دراسة مصورة لنظام التاريض

Download as pdf or txt
Download as pdf or txt
You are on page 1of 10

LOCATION

DISCIPLINE ELECTRICAL
CHLORINE
SUBJECT: EARTHING SYSTEM CONTACT TANK

1-DETERMINE LEVEL OF EARTING CONNECTION BY SURVEYOR DEPEND ON SPEC’S AND


STRUCTURAL DRAWING, AS THE FOLLWING

Please find attached file of the approved IFC structural drawing for the Chlorine Contact Tank
noting that the F.G.L around this tank is equal to (+578.75) and as per project’s specification
(Highlighted below ) the copper cable will be laid in trench not less than 600mm deep so you are
kindly requested to apply the connection at the same level ( around + 578.15 ) or deeper.

Page 1 of 10
2- MAKE GOOD CONNECTION BETWEEN REBAR (AFTER STELL WIRE MESH FINISHED) AND BARE
COPPER CONDYCTOR BY CLAMP.

*USE VERTICAL REBAR TO CONNECTION.

EARTHING
LEVEL

PULL EARTHING
TERMINAL TO THIS
SIDE AND THIS LEVEL
AFTER CASTING

3-INSTALL THIS SMALL PIPE BETWEEN REBAR AND EARTHING TERMINAL TO ELIMENATE THE
SPACE BETWEEN EARTHING TERMINAL AND THE EDG OF CONCRETE AFTER REMOVING FORM
WORK AND CASTEING WILL BE FINISHED,TOM MAKE SMALL CHIPPING IN BEAM TO PULL
TERMINAL AT CONNECTION LEVEL.

Page 2 of 10
WILL BE PULLED OUT
SIDE BUILD
SURROUNDING TO
COMPLETE EARTHING
CONNECTIONS

4- INCREASE THE LENGTH OF EARTING TERMINAL AROUND 3M TO FUTURE CONNECYION AFTER


CASTING.

GENERAL VIEW OF TANK

Page 3 of 10
For Building # 17 – CHLORINE CONTACT TANK :-
Chlorine Contact Tank grounding calculation will be based on schwarz’s
grounding design methods.

R1= Π.Lc*{ln (2Lc/ a') + (K1.Lc/√A)-K2}.


R2 = /2 Π.nr.Lr*{ln(2Lr/b)-1 + (2k1.Lr/√A).( √(nr-1)2 }.
Rm = Π.Lc * { ln (2Lc/ Lr)+( K1.Lc/√A)-k2 +1}.
RG= R1.R2-Rm2/R1+R2-2Rm

Where:-
R1 :- ground resistance of grid conductors in Ω
R2 :- ground resistance of all ground rods in Ω
Rm : - mutual ground resistance between the group of grid conductors,
R1,and group of ground rods, R2 in Ω
ρ :- is the soil resistivity in Ω·m
Lc : -is the total length of all connected grid conductors in m
2a :- is the diameter of conductor in m
a' :- is√1 ∗ 2ℎ for conductors buried at depth h in m, or
a' :- is a for conductor on earth surface in m
h :- is conductors buried depth in m
A : - is the area covered by conductors in m2
k₁, k₂:- are the coefficients [see Figure 25(a) and (b)]
Lr : -is the length of each rod in m
2b :- is the diameter of rod in m
nr :- number of rods placed in area A
Input data:-
(ρ₃ = 126.1 Ω·m) , (Lc= 74.3 m) ,( 2a = 0.0124 m), (a' = √1 ∗ 2ℎ = √0.0062 ∗ 2 ∗ 0.6
= 0.086 m) , (h = 0.6 m),(A = 342.7 m2 ), (Lr= 3 m) ,(b= 0.0095m) ,(nr = 4)
For K1:-
Length to width ration = 20/17= 1.17
For h=0.6m curve B will be used
So K1 = -0.05*1.17+1.2 = 1.14
For K2:-
Length to width ration = 20/3=6.67
For h=0.6m curve B will be used
So K2 = -0.1*6.67+4.68 = 4.01

Calculation & Result :-


R1=1.39Ω.
R2=9.7 Ω.
Rm=3.0 Ω.

Rg= (4.39*9.7-(3)2/4.39+9.7-(2*3) = 4.15 >5Ω.

Page 4 of 10
Main factors in calculations
1- Soil resistivity in Ω.m.
2- The diameter and cross section of conductor ,
Depend of this factor we can decide the cable conductor cross section 95 mm2, 95
mm2, 70,16 mm2,…………….,etc.
3- The conductor buried depth h ,
Determined by civil eng and surveyor, in our spec’s 60cm from F.F.L,
Usually this depth is used.
4- The length of each rod in m,
Depend of this factor we can decide The length of each rod
3m,2.4m,1.8m,……….,etc.
5- No of rods placed in area.

Page 5 of 10
Page 6 of 10
GROUNDING SYSTEM LAYOUT

Conductor

Rod

Page 7 of 10
SOIL RESISTIVITY CALCULATION

1.1 WENNER’S PROCEDURE ( ASTM-G57)

A. General

a. Purpose

This document was developed as a guideline and process for understanding

the concepts, and determining soil resistivity.

b. Scope

This document presents the theory and methodology of soil resistivity testing,

the equipment required, a detailed test procedure and forms. It also explains

the use of the soil resistivity data in designing grounding systems to meet

specific performance requirements.

c. Introduction

Soil resistivity data is the key factor in designing a grounding system for a

specific performance objective. All soil conducts electrical current, with some

soils having good electrical conductivity while the majority has poor electrical

conductivity.

The resistivity of soil varies widely throughout the world and changes

dramatically within small areas. Soil resistivity is mainly influenced by the

type of soil (clay, shale, etc.), moisture content, the amount of electrolytes

(minerals and dissolved salts) and finally, temperature.

When designing a grounding system for a specific performance objective, it is

necessary to accurately measure the soil resistivity of the site where the

ground is to be installed. Grounding system design is an engineering process

that removes the guesswork and “art” out of grounding. It allows grounding to

be done “right, the first time”.

The result is a cost savings by avoiding change orders and Ground

“enhancements”.

Page 8 of 10
d. Theory

The best method for testing soil resistivity is the Wenner Four Point method.

It uses a 4-pole digital ground resistance meter, such as the Megger 5/4 or

the AEMC 4500 meters, probes, and conductors.

It requires inserting four probes into the test area. The probes are installed in

a straight line and equally spaced (See Figure 1-1). The probes establish an

electrical contact with the earth.

The four pole test meter injects a constant current through the ground via the

tester and the outer two probes. The current flowing through the earth (a

resistive material) develops a voltage / potential difference. This voltage drop

resulting from the current flow is then measured between the two inner

probes.

The meter then knows the amount of current that is flowing through the

earth and the voltage drop across the two center probes. With this

information the meter uses ohms law (R=E/I) to calculate and display the

resistance in ohms this displayed resistance value is in ohms and must be

converted to ohms-meter, which are the units of measure for soil resistivity.

Page 9 of 10
Page 10 of 10

You might also like