL BUILDING BY ETABS
The matrix methods and finite element methods are general methods of analysis
and can be used for analysis of any structure. These methods involve solving various
matrices. This can be done either by hand or by the use of the computer. The same
method is adopted in Etabs also. The finite element method involves dividing the
structure into many small elements, the combination of which is the analyzed. It is usually
done only on a computer.
In the method of substitute frames only a part of the frame is considered for the
analysis. The part considered is called a substitute frame. The moments for each floor are
separately computed. It will be assumed that the moments transferred from one floor to
another are small. Each floor will be taken as connected to column above and column
below their ends as fixed. The frames taken this way are analyzed for the moment and
shear in the beams and columns. This method is very laborious and time consuming. This
method can be conveniently adopted for frame with single bay or with two bays at most
as computations can be done with relative ease the Kani’s or Takabeya’s when done by
hand.
The most adopted methods for analysis of multistory, multi-bay frame are the
“Rotation contribution method”, popularly known as Kani’s method and the Takabeya
method. The rotation contribution method was developed by Gasper Kani of Germany
and Takabeya method by Dr. Fukehi Takabeya. Both the methods are extension of slope
deflection methods and differ from each other slightly in the method of approach. The
working procedures for both are similar though computations are different. The Takabeya
method gives the answers faster than the Kani’s method. In Kani’s method, it is possible
to include changes in loading, length of members etc. during computations itself and the
iterations simply continued. This is not possible in Takabeya Method. In Kani’s method
error done in computation if any cycle is removed/rectified in the following cycles
automatically even if the person computing does not find the error i.e., any error
committed is rectified without it coming into the knowledge of the person. This is not so
in Takabeya method. Here the error is carried into the following cycles.
In Takabeya method the rotation of the joints is assumed and iterations are done to
obtain the refined values of rotation of the joints. In Kani’s method the moments induced
due to rotation of joints is directly iterated. The portal method, cantilever method and
factor methods are mainly the analysis procedures for wind load. When the effect of wind
load is taken along with dead load and live load on a frame, then the analysis for wind
load + dead load + live load becomes very tough, tedious and cumbersome using either
Kani’s method of Takabeya method. Hence, it is the usual procedure to analyze the frame
first for dead load and live load using Kani’s or Takabeya, then analyze the frame for
wind load using any one of the above three methods. The moments obtained in each
member is then algebraically added to obtain the final moments in the members .
2.2 DIMENSIONS:
2.3 DENSITIES:
2.4 LOADS:
AUTO CADD
2.5 INTRODUCTION
engineers to optimize the parts used in the process to cut costs by making sure that the
parts don’t get over engineered.
Some of the most common application of AutoCAD sample drawings and models can be
found in the following industries.
Aerospace:
Satellites, space vehicles, missiles, and aircrafts are produced in the aerospace
industry. Auto CAD sample drawings play an important role in the first step of the design
process, because any one these process costs millions of dollars. The details are
thoroughly planned with the AutoCAD software before starting work on the final
product.
Automotive:
Complex designs and software are required in all aspects of automotive designing. CAD
is used to build prototypes and design of components like upholstery, circuitry boards,
engines, tires, and so on.
Architecture:
Before beginning with the definite construction project, buildings have to be planned
perfectly.2D and 3D plans are designed using CAD. Schematics of offices, houses, and
various other commercial buildings are designed as well using CAD. Accurate
specifications like weights, volumes, and measurements are found
using AutoCAD sample drawings.
Civil engineering:
Metropolitan planners use CAD software to plan infrastructure projects such as Bridges,
office complexes, industrial units, and so on.
Site:
CAD software is used by landscapers to conceptualize great outdoor settings, and find
the proper placement of components like fences, gardens, trees, patios, and other similar
things.
Interior designing:
Detailed and accurate digital designs are made by designers using CAD software. They
are then used by the designers to demonstrate their product to clients with detailed
drawings.
The above described details are only few uses of CAD software. Other than these, it is
also used for designing circuit boards, furniture, electronics, jewelry, packaging, and
more. The extensive applications of CAD software and AutoCAD sample drawings
ensure its inevitability and durability in today’s world.
ETABS
2.6 Introduction
ETABS is a sophisticated, yet easy to use, special purpose analysis and design program
developed specifically for building systems. ETABS 2016 features an intuitive and
powerful graphical interface coupled with unmatched modeling, analytical, design, and
detailing procedures, all integrated using a common database. Although quick and easy
for simple structures, ETABS can also handle the largest and most complex building
models, including a wide range of nonlinear behaviors necessary for performance based
design, making it the tool of choice for structural engineers in the building industry.
Dating back more than 40 years to the original development of TABS, the predecessor of
ETABS, it was clearly recognized that buildings constituted a very special class of
structures. Early releases of ETABS provided input, output and numerical solution
techniques that took into consideration the characteristics unique to building type
structures, providing a tool that offered significant savings in time and increased accuracy
over general purpose programs.
ETABS offers the widest assortment of analysis and design tools available for the
structural engineer working on building structures. The following list represents just a
portion of the types of systems and analyses that ETABS can handle easily:
The ETABS building is idealized as an assemblage of shell, frame, link, tendon, and joint
objects. Those objects are used to represent wall, floor, column, beam, brace, tendon, and
link/spring physical members. The basic frame geometry is defined with reference to a
simple three-dimensional grid system. With relatively simple modeling techniques, very
complex framing situations may be considered.
In the software the units are set to KN and meter and the Co-ordinates for every
column and beam to beam connections are given along x, y and z direction to get the
model of the structure as shown below
The support conditions are given for the ends of the columns as fixed support
Select the required geometry, in our case it is rectangle for beams and columns.
Define the dimensions.
Assign the above dimensions by selecting the respective beams and columns.
Fig.2.6.9 3D RENDRING
SBC of soil
2.7 REPORT
This is to certify that the core soil sample submitted by you, have been tested
for S.B.C of soil and the results of the tests conducted by us are as follows.
Remarks:
1. No ground water observed.
2. Rectangular Footing is assumed.
3. S.B.C of soil is calculated from laboratory test through shear failure condition.
4. Factor of safety= 3.0 is assumed.
5. All field & laboratory tests are done as per Indian Standards.
6. The above results are based on trial pit samples. However the consultant shall
verify the soil strata before executing work.
CHAPTER 3
SLABS
3.1 INTRODUCTION:
Slabs are the structural members used as coverings for roofs and floors. Slabs are
to be cast along with beams and columns. Therefore it can be assumed as restrained slabs
that are corners of slabs are prevented from lifting. They generally carry uniformly
distributed loads primarily by flexure. The load distribution along any direction depends
upon the relative stiffness of the slab along both direction is proportional to the stiffness
of the slab along that direction. The stiffness of the slab along any particular direction
more is the flow of load along that direction. The stiffness of the slab along any direction
depends upon the area of steel. When the slab is stiffened in that direction along which
the load tend to distribute, then the transfer of load from the slab to beams would be
effective thus design is economical on the basis of the direction to transfer of the load.
a) One-way slab
b) Two-way slab
c) Flat slabs
d) Flat plates
When the load on the slab is transferred along only one direction then the slabs are
called One-way slabs. In general when the aspect ratio Ly/Lx is greater than 2 than the
slab is designed as One-Way slab.
When the load on the slab is transferred along both the direction then the slabs are
called Two-way slabs. In general slabs are designed as Two way slabs when the ratio
Ly/Lx is less than 2.
Flat slabs and flat plates are those multi- span slabs, which directly rest on
columns without beams. Flat slabs differ from flat plates in that they have either drop
panels (increased thickness of slab) or column capitals in regions of the columns. Flat
plates have uniform slab thickness, and the high shear resistance around the columns is
obtained usually by the special reinforcement called ‘shear- head reinforcement’ placed in
the slab around the columns.
Dead load of slabs consists of its own weight and in addition, the weight of
finishes, fixtures and partitions. Live load or imposed load is specified as per IS code.
This live load varies according to the use for which the building is to be put after
construction. It is important to note that for design of buildings these live loads are
considered as either acting on the full span or assumed to be absent altogether in the span.
In continuous slabs, they are to be so placed as to get the maximum bending moment and
shear effect in the structure. In design of slabs for other structures like bridges, the effects
of partial loading of the slab may have to be considered.
According to IS 875, the loading on slabs for buildings are calculated as follows
In buildings the dead loads is generally equal to or greater than the live load so that
the dead load to live load ratio is usually unity or more than unity, when this ratio is 1.33
or more, the maximum moments obtained by considering all loads as dead loads are
allowed by the Indian code for arriving at the design moments, shear etc., (IS 456, clause
22.4.1)
For a given type of support condition, the same span / depth basic ratio as given
for beams in IS 456 is applicable for slabs also. However, as the percentage of
reinforcement in slabs is generally low, the effective span/depth ratios can be much larger
than the basic ratios. It should also be remembered that with heavy loadings when the
percentage of steel in slabs increases, this ratio would tend to be the same as in beams.
For the first trail, a convenient percentage of steel may be assumed for the slab and the
span / effective depth ratio calculated. Thus, assuming 0.3 % of steel, the correction factor
F1 from figure of IS 456 will be 1.4 and the span/ effective depth ratio for a continuous
slab will be of the order of 1.4× 26 = 36. Because of these consideration, IS 456, clause
24.1 recommends the following span – overall depth factor for two way slabs using Fe415
steel; up to 3.5 m span loading class up to 3KN/m2 .
There is a nominal cover specified for slabs for different exposures. Also, a
minimum cement content and maximum water cement ratio are specified for different
environment conditions. However, as increased cover raises the dead load, the slab has to
carry; one should be judicious in the choice of cover. Strict maintenance of the chosen
cover during construction and using a good grade of concrete for the construction will go
a long way to ensure durability of slabs and reduce the dead load due to cover.
It should be noted that the depth of slab chosen for deflection requirements will
be usually greater than the depth required for balance design. Hence the area of steel
required will be less than the balanced amount. The fundamental formula used for this
purpose is Mu = (fst × Ast ) × liver arm
The three rules for choosing steel slabs for determining steel area for an under
reinforced section may be used for calculations are as follows (clause 26.5.2)
1. The diameter of the steel should not exceed 1/8 th total thickness of slab.
2. The amount of steel area in either direction should not be less than 0.12% of total
sectional area when using Fe415 steel.
3. Spacing of main steel should not be greater than 3d or 300 mm; secondary should
not be greater than 5d or 450 mm.
The procedure of design of one way slabs is to consider them as ‘beams of one
meter width’ in the shorter direction. The steps in design are as follows
i. Assume a suitable overall thickness for that slab; calculate the factored loads
(Dead and Live load) for design. This initial guess for thickness of slab may be
made from empirical relations between depth and span. The allowable span/depth
ratio of slabs may be taken as given earlier. The minimum depth of ease
construction is 100 mm. The factored load is (1.5 DL + 1.5 LL). A suitable cover
depending on exposure condition should be assumed.
ii. Considering the slab as beam of one meter width and using effective span,
determine the maximum bending moments M for the ultimate factored load. For
continuous slabs, co- efficient of the table (IS 456, table 26) may be used for this
purpose. Otherwise any established elastic analysis may be used. In latter case
redistribution of moments is also allowed.
iii. Using the formula Mu = K fck b d2 and b = 1000 mm, find the minimum effective
depth required as in beams. Add cover and find the total depth of slab from
strength considerations. Check the depth with the width assumed in step 1.
