PAM Contract (High Court Case)
PAM Contract (High Court Case)
PAM Contract (High Court Case)
BETWEEN
AND
BETWEEN
AND
1
[2018] 1 LNS 2105 Legal Network Series
THE JUDGMENT OF
Y.A. LEE SWEE SENG
[1] There were two trials that were heard together because they were
related. The first was a 2017 Suit between Itagres Sdn Bhd (“Itagres”)
v. Mix Target Sdn Bhd (“Mix Target”) and the second was a 2016 Suit
between Mix Target v. Najcom Sdn Bhd (“Najcom”).
[3] Najcom was the Subcontractor for the Works having been
appointed by UEM Builder - Najcom JV (“UNJV”), the Main Contractor
for the same contract sum. UNJV had earlier on 11.3.2014 been awarded
a contract by the Employer Konsortium ProHAWK Sdn Bhd for the
design, construction, completion, testing and commissioning of the said
Project for a total fixed lump sum of RM92,000,000.00 with respect to
Mechanical Works.
Problem
2
[2018] 1 LNS 2105 Legal Network Series
work carried out and completed to Najcom for payment. Najcom in turn
submitted the Progress Claims to UNJV for assessment and
certification.
[7] As Mix Target was repeatedly falling behind time to complete the
different floors and in particular the 3 rd floor by 20.2.2015 and 4 th floor
by 7.3.2015, Najcom had terminated Mix Target on 31.3.2015 after
many reminders to catch up with the revised schedule of completion but
to no avail.
[8] In the meanwhile Mix Target had failed to pay Itagres under the
supply of labour/workers contract for the Works to the tune of
RM731,000.00 being amount outstanding for the supply of labour to
install the Fire Fighting System.
Prayers
[9] In the 2017 Suit Itagres had claimed for RM731,000.00 for the
amount outstanding under the supply of labour/workers contract with
Mix Target.
[10] Mix Target denied owing the said sum and labour supplied to carry
out the subcontract work. Mix Target contended that they had overpaid
Itagres based on the payment received from Najcom. They further
pleaded that Itagres had agreed that they would be paid after Mix Target
had been paid by Najcom.
[11] In the 2016 Suit Mix Target had claimed for the balance sum of
RM2,650,360.10 due and owing for the work carried out and completed
3
[2018] 1 LNS 2105 Legal Network Series
(a) Balance progress claim due and owing by Najcom in the sum
of RM2,650,360.10;
(d) Costs.
4
[2018] 1 LNS 2105 Legal Network Series
[13] The Defence of Najcom was that Mix Target had over claimed for
the Works done as they had unilaterally changed the rationalized rates
by heavy front loading such that their rates were materially out of sync
with the rates between UNJV and Najcom for the same Fixed Lump Sum
Contract of RM9.9 million.
[14] Najcom maintained that the termination was valid and also
counterclaimed for the extra costs incurred in engaging another rescue
Subcontractor to finish the Works and for the costs incurred in
rectifying the Works completed by Mix Target.
Proceedings
[15] Itagres called one witness who is Kelvin Chew Weng Keong in the
2017 Suit. Mix Target witnesses in both the 2017 Suit and 2016 Suit
were:
5
[2018] 1 LNS 2105 Legal Network Series
[17] Both Mix Target and Najcom did not execute a PAM Contract after
the LoA and at the trial learned counsel for Mix Target informed the
Court that he was not proceeding under the premise that the terms of the
PAM Contract should apply.
Principles
[18] Mix Target appointed Itagres to supply labour for the installation
of the Fire Fighting System Works. The appointment was contained in
the following documents:
Less RM310,000.000
6
[2018] 1 LNS 2105 Legal Network Series
7
[2018] 1 LNS 2105 Legal Network Series
[21] Mix Target did not deny receiving the various Progress Claims as
can be seen in paragraph 2.1 of Mix Target‟s Statement of Defence.
Therefore Itagres had claimed against Mix Target for:
[23] As Itagres is not a party to the contract between Mix Target and
Najcom, and neither has Itagres agreed to the claims as may be
submitted by Mix Target and as may be approved by Najcom, this Claim
has to be decided based on the terms of payment agreed between Itagres
and Mix Target as provided in the Purchase Order dated 13.10.2014
which reads as follows:
1. …
2. …
4. …”
8
[2018] 1 LNS 2105 Legal Network Series
[24] I agree with learned counsel for Itagres that this contention is
untenable. There is no term of payment that states that the payment is
conditional upon the certification of Mix Target‟s claim by Najcom.
