Session 2 Session 2: Introduction To Project Management Introduction To Project Management
Session 2 Session 2: Introduction To Project Management Introduction To Project Management
Session 2 Session 2: Introduction To Project Management Introduction To Project Management
Session 2
Introduction to Project Management
• Issues and Strategic challenges in project management
• Essential skills and attribute of Project Managers
• Modern Practices in Project Management
• Components of Project Charter and Project Management Plan
• Project Planning, Project organization and control
1
6/28/2019
2
6/28/2019
What is a Project?
“Unique process consisting of a set of coordinated and
controlled activities with start and finish dates, undertaken to
achieve an objective conforming to specific requirements,
including constraints of time, cost, quality and resources”
3
6/28/2019
Exercise 1
ATTRIBUTES OF PROJECTS
• Unique purpose
• Temporary; means it has a
specific start and finish
• Require resources, often
from various areas
• Should have a primary
sponsor and/or customer
• Involve uncertainty
4
6/28/2019
What a project is
What project is not
5
6/28/2019
Stakeholder Engagement
Stakeholder
6
6/28/2019
Exercise 2
7
6/28/2019
• Identify Stakeholders
• Assess needs
• Define actions
• Establish communication channels
• Gather feedback
• Monitor and review
Initiate Project
Prepare Technical Design
Ensure Machine Compatibility Prepare
Safety Case Modification
Undertake Tender
Project
set-up Project
Major
Definition Conceptual
Project Scheme
Design
Proposals Design Detailed Tender
Appoint Project Sponsor Design Invitation &
Assess Project Priority
Assess Budget Implications
Est. Proj. Deliverables and Objectives
Raise/Extend/Update initial TCD-R/PERF Assessment
Prepare Outline Conceptual Design
Appoint Project Leader
Define Design Constraints Prepare Extend TCD-Rs/PERFs
Approve Project Set-up
Interface Requirements Spec. (IRP) Prepare Sub-system Detailed Design Hold
Finalise Conceptual Design Detailed Design Review (DDR)
EFDA/CSU/JOC Management Hold Conceptual Design Review (CDR) Clear Sub-system DDR Issues
Clear CDR Issues Use TCD-I/MMAC for Sub-system DD Approval
Initiate Modification Safety Case Prepare Final Documents including:
Update PMP - Design Documents., Machine Compatibility *** These will comprise:
Approve Proceed to Detailed Design Documents., Safety Case Modification - Technical Specification
- Drawings
Project Team/IRP/EFDA/CSU/JDC Project Team/Interfaces/EFDA/CSU/JDC - Contractual Requirements
UNCONTROLLED
Complete Release Note Project Team/ICM/EFDA/CSU
Approve Complete Package**** Project Review
Approve Release Note
Pack & Dispatch Equipment Project Team/CSU
WHEN PRINTED
Confirm Technical Completion
Receive Equipment
Project Team/Contractor/ICM Review Project Records Complete
Pre-test Equipment
Handover Documents Resolve
Install equipment
Reservations Obtain
Acceptance of Completed Project
**** This includes Project Team/ICM
supporting documentation
Project Team/EFDA/CSU
8
6/28/2019
9
6/28/2019
Project Planning
Project Planning
• Adequate planning leads to the correct completion of
work
10
6/28/2019
Planning
• Inadequate planning leads to frustration
towards the end of the project & poor project
performance
11
6/28/2019
Bulk W Bulk Metal Torus Installation Contractual Prepare & Ship Bulk Metal Tiles Erosion/Deposition
Divertor Tiles Group Management JET Be Install Prep. Assemby & Calib.
1.1.2.0.0 1.2.2.0.0 1.3.2.0.0 1.4.2.0.0 1.5.2.0.0 1.6.2.0.0 1.7.2.0.0
R&D Engineering D&M ILW Tile Removal FZJ Contract Install Prep.