Generally the depth from step 1 will be more than the obtained from the strength
formula.
iv. Check the depth used for shear. As the actual percentage of steel at supports is not
known, the check is only approximate. A value of τc corresponding to the lowest
percentage of steel in table 13 of IS 456 may be used for this purpose. This value
can be increased by a factor k. The depth used should be such that, in the final
analysis, the slab is safe without any shear reinforcements.
v. As the depth selected is usually greater than the minimum depth d, the tension
steel required will be less than balanced amount for the section. Determine the
steel requirement by a suitable formula or by use of SP 16 charts and tables.
SLAB :
Assume, D = 150 mm
Cover =25 mm
LOAD CALCULATION:
REINFORCEMENT:
Mu 7.297 x106
𝑏d 2 = 1000x 1252
= 0.467
From table 2 of sp 16
Pt = 0.16
50.26
Spacing = x 1000 = 251.3 mm
200
SLAB NO. 1
Lx = 3.35 m
Ly = 3.66 m
𝐿𝑦
= 1.1 < 2
𝐿𝑥
The ratio of long to short span is less than 2; hence the slab should be designed as two
way slab.
Cover = 25 mm
LOAD CALCULATION:
From table 26 of IS 456:2000 bending moment coefficients for long to short span ratio is
Coefficients Continuous edge Mid span
αx 0.05225 0.0396
αy 0.047 0.035
At continuous edge:
Mux = αx Wu lx2
= 0.05225X 13.125X3.352
= 7.74 KN-m
At mid span:
Mux = αx Wu lx2
= 5.837 KN-m
At continuous edge:
Muy = αy Wu lx2
= 6.923 KN-m
At mid span:
Muy = αy Wu lx2
= 5.155 KN-m
REINFORCEMENT:
a) SHORT SPAN:
At continuous edge:
Ast fy
Mu = 0.87 fy Ast d [1 − ]
b d fck
A x 415
7.807 X 106 = 0.87 x 415 Ast x 150 [1 − 1000stx125x 25 ]
Ast = 147.78mm2
𝑎𝑠𝑡
Spacing = x 1000
𝐴𝑠𝑡
50.26
= x 1000
𝟏𝟖𝟎
= 279.2 mm
At mid span:
Ast fy
Mu = 0.87 fy Ast d [1 − ]
b d fck
50.26
Spacing = x 1000 = 279.2 mm
180
b) LONG SPAN:
Continuous edge:
Ast fy
Mu = 0.87 fy Ast d [1 − ]
b d fck
50.26
Spacing = x 1000 = 279.2mm
180
Mid span:
Ast fy
Mu = 0.87 fy Ast d [1 − ]
b d fck
50.26
Spacing = x 1000 = 279.2 mm
180
Vu 21.98 x 103
τv = = = 0.1758 N/mm2
bd 1000 x 125
(L/d) basic = 20
(L/d)max = 20 X 1.7 = 34 mm
For Pt = 0.144
CHAPTER 4
BEAMS
4.1 GENERAL:
A beam is a member, which provides support to the slab and the vertical walls.
Bending effects load transferred. A reinforced concrete beam should be able to resist
tensile, compressive and shear stressed induced in it by the loads on the beam. Concrete is
fairly strong in compression but weak in tension. Plain concrete beams are thus limited in
carrying due to the low tensile strength. Steel is very strong in tension. Thus, the tensile
weakness of concrete is overcome by the reinforcing steel in the tension zone in the
concrete to make a reinforced concrete beam.
A section having percentage of steel less than the critical percentage is known as
under reinforced section. Since steel is insufficient to balance compression in concrete,
the tensile strain in steel reaches yield value while the maximum compressive strain in
concrete is less than its ultimate crushing value. The section undergoes large rotational
deformation from the initial stage (yielding of steel), to final stage (crushing) and
impending failure. Since the failure is initiated by yielding of steel in tension, it is known
as primary tension failure.
A Beam section is called as over reinforced if the cross sectional area of steel bars
provided as reinforcement in the beam section is such that the ratio of steel P = (A s/bd) is
more than that for balanced section. It will be seen that the strain in concrete will reach
the ultimate value €cu (and hence the beam will fail) prior to the strain in steel reaches €syl
The beams, which are provided with steel reinforcement in tension zone only, are
called singly reinforced beams.
The beams, which are provided with steel reinforcement in both tension and
compression zones, are called Doubly Reinforced Beams. The necessity of steel in
compression zone arises due to two following reasons: when the depth of the beam is
restricted the strength available from a singly reinforced beam is inadequate and at
support of continuous beam, bending moment changes sign.
This becomes necessary under the following circumstances:
i. Where the beam depth is restricted and the beam has to carry a moment greater
than the moment capacity of singly reinforced beam.
Mu = k × fck × b d2
This usually occurs in beams where the depth is controlled by architectural
considerations.
ii. Where the bending moment in the section can change in sign (as may occur in a
section in the span of a continuous beam with moving loads) so that the
compression zone with one sign of the moment become the tension zone with the
opposite sign of the moment as in continuous bridge girders.
iii. Compression steel is always used in structures in earth quake region to increase
their ductility.
iv. Compression reinforcement will also aid significantly in reducing the long term
deflection of beams.
In a beam, the concrete below the neutral axis does not resist any bending moment
but simply serves to tensile strength. Also, the portion of the concrete just above the
neutral axis carries only very little compressive forces since the intensity of compressive
stress there, is of a very small magnitude. This suggests that the section of the beam
should be such that it has greater width at the top (compression strength) in comparison to
the width below the neutral axis. Such a section is T-beam.
4.3.1 ASSUMPTION:
The design of a reinforced concrete section for Limit State of collapse in bending
is based on following assumptions:
According to the IS code the maximum strain in steel in tension shall not be less than
fy
0.002+ at collapse.
1.15 Es
For beams and slab the vertical deflection limits may be generally to be satisfied
provided that the span to depth ratios are not greater than the values obtained as below:
a) For span up to 10 m
Cantilever 7
Simply supported beams 20
Continuous beams 26
b) For spans above 10m, the values in (a) may be multiplied by 10/span in meters,
except for cantilever in which case deflection calculations should be made.
c) Depending on the area and the stress of steel for tension reinforcement, the values
in (a) or (b) shall be modified by multiplying with the modification factor
obtained as per fig 4 of IS 456-2000.
d) Depending upon the area of compression reinforcement, the value of span to depth
ratio be further modified by multiplying with the modification factor obtained as
per fig 5 of IS 456-2000.
Effective depth of a beam is the distance between the centroid of the tension
reinforcement and the maximum compression fiber, excluding the thickness of finishing
materials or any concrete provided to allow for wear. This will not apply to deep beams.
To find: Ast
Steps:
The beam dimensions b and d and the grades of concrete and steel are given. We
have to find Asc and Ast for a given value Mu.
Mu1 = Mu lim
Mu1 = k fck b d2
Step (ii): Calculate Ast1. Find Ast1 from the expression for ”balanced steel” assuming it
reaches yield point
Step (iv): Calculate Ast2, the area of the tension steel for the above Mu2;
Step (v): Find the compression steel (fsc) which will depend on d/d’.
Ast and Asc respectively above are required tension and compression steel areas.
Since the loads are transferred to columns by beams in framed structure, walls do not play
any significant part in carrying loads. Nominal thickness of wall required to shield the
building from bad effects of weather is provided.
BEAM 2:
Mu 88.337 × 106
= = 1.90
b D2 230×4502
From table 2 of SP 16
Pt = 0.602
bd 0.602x 230 x 425
Tension steel; Ast = pt =
100 100
Ast = 588.45 mm2
Ast 588.45
No. of bars = = ≈ 2 bars
ast 314.16
AT MID SECTION:
Mu 43.733 × 106
= = 0.94
b D2 230×4502
From table 2 of SP 16
Pt = 0.28
Area of tension steel
bd
Ast = pt
100
0.28 x 230 x 425
=
100
Ast 273.7
No. of bars = = ≈ 2 bars
ast 201.06
SHEAR REINFORCEMET:
Vu = 88.34
b = 230 mm d = 425 mm
V 88.34 × 1000
Nominal shear stress τv = b ud = = 0.90N/mm2
230× 425
100 𝐴𝑠𝑡
Pt = = 0.60
𝑏𝑑
0.87 fy Asv d
Vus = Vu – τc b d =
Sv
Spacing Sv = 185 mm
CHAPTER 5
COLUMN
5.1 INTRODUCTION:
A column is an element used primarily to support the axial compressive loads and to
transfer the loads from slabs to the columns or indirectly transferred to the columns through
the beams. All columns are compression members.
The columns are said to be SHORT when the slenderness ratio is less than 12 and the
columns are said to be LONG or SLENDER if the slenderness ratio is more then 12.
However, maximum slenderness ratio of a column should not exceed 60.
Whenever column and beam are rigidly connected, the columns will be subjected to
bending moments. Even the beams are simply supported over the columns, at times, bending
moments are developed in column results in zero net bending moment, and the columns will
be acted upon by only with no moment. Such columns are called Axially Loaded Columns.
When the columns are subjected to some net bending moment along any one
direction, in addition to axial load due to the beams connected to the columns, they have to be
designed for both the axial load and the uni-axial bending moment.
When the column is connected to the beams from different directions, and if the
column is subjected to bending moment along both the X-X and Y-Y axis, in addition to the
axial load, then the column has to be designed for both axial load and Bi-Axial bending
moment.
Concrete being very strong in compression should not theoretically require any
reinforcement. However, because it is very weak in tension, all circumstances leading to
development of tension need to be examined, and reinforcement provided for resisting the
same.
1. To resist any tension that might develop due to bending caused by transverse loads,
eccentric loads or the moments.
2. To assist concrete in the resulting compression so as to reduce the overall size of the
column.
3. To reduce the effects of creep and shrinkage due to sustained loading.
4. To impart necessary ductility to the column.
5. To prevent or delay sudden brittle collapse.
6. To hold the transverse reinforcement.
COLUMN 1:
Pu = 515.8 kN
Mu = 10.15 kN-m
Unsupported length = 3m
Effective cover = 40 mm
fck = 20 kN/m2
𝐿𝑒𝑓𝑓 1.95
= 0.45 = 4.3 < 12
𝐷
𝐿𝑒𝑓𝑓 1.95
= 0.23 = 8.5 < 12
𝑏
𝑙 𝐷 3000 450
emin = + = + = 21
500 30 500 30
𝑒𝑚𝑖𝑛 21
= = 0.044 < 0.05
𝐷 450
LONGITUDINAL REINFORCEMENT:
Mu 10.15x 106
2
= = 0.011
fck b D 20 x 230 x 4502
Pu 515.8 x 103
= = 0.245
fck b D 20 x 230 x 450
𝑑′ 40
= = 0.088 ≈ 0.01
𝐷 450
pt
= 0.04
fck
p = 0.04 x 20 = 0.8 %
0.8
∴ Asc = 100 b D
0.8
= 100 x 230 x 450
LATERAL REINFORCEMENT:
CHAPTER 6
FOOTING
6.1 INTRODUCTION:
The function of a foundation or substructure is to safely transfer the loads from the
super structure to the ground. Different types of foundation structures like isolated footings,
continuous footings, combine footings, slab rafts, piles, piled rafts, caissons are used for this
purpose. Design of foundation structure is a subject in its own right and only the design of
elementary foundation structures, such as reinforced concrete individual footings, pedestal
and pile caps, is covered in this chapter. IS 456, Clause 34 deals with design of footings.