Mix Target therefore cannot argue that it was the intention of the parties
that the payment to Itagres is made conditional upon certification of Mix
Target‟s Claim by Najcom. I agree with Itagres that if this was the
intention, the provision in the Purchase Order would not have provided
that payment is made progressively within 45 to 60 days.
[25] The evidence showed that Mix Target made payment irrespective
of Najcom‟s certification of Mix Target‟s work. Learned counsel for
Itagres summarized the following evidence to establish that Itagres‟
payment is not subject to Mix Target‟s claim being certified by UNJV or
Najcom and that Mix Target intended it to be so as follows:
9
[2018] 1 LNS 2105 Legal Network Series
b. Itagres made its third claim after the second claim went
unpaid. The third claim was dated 5.1.2015 (see page 97 and
98 of CBOB 7). The value of the third cumulative claim
(including the 2 nd claim) is RM211,127.34. Mix Target
subsequently submitted their claim encompassing the 3 rd
claim in January 2015 (see page 547 of CBOD 2). Mix
Target‟s claim based on this claim is RM978,222.88.
Najcom claimed from UNJV thereafter. UNJV certified the
claim on 22.1.2015 (COP 7 at page 72 to 74 of CBOD 4).
10
[2018] 1 LNS 2105 Legal Network Series
[26] Learned counsel for Itagres submitted that the intention of the
parties is deduced from the words used in the written contract.
Construction of a document is an issue of law. Further, the object in the
construction of documents is to ascertain the true intentions of the
parties as manifested by the language they have employed in the
document and not by their subjective intentions. That is to say the
meaning accorded shall be based on the meaning of the words used and
not based on what the parties would want it to mean.
[27] Learned counsel for Itagres referred to the case of Hotel Anika Sdn
Bhd v. Majlis Daerah Kluang Utara [2006] 4 CLJ 981 at paras [20] to
[35] which provided a useful summary of the applicable principles in the
interpretation and construction of contracts and specifically at para [31]
& [32] as follows:
11
[2018] 1 LNS 2105 Legal Network Series
12
[2018] 1 LNS 2105 Legal Network Series
[28] It would be fair to say that giving the words used its natural and
ordinary meaning, it is clear that Mix Target intended to pay and Itagres
expected to receive payment progressively and not subject to
certification of Mix Target‟s claim by Najcom/UNJV.
[29] This was further confirmed by the conduct of Mix Target issuing
certificates of payment and making payments even before
Najcom/UNJV issued their certifications.
[31] PW2 Ahmad Fitri Bin Zainal Abidin, the Project Director of Mix
Target, also admitted that the work stated in Progress Claim 1 to
Progress Claim 5 above were indeed completed by Itagres.
[32] This is a clear departure from Mix Target‟s Defence wherein they
had pleaded that there were repeated delays in the Works and that at the
13
[2018] 1 LNS 2105 Legal Network Series
point of termination Najcom had only certified 11% of what Mix Target
had claimed. Mix Target stated that they had only been paid
RM324,675.00 by Najcom as at the date of termination.
[35] If Mix Target was serious on the overpayment this was not
reflected at all in their Defence filed as there was no set-off or
Counterclaim pleaded together with the Defence.
[37] Itagres had contracted with Mix Target not on the basis of what
would be certified, approved and paid by Najcom. If that was the basis
then it should be written into the contract between Itagres and Mix
Target. Itagres‟ contract was for a pure supply of labour save for some
supplies of conduits and cabling. There was no “pay when paid clause”
or a “back to back” payment from Najcom before Mix Target needed to
make payments to Itagres. At any rate it was not pleaded by Mix Target
as such. It was thus too late for the two father and son witnesses in PW
14
[2018] 1 LNS 2105 Legal Network Series
1 Encik Zainal Abidin Bin Mamat and PW 2 Encik Ahmad Fitri Bin
Zainal Abidin to say in Court that the obligation of Mix Target to pay
Itagres was after Mix Target has been paid.
[38] It would be different if the Works had been rejected by Najcom for
defects and as would be seen later in the Claim by Najcom against Mix
Target this Court had dismissed their claim for defective works as not
having been proved. Mix Target here had not pleaded that Itagres‟ Work
was defective or that they had incurred costs to rectify defective works.
