ElectroFlow Systems Information Book
ElectroFlow Systems Information Book
Systems Information
Prepared By
Initial Survey
The initial reading tests and measures the electrical load(s) and the distribution(s) in a
facility. From this information, both the impedance or z factor of the system and the X/R ratio are
determined. X being the reactance of the system and R being the resistance of the system. From
that, we are able to point out the areas in your plant where energy is being wasted.
To obtain an accurate report of savings and payback, the following criteria/data are
required:
- Plant operations must be equal to or greater than 70% at the time the measurements
are to be taken otherwise distorted results will be obtained.
- Access to the main distribution(s).
- Copies of the most recent 12-month electric bills. Just the monthly total charge is not
sufficient. The computer analysis we perform incorporates the actual KWH consumed,
the energy charge, KWD, KWD charges, and any discounts.
- Explanations of any unscheduled operating changes for the past year from normal
yearly cycle/operations.
- Details of any future changes to normal plant operations, such as, expansion, product
changes cutbacks, etc.
- List of any known problems suffered in the electrical system, such as,
surges, harmonics, unusual failure or breakdown of equipment or machinery,
etc.
- If Power Factor Correction Capacitors are installed. If they are, we require a list of
where they are installed, the type, and the sizes in KVAR.
- Access to the main transformer is preferred. This is to obtain the size (KVA),
impedance, primary and secondary transformer voltage ratings, delta or wye
configurations, and if it is dry or liquid cooled.
- The estimated percent of DC load related to the normal total load.
- Notification of any variable frequency drives and SCR controls.
- Number of transformers/total transformers on each electric bill.
- If metered on the primary side or the secondary side.
- Site plan of electrical system, if available.
- Hours of Operation. This refers to the adjusted hours of continuous normal operation
of the electrical load reflecting “percent in operation” in hours per week, per each
measurement location.
Proposal
Once the initial survey has been completed, an ElectroFlow TM Systems proposal will be
presented. The proposal contains the following information:
- Executive Summary
- ElectroFlowTM Benefits and Features
- Introduction and Qualification
- Engineering Analysis
- Electric Bill Breakdown
1
- Electric Bill Analysis
- Existing Power Profile
- ETI Report Information
- Audit Measurements
- Existing Resultants
- Projected Resultants
- Savings Profile and Payback Chart
- Calculation Tables
- Existing and Projected Energy and Savings charts
- Outline of Other Benefits
- Performance Guarantee
- General Terms and Conditions
Note: If there are any drastic changes found after the Link Analysis is performed from the initial
survey, the original price/proposal may be subject to change.
Link Analysis
Upon acceptance of the proposal, a link analysis will be performed. The link analysis is
conducted for the following reasons:
The link analysis is a complex computer analysis that identifies the effects of various large
loads switching ON and OFF on various sub mains and the hand shaking effect that occurs between
each of the sub mains or branch circuits.
The following situations are a guide to when and where the link analysis measurements
will be taken:
Note: If the period between the original measurements and the link analysis is in excess of three
months, it will be necessary to provide copies of the electric bills for the period from the last
measurement to the time of the link analysis.
Physical Mounting of System Components
- ElectroFlowTM units must be installed within 20 linear feet of the distribution feeder
attachment point.
- Each ElectroFlowTM unit will be installed using good engineering practice and will be
in accordance with applicable national and local codes.
- If an ElectroFlowTM unit is to be mounted near a ceiling, a minimum of 12 inches is
required between the top of the unit and the ceiling.
- If ElectroFlowTM units are to be mounted side by side, a minimum of 1 inch between
enclosures is required.
Ambient Temperatures
High ambient temperatures will reduce the life of the ElectroFlow TM System. Therefore,
the system should be located in an area of unrestricted ventilation and mounted away from hot
objects and surfaces.
Maximum safe ambient temperature is 500C. Should the temperature fall below –400C
before the ElectroFlowTM System is energized, internal damage to the capacitance cells may occur
when the system is turned on. To prevent this, the components should be brought to at least
-120C before being energized. If extremely low temperatures are expected, it is advisable to keep
the capacitors energized in order to maintain their internal temperature above the critical point.
ELECTROWFLOWTM OPERATING PARAMETERS
An ElectroFlowTM System provides the following standard benefits and features for an
electrical distribution:
1. Improves and levels out the voltage, thereby, increasing equipment efficiency
and longevity.
2. It can balance the three phases, thereby, reducing Kilowatt Demand while
increasing longevity of the system.
3. Filters harmonics, surges and transients, thereby, improving longevity of
equipment and eliminating downtime.
4. Reduces line, eddy current, and hysteresis losses, thereby, reducing the
Kilowatt Demand and Kilowatt Hour consumption.