The condition to be satisfied by the subsoil in design of foundation is that its safe
bearing capacity (which is based on both strength and settlement) should not exceed by the
loads from the structure. As the safe bearing capacity of the soil by a suitable factor of safety,
its value represents the serviceability condition, and not the limit state condition. According,
the loads to be used to determine the size of the foundation should be the service loads and
not the factored loads. The loads to be used are
In multistoried buildings, one should take advantage of the allowable reduction in live load
for residential, office buildings.
If the structure is to be planned to take the horizontal load by moment as its base, it
should be properly fixed to the ground so that a fixing moment opposite to the applied
moment will be produced by the reactions. Alternatively, the foundation pressure should be
considered as non-uniform.
Footings under walls are called one-way footings and those under columns, two way
footings. The first step in design of footing is to calculate the necessary area from the
formula.
Having thus determined the size of the footings, its structural design is carried out by
using factored loads and principles of limit state design as already discussed in the case of
other RC members. The main items to be designed are the thickness of footings and its
reinforcement. The thickness should be sufficient to
1. Resist the shear force without shear steel and the bending moment without
compression steel.
2. Give the structure the required structural rigidity so that foundation reaction below
can be assumed.
3. Withstand the corrosion that can be caused from the ground. (This minimum cover
required is not less than 75mm when the concrete is cast against the ground and not
less than 40mm when it is cast against the ground, and not less than 40mm when it is
cast against a layer of binding concrete of 75 to 80mm thickness.) The minimum
cover specified in IS 456 for footing is 50mm (clause 26.4.2.2). It is also important to
remember that the percentage of steel provided should not be less than 0.15 for Fe 250
and 0.12 for Fe 415 steel as specified for slabs in IS 456, Clause 26.5.2.1.
In most design of foundations and especially in individual footing design, the soil is
considered as elastic and the RC foundation structure is infinitely rigid. Hence, if foundation
pressures on these rigid structures are assumed as uniformly distributed on the base, it is
necessary that the center of gravity of the external load system always coincide with the CG
of the loaded area. Otherwise, there will be variation of pressure on the base of the foundation
that, for rigid foundations, may be assumed as linearly varying. In all layouts of foundations,
this basic principle should always be borne in mind.
With a vertical load P and a moment M acting on a column, base pressure under the
rigid footing will be non-uniform but will be linearly varying from a maximum value of q1 to
minimum value of q2.
If the center of gravity of the foundation and the line of application of P coincide, the
values of q1 and q2 are
q1= (P) / (BL) + (6M) / (BL2), q2= (P) / (BL) – (6M) / (BL2)
B = the breadth
The eccentricity ‘e’ produced by the resultant base reaction will produce the necessary
𝑀
moments to counteract the applied moment so that E =
𝑃
In soils such as clays, large non-uniform base pressures can lead to differential
𝑞1
settlements and consequent tilt in the column. Hence the ratio of ( ) should not exceed 2 to
𝑞2
4, depending on whether permanent or transient loads cause it. In the case of small
eccentricities due to P and M, the Centre of gravity of the foundation itself may be offset
from the line of action of the load P to produce uniform resultant distribution on the base.
𝑀 𝐿
The value of e = gives indication of the probable variation of q1 and q2.If e = ,
𝑃 6
according to the middle third rule, q2 = 0 and q1 will be twice the average pressures. If e is in
the range 1/10 – 1/12, the eccentricity can be considered to be small. When e is greater than
1/6, part of the base will not be in contact. The maximum soil pressure q on the foundation
can be calculated from the following equation
1
P = 𝑞𝑠 𝐵
2
Where B is the breadth of the footing‘s’ is the length of foundation in contact with the
ground.
𝑀 1 𝑠
=e=( − )
𝑃 2 3
In footings subjected to biaxial bending, the effect of variation of base pressures in both
planes should be considered and combined to get the final values.
General planning, there can be three types of individual footings: rectangular, sloped
or stepped. They may rest on soil, rock or on piles. The minimum thickness of edge of the
footing on soil and rock should be 150 mm and on top of piles should not be less than 300
mm (IS 456 Clause 34.1.2)
The column transfers the load to top of footing by bearing. In limit state design, the
value of the pressure allowed under direct compression on an unreinforced loaded area of
same size is to be limited to 0.45fck as given by IS 456, Clause 34.4. However, when the
supporting area is larger than the loading area on all sides, it may be increased by the factor
A1/A2 (where in the case of a footing A1 = area of the footing and A2 = area of the column
base), but the factor should not be greater than 2.
If the above permissible stresses are exceeded, the transfer of forces should be with
steel reinforcement, by extending the reinforcement into the footing or by providing dowel
(starter) bars. According to IS 456, if dowel bars are provided, they should extend into
column a distance equal to the development length of the column bars (IS 456, Clause
34.4.4). however, this requirement for development length has been relaxed in BS 8110
(1985): clause 3.12.8.8 according to BS code, compression bond stress that develops on
starter bars within bases need not be checked provided the starter bars extend down to the
level of the bottom reinforcement. Application of this clause can reduce the depth required in
footings and save on steel reinforcement.
According to IS 456, clause 34.4.3, the extended longitudinal bars or dowels should
be at least 0.5% of the cross-sectional area of the supported columns or pedestal, and a
minimum of four bars should be provided. The diameter of the dowels should not exceed the
diameter of the column bars by 3 mm.
Rectangular footings are generally used with rectangular columns. The most
economical proportions of the footing are given if the rectangular base projects the same
distance beyond all the columns faces, so that the footing require the minimum amount of
materials.
= 76 KN
837
Area of footing required = = 4.4 m2
185
= 0.247 N/mm2
Vu = τc b d
d = 555.42 mm
12752
Mu = qu X 3000 X 8
12752
Mu = 0.247 X 3000 X 8
Mu = 150.57 KN-m
= 2280 x 600
= 630.47 KN
Vu 630.47 x 103
Nominal shear (τv) = = = 0.47 N/mm2
resisting area 1.368 x 106
ks = (0.5 + β) < 1
b 230
β= = = 0.4
d 600
ks = 0.96 Take ks = 1
DESIGN OF REINFORCEMENT:
a) In long direction:
Mu = 150.573 x 106
𝐴𝑠𝑡 𝑥 fy
Mu = 0.87 x fy x Ast x d x [1 − 𝑓𝑐𝑘 𝑥 𝑏 𝑥𝑑
]
𝐴𝑠𝑡 𝑥 415
Mu = 0.87 x 415 x Ast x 600 x [1 − 20 𝑥 3000 𝑥 600
]
b) In short direction:
Mu =150.573 x 106
𝐴𝑠𝑡 𝑥 fy
Mu = 0.87 x fy x Ast x d x [1 − 𝑓𝑐𝑘 𝑥 𝑏 𝑥𝑑
]
𝐴𝑠𝑡 𝑥 415
Mu = 0.87 x 415 x Ast x 600 x [1 − 20 𝑥 1500 𝑥 600
]
In order to get uniform upward pressure, “The C.G of column load should coincide with C.G
of footing”
Fig. 6.9(b) Bending moment and Shear force diagram of combined footing
Location of POC:
X1 = 1.62487 m
X2 = 0.37513 m
Mu = 51.695kN-m
Take D = 380mm
d = 330 mm
REINFORCEMENT:
Mu 51.695 x 106
= = 0.47
b d2 1000 x 3302
Pt = 0.20 %
bd 0.20
Ast = pt = x 1000 x 330 = 660 mm2
100 100
ast
Spacing = x1000 = 304.6 mm
Ast
Distribution steel:
Ast = 0.12% of cross sectional area
= 420 mm2
Vu = 57.9 kN
Vu 57.9 x 103
Nominal shear stress, τv = = = 0.18 N/mm2
bd 1000 x 330
Pt = 0.15%
` CHAPTER 7
STAIR CASE
7.1 INTRODUCTION:
Stairs consists of steps arranged in a series for the purpose of giving access to
different floors of a building. Usually, the staircase may be provided near the main entrance
of the building. All stair cases should be adequately ventilated and properly designed.
Over the years several types of stair cases have been developed with varying
geometrical shapes and structural behavior. The most common types are classified as follows:
7.2.1 Dog legged stair case: It is the most common type used in all types of buildings.
It comprises of two adjacent flights running parallel with a landing slab at mid height.
7.2.2 Open well stair case: It is generally adopted in public buildings where large
spaces are available. This type of stair case consists of smaller flights and provides
better accessibility comfort and good ventilation due to open well at the center.
7.2.3 Tread-Riser type stair case: It is very popular due to its superior aesthetic
appearance without any waist slab and comprising only the horizontal and vertical
slabs in the form of a folded plate.
7.2.4 Isolated cantilever type stair case: It comprising only the horizontal tread slab
projecting from a wall or inclined beam serving as a fixed end with open risers.
7.2.5 Double cantilever precast tread slab stair case in which cantilever tread slab
projects on either side with a central inclined beam.
3000
Floor to floor height = =1500 mm
2
1500
No of rise = = 10 No
150
No of tread =10 – 1= 9 No
LOAD CALCULATION:
𝑅 2 0.15 2
Weight of waist slab = t √1 + [𝑇 ] x 25 = 0.2√1 + [0.30] x 25 = 5.59 KN/m
𝑅 2
Finishes = 1 KN/m√1 + [𝑇 ]
Finish = 1 KN/m
=65.86 KN
∑MA=0
RB=32.16 KN
RA=33.69 KN
Mo = 34.03 KN-m
REINFORCEMENT:
Ast fy
Mu = 0.87 fy Ast d [1 − ]
b d fck
Ast x 415
34.03 x 106 = 0.87 x 415 x Ast x 200 [1 − ]
1000 x200x 20
Using 12 mm bars
𝑎𝑠𝑡 113.09
Spacing = x 1000 = = 227.61 mm
𝐴𝑠𝑡 496.87
Distribution bar:
0.12
Ast= x 1000 x 200 = 240 mm2
100
Use 10 mm bar
78.54
Spacing = x 1000 = 327.24 mm
240
CHAPTER 9
ESTIMATION
Accurately forecasting the cost of future projects is vital to the survival of any business or
organization contemplating future construction. Cost estimators develop the cost information
that business owners or managers, professional design team members, and construction
contractors need to make budgetary and feasibility determinations. From an Owner's
perspective the cost estimate may be used to determine the project scope or whether the
project should proceed. The construction contractor's cost estimate will determine the
construction bid or whether the company will bid on the construction contract.
There were about 198,000 cost estimators in 1994 according to the U.S. Department of
Labor, Bureau of Labor Statistics,
2006-2007 Occupational Outlook Handbook, Cost Estimators, of which 58% work in the
construction industry, 17% are employed in manufacturing industries, and the remaining 25%
elsewhere. Most construction estimators have considerable experience gained through
working in the building construction industry. This guide will be confined to cost estimating
in the building construction industry.