[41] Be that as it may, this Court can accept the admission made by Mix
Target at the trial and enter judgment accordingly against Mix Target
for what was essentially not disputed except that Mix Target now said
that Itagres‟ claim is subject to Najcom‟s approval, certification and
payment.
[42] There is no express term on that and as for implied term, it is not
pleaded. Neither is it a Defence of or a Counterclaim for
misrepresentation, whether innocent, negligent or fraudulent that Mix
Target had pleaded against Itagres.
15
[2018] 1 LNS 2105 Legal Network Series
[45] With respect to evidence of their workers having done the work for
which Itagres had claimed, general worker‟s wage sheet and wage
16
[2018] 1 LNS 2105 Legal Network Series
[46] The supply of workers was also corroborated by the site daily
report found in PBOD 1 and at pages 122 to 177 of CBOD 8 are found
the general workers wages sheet.
[48] The materials for Level 3 and Level 4 were delivered on 5 th , 6 th and
7 th of February 2015 according to DW 8 Haja Najmudeen, the Managing
Director of Najcom (Q&A 23 of his Witness Statement). Najcom in their
letter dated 17.3.2015 (page 789 CBOD 3) had confirmed that the
materials supplied before the date of the letter had been used or
installed. Mr Kelvin Chew, the Managing Director of Itagres, testified
that all the materials delivered to site had been installed by them and
17
[2018] 1 LNS 2105 Legal Network Series
they were waiting for Mix Target to supply further materials for the
Works to be expedited.
Whether Mix Target had proved the value of the Work done of
RM2,975,035.10
[50] The amount claimed by Mix Target against Najcom is for the
balance of RM2,269,072.68 after deducting RM324,675.00 being
payment received from Najcom.
[51] In the course of executing the Works Mix Target had submitted 6
Progress Claims and a Final Claim after termination for the cumulative
sum of RM2,269,072.68 which is about 30% of the Contract Sum. They
are tabulated below with the relevant pages in Mix Target‟s Core Bundle
(“CB”) as follows:
No. Date Amount claimed Refer
(RM)
1. 22.10.2014 219,830.00 1 – 65 CB-1
2. 19.11.2014 911,060.00 66 – 135 CB-1
18
[2018] 1 LNS 2105 Legal Network Series
[52] Between Najcom and the Employer the following are the relevant
Certificates of Payment:
No. Certificate Dated Bundle Page
No.
4. 11 19-03-2015 CBOD5 1 ~2
[53] Najcom‟s evidence was that they relied and indeed are bound by
the Certificates of Payment issued by the Employer and that Mix Target
was aware that payments to them would be based on those Certificates
issued for finally the Fire Fighting System Works must be assessed,
verified and accepted by the Main Contractor and the Employer as stated
in the LoA with Mix Target.
[54] It is against that backdrop that I would not place so much emphasis
on the fact that Mix Target‟s Progress Claims were not rejected by
Najcom but rather that Mix Target knew for a fact that whatever may be
the amount claimed under their Progress Claims must be certified by the
Main Contractor and Employer.
[55] That explains why there was no written complaint from Mix
Target if indeed they were waiting for Najcom‟s certification that did
not come or that they were paid less than the amounts claimed. Najcom
themselves admitted that they did not have any consultants to certify the
19
[2018] 1 LNS 2105 Legal Network Series
progress of the Works done but rather relied on and are bound by the
certification done by the independent consultants engaged by the
Employer and DW 6 and DW 7 were part of the consultants team that
were subpoenaed by Najcom to come to Court and give evidence.
[56] Najcom disagreed with the amount claimed. Take for example
Progress Claim No.1 dated 22.10.2014 wherein Mix Target had claimed
RM219,830.00 as at 22.10.2014 for the Sprinkler System done for Level
2.
[57] The Senior Project Manager in DW 2 said the Defendant did not
accept this sum claimed but rather is bound by the Certification done by
the consultant of the Main Contractor that only certified the Works done
by Mix Target as at end of 30.10.2014 for RM49,812.00 in Payment
Certificate No.6.
20
[2018] 1 LNS 2105 Legal Network Series
[61] Then Progress Claim No. 3 and No. 4 were made on the same day
of 4.12.2014 for RM 928,297.88 and RM 978,222.88 respectively which
Najcom said were wild Claims as the Main Contractor only certified
RM100,000.00.