5. Improves power factor by reducing reactive and apparent power, thereby,
improving system efficiency while eliminating possible related charges. This
is done without any capacitor's deleterious side effects.
6. Frees up wasted KVA capacity of the electrical system, thereby, allowing
additional loads without requiring any transformers or capital expenditure.
The sampling rate of an ElectroFlowTM unit is 3840 samples per second all the way up to
15000 samples per second. This sampling rate is handled by utilizing Motorola microprocessors
HC6811 and HC6816. The ElectroFlowTM unit samples voltage, amperage, power factor, and
current threshold. After the samples have been taken, it calls for different stages and different
configurations and different hybrid configurations of the stages to address a particular or multiple
problems that exist. The unit then reads again to see that the steps it took corrected the problem(s).
If the problem(s) were not corrected, it stops and samples again. If the problem is fixed, it
continues to correct the problem(s). In other words, it works with the plant’s electrical load. As
the load changes, the performance of the system changes – it moves with the load. The more
problems there are, the more the system will activate the various stages. The less the load, the less
the system will bring on and off line.
The primary operation of an ElectroFlowTM system is based on tuned tank circuits - LCR
(inductive/reactive, capacitive, resistive). These tuned tank circuits have minimal resistive
components, therefore, they do not waste energy but save energy.
Tank Circuit
L C
C = -900 leading PF
L = +900 lagging PF i = C*(dv/dt)
R = 00 PF=1 V = L*(di/dt)
R
The principle of the operation is based on Ladder Logic for the activation of the various
circuits. There are 18 circuits per stage in an ElectroFlow TM unit. The system is sized for three
phase systems operating from 208 volts to 345 kilovolts regardless of the line frequency (40Hz to
400Hz). The largest system installed is over seas with a size of 300 Megawatts.
In most cases, contactors of different ratings are used because 99.9% of the time you do
not need that fast of a response to rectify a problem. We have the technology which we can offer
for a much faster response if it is required. The design is to deliver a more uniform and damped
response because it does not require that immediate response to the load and inrush currents.
The system is equipped with a self diagnostic feature (SDF) which will identify any
component failure in itself on both per phase and per stage basis. The reason this system is
equipped with a SDF is, since the systems are worldwide, it would be too expensive to send
technicians. The in-house electricians will be able to identify the problems of the system in ten to
fifteen minutes.
The system consists of multi-stage LCR tank circuits which are activated according to the
preset designed parameters based on the Ladder Logic Principle.
ElectroFlowTM can be designed for applications at low, medium, and high voltages as well
as various international line frequencies.
The system is equipped with a unique Self Diagnostic Feature (SDF) which identifies the
status/failure of components on a per phase and per stage basis.
The actual designing of an ElectroFlowTM unit can only begin after a link analysis has been
performed. This is similar to a load flow. Measurements are taken on the secondary load side of
the main transformer on the common buss as well as each subsequent feeder downstream of the
main distribution. The common buss reading identifies the overall picture and the behaviour of the
load profile on the whole for the facility. The measurements downstream help to identify any
specific problems at any one of the downstream feeders.
Any variations of the facility’s load, such as, inrush currents, short-circuits, will be
protected as well as from any deleterious effects from the high voltage side. This can only be
accomplished by having multiple impedances in the electrical system. There are three levels of
impedance which are designed to address the problems of the facility – lower, equal to load, and
higher impedances. A lower impedance introduces a path of least resistance to filter harmonics,
surges, transients, spikes, and other variances which may “hit” the facility. If the impedance is
lower, according to Kirchoff’s Law, all the problems will “hit” the ElectroFlow TM unit first and not
the facility’s loads. A load/equal impedance to the facility’s electrical system is able to correct
imbalanced conditions based on X/R ratio and z factor. A higher impedance than the facility’s
electrical system impedance allows the stabilization of the voltage.
Load
1
2
3
} ZLow (Surges & Harmonics)
4
5 } ZLoad (Load Balancing)
} ZHigh (Voltage)
This design set up of the ElectroFlowTM system allows the correction of multiple problems
at once, which results in energy savings and power quality. If there are specific problems
downstream at a sub-feeder, for more effectiveness and economic reasons, a unit will be installed
onto that particular feeder. Again, this will only be done if the load profile of the facility’s load
exceeds the standard design criteria and the set level ETI has set for the industry. This will isolate
the specific problem(s) at the specific load feeder and filter them out so the common buss will not
see these problems and as a result, the losses associated between the feeder and the main
distribution will be eliminated.