Construction cost estimators can be contractually hired in many different ways. They may be
employed by the owner's representative/project manager, employed by the construction
manager, employed as a member of a professional design team, or separately hired by the
owner. They estimate building costs through all the stages of design and the construction of
the project. On large projects it is common for estimators to specialize in disciplines that
parallel design discipline specialization.
It is very important to have the cost estimator involved right from the start of the project to
ensure that the project budget reflects the decisions made by the rest of the project team
throughout the integrated design process.
GENERAL ABSTRACT
Name of Work: CONSTRUCTION OF POST METRIC B.C.M HOSTEL (OLDER)
AT CHITTAWADIGI IN SURVEY NO : 249AS
0.2 ACRE LAND OF HOSPET TOWN
SI.
Type of Work Amount in Rs.
No.
14 Lumpsum Provision towards HKRDB Name Board & Other Miscl 16034.70
DETAILED
ESTIMATE
CONSTRUCTION OF POST METRIC B.C.M HOSTEL
(OLDER)AT CHITTAWADIGI IN SURVEY NO : 249 Estimated cost: 109.00 Lakhs
AS 0.2 ACRE LAND OF HOSPET TOWN
Itm
Descripti Unit. No Length Breadth Depth D Quantity Rate in Rs. Amount in Rs.
No
on L B
.
1 2 3 4 5 6 7 8 9 10
1 KSRRB 200-9: Clearing and grubbing road land including uprooting rank vegetation, grass,
bushes, shrubs, saplings and trees of girth upto 300mm, by manual means, in area of light
jungle, removal of stumps, disposal of unserviceable materials, stacking of serviceable
materials within a lead of 100 metres from road boundary, labour charges complete as per
specifications. Specification No. KRBS 200-1 MORT & H Specifications No. 201(PWD SR 2018-
19 Page No. 138, Item No. 18.11)
PREPARATION GROUND
FOR FOUNDATION
Deductions
Itm
Description Unit. No Length L Breadth B Depth D Quantity Rate in Rs. Amount in
No.
Rs.
1 2 3 4 5 6 7 8 9 1
0
4 KSRB 4-1.3: Providing and laying in position plain cement concrete of mix M 1:4:8 with OPC cement
@ 180 kgs, with 40 mm and down size graded granite metal coarse aggregates @ 0.85 cum and
fine aggregates @ 0.57 cum machine mixed, concrete laid in layers not exceeding 15 cms, thick well
compacted, in foundation and plinth, including cost of all materials, labour, HOM of machinery,
curing complete as per specifications. Specification No. KBS 4.1, 4.2 (PWD SR 2018-19 Page No. 13
, Item No. 4.3)
DROP WALL
PARTITION WALLS
FOR FOUNDATION
FLOORING CONCRETE
Flogging Concrete(Plinth
Protection Works)
Deductions
7 KSRB 2.5: Earthwork excavation in all soil deposits and filling sides of foundation upto plinth in
layers not exceeding 20cms. In depth, compacting each deposited layer by ramming after watering
with all lead and lift including cost of all labour complete as per specification. No. KBS
2.9.9/2.9.10.1/2.1.1 PWDSR 2018-19 Page No: 7, Item No 2.12
FOR FOUNDATION
Itm
Description Unit. No Length L Breadth B Depth D Quantity Rate in Rs. Amount in Rs.
No.
1 2 3 4 5 6 7 8 9 10
ALL WALLS
LONG WALL cum 2 28.53 0.90 1.50 77.03
SHORT WALL cum 2 18.16. 0.90 1.50 2.70
SHORT WALL cum 2 3.68 0.90 1.50 9.94
BELOW THE FLOORING
ROOM cum 2 4.77 7.12 0.90 61.13
KITCHEN cum 1 4.77 7.12 0.90 30.57
DINNING HALL cum 1 9.77 7.12 0.90 62.61
DIGITAL ROOM cum 1 4.77 7.12 0.90 30.57
STORE ROOM cum 1 3.00 7.12 0.90 19.22
LENIN ROOM cum 1 4.84 3.45 0.90 15.03
SICK ROOM cum 1 4.84 3.45 0.90 15.03
TOILET BLOCK cum 1 4.84 7.12 0.90 31.01
STAIRCASE ROOM cum 1 3.00 7.12 0.90 19.22
WARDEN ROOM cum 1 3.12 3.48 0.90 9.77
BATH/WC cum 1 1.50 3.48 0.90 4.70
WARDEN OFFICE cum 1 4.77 3.49 0.90 14.98
CORRIDOR/OPEN PASSAGE cum 1 28.53 3.00 0.90 77.03
ENTRANCE LOBBY cum 1 4.77 3.50 0.90 15.03
CORRIDOR 2.1M WIDE cum 1 4.77 2.10 0.90 9.02
Basic rate as per PWD DSR 2018-19: 403.00
Area weaightage 5%: 20.15
Total: 884.28 423.15 374181.00
8 KSRB 4.2.2: Providing and laying in position reinforced cement concrete of design mix M20 with
OPC cement @ 320 kgs, with 20 mm and down size graded granite metal coarse aggregates @
0.69cum and fine aggregates @ 0.46cum, with superplastisiser @ 3lts confirming to IS9103-1999
Reaffirmed-2008, machine mixed, concrete laid in layers not exceeding 15 cms thick, vibrated for all
works in foundation for footings,pedastals,retaining walls,return walls,walls(any thickness) including
attached pilaster,columnspillars,posts,struts,buttresses,bed blocks,anchor blocks & plinths etc.,
including cost of all materials, labour, HOM of Specifications. Specification. No. KBS 4.1,4.6( PWDSR
-2018-19 Page No.14 Item No 4.11 )
FOOTING
FC 38 Cum 22 2.80 2.60 0.500 80.08
FC 32 Cum 9 2.90 2.70 0.525 37.00
FC 34 Cum 9 3.00 2.80 0.525 39.69
FC 13 Cum 2 3.15 2.95 0.550 10.22
FC 1 Cum 2 1.60 1.60 0.300 1.54
COLUMNS
RC 450X450 Cum 2 0.45 0.45 7.80 3.16
RC 230X450 Cum 42 0.23 0.45 7.80 33.91
GROUND/TIE BEAM
LONG WALL Cum 2 28.53 0.23 0.300 3.94
SHORT WALL cum 2 18.16. 0.23 0.300 0.14
SHORT WALL cum 2 3.68 0.23 0.300 0.51
FOR PORTICO
LONG WALL Cum 1 4.77 0.23 0.300 0.33
SHORT WALL Cum 2 4.29 0.23 0.300 0.59
DROP RCC WALL
LONG WALL Cum 2 28.53 0.23 3.300 43.31
SHORT WALL cum 2 18.16. 0.23 3.300 1.52
SHORT WALL cum 2 3.68 0.23 3.300 5.59
PLINTH BEAM
LONG WALL Cum 2 28.53 0.23 0.380 4.99
LONG WALL Cum 2 13.21 0.23 0.380 2.31
LONG WALL cum 2 9.92 0.23 0.380 1.73
SHORT WALL cum 2 18.16 0.23 0.380 3.17
SHORT WALL cum 10 7.12 0.23 0.380 6.22
BET LENIN ROOM & SICK ROOM cum 1 4.84 0.23 0.380 0.42
ENTRANCE LOBBY & CORRIDOR Cum 2 4.77 0.23 0.380 0.83
PARTITION WALLS
BET WARDEN OFFICE & WARDEN 1 4.77
ROOM Cum 0.23 0.380 0.42
BET WARDEN ROOM & BATH/WC Cum 1 3.48 0.23 0.380 0.30
TOILET BLOCK LONG WALLS cum 2 7.12 0.23 0.380 1.24
TOILET BLOCK SHORT WALLS cum 4 4.77 0.23 0.380 1.67
Itm
Description Unit. No Length L Breadth B Depth D Quantity Rate in Rs. Amount in Rs.
No.
1 2 3 4 5 6 7 8 9 10
LINTEL
LONG WALLS Cum 2 28.53 0.23 0.15 1.97
LONG WALL Cum 2 13.21 0.23 0.15 0.91
LONG WALL Cum 2 9.92 0.23 0.15 0.68
SHORT WALL Cum 13 7.12 0.23 0.15 3.19
BET ENTRANCE LOBBY & CORRIDOR
Cum 1 4.77 0.23 0.15 0.16
BET LENIN ROOM & SICK ROOM cum 1 4.84 0.23 0.15 0.17
BET WARDEN OFFICE & WARDEN
ROOM Cum 1 4.77 0.115 0.15 0.08
BET WARDEN ROOM & BATH/WC cum 1 3.48 0.115 0.15 0.06
TOILET BLOCK LONG WALLS cum 2 7.12 0.115 0.15 0.25
TOILET BLOCK SHORT WALLS cum 8 1.70 0.115 0.15 0.23
ROOF BEAM
LONG WALL Cum 5 28.53 0.23 0.45 14.76
Cum 1 25.53 0.23 0.45 2.64
SHORT WALL Cum 7 18.16 0.23 0.45 13.16
PORTICO BEAM
LONG WALL Cum 1 4.77 0.23 0.45 0.49
SHORT WALL Cum 2 4.29 0.23 0.45 0.89
ROOF SLAB
WHOLE BUILDING Cum 1 28.53 18.16 0.125 64.76
PORTICO Cum 1 6.40 4.29 0.125 3.43
STAIRCASE
Staircase Waist slab Cum 2 4.00 1.50 0.150 1.80
Steps Cum 21 1.50 0.150 0.150 0.71
Staircase Landing Cum 1 3.00 2.00 0.150 0.90
Staircase Beam Cum 1 3.00 0.23 0.300 0.21
DEDUCTIONS
STAIRCASE SLAB PORTION Cum -1 3.00 4.50 0.125 -1.69
Basic rate as per PWD DSR 2018-19: 5780.00
Area weaightage 5%: 289.00
Total: 394.61 6069.00 2394858.00
9 KSRB 4.2.10: Providing and laying in position reinforced cement concrete of design mix M20 with .
OPC cement @ 24kgs, with 12mm and down size graded granite metal coarse aggregates @
0.05175cum and fine aggregates @ 0.0345cum, with superplastisiser @ 0.225lts, machine mixed,
well compacted for plain chajja of 7.5cms. average thickness, upto ground floor level, including cost
of all materials, labour, HOM of machinery, finishing, curing, complete as per specifications.
Specification No. KBS 4.1,4.6 (PWD SR 2018-19 Page No.15, Item No. 4.19)
Chejja Sqm 1 28.53 0.60 17.12
2 7.58 0.60 9.10
1 13.21 0.60 7.93
1 9.92 0.60 5.95
Basic rate as per PWD DSR 2018-19: 443.00
Area weaightage 5%: 22.15
Total: 40.09 465.15 18649.00
10 KSRB 4-2.12: Extra for providing throating or drip moulding to R.C.C. chajja with plastering (labour .
charges only) as per specifications. Specification. No. KBS(PWD SR 2018-19 Page No. 15, Item No.