[64] The breakdown reflects that work done for the said Fire Protection
System Works as at 15.3.2015 and 15.4.2015 were respectively valued
by the consultants at RM442,275.00 showing no progress of work after
the date of termination and the value of work remained the same
consecutively for 2 months.
21
[2018] 1 LNS 2105 Legal Network Series
[66] It can be clearly seen that to justify the sum claimed, Mix Target
had unilaterally revised upward by some three times certain items in a
clear heavy front loading in their rationalizing of rates after the initial
rationalization had been agreed. That cannot be justified and more so
when Mix Target knew or at least were deemed to have known the rates
between Najcom and the Main Contractor as the Fixed Lump Sum is the
same and Najcom has subcontracted the whole of the Works to Mix
Target.
[67] Mix Target said their Claims were supported by among others
shop drawings wherein the area which the work has been completed is
highlighted in yellow (Refer page 437-442 CB-2). Mix-Target had
reduced values for items which they are not claiming and increased the
value for items which they are claiming (highlight in yellow at sidebar)
as seen in Tab T in the further submission of Najcom.
[68] After Progress Claim No. 1-4 Mix Target had from Progress Claim
No.5-7 submitted their claim based on their unilateral increase in the
BQ in the items claimed without the consent of Najcom. See Tab T in the
Further Submission of Najcom.
22
[2018] 1 LNS 2105 Legal Network Series
[70] Learned counsel for Mix Target offered the explanation that the
front loading/adjustment was due to the re-engineering, namely the
change of design from 2 parallel pipes into 1 single pipe (Main Item A,
Sub-Item M and Sub-Item O).
[73] I agree with Najcom that Mix Target had not raised any objection
to Certificates issued by the consultants of the Employer throughout the
23
[2018] 1 LNS 2105 Legal Network Series
Works and that they only raised the objection after the termination and
when they refused to sign off the joint Valuation.
[74] I agree with learned counsel for Najcom that in the particular
matrix of this case in the chain of contracts, the parties ought to and
shall apply the BQ that was rationalized and approved by the Employer
which summary of the value of the rationalized BQ is also provided in
Tab T of Najcom‟s Further Submissions. Otherwise there would
definitely be diverging differences that would not be reconcilable as the
Works claimed to be completed by Mix Target would not be the Works
as verified and certified by the Employer with the consequence that the
Main Contractor and subsequently Najcom would be paid based on such
a certification.
[75] It must also be noted that for Progress Claims No.2, 3 and 4 at
pages 217, 287 and 349 respectively of CBOD 1 Mix Target had
included an amount for total material claimed at site for respectively the
amount of RM664,320.00, RM670,117.88 and RM670,177.88. Hence,
their total alleged material claim had been alleged as RM670,188.88.
[77] Mix Target was reluctant to show the invoices indicating their
costs in purchasing these materials on ground that by disclosing them
their profit margin would have been known to Najcom.
[78] In any event the contract between Najcom and Mix Target is a
fixed lump contract of RM9.9 million to carry out the construction,
completion, testing and commissioning of the Fire Fighting System
wherein Mix Target are to supply tools, equipment, materials and
24
[2018] 1 LNS 2105 Legal Network Series
labours for the performance of the same. There is no place to claim the
costs of materials for Works not done yet with respect to the materials
bought and delivered to site.
[80] In Airsquare Sdn Bhd v. Eng Keat Seng and another appeal [2013]
5 MLJ 526, the Court of Appeal held as follows at page 530:
25
[2018] 1 LNS 2105 Legal Network Series
[81] Therefore all the cost involved specifically the material costs have
been included in the BQ and as such Mix Target cannot make a separate
claim on the materials in the Progress Claims against Najcom. PW 1
Encik Zainal Abidin Bin Mamat who is the Managing Director of Mix
Target admitted this under cross-examination though not without some
reluctance.
[82] I further agree with learned counsel for Najcom that the
consultants when doing the inspection had inspected the work done by
Mix Target which included the material and fittings that have been
installed. The consultants of the Employer value such work into
percentage and subsequently convert the percentage into monetary
value against the rationalised BQ. There is thus no justification for
including costs of materials into the Progress Claims.