Transformer
EF
EF
EF ElectroFlowTM Unit
ElectroFlowTM Model
K1 K2 K3
Voltage (Volts) 208-600 208-600 208-600
Frequency (HZ) 40-400 40-400 40-400
Phases 3 3 3
Circuit Control Regulator 1333 CAPTEL 618 CAPTEL 618
Stages 1-6 1-2 1
KVAR 50/Stage 50/Stage 50
Safe Ambient Temperature (0C) -10 – 50 -10 – 50 -10 – 50
Approved Rating CSA,UL CSA,UL CSA,UL
Dimensions (Inches) 302554 20822 8822
Mounting Floor Wall Wall
Design Life (Years) 20 20 20
PROBLEMS AND THE ELECTROFLOWTM SOLUTION
Voltage
95% of problems faced in industry and commerce relates to voltage. For a low voltage
condition (under rated voltage), you can expect higher current and more losses, etc. For a high
voltage condition, you can expect breakdown of equipment/machinery and insulation.
MO TO R O VERH EATING
In line with the above two conditions, if we
200 have imbalanced voltages between the phases
(single phase loads are most of the problem), you
Temperature Rise (%)
HORSEPOWER DERATING
IMBALANCED PHASE VOLTAGES
120
Derating Factor (%)
If we have under voltage, over voltage, and/or imbalanced voltage conditions, we can
expect the following problems:
Waste energy.
Connect in series.
Generate harmonics.
Have limited fixed sizes and are not expandable.
Are bulky and expensive.
AC Current (Amps)
Circulating currents. 1450
IMBALANCED LOAD
1500 1200
Increased current in neutral conductor 1500
1300 1400 1250
(causes-imbalanced currents and 1350 1450 1200
1300
harmonics). 1300 1350 1200
Increased neutral to ground voltage (stray voltage 1350
1100
1400 1300 Phase A
or tigal voltage - reduced power quality and 1300 1350 1250 Phase B Phase C
wasted energy). 1400
900 1400 1200
Overheating of motors which leads to insulation 1350 1400 1250
500
1300 1450 1250
breakdown. 700
Reduced motor efficiency. 1400 1400 Time 1200
Motor bearings failure.
In line with the above problems, we can expect energy wasted and reduced power quality
through:
Increased maintenance of equipment and machinery.
Wasted energy/higher electric bills – KWD and KWH.
Wasted investment and operation capital.
Three-Phase Balancing
ElectroFlowTM Feature #2 - Standard
Assume:
Phase A = 800 Amps, Phase B = 1100 Amps, Phase C = 800 Amps
A
L
Based on X/R ratio and Z (impedance), ElectroFlowTM’s LCR circuits would be configured inRthe following sequence toR balance the three ph
C B
C
L
R
Tconstant = RC
Voltage sag – is the reduction of the magnitude of the voltage from the nominal rated value that is
assigned for a duration of less than or equal to half a cycle.
programs.
Amplitude
For surges and transients, industry can provide a lot of different products to address these
problems. But, all surge suppressors have two major functions:
1) whether it is a MOV, Zener diode, silicone avalanche diode, they have one thing
in common, the higher the voltage goes over the threshold rating of the device, the lower the
resistance becomes and the closer it gets to zero. The ideal working condition of these devices is to
channel the magnitude of that phase to ground. The idea is to clip the excess, this does protect the
equipment but, if the magnitude of the spike exceeds its designed joules/second, its tanks will
rupture and you take it for granted that it is protecting the equipment (but it is not).
2) when it takes a spike from one phase and channels it to ground (protecting the
equipment), it is wasting the true RMS value(voltage) that otherwise could be collected. If we
could protect the equipment and not waste energy, this would be ideal.
A B C
A
C
L
R
Tank Circuits
B
Tank Circuits
Load
Harmonics
Harmonics by definition is
multiple images of line frequencies. In HARMONICS
North America, the line frequency is
60Hz, therefore, H3 = 180Hz, H5 =
300Hz, etc. Major causes of harmonics
Fundamental h3
are non-linear loads, such as, computers,
Amplitude
h5 h7
electronic equipment, robotics, SUM
electronic lighting ballasts, variable-
speed drives, frequency inverters, UPS
systems, DC drives, battery chargers, Time
etc. These devices are becoming more
and more common in industry. As a
result, the more total harmonic
distortion, the more the distortion of
waveforms, whether voltage or current.
Harmonics cause the following adverse side-effects:
If you took a true RMS meter and took a measurement on voltage and current,
for example, take the true RMS value based on FFT (that is what the
transformer registers), and compare it to average RMS value, the value of true
RMS is much higher than the average RMS values. The difference between
the two magnitudes, chances are, is caused by harmonics. This may be taken
for granted. Example – look at the panel meter, it reads 800Amps for a
1000KVA transformer, it appears like there is no problem, but, if you take a
true RMS measurement, chances are the draw is much more than 800Amps.
This could lead to overheating/loading of cables, transformers, protective
equipment, buss bars, etc., causing problems without even knowing it.