4.21)
Chejja M 1 29.73 29.73
2 8.78 17.56
1 14.41 14.41
1 11.12 11.12
Basic rate as per PWD DSR 2018-19: 33.00
Area weaightage 5%: 1.65
Total: 72.82 34.65 2523.00
Itm
Description Unit. No Length L Breadth B Depth D Quantity Rate in Rs. Amount in Rs.
No.
1 2 3 4 5 6 7 8 9 10
11 KSRB 6-1.3: Providing and constructing burnt brick masonry with approved quality of non-modular
bricks of standard size of class designation 3.5N/mm²(table mounded) with cement mortar 1:6 for
basement and superstructure including cost of materials, labour charges, scaffolding, curing
complete as per specifications. Specification No.KBS 6.2(PWD SR 2018-19 Page No. 29, Item No.6.3)
MAIN WALLS
LONG WALLS Cum 2 28.530 0.23 3.15 41.34
BET ENTRANCE LOBBY & CORRIDOR Cum 1 4.770 0.23 3.15 3.46
BET LENIN ROOM & SICK ROOM Cum 1 4.840 0.23 3.15 3.51
PARTITION WALLS
BET WARDEN ROOM & BATH/WC Cum 1 3.480 0.10 3.15 1.10
DEDUCTIONS
DOORS
Main Door Cum -1 1.80 0.23 2.10 -0.87
WINDOW
VENTILATOR
12 KSRB 4.9.2 : Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting,
bending, hooking, placing in position, lapping and / or welding wherever required, tying with
binding wire and anchoring to the adjoining members wherever necessary complete as per design
(laps, hooks and wastage shall not be measured and paid) cost of materials, labour, HOM of
machinery complete as per specifications. Specification No. KBS 4.6.3 for TMT Bars Fe 500 (PWD
SR 2018-19 Page No. 18 , Item No. 4.46.2)
13 KSRB 9-7.1: Providing and fixing in position fully panelled Teak wood shutters for doors, styles and
rails of 30mm. thick with bottom and lock rails 180mm wide top rail and styles 100mm wide as per
drawing and panels of 25mm thick including cost of materials, labour, HOM of machineries complete
as per specifications. (excluding cost of fixtures) Specification No. KBS 9.34 (PWD SR 2018-19 Page
No. 54 , Item No. 9.20)
Itm
Description Unit. No Length L Breadth B Depth D Quantity Rate in Rs. Amount in Rs.
No.
1 2 3 4 5 6 7 8 9 10
20 KSRB 15-18.2 : Providing and applying enamel metal paint two coats (excluding priming coat) over
new steel or other metal surface brushing to give an even shade after cleaning oil, grease, dirt and
other foreign matter, including cost of materials, labour, complete as per specifications.(PWD SR
2018-19 Page No. 123 Item No.15.74)
WINDOW
W Sqm 20 1.50 1.50 45.00
V Sqm 7 0.90 0.45 2.84
V1 Sqm 26 1.50 0.45 17.55
FG Sqm 2 0.90 1.50 2.70
SECURITY GRILL WORK Sqm 2 3.00 3.15 18.90
Basic rate as per PWD DSR 2018-19: 95.00
Area weaightage 5%: 4.75
Total: 86.99 99.75 8677.00
21 KSRB 7.10: Providing and fixing in position aluminium windows and ventilators as per approved
drawings with sliding shutters using double track window frame section of size 61.85x31.75mm.
With 1.2mm thick, bottom section weight 0.695 kg/m, sides and top sections 1.3mm thick weight
0.695 kg/m; and shutter comprising top and bottom section of size 40mmx18mm, 1.25mm thick
0.417 kg/m; shutter interlock section 40mmx26.7mm, 1.1mm thick, weight 0.469 kg/m. the shutters
mounted on nylon rollers with approved quality of fixtures such as aluminium handles tower bolts
etc.; and providing and fixing 5.5mm. thick plain glass for shutters fitted with rubber beading
aluminium sections including cutting to required length, joints mitred subdividing the frame
tononned and rivetted in the assembled frame stiffened with end clips at corners angles etc., and
fixed to the walls, lintels, floor beams/cills as the case may be with necessary steel screw, raul
plugs, or teak wood gatties including cutting masonry or concrete and making good the original
surgace using cement mortar, aluminium sections pretreated for removal of any Specification. 1) -
do- using aluminium section anodized to 12-15 microns.(PWD SR 2018-19 Page No. 34,35 Item
No.7.10.1)
Windows W Sqm 20 1.50 1.50 45.00
FG Sqm 2 0.90 1.50 2.70
Basic rate as per PWD DSR 2018-19: 4266.00
Area weaightage 5%: 213.30
Total: 47.70 4479.30 213663.00
22 Providing and fixing Special make glazed Vitrified tiles (Granomite finish) of approved make, quality
and colour of size 600x600x10mm thick fixed on existing flooring with a special adhesive for
flooring, skirting & jointed with neat cement slurrry mixed with pigment to match shade of tiles
complete including providing spacers at requred intleval and removing stains etc., cost of materials,
mortar, labour etc., complete as per specification(PWD SR 2018-19 Page No. 109 Item No.14.43)
Itm
Description Unit. No Length L Breadth B Depth D Quantity Rate in Rs. Amount in Rs.
No.
1 2 3 4 5 6 7 8 9 10
24 Providing and fixing 40mm thick sadarhalli grey flammed granite slab for bath areas in bathrooms
over a bed of 25mm thick CM 1:6 and fixing granite slab with CM 1:3.(PWD SR 2018-19 Page No.
111 Item No.14.57)
WASHING AREA OF KITCHEN Sqm 1 4.77 2.000 9.54
Basic rate as per PWD DSR 2018-19: 1826.00
Area weaightage 5%: 91.30
Total: 9.54 1917.30 18291.00
24 KSRB 14.14-5 : Providing Ceramic tiles of approved make, shade and size for flooring, treads of
steps and landings laid on a bed of 12 mm thick, cemetn mortar 1:3 mix, flush pointing with white
cement using colour pigment, including cost of materials, laobur, curing, complete as per
specifications For Ceramic Tiles of size 15x15cms 6mm thick (PWD SR 2018-19 Page No. 107-108
Item No.14.36.1)
TOILET BLOCK PASSAGE Sqm 1 1.29 7.350 9.48
WC/BATH ROOMS Sqm 10 1.34 1.680 22.51
Basic rate as per PWD DSR 2018-19: 1122.00
Area weaightage 5%: 56.10
Total: 31.99 1178.10 37692.00
24 Providing and fixing of wall cladding using 20 mm thick gang saw water cut Shiva gold/ lacker red
granite, grey granite in CM 1:3 proportion cut to required shape, pattern with paper joints, finished
with cement mortal using white cement and colour pigments to match the colour of slab making
through jointing wiht sealant, making holes 25mmx12mm grooves in joints including curing etc.,
complete.(PWD SR 2018-19 Page No. 110 Item No.14.49)
ENTRANCE WALL Sqm 1 4.77 3.600 17.17
DEDUCTIONS
MD Sqm -1 1.80 2.100 -3.78
FG Sqm -2 0.90 1.500 -2.70
Basic rate as per PWD DSR 2018-19: 3548.00
Area weaightage 5%: 177.40
Total: 10.69 3725.40 39832.00
25 KSRB 14-17.1 : Providing skirting, dado, rises of steps with white glazed tiles 6mm thick on 10mm
thick cement plaster 1:3 and jointed with white cement slurry over rough plaster surface (excluding
cost of rough plastered surface which should be measured and paid separately) using glazed tiles of
approved make and size including cost of materials, labour, complete as per
specifications.Specification No. KBS 14.1614.17(PWD SR 2018-19 Page No. 108 Item No.14.40)
SKIRTING, DADO, RISES
TOILET BLOCK PASSAGE Sqm 1 14.70 2.100 30.87
WC/BATH ROOMS Sqm 10 6.04 2.100 126.84
Staircase(Treads) Sqm 20 2.00 0.30 12.00
Staircase(Rise) Sqm 21 2.00 0.15 6.30
Staircase Landing Sqm 1 3.00 1.50 4.50
Out side tread steps Sqm 4 2.385 0.30 2.86
Out side rise steps Sqm 5 2.385 0.15 1.79
DEDUCTIONS
TOILET ROOM DOOR DEDUCTIONS
D1 Sqm -10 0.90 2.10 -18.90
Basic rate as per PWD DSR 2018-19: 1166.00
Area weaightage 5%: 58.30
Total: 166.26 1224.30 203553.00
Itm
Descriptio Unit. No Length L Breadth B Depth D Quantity Rate in Rs. Amount in Rs.
No.
n
1 2 3 4 5 6 7 8 9 10
26 KSRB 4-6.2 : Providing and removing centering, shuttering, strutting, propping etc., and removal
of form work for flat surface such as roofs, landings, balconies and likes, thickness upto 200 mm
including cost of all materials, labour complete as per specificaitons.up to 3.50m from Ground
level.
Specification No. KBS 4.6.2(PWD SR 2018-19 Page No. 16, Item No. 4.29)
Roof slab(Same as Item No: 18) Sqm 431.97
Portico Sqm 1 6.40 5.86 37.50
Slab Sides Sqm 1 101.93 0.150 15.29
Staircase slab landing 1 3.00 1.50 4.50
Staircase Slab sides Sqm 2 1.50 3.00
Basic rate as per PWD DSR 2018- 408.00
19:
Area weaightage 5%: 20.40
Total: 492.26 428.40 210885.00
26 KSRB 4-6.11: Providing and romoving centering, shutting, strutting, propping etc., and removal of
form work for stairs (excluding landing) except spiral staircase including cost of all materials,
labour complete as per specifications.Specification No. KBS 4.6.2(PWD SR 2018-19 Page No. 17,
Item No.
4.38)
Staircase slab 1 3.00 4.50 13.50
Basic rate as per PWD DSR 2018- 556.00
19:
Area weaightage 5%: 27.80
Total: 13.50 583.80 7881.00
27 KSRB 4-6.7: Providing and romoving centering, shutting, strutting, propping etc., and removal of
form work for sides and soffits of beams, beam haunchings,cantilever girders, bressumers
and lintels not exceeding 1m in depth including cost of all materials, labour complete as per
specifications.Specification No. KBS 4.6.2 (PWD SR 2018-19 Page No. 17, Item No. 4.34)
GROUND/TIE BEAM
Sqm 2 28.53 0.60 34.24
Sqm 2 18.16. 0.60 1.20
Sqm 2 3.68 0.60 4.42
Sqm 1 4.77 0.60 2.86
Sqm 2 4.29 0.60 5.15
PLINTH BEAM
Sqm 2 28.53 0.76 43.37
Sqm 2 13.21 0.76 20.08
Sqm 2 9.92 0.76 15.08
Sqm 2 18.16 0.76 27.60
Sqm 10 7.12 0.76 54.11
Sqm 1 4.84 0.76 3.68
Sqm 2 4.77 0.76 7.25
Sqm 1 4.77 0.76 3.63
Sqm 1 3.48 0.76 2.64
Sqm 2 7.12 0.76 10.82
Sqm 4 4.77 0.76 14.50
ROOF BEAM
Sqm 5 28.53 1.13 161.19
Sqm 1 25.53 1.13 28.85
Sqm 7 18.16 1.13 143.65
PORTICO BEAM
Sqm 1 4.77 1.13 5.39
Sqm 2 4.29 1.13 9.70
LINTEL
Sqm 2 28.53 0.30 17.12
Sqm 2 13.21 0.30 7.93
Sqm 2 9.92 0.30 5.95
Sqm 13 7.12 0.30 27.77
Sqm 1 4.77 0.30 1.43
Sqm 1 4.84 0.30 1.45
Sqm 1 4.77 0.30 1.43
Sqm 1 3.48 0.30 1.04
Sqm 2 7.12 0.30 4.27
Sqm 8 1.70 0.30 4.08
Basic rate as per PWD DSR 2018- 292.00
19:
Area weaightage 5%: 14.60
Itm
Description Unit. No Length L Breadth B Depth D Quantity Rate in Rs. Amount in Rs.