[83] For the sake of argument and assuming that there is a basis for
factoring in the price of materials to gauge the percentage of the Works
done, I do not accept that confidentiality as a good reason for not
disclosing for how else is the Court to determine if the amount is
reasonable. In claiming for loss of profit which generally is an available
remedy to a contractor like Mix Target in the event of a wrongful
termination the contractor would still have to disclose his costs and
profit margin.
26
[2018] 1 LNS 2105 Legal Network Series
[85] With respect, this amount in the police report is clearly in stark
contradiction of the material claim for RM670,177.88 as earlier
contended. Further, PW 1 had failed to produce any bank statement to
show or support his allegation that Mix Target had spent RM106,319.28
for the purchase of such material using credit card.
[86] Mix Target admitted that they had requested Najcom to purchase
materials on their behalf to the sum of RM653,086.40 whereby as at
31.3.2015, RM404,054.35 had already been delivered on site. (Refer
page 473 CB-2). Altogether, Mix Target said the materials purchased to
carry out the work as at the date of termination is RM 1,184,134.30.
Najcom through their Managing Director DW 8 said the sum advanced
on Mix Target‟s behalf for the purchase of materials on 26.1.2015 was
RM694,614.11.
[87] As at the date of termination, Najcom had paid Mix Target a total
sum of RM324,675.00, details of which are as follows:
No. Date Amount
1. 26.11.2014 RM100,000.00
2. 18.12.2014 RM20,860.55
3. 26.1.2015 RM150,354.45
4. 26.2.2015 RM53,460.00
Total RM324,675.00
[88] Both Mix Target and Najcom have accepted in practice that the
Mechanical and Electrical Consultant, Mesra Associates Sdn Bhd, shall
perform the monthly inspection of Mix Target‟s Works which is part of
the Mechanical Works component of the Project. The consultants
27
[2018] 1 LNS 2105 Legal Network Series
[89] Learned counsel for Mix Target referred this Court to the case of
ISO Technic Electrical Sdn Bhd v. Calibre M&E Sdn Bhd [2017] 1 LNS
212 where it was observed as follows:
“[22] What can be seen is that the Defendant would not make the
full payment on each Progress Claim received but instead would
pay a reduced amount.
“(7) It was not disputed that the defendant and the architect
had received progress claims No. 6-7 and the architect had
not certified them. The architect's evidence in not approving
the claims was that there were no consultant reports to
28
[2018] 1 LNS 2105 Legal Network Series
29
[2018] 1 LNS 2105 Legal Network Series
[90] The factual matrix in the above case is different from the present
case. In the present case there was a monthly valuation done by UNJV‟s
consultants in DW 6 and the Resident Engineer DW 7 from the
Employer together with the representatives of Najcom and Mix Target.
[91] Whilst in ISO Technic’s case (supra) no one from the Employer
MRCB was called to give evidence and to confirm the actual value of the
Works done, here the consultants from UNJV the Employer in DW 6 and
the Resident Engineer DW 7 from the Employer were subpoenaed by
Najcom and they came to Court to testify on their valuation of the Works
done.
[92] Mix Target themselves said there was conspiracy between Najcom
and the consultants engaged by the Employer but I find no evidence of
that. Mix Target also said that they had engaged a third party consultant
to do the verification of the Works done for which they paid
RM32,400.00 as can be seen in the witness statement of PW 1 I. Q&A 20
at item G.
[93] One would have thought that Mix Target would have called the
said consultant to testify in Court on their own independent valuation of
the Works done. For reasons best known to Mix Target the said third
30
[2018] 1 LNS 2105 Legal Network Series
party Consultant was not called and so their Progress Claims remained
self- serving Documents bereft of an independent corroboration. See the
cases of Arensi-Marley (M) Sdn Bhd v. Middy Industries Sdn Bhd and
others [2009] MLJU 667 and Vee Seng Development Sdn Bhd and others
v. Datuk Seri Panglima Mohd Sari bin Datuk HK. Nuar [2005] MLJU
454 where Courts would not be inclined to place much probative value
on self- serving documents unless independently corroborated.