Breakers and fuses tripping – all breakers and fuses are designed,
manufactured, and tested based on the true RMS value and the heat content of
the amperage draw. From time to time, a breaker trips, the technician goes and
takes a measurement expecting to find a short circuit but there is no short
circuit. He turns the breaker on and it works. Quite often harmonics under a
resonance condition, in particular, are the cause of this type of problem.
Unreliable operation of electronic equipment and generators. As we know, t =
1/f. The higher the frequency, the lower the t (period), the faster the firing
order of the SCRs, and the more breakdowns we can expect in our more
sensitive equipment and the faster responsive equipment purchased for
production.
In line with the above problems, we can expect energy wasted and reduced power quality
through:
Increased maintenance of equipment and machinery.
Wasted energy/higher electric bills – KWD and KWH.
Waste energy.
Connect in series.
Generate harmonics (through injection).
Have limited fixed sizes and are not expandable.
Are bulky and expensive.
Amplitude
A lagging power factor is generally
caused as a result of inductive loads
and particularly motors not being
fully loaded.
Voltage
Current
Time
In line with the above problems, we can expect energy wasted and reduced power quality
through:
Resonance and overheating (Xc = Xl). Regardless of which capacitors are used,
automatic, static-dynamic, or aerostatic, the Xc is constant, but Xl (inductive/reactive),
is the load which is constantly changing, as it changes through the course of operation.
If Xc = Xl, a resonance condition occurs. This results in overvoltage conditions,
overheating, and the damaging effects of these conditions.
Capacitor cell failure (Xc = 1/(2fC)). Ideally, we want f = 60Hz, but, if harmonics are
present, it is not possible (higher number). The higher the value, the lower X c becomes
and approaches zero, resulting in capacitor breakdown, etc.
KVA Capacity
Brownouts
155 -0.444
BROWNOUT
156 -0.50325
Amplitude
157 -0.54594
Brownout by definition is low voltage for 158 -0.57008
an extended period of time (greater than half a 159 -0.57431
cycle) in which the magnitude of the voltage is 160 -0.55793
reduced. 161 -0.52098
162 -0.46424
Time
163 -0.3892
Waste energy.
Connect in series.
Generate harmonics.
Have limited fixed sizes and are not expandable.
Are bulky and expensive.
Time
Specific Harmonics
100
Increased hysteresis losses. 90
80
waveforms. 50
40
30
Failed capacitor banks. 20
10
Harmonic
Erroneous register of electric meters.
Neutral overloading / unacceptable
neutral-to-ground voltages.
Unreliable operation of electronic
equipment and generators.
In line with the above problems, we can expect energy wasted and reduced power quality
through:
Wasted capacity – Inefficient distribution of power.
Increased maintenance of equipment and machinery.
Wasted energy / higher electric bills (KW,KWH).
Waste energy.
Connect in series.
Generate harmonics (through injection).
Have limited fixed sizes and are not expandable.
Are bulky and expensive.
Phase Loss
3) This leaves 600 to be compensated for to finish establishing the A phase. The compensations which have been made thus far
Implementation of ElectroFlowTM's phase synthesis unit:
The installation of the ElectroFlowTM phase synthesis unit would be between the main transformer
and the plant’s main distribution panel. The operating time of the phase synthesis unit is
continuous/indefinite(until the lost phase is restored).
If the utility company losses a phase, the protection devices(short-circuit relays, fault currents,
etc.) of the plant have to be bypassed. If this is not done, every time the ElectroFlowTM phase synthesis unit
comes on, it will trip these protection devices. A bypass is used from the secondary transformer and the
plant’s load so there will be no feedback from the lost phase. In other words, if A phase is lost, interlocks
will open and close to make this phase in series through the phase synthesis unit.
Certain criteria have to be taken into account to see if a phase synthesis unit can be installed in a
plant. Some of these criteria are:
1) make sure the ampacity is there for the conductors to carry the load of the other
two phases.
2) the sizing/rating of the short-circuit relays on the primary side so they do not trip.
3) is the transformer capable of sustaining this type of operation.
4) the full load of the main transformer has to be less than 67% at the time the phase
synthesis unit comes on. If the full load of the transformer is greater than 67%, the
phase synthesis unit will not engage. Etc.
The ElectroFlowTM phase synthesis unit is not really intended for North America because phase loss
situations are rare but will be installed if a customer requires it.
Savings
1 – Reduces KW Demand
2 – Reduces KWH Consumption
3 – Eliminates Power Factor
Penalty 4 – Reduces Monthly
Electric Bill
5 – Reduces Maintenance & Downtime
Power Quality
1 – Improves Voltage
2 – Balances Three Phases
3 – Filters Surges, Transients
4 – Filters Harmonics
5 – Improves Power Factor