No.
1 2 3 4 5 6 7 8 9 10
28 KSRB 4-6.5: Providing and romoving centering, shutting, strutting, propping etc., for columns,
pillars, post and struts, square/rectangular/polygon in plan including cost of all materials, labour
complete as per specifications. Specification No. KBS 4.6.2 (PWD SR 2018-19 Page No. 16, Item
No. 4.32)
RC 450X450 Sqm 2 1.80 7.80 28.08
RC 230X450 Sqm 42 1.36 7.80 445.54
Basic rate as per PWD DSR 2018-19: 456.00
Area weaightage 5%: 22.80
Total: 473.62 478.80 226767.00
30 KSRB 4-6.1 : Providing and removing centering, shuttering, strutting, propping etc., and removal of
form work for foundations, footings, bases of columns for mass concrete including cost of all
materials, labour complete as per specificaitons. Specification No. KBS 4.6.2 (PWD SR 2018-19 Page
No. 15, Item No. 4.28)
FC 38 Sqm 22 10.80 0.500 118.80
FC 32 9 11.20 0.525 52.92
FC 34 9 11.60 0.525 54.81
FC 13 2 12.20 0.550 13.42
FC 1 2 6.40 0.300 3.84
Basic rate as per PWD DSR 2018-19: 263.00
Area weaightage 5%: 13.15
Total: 243.79 276.15 67323.00
30 KSRB 4-6.4: Providing and romoving centering, shutting, strutting, propping etc., and removal of
form work for vertical surface such as walls at any thickness, including attached pilasters,
buttresses, plinth and string courses cost of all materials, labour complete as per
specifications.Specification No. KBS 4.6.2(PWD SR 2018-19 Page No. 16, Item No. 4.31)
LONG WALL Sqm 2 28.53 6.600 376.60
SHORT WALL 2 18.16. 6.600 13.20
SHORT WALL 2 3.68 6.600 48.58
Basic rate as per PWD DSR 2018-19: 360.00
Area weaightage 5%: 18.00
Total: 438.37 378.00 165705.00
31 KSRB 4-6.10: Providing and romoving centering, shutting, strutting, propping etc., and removal of
form work for chajjas, corbels etc.,including edges including cost of all materials, labour complete
as per specifications.Specification No. KBS 4.6.2 (PWD SR 2018-19 Page No. 17, Item No. 4.37)
Deductions
Itm
Description Unit. No Length L Breadth B Depth D Quantity Rate in Rs. Amount in Rs.
No.
1 2 3 4 5 6 7 8 9 10
33 KSRB 15-4.4 : Extra for providing and mixing waterproofing compound in cement plaster work at
one kg per bag or in the proportion recommended by the manufactures, for cement mortar 1:4,
18mm thick cost of materials complete as per specifications.(PWD SR 2018-19 Page No. 114 Item
No.15.26)
Qty Same as Item NO KSRB 15-3.12 534.61
Basic rate as per PWD DSR 2018-19: 8.00
Area weaightage 5%: 0.40
Total: 534.61 8.40 4491.00
34 KSRB15-3.9 : KSRB 15.3.5 : Providing 15mm thick cement plaster in single coat with cement mortar
1:4, to brick masonry including rounding off corners wherever required smooth rendering, :
Providing and removing scaffolding, including cost of materials, labour, curing complete as per
specifications. (PWD SR 2018-19 Page No. 113 Item No.15.13)
INTERIOR PLASTERING
AT ENTRANANCE LOBBY Sqm 2 3.45 - 3.60 24.84
PASSAGE/CORRIDOR Sqm 2 28.53 - 3.60 205.42
ROOMS Sqm 2 23.78 - 3.60 171.22
KITCHEN Sqm 1 23.78 - 3.60 85.61
DINNING HALL Sqm 1 33.78 - 3.60 121.61
DIGITAL ROOM Sqm 1 23.78 - 3.60 85.61
STORE ROOM Sqm 1 20.24 - 3.60 72.86
LENIN ROOM Sqm 1 16.58 - 3.60 59.69
SICK ROOM Sqm 1 16.58 - 3.60 59.69
TOILET BLOCK PASSAGE Sqm 2 7.12 - 3.60 51.26
WC/BATH ROOMS Sqm 10 6.04 - 3.60 217.44
STAIRCASE ROOM Sqm 2 7.12 - 3.60 51.26
WARDEN OFFICE Sqm 1 17.34 - 3.60 62.42
WARDEN ROOM Sqm 1 13.20 - 3.60 47.52
BATH/WC Sqm 1 9.96 - 3.60 35.86
35 KSRB 15-16.2 : Water proof cement paint KSRB 15-16.2 : Providing and finishing external walls in
one coat with waterproof cement paint of approved brand and shade to give an even shade after
throughly brooming the surface to remove all dirt and loose powdered material, free from mortar
drops and other foreign matter cost of materials, labour, complete as per specifications.do with
primer.(PWD SR 2018-19 Page No. 120 Item No.15.54.2)
Qty as per Exterior plastering Sqm 534.61
PORTICO BOTTOM SLAB Sqm FROM CAD MEASUREMENTS 44.94
Basic rate as per PWD DSR 2018-19: 51.00
Area weaightage 5%: 2.55
Total: 579.55 53.55 31035.00
36 KSRB 15-15.1 : Providing and applying painting in two coats with plastic emulsion paint of approved
brand on wall surface to give an even approved shade after throughly brushing the surface, free
from mortar drops and other foreign matter including preparing the surface even and sand paper
smooth, cost of materials labour complete as per specifications.(PWD SR 2018-19 Page No. 119
Item No.15.51)
Qty as per Exterior plastering Sqm 534.61
PORTICO BOTTOM SLAB Sqm FROM CAD MEASUREMENTS 44.94
Basic rate as per PWD DSR 2018-19: 87.00
Area weaightage 5%: 4.35
Total: 579.55 91.35 52942.00
Itm
Description Unit. No Length L Breadth B Depth D Quantity Rate in Rs. Amount in Rs.
No.
1 2 3 4 5 6 7 8 9 10
43 Providing and fixing stainless steel staircase raling with hand rail 50mm dia 16 guage hollow pipe
welded to vertical hollow 50mm dia pipe of 16 guage, stainless steel vertical pipe spaced at 1.20m
regular intervals, and 5 Nos of 25mm dia. Stainless steel hollow horizontal pipe are welded to
vertical 50mm dia hollow pipe. The entire assembly is fixed to staircase concrete by using expansion
bolts by drilling concrete etc., complete including cost of materials, labour, HOM of machineries and
electrical charges, etc., complete as per specification(PWD SR 2018-19 Page No.45, Item No.7.38)
Each 11 11.00
Basic rate as per PWD DSR 2018-19: 1050.00
Area weaightage 5%: 52.50
Total: 11.00 1102.50 12128.00
47 P/F Fret work for front Elevation (L/S)
Total: 1.00 200000.00 200000.00
Net Total : 10907288.00
Total in lakhs : 109.00
DETAILED ESTIMATE
CONSTRUCTION OF POST METRIC B.C.M HOSTEL (OLDER)
AT CHITTAWADIGI IN SURVEY NO : 249 Estimated cost: 58.00 Lakhs
AS 0.2 ACRE LAND OF HOSPET TOWN
Itm
Description Unit. No Length L Breadth B Depth D Quantity Rate in Rs. Amount in Rs.
No.
1 2 3 4 5 6 7 8 9 10
II.HOSTEL BLOCK [FIRST FLOOR]
1 KSRB 4.2.2: Providing and laying in position reinforced cement concrete of design mix M20 with OPC
cement @ 320 kgs, with 20 mm and down size graded granite metal coarse aggregates @ 0.69cum
and fine aggregates @ 0.46cum, with superplastisiser @ 3lts confirming to IS9103-1999 Reaffirmed-
2008, machine mixed, concrete laid in layers not exceeding 15 cms thick, vibrated for all works in
foundation for footings,pedastals,retaining walls,return walls,walls(any thickness) including attached
pilaster,columnspillars,posts,struts,buttresses,bed blocks,anchor blocks & plinths etc., including cost
of all materials, labour, HOM of Specifications. Specification. No. KBS 4.1,4.6( PWDSR -2018-19 Page
No.14 Item No 4.11 )
COLUMNS
RC 450X450 Cum 2 0.45 0.45 3.73 1.51
RC 230X450 Cum 42 0.23 0.45 3.73 16.19
LINTEL
LONG WALLS Cum 4 28.53 0.23 0.15 3.94
SHORT WALL Cum 14 7.12 0.23 0.15 3.44
TOILET BLOCK LONG WALLS cum 2 7.12 0.115 0.15 0.25
TOILET BLOCK SHORT WALLS cum 8 1.70 0.115 0.15 0.23
ROOF BEAM
LONG WALL Cum 5 28.53 0.23 0.45 14.76
Cum 1 25.53 0.23 0.45 2.64
SHORT WALL Cum 7 18.16 0.23 0.45 13.16
ROOF SLAB
WHOLE BUILDING Cum 1 28.53 18.16 0.125 64.76
STAIRCASE
Staircase Waist slab Cum 2 4.00 1.50 0.150 1.80
Steps Cum 21 1.50 0.150 0.150 0.71
Staircase Landing Cum 1 3.00 2.00 0.150 0.90
Staircase Beam Cum 1 3.00 0.23 0.300 0.21
DEDUCTIONS
STAIRCASE SLAB PORTION Cum -1 3.00 4.5 0.125 -1.69
Basic rate as per PWD DSR 2018-19: 5780.00
Area weaightage 5%: 289.00
LIFT CHARGES: 60.00
Total: 122.81 6129.00 752717.00
2 KSRB 4.2.10: Providing and laying in position reinforced cement concrete of design mix M20 with .
OPC cement @ 24kgs, with 12mm and down size graded granite metal coarse aggregates @
0.05175cum and fine aggregates @ 0.0345cum, with superplastisiser @ 0.225lts, machine mixed,
well compacted for plain chajja of 7.5cms. average thickness, upto ground floor level, including cost
of all materials, labour, HOM of machinery, finishing, curing, complete as per specifications.