[94] Learned counsel for Najcom also referred to the case of Liew Soo
Hoi & Anor v. Waja Resort Sdn Bhd & Ors [2014] 2 MLRH 37 where it
was held as follows in the headnotes:
31
[2018] 1 LNS 2105 Legal Network Series
[96] I agree with learned counsel for Najcom that between the evidence
of Najcom corroborated by the independent testimony of DW 6 and DW
7 from the Employer and that of Mix Target which evidence of PW 1 was
based on the Progress Claims prepared by his son PW 2, I would be
inclined to believe the evidence of Najcom for the following reasons:
(c) Mix Target did not request for a third party consultant to do
the evaluation of work, although Mix Target was dissatisfied
with the evaluation done by the consultant from the
Employer;
(d) Mix Target also did not request for re-evaluation or re-joint
inspection to be carried out, although Mix Target was
dissatisfied with the evaluation done by the consultant from
the Employer.
[97] The joint inspection was done by the Resident Engineer of the
Employer Ir Zulkifli DW 7 and assisted by Norazlan DW 3 from Najcom
and in the presence of PW 2 Encik Ahmad Fitri. He was a subpoenaed
witness and his evidence was as follows:
32
[2018] 1 LNS 2105 Legal Network Series
ZULKIFLI Ya.
ZULKIFLI Betul.
ZULKIFLI Ya
JSC Yang lain tak ada buat sebab tak ada kerja
dipasangkan?
ZULKIFLI Betul.
YA 1, 3 dan 4?
JSC Yes.
33
[2018] 1 LNS 2105 Legal Network Series
JSC Maksudnya?
JSC Ok, kita rujuk kepada muka surat sama, 1012 ok.
YA 1012.
JSC Yes, you are seeing one of the nota there, ok. Di
sini ok, katakan lah kalau... 1012. Ok katakan
L-4 kalau dia buat dengan mechanical coupling,
berapakah percentage yang akan capai?
ZULKIFLI Ya
34
[2018] 1 LNS 2105 Legal Network Series
[98] There was also another subpoenaed witness, Khaw Kok Aun from
Kejuruteraan Union Fire Langkasi Sdn Bhd (DW-1) who was the rescue
contractor engaged by Najcom to take over from where Mix Target had
stopped when they were terminated. He had also given evidence on the
percentage of the Work that is similar to those evaluated by the
consultants from the Employer despite the fact that DW 1 had never seen
the results of the joint inspection report.
[99] Whilst Mix Target may refuse to sign on the statement of final
accounts showing their objection to it, they must indicate which part of
the measurement of the Works done they did not agree or that their own
consultant would do a valuation for them seeing that they did not trust
the consultants of the Employer.
35
[2018] 1 LNS 2105 Legal Network Series
[101] How then is the Court to determine the amount of the Works done
and to justify payment?
[104] I would state that this is a reasonable amount for the work done
between February 2015 and 31.3.2015 which is the termination date. I
say this because the Certification at end of February 2015 in Certificate
No. 11 at Tab 13 Najcom Core Bundle showed an amount of
RM442,275.00. The Certification at end of March 2015 in Certificate
No. 12 at Tab 17 CBOD 5 showed the amount to be the same which is
RM442,275.00.
[105] However there is some evidence of work done in March 2015 when
Najcom had confirmed in their letter dated 14.3.2015 (Refer page 532-
533 of CB-2) that installation of pipes was carried out at Level 3 and 4
in March 2015 and the same was also confirmed by UNJV personnel in
the site daily reports from early March to the 30 th of the same month.
(Refer page 553- 578 of CB-2). This figure remained constant in
Certificate No. 13 for period ending April 2015 Tab 18 Najcom Core
Bundle for the same sum; termination was on 31.3.2015.
[106] The Certificate after Termination i.e. Certificate No.14 for period
ending May 2015 showed however a different sum of RM1,029,446.95
which cannot be attributed to Mix Target because they had already been
36
[2018] 1 LNS 2105 Legal Network Series
[109] Both Mix Target and Najcom agreed at para 6 of Mix Target‟s
Statement of Claim the sum of RM324,675.00 had been paid so far by
Najcom to Mix Target.
[110] Therefore the balance that Mix Target can claim is RM218,613.58
and I allowed judgment to be entered for this sum. Interest shall be 5%
per annum from date of Statement of Claim till realization.