Management Management & Replacement Management Management
1.1.5.0.0 1.2.5.0.0 1.3.5.0.0 1.4.5.0.0 1.6.5.0.0
12
6/28/2019
Thomson Scattering
Core (LIDAR)
5.5.C.1.0.0.0.0
LIDAR Project LIDAR System Laser Collection Laser Path Control & LIDAR LIDAR Interfaces &
Management Concepts Systems Optics Optics Acquisition Port Engineering Services Integrated Testing
1.1.0.0.0 1.2.0.0.0 1.3.0.0.0 1.4.0.0.0 1.5.0.0.0 1.6.0.0.0 1.7.0.0.0 1.8.0.0.0 1.9.0.0.0
Key Project Overall Cluster Lasers Collection Laser Path Control System Shutters Water LIDAR
Milestones Co-ordination 1.3.1.0.0 Optical Design Optical Design Interface Definition 1.7.1.0.0 Services Interfaces
1.1.1.0.0 1.2.1.0.0 1.4.1.0.0 1.5.1.0.0 1.6.1.0.0 1.8.1.0.0 1.9.1.0.0
Key Project Performance Laser Collection Laser Control Labyrinth Interspace Mock-up
Deliverables Analysis Layout Windows Windows System 1.7.2.0.0 Vacuum Facility
1.1.2.0.0 1.2.2.0.0 1.3.2.0.0 1.4.2.0.0 1.5.2.0.0 1.6.2.0.0 1.8.2.0.0 1.9.2.0.0
Key ITER LIDAR Laser Beam In-Vacuum Plasma Facing Acquisition Extension Tubes & LIDAR Basic Mock-up
Milestones & IPL Neutronics Combiner Collection Mirrors Laser Mirrors System Mirror Mounting Power Tests
1.1.3.0.0 1.2.3.0.0 1.3.3.0.0 1.4.3.0.0 1.5.3.0.0 1.6.3.0.0 1.7.3.0.0 1.8.3.0.0 1.9.3.0.0
Overall Scattering Ex-Vacuum Other Laser LIDAR External Port Optics Spectrometer Tokamak
Management Theory Collection Optics Mirrors Instrumentation Mounting Area Tests
1.1.4.0.0 1.2.4.0.0 1.4.4.0.0 1.5.4.0.0 1.6.4.0.0 1.7.4.0.0 1.8.4.0.0 1.9.4.0.0
Safety & HP R&D Collection Optics Laser Path Safety Bioshield Laser Final System
Management Tasks Mechanical Design Mechanical Design Interlocks 1.7.5.0.0 Room Testing
1.1.5.0.0 1.2.5.0.0 1.4.5.0.0 1.5.5.0.0 1.6.5.0.0 1.8.5.0.0 1.9.5.0.0
Risk Radiation Spectrometer Beam Safety BSM Port Cell/ System Assembly
Management Effects Data System Dump System Penetrations Interspace & Dis-assembly
1.1.6.0.0 1.2.6.0.0 1.4.6.0.0 1.5.6.0.0 1.6.6.0.0 1.7.6.0.0 1.8.6.0.0 1.9.6.0.0
Engineering Calibration
Analysis System
1.2.9.0.0 1.4.9.0.0
13
6/28/2019
Project Planning
A word about Scheduling
– Schedules (task durations) can have a wide
variation
– There is no unique answer. Rather, there is a
statistical variation depending on assumptions
– Need to understand the basis of scheduling
(Most challenging; Most likely; Absolute certainty
- bet your life on it!)
– Most people are very optimistic/naive
14
6/28/2019
100
90
80
Subsequent
70 Estimates
Probability
60
50
40
30 First
Estimate
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Timescale
15
6/28/2019
16
6/28/2019
Risk Impact
17
6/28/2019
• Identify Risks
• Assess likelihood and impact
• Rank risks and prioritise
• Define risk management approach & actions
• Implement actions
• Monitor & review
18
6/28/2019
19
6/28/2019
Exercise 3
Project Monitoring
• Typical Monitoring Activities
– regular reviews of progress against schedule using
WBS as basis (Plan against Baseline)
– regular review of actual costs (O/P from SAP) against
budgeted costs and Earned Value at WBS level
– regular review of resource loading
– regular progress meetings with project team
– regular meetings with contractors
– production of periodic progress reports
– risk reviews
– inspections/ audits
20
6/28/2019
Project Control
• Typical Control Activities
– assign responsibilities at Work Package level
– staged authorisation of work to be done
– staged release of budgets (staged release of WBS(e)
numbers)
– ensure PM has a ‘Management Reserve’ under his
control
– seek corrective action reports when WPs go ‘off
track’ (overrunning or overspending)
– release Management Reserve carefully
PROJECT CONSTRAINTS
21
6/28/2019
• Un realistic deadline
Un realistic deadline
• A KPMG study found
A KPMG studythat
found that 60% of failed
projects have a deadline of less than a year
60% of failedScope
projects
Creep have
a deadline ofAccording
less than to TheaState of Project
Management Annual Survey 2016 conducted
year by Wellingtone, more than 34% projects have
• Scope Creep no baseline.
• According to The State of
Project Management
Annual Survey 2016
conducted by Wellingtone,
• more than 34% projects
have no baseline.
22
6/28/2019
No risk management
23
6/28/2019
24