Specification No. KBS 4.1,4.6 (PWD SR 2018-19 Page No.15, Item No. 4.19)
Chejja Sqm 2 28.53 0.60 34.24
4 8.18 0.60 19.63
Basic rate as per PWD DSR 2018-19: 443.00
Area weaightage 5%: 22.15
LIFT CHARGES: 5.00
Total: 53.87 470.15 25326.00
3 KSRB 4-2.12: Extra for providing throating or drip moulding to R.C.C. chajja with plastering (labour .
charges only) as per specifications. Specification. No. KBS(PWD SR 2018-19 Page No. 15, Item No.
4.21)
Chejja M 2 29.73 59.46
4 9.38 37.52
Basic rate as per PWD DSR 2018-19: 33.00
Area weaightage 5%: 1.65
96.98 34.65 3360.00
Itm
Description Unit. No Length L Breadth B Depth D Quantity Rate in Rs. Amount in Rs.
No.
1 2 3 4 5 6 7 8 9 10
4 KSRB 6-1.3: Providing and constructing burnt brick masonry with approved quality of non-modular
bricks of standard size of class designation 3.5N/mm²(table mounded) with cement mortar 1:6 for
basement and superstructure including cost of materials, labour charges, scaffolding, curing
complete as per specifications. Specification No.KBS 6.2(PWD SR 2018-19 Page No. 29, Item No.6.3)
MAIN WALLS
LONG WALLS Cum 3 28.530 0.23 3.15 62.01
Cum 1 25.530 0.23 3.15 18.50
SHORT WALL Cum 14 7.120 0.23 3.15 72.22
TOILET BLOCK LONG WALLS Cum 2 7.120 0.10 3.15 4.49
TOILET BLOCK SHORT WALLS Cum 8 1.700 0.10 3.15 4.28
DEDUCTIONS
DOORS
D Cum -10 1.20 0.23 2.10 -5.80
OPENING Cum -1 1.29 0.23 2.10 -0.62
D1 Cum -10 0.90 0.10 2.10 -1.89
WINDOW
W Cum -26 1.50 0.23 1.50 -13.46
VENTILATOR
V Cum -7 0.90 0.23 0.45 -0.65
V1 Cum -26 1.50 0.23 0.45 -4.04
V1 Cum -9 0.90 0.23 0.45 -0.84
COLUMN 230*450 Cum -42 0.23 0.45 3.15 -13.69
Basic rate as per PWD DSR 2018-19: 5358.00
Area weaightage 5%: 267.90
LIFT CHARGES: 60.00
Total: 120.51 5685.90 685209.00
5 KSRB 4.9.2 : Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting,
bending, hooking, placing in position, lapping and / or welding wherever required, tying with binding
wire and anchoring to the adjoining members wherever necessary complete as per design (laps,
hooks and wastage shall not be measured and paid) cost of materials, labour, HOM of machinery
complete as per specifications. Specification No. KBS 4.6.3 for TMT Bars Fe 500 (PWD SR 2018-19
Page No. 18 , Item No. 4.46.2)
Concrete Qty cum Cum 1 122.81
At 115Kg/cum = KGS 1 14123.43 14.12
CHEJJA @ 30Kg/Sqm KGS 1 1616.04 1.62
Basic rate as per PWD DSR 2018-19: 70307.00
Area weaightage 5%: 3515.35
Total: 15.74 73822.35 1161925.00
6 Providing and fixing factory made single lear rigid GRP Sandwich composite door shutter of 40 mm
thick, laminated with two GRP skins with wood grain finish, fabricated using U.V-stabilized Isopthalic
Gelcoat and one layer of 450 gns E-Glass Chopped Strand Mat(CSM) impregnated with orthopthalic
polyester resin.The thickness of the skins shall no be less than 1.5mm Expanded Polystyrene (EPS)
strucutral foam panel of 37mm thickenss and a density of 20 Kg/m3 shall be used as core material.
Wooden reinforcements made of Seasoned Salwood block of cross section not lessthan
36mmx32mm and also necessary salwood reinforcements for fixing the metal fittings such as tower
bolts, aldrops, handles,etc. shall be provided A stuctural adhesive compatible with EPS foam shall be
used for bonding the core material, the salwood reinforment and the skins. The material and process
for manufacturing the door shutters shall confirm to RV-TIFAC Composites Design Centre Standards
and specifications and the door shutters tested in confiramation to IS 4020-1994. The finish of
shutter will be plain colur White/Ivory/Beig/Light Grey or any other colour using high quality
pigments. Excluding cost of fixtures and inclusive of supply of shutters to respective work spot.(PWD
SR 2018-19 Page No. 62 Item No.9.94)
D Sqm 10 1.20 2.10 25.20
Basic rate as per PWD DSR 2018-19: 3800.00
Area weaightage 5%: 190.00
ADDITIONAL CHARGES: 6.00
Total: 25.20 3996.00 100699.00
7 KSRB 9.4-4 : Providing White sal wood frames of doors, windows, clerestory windows, ventilators
and other frames, wrought, framed or assembled including making plaster groves ( excluding cost of
cement concrete and side clamps ), but including cost of materials, labour, HOM of machineries
complete as per specifications. Specification No. KBS 9.33(PWD SR 20118-19 Page No. Page No. 51
Item No.9.13)
Door, D cum 20 1.20 0.100 0.125 0.30
20 2.10 0.100 0.125 0.53
Door, D1 cum 10 0.90 0.075 0.125 0.08
20 2.10 0.075 0.125 0.39
Basic rate as per PWD DSR 2018-19: 61672.00
Area weaightage 5%: 3083.60
Total: 1.30 64755.60 84385.00
Total:
Itm
Description Unit. No Length L Breadth B Depth D Quantity Rate in Rs. Amount in Rs.
No.
1 2 3 4 5 6 7 8 9 10
8 KSRB 9-27.1 : Fixing of door frame in an existing opening including embeeding frame in floor and
walls after cutting masonry for holdfasts for embedding holdfast in cement concrete 1:3:6 of 20mm
and down size granite metal painting two coats of coal tar to sides of frame, making good the
damages to walls and floor as required and disposal of the debries with lead upto 50 m including
cost of materials, labour charges, complete as per specifications.(PWD SR 2018-19, Page No. 60
Item No.9.80)
Doors Nos 20 20.00
Basic rate as per PWD DSR 2018-19: 1370.00
Area weaightage 5%: 68.50
Total: 20.00 1438.50 28770.00
9 "PVC DOOR SHUTTER (Nandi or Equivalent) Supply and fixing of door shutters made of rigid PVC
extruded hollow section (Nandi or equivalent) of 20mm x 200mm with the wall thickness of
1.0mm+/0.1mm equally divided into 4no's with tongue and groove locking arrangements. the
shutter frame is made of 58x24 mm with the wall thickness of 1.5mm+/ -0.15mm section metricut
and joined at 4 corners with 125mmx225mm plastic brackets. the shutter shall be horizontally
reinforced inside the door shutter during the fabrication of the door shutter at those points wherever
the hardware is fixed on to the door shutter.(PWD SR 2018-19 Page No. 61 Item No.9.86)
WINDOW
W KGS 26 1.50 23.00 1.50 1345.50
V KGS 7 0.90 23.00 0.45 65.21
V1 KGS 26 1.50 23.00 0.45 403.65
V1 KGS 9 1.50 23.00 0.45 139.73
SECURITY GRILL WORK KGS 2 3.00 30.00 3.15 567.00
Basic rate as per PWD DSR 2018-19: 95.00
Area weaightage 5%: 4.75
LIFT CHARGES: 6.00
Total: 2521.08 105.75 266604.00
11 KSRB 15-18.2 : Providing and applying enamel metal paint two coats (excluding priming coat) over
new steel or other metal surface brushing to give an even shade after cleaning oil, grease, dirt and
other foreign matter, including cost of materials, labour, complete as per specifications.(PWD SR
2018-19 Page No. 123 Item No.15.74)
Itm
Description Unit. No Length L Breadth B Depth D Quantity Rate in Rs. Amount in Rs.
No.
1 2 3 4 5 6 7 8 9 10
13 Providing and fixing Special make glazed Vitrified tiles (Granomite finish) of approved make, quality
and colour of size 600x600x10mm thick fixed on existing flooring with a special adhesive for flooring,
skirting & jointed with neat cement slurrry mixed with pigment to match shade of tiles complete
including providing spacers at requred intleval and removing stains etc., cost of materials, mortar,
labour etc., complete as per specification(PWD SR 2018-19 Page No. 109 Item No.14.43)
16 KSRB 14-17.1 : Providing skirting, dado, rises of steps with white glazed tiles 6mm thick on 10mm
thick cement plaster 1:3 and jointed with white cement slurry over rough plaster surface (excluding
cost of rough plastered surface which should be measured and paid separately) using glazed tiles of
approved make and size including cost of materials, labour, complete as per
specifications.Specification No. KBS 14.1614.17(PWD SR 2018-19 Page No. 108 Item No.14.40)
SKIRTING, DADO, RISES
TOILET BLOCK PASSAGE Sqm 1 14.70 2.100 30.87
WC/BATH ROOMS Sqm 10 6.04 2.100 126.84
Staircase(Treads) Sqm 20 2.00 0.30 12.00
Staircase(Rise) Sqm 21 2.00 0.15 6.30
Staircase Landing Sqm 1 3.00 1.50 4.50
PASSAGE/CORRIDOR Sqm 2 28.530 0.15 8.56
ROOMS Sqm 9 23.780 0.15 32.10
ROOMS Sqm 1 20.240 0.15 3.04
DEDUCTIONS
TOILET ROOM DOOR DEDUCTIONS
D1 Sqm -10 0.90 2.10 -18.90
Basic rate as per PWD DSR 2018-19: 1166.00
Area weaightage 5%: 58.30
LIFT CHARGES: 2.00
Total: 205.31 1226.30 251769.00
Itm
Description Unit. No Length L Breadth B Depth D Quantity Rate in Rs. Amount in Rs.
No.
1 2 3 4 5 6 7 8 9 10
17 KSRB 4-6.2 : Providing and removing centering, shuttering, strutting, propping etc., and removal of
form work for flat surface such as roofs, landings, balconies and likes, thickness upto 200 mm
including cost of all materials, labour complete as per specificaitons.up to 3.50m from Ground level.
Specification No. KBS 4.6.2(PWD SR 2018-19 Page No. 16, Item No. 4.29)
Roof slab(Same as Flooring Qty) Sqm 465.97
Slab Sides Sqm 1 94.28 0.150 14.14
Staircase slab landing 1 3.00 1.50 4.50
Staircase Slab sides Sqm 2 1.50 3.00
Basic rate as per PWD DSR 2018-19: 408.00
Area weaightage 5%: 20.40
LIFT CHARGES: 25.00
Total: 487.61 453.40 221081.00
18 KSRB 4-6.11: Providing and romoving centering, shutting, strutting, propping etc., and removal of
form work for stairs (excluding landing) except spiral staircase including cost of all materials, labour
complete as per specifications.Specification No. KBS 4.6.2(PWD SR 2018-19 Page No. 17, Item No.