37
[2018] 1 LNS 2105 Legal Network Series
[111] I agree with Najcom that throughout the execution of the Works by
Mix Target, Najcom had sent several reminder letters to Mix Target
raising numerous issues of breaches of the LoA as follows:
[112] These letters were all acknowledged received by Mix Target‟s site
engineer known as Mohd Faizal and are listed below as follows:
No. Letter Dated Bundle Page
1. 12-12-2014 CBOD 3 726
2. 16-12-2014 CBOD 3 727
3. 17-12-2014 CBOD 3 728
4. 24-12-2014 CBOD 3 731
5. 30-12-2014 CBOD 3 732
6. 02-01-2015 CBOD 3 733
38
[2018] 1 LNS 2105 Legal Network Series
terms. The Plaintiff‟s witness, Zainal Abidin Bin Mamat (PW-1) agreed
with the letter in the form of an Undertaking, and had admitted during
cross-examination that Najcom would have the right to terminate the
contract if Mix Target should fall behind the time deadline set.
39
[2018] 1 LNS 2105 Legal Network Series
40
[2018] 1 LNS 2105 Legal Network Series
[118] In the Bill of Quantities at page 42 Mix Target had clearly under
(Item B) promised that they would provide “Acceleration of works for
Wet Riser system installation and commissioning works including
tanks, pump sets, electrical works, pipe works, landing valves, hoses,
etc. in order for system to be active and provide protection to the
building during construction period as required by the Uniform
Building By Law required.” (emphasis added).
41
[2018] 1 LNS 2105 Legal Network Series
[119] By laws 52 and 232 of the Uniform Building By Laws 1984 state
as follows:
[120] Najcom‟s sober submission was that Mix Target had failed,
neglected and/or refused to execute the mandatory Uniform Building
By-Laws 1984 (UBBL) requirements. More than that Mix Target had
clearly exposed their own inability to execute the promises they have
made in accordance with the agreement. The safety of the whole site had
been compromised exposing others to unnecessary risk.
42
[2018] 1 LNS 2105 Legal Network Series
[121] Najcom gave their final reminder by their letter dated 6.3.2015
reminding Mix Target to rectify the complaints made including the
following:
43
[2018] 1 LNS 2105 Legal Network Series
[123] What is disquieting and even distressing is that Mix Target did not
reply to any of these allegations and warnings. This is the kind of silence
that would lead one to conclude that if there had been any dispute on all
these letters, Mix Target would surely have replied to these letters.
Under such a circumstance one is entitled to rely on the principle stated
in David Wong Hon Leong v. Noorazman bin Adnan [1995] 4 CLJ 155 at
page 159 as follows:
44
[2018] 1 LNS 2105 Legal Network Series
[124] The allegations are serious enough and when taken together would
justify termination of the LoA. Yet Mix Target did not see it fit to
respond and the only reasonable inference is that the allegations must be
true.
[125] If Encik Mohd Faizal the site Engineer of Mix Target had not
received those letters then surely Mix Target must subpoena him to give
evidence for otherwise an adverse inference would be drawn against
Mix Target. It is trite that under section 114(g) of the Evidence Act 1950
the Court may presume that evidence which could be and is not
produced would, if produced, be unfavorable to the person who
withholds it.
[126] There was the telling evidence from Mix Target‟s site daily
reports wherein Mix Target had candidly recorded their work activities
as follows:
45
[2018] 1 LNS 2105 Legal Network Series
46
[2018] 1 LNS 2105 Legal Network Series
[127] Mix Target‟s argument was that even if their work progress was
slow, they still had another 19 months to complete the subcontract work.
As such, to terminate Mix Target 5 months into the subcontract on the
ground of delay and inability to complete the Works is certainly unfair
and wrong.
[128] It is not the law that one must wait until after completion date or
close to completion date before one can terminate one‟s contractor on
ground of inability to complete the works. If that were true then one
would have to suffer the agonizingly slow progress in the works with no
ability to terminate against the sure certainty that the contractor would
not be able to complete, short of a miracle!
47
[2018] 1 LNS 2105 Legal Network Series
[129] The Court is entitled to look at the cumulative conduct in this case
of Mix Target and their failure to meet the work schedule that had been
set for them and to which they have agreed. The whole completion on
time is the sum total of the completion of the various floors on time and
the Court is entitled to look at the overall physical and financial
completion to gauge whether it is reasonable for Najcom to conclude
that Mix Target would be unable to complete the Works on time.