4.38)
Staircase slab 1 3.00 4.50 13.50
Basic rate as per PWD DSR 2018-19: 556.00
Area weaightage 5%: 27.80
LIFT CHARGES: 25.00
Total: 13.50 608.80 8219.00
19 KSRB 4-6.7: Providing and romoving centering, shutting, strutting, propping etc., and removal of
form work for sides and soffits of beams, beam haunchings,cantilever girders, bressumers and lintels
not exceeding 1m in depth including cost of all materials, labour complete as per
specifications.Specification No. KBS 4.6.2 (PWD SR 2018-19 Page No. 17, Item No. 4.34)
ROOF BEAM
Sqm 5 28.53 1.13 161.19
Sqm 1 25.53 1.13 28.85
Sqm 7 18.16 1.13 143.65
LINTEL
Sqm 4 28.53 0.30 34.24
Sqm 14 7.12 0.30 29.90
Sqm 2 7.12 0.30 4.27
Sqm 8 1.70 0.30 4.08
Basic rate as per PWD DSR 2018-19: 292.00
Area weaightage 5%: 14.60
LIFT CHARGES: 25.00
Total: 406.18 331.60 134690.00
20 KSRB 4-6.5: Providing and romoving centering, shutting, strutting, propping etc., for columns,
pillars, post and struts, square/rectangular/polygon in plan including cost of all materials, labour
complete as per specifications. Specification No. KBS 4.6.2 (PWD SR 2018-19 Page No. 16, Item
No. 4.32)
RC 230X450 Sqm 42 1.36 3.73 212.77
Basic rate as per PWD DSR 2018-19: 456.00
Area weaightage 5%: 22.80
LIFT CHARGES: 25.00
Total: 212.77 503.80 107195.00
21 KSRB 4-6.10: Providing and romoving centering, shutting, strutting, propping etc., and removal of
form work for chajjas, corbels etc.,including edges including cost of all materials, labour complete
as per specifications.Specification No. KBS 4.6.2 (PWD SR 2018-19 Page No. 17, Item No. 4.37)
Itm
Description Unit. No Length L Breadth B Depth D Quantity Rate in Rs. Amount in Rs.
No.
1 2 3 4 5 6 7 8 9 10
22 KSRB15-3.12 : Providing 18mm thick cement plaster in single coat with cement mortar 1:4, to brick
masonry including rounding off corners wherever required smooth rendering, : Providing and
removing scaffolding, including cost of materials, labour, curing complete as per specifications.(PWD
SR 2018-19 Page No. 116 Item No.15.16)
EXTERIOR PLASTER
LONG WALL SQM 2 28.53 3.73 212.55
SHORT WALL SQM 4 7.58 3.73 112.94
PARAPET WALL SQM 2 28.53 1.95 111.27
SQM 2 18.61 1.95 72.58
CHEJJA SQM 1 39.11 1.33 51.82
Deductions
W SQM -13.0 1.50 1.50 -29.25
V SQM -3.5 0.90 0.45 -1.42
V1 SQM -13.0 1.50 0.45 -8.78
Basic rate as per PWD DSR 2018-19: 256.00
Area weaightage 5%: 12.80
SCAFFOLDING CHARGES: 12.00
Total: 660.36 280.80 185429.00
23 KSRB 15-4.4 : Extra for providing and mixing waterproofing compound in cement plaster work at
one kg per bag or in the proportion recommended by the manufactures, for cement mortar 1:4,
18mm thick cost of materials complete as per specifications.(PWD SR 2018-19 Page No. 114 Item
No.15.26)
Qty Same as Item NO KSRB 15-3.12 660.36
Basic rate as per PWD DSR 2018-19: 8.00
Area weaightage 5%: 0.40
Total: 660.36 8.40 5547.00
24 KSRB15-3.9 : KSRB 15.3.5 : Providing 15mm thick cement plaster in single coat with cement mortar
1:4, to brick masonry including rounding off corners wherever required smooth rendering, :
Providing and removing scaffolding, including cost of materials, labour, curing complete as per
specifications. (PWD SR 2018-19 Page No. 113 Item No.15.13)
INTERIOR PLASTERING
ROOMS Sqm 9 23.78 - 3.60 770.47
ROOM Sqm 1 20.24 - 3.60 72.86
STAIRCASE ROOM Sqm 1 14.24 - 3.60 51.26
PASSAGE/CORRIDOR Sqm 2 28.53 - 3.60 205.42
TOILET BLOCK PASSAGE Sqm 2 7.12 - 3.60 51.26
WC/BATH ROOMS Sqm 10 6.04 - 3.60 217.44
ROOF BEAM Sqm 7 3.00 - 1.13 23.73
Sqm 10 4.77 - 1.13 53.90
Sqm 1 3.00 - 1.13 3.39
Deduction
TOILET BLOCK PASSAGE Sqm -1 14.70 - 2.10 -30.87
WC/BATH ROOMS Sqm -10 6.04 - 2.10 -126.84
D Sqm -10.0 1.20 - 2.10 -25.20
O Sqm -1.0 1.00 - 2.10 -2.10
D1 Sqm -10.0 0.90 - 2.10 -18.90
W Sqm -13.00 1.50 - 1.50 -29.25
V Sqm -3.50 1.50 - 1.50 -7.88
V1 Sqm -13.00 1.50 - 1.50 -29.25
V1 Sqm -9.00 0.90 - 0.45 -3.65
Basic rate as per PWD DSR 2018-19: 217.00
Area weaightage 5%: 10.85
LIFT CHARGES: 6.00
Total: 1175.81 233.85 274963.00
31 Providing and casting reinforced cement concrete racks with design mix M20, granite or trap jelly 12
mm and down size 5 cms thick and below with reinforcements of 6 mm dia MS bars at 15 cms.
Centre to centre for main reinforcement and at 30 cms centre to centre for distribution including
supports wherever necessary with burnt brick in CM 1:4 including centring, form work, curing etc.,
complete (Inclusive of cost of steel and fabrication charges)(PWD SR 2018-19 Page No.19, Item No.
4.53)
ROOM Sqm 9 2.50 2.10 47.25
ROOM Sqm 1 1.50 2.10 3.15
Basic rate as per PWD DSR 2018-19: 984.00
Area weaightage 5%: 49.20
Total: 50.40 1033.20 52073.00
32 Providing and fixing stainless steel staircase raling with hand rail 50mm dia 16 guage hollow pipe
welded to vertical hollow 50mm dia pipe of 16 guage, stainless steel vertical pipe spaced at 1.20m
regular intervals, and 5 Nos of 25mm dia. Stainless steel hollow horizontal pipe are welded to
vertical 50mm dia hollow pipe. The entire assembly is fixed to staircase concrete by using expansion
bolts by drilling concrete etc., complete including cost of materials, labour, HOM of machineries and
electrical charges, etc., complete as per specification(PWD SR 2018-19 Page No.45, Item No.7.38)
Quantity Takeoff: The foundation for a successful estimate relies upon reliable
identification (takeoff) of the quantities of the various materials involved in the project.
Labor Hours: Labor hour amounts can be developed by crew analysis or applied on a unit
man-hour basis. The use of a labor dollar per unit of work (ex: $15 per cubic yard for grade
beams or $20 per cubic yard for walls) is only applicable when the cost history supports the
data being used. The estimator must make allowance for the varying production capability
that will occur based upon the complexity of a project.
Labor Rates: The labor rate is the cost per hour for the craftsmen on the project. To
determine any craft rate, whether union or open shop, the estimator starts with the basic
wages and fringe benefits.
To the wages and fringe benefits, the estimator must add payroll burdens. These are
FICA (Social Security), FUI (Federal Unemployment Insurance), SUI (State
Unemployment Insurance), WC (Worker Compensation) and others mandated by
legislation and/or company operations. These burdens, plus the base wages and fringe
benefits, determine the hourly cost of a craft classification (i.e., carpenter, pipefitter,
etc.).
The hourly rate can also involve a mixed crew where a mix of different crafts for a
work crew for the performance of the work.
Overtime or the lack of overtime is another consideration in determining the
calculation of the hourly rates. A project that is scheduled for completion using a forty
hour work week (Some areas may have a standard 35 hour week) will have a modest
amount of overtime costs required in the estimate. A project that is scheduled for
extended 50, 60 or even 70 hour work weeks will have a substantial amount included
for overtime and loss of productivity.
Material Prices: Material prices, especially in today's current market, fluctuate up and down.
The estimator must both understand and anticipate the frequency and extent of the price
variations and the timing of the buying cycle. Material prices may be affected by:
physical requirements for delivery, such as distance, road size, or site access
payment terms and history on previous purchases
sole-source items
Exchange rates (if the material will be imported into the U.S.)
Equipment Costs: Equipment rates depend on the project conditions to determine the correct
size or capacity of equipment required to perform the work. When interfacing with other
equipment, cycle times and equipment capacity control the costs on the project. Costs will
also differ if the equipment is owned by the contractor as opposed to rent.
Subcontractor Quotes: A subcontractor quote, like the general estimate, contains labor,
material, equipment, indirect costs, and profit. It is dependent upon having the quantities,
labor hours, hourly rate, etc., prepared in a reliable manner just like any other part of an
estimate. The amount of the subcontractor quote is also dependent upon the payment terms of
the contract, and previous payment history between the subcontractor and general contractor.
Bonding costs should also be considered.
Indirect Costs: Indirect costs consist of labor, material, and equipment items required to
support the overall project.
For the owner: design fees, permits, land acquisition costs, legal fees, administration
costs, etc.
For the contractor and subcontractor: mobilization, staffing, on-site job office,
temporary construction, temporary heat/cooling, and temporary utilities, equipment,
small tools and consumables, etc.
Profit Amount: Apply appropriate or contracted profit rate uniformly to all contractors and
to original bid and change orders.
CHAPTER 10
CONCLUSION
This project report has sought to give details of the components of a multi-storey
building and an idea of structural components can be achieved when structural
drawings are read.
ETABS was used for the analysis for all loading combinations since it reduces the
time consumption and gives required accurate results, but when it comes to designing,
ETABS gives uneconomical design and hence manual design is adopted.
The Detailing of Reinforcement is made as per IS- code provision which provides
Ductility to the Structure and hence better performance.
All the structural components are checked to satisfy the serviceability criteria and
hence provided dimension of all structural components are adequate.
From the “Analysis and design”, we can estimate the cost of whole structure before
the work is to be executed. Hence the appropriate cost of whole building will be
known in advance.
CHAPTER 12
Shear walls and lateral bracing can also be provided to make the structure safer
against earthquake load and their influence in the analysis can be considered.
Low cost building material and their strength can be used in multi storey buildings to
achieve overall economy of structures.
The above project can further planned using the project management tools like
Primavera Project Planner or Microsoft project and can be managed and monitored
during execution to achieve fast and efficient execution.
CHAPTER 13
REFERENCE
Divya Bahraini HOD Nova College of Engineering and Technology: “Optimized
Design of a G+20 Storied Building Using ETABS” .There is a gradual increase in the
value of lateral forces from bottom floor to top floor in software analysis.
Rohit kumar.B.R. : Analysis and design of Multi storey Structure Using ETABS
(IRJET).” The analysis and design results obtained from software are safe when
compared with manual calculations and design”.
IS: 875-1987 (Part 1) – 1987, Code of Practice for Design Loads (other than
earthquake) for buildings and structures.
IS: 875-1987 (Part 2) – 1987, Code of Practice for Design Loads (other than
earthquake) for buildings and structures - Imposed loads.