[130] Learned counsel for Mix Target cited the case of Kerajaan
Malaysia v. Ven-Coal Resources Sdn Bhd [2014] 5 CLJ 186 where it was
held at page 210 that:
48
[2018] 1 LNS 2105 Legal Network Series
[133] Mix Target had failed to honor its promise to expedite and
complete the work which was originally scheduled for completion
respectively by 15.2.2015 and by the end of February 2015 where Level
3 and Level 4 were concerned.
[135] I agreed with Najcom that because of the slow progress and the
various breaches, Mix Target had evinced its inability to complete the
works despite numerous extensions of time. Indeed the combined
breaches and non-compliance pointed inexorably to Mix Target having
repudiated the contract as shown in their inability to render substantial
performance of the agreement.
[136] Moreover Mix Target did not have the capacity, resources and
commitment to complete the Works as exhibited in the following
disabilities:
49
[2018] 1 LNS 2105 Legal Network Series
50
[2018] 1 LNS 2105 Legal Network Series
[140] I would uphold the said termination as been justified against the
backdrop of repeated delays and falling behind time in spite of repeated
reminders to rectify the breaches referred to above.
[141] Having held that the termination was valid and lawful Mix
Target‟s Claim for losses arising out of unlawful termination would
therefore have to be dismissed.
51
[2018] 1 LNS 2105 Legal Network Series
[147] There is also now 2 pipes to be done because of the change back to
parallel piping causing a likelihood of clashing with aircon ducts.
[148] There was no written rejection by Najcom and the M&E consultant
of the Works carried out by Mix Target. Najcom or the M&E consultant
also had not issued any non-compliance report or notice to rectify any
defect in respect of Mix Target‟s work to Kejuruteraan Union Fire
Langkawi Sdn Bhd as confirmed by DW-1 during cross examination. On
the balance of probabilities this cannot be attributed to Mix Target as
their fault. Whoever is supervising the work from UNJV should have
exercised greater caution in the supervision.
Whether Najcom had proved its Claims for losses arising out of
lawful termination of the contract with Mix Target
52
[2018] 1 LNS 2105 Legal Network Series
[152] Granted it is for the balance works but the question is what is the
additional costs incurred in completing the Works arising out of the
lawful termination of Mix Target.
[153] Najcom has not shown that the balance Works to be completed by
their rescue contractor is the same Works that had been awarded to Mix
Target. In the event that there are extra costs arising out of additional
works or variation works, these cannot be charged to Mix Target.
Najcom referred to DBOD 2, pages 563-578 whereby DW 1 had
provided bank-in slips and bank statements of receiving total amount of
RM11,142,601.09.
[154] It would reflect that there is evidence that Najcom had made
payments of a total sum of RM11,142,601.09 but then this included
variation works as well, as submitted by learned counsel for Najcom. As
there is no clear evidence of what constituted the variation orders and
how much was the variation works it is impossible to compare like with
like and to determine the additional costs incurred by Najcom to
complete the balance Works.
[155] There is also no evidence that UNJV has charged Najcom for any
LAD arising out of the delay caused by Mix Target or that Najcom had
failed to obtain any extension of time from UNJV.
[156] On the balance of probabilities, Najcom has not been able to prove
the loss suffered as a result of any extra costs incurred in finishing the
balance Works under the rescue contractor.
53
[2018] 1 LNS 2105 Legal Network Series
Pronouncement
[161] After hearing parties on costs I had allowed only nominal costs of
RM15,000.00 to be paid by Najcom to Mix Target as this matter clearly
could have been disposed of in the Sessions Court.
54
[2018] 1 LNS 2105 Legal Network Series
COUNSEL:
Hotel Anika Sdn Bhd v. Majlis Daerah Kluang Utara [2006] 4 CLJ 981
Airsquare Sdn Bhd v. Eng Keat Seng and another appeal [2013] 5 MLJ
526
ISO Technic Electrical Sdn Bhd v. Calibre M&E Sdn Bhd [2017] 1 LNS
212
Arensi-Marley (M) Sdn Bhd v. Middy Industries Sdn Bhd and others
[2009] MLJU 667
Vee Seng Development Sdn Bhd and others v. Datuk Seri Panglima
Mohd Sari bin Datuk HK. Nuar [2005] MLJU 454
Liew Soo Hoi & Anor v. Waja Resort Sdn Bhd & Ors [2014] 2 MLRH 37
David Wong Hon Leong v. Noorazman bin Adnan [1995] 4 CLJ 155
55
[2018] 1 LNS 2105 Legal Network Series
56