Paper 15
Paper 15
Strategic Cost Management – Decision Making‐ Bit Questions
(I) Choose the most appropriate answer to the following questions giving justification.
5. Which of the following is a recognised method of arriving at the selling price for the
products of a business?
(A) Life cycle pricing (B) Price skimming (C) Penetration pricing (D) Target costing
(A) (A) and (B) only
(B) (A), (B) and (C) only
(C) (B) and (C) only
(D) (A), (C) and (D) only
(E) (A), (B), (C) and (D)
6. A company has estimated the selling prices and variable costs of one of its products
as follows:
The order would require 1,250 kgs of material D. This is a material that is readily
available and regularly used by the organisation on its normal products. There are 265
kgs of material D in stock which cost ₹795 last week. The current market price is ₹3.24
per kg.
Material D is normally used to make product X. Each unit of X requires 3 kgs of material
D, and if material D is casted at ₹3 per kg, each unit of X yields a contribution of ₹15.
The relevant cost of material D to be included in the costing of the special order is
nearest to:
(A) ₹3,990
(B) ₹4,050
(C) ₹10,000
(D) ₹10,300
8. Aderholt uses activity based costing to allocate its overheads. The budgeted
cost/expected for the Supervisor cost pool was:
Budgeted units 5,000
Number of employees 75
Budgeted Cost ₹7,500
The actual costs incurred were:
Actual Units 5,500
Actual Employees 77
Actual cost ₹8,085
What was the total variance for the setups?
(A) ₹585 Adverse
(B) ₹165 Favourable
(C) ₹5550 Favourable
(D) ₹385 Adverse
9. P operates an activity based costing (ABC) system to attribute its overhead costs to
cost objects.
In its budget for the year ending 31August 2017, the company expected to place a
total of 2,895 purchase orders at a total cost of ₹1,10,010. This activity and its related
costs were budgeted to occur at a constant rate throughout the budget year, which is
divided into 13 four-week periods. During the four-week period ended 30 June 2016, a
total of 210 purchase orders were placed at a cost of ₹7,650.
The over-recovery of these costs for the four-week period was:
(A) ₹330
(B) ₹350
(C) ₹370
(D) ₹390
10. A manufacturing company recorded the following costs in October for Product X:
₹
Direct Materials 20,000
Direct Labour 6,300
Variable Production Overhead 4,700
Fixed Production Overhead 19,750
Variable Selling Costs 4,500
Fixed Distribution Costs 16,800
Total costs incurred for Product X 72,050
During October 4,000 units of Product X were produced but only 3,600 units were sold.
At the beginning of October there was no inventory. The value of the inventory of
Product X at the end of October using throughput accounting was:
(A) ₹630
(B) ₹1,080
(C) ₹1,100
(D) ₹2,000
11. Company B uses a throughput accounting system. The details of product X per unit are
as follows:
₹
Selling Price 50
Material Cost 16
Conversion Costs 20
Time on bottle neck resource 8 minutes
The return per hour for product X is:
(A) ₹105
(B) ₹225
(C) ₹255
(D) ₹375
13. Which of the following would take place if a company is able to reduce its variable
cost?
Contribution Margin Break-Even Point
(A) Increase Increase
(B) Decrease Decrease
(C) Increase Decrease
(D) Decrease Increase
15. A company makes a single product which it sells at ₹10 per unit. Fixed costs are ₹48,000
per month and the product has a contribution to sales ratio of 40%. In a period when
actual sales were ₹1,40,000, the company's margin of safety in units was:
(A) 2000
(B) 3000
(C) 3500
(D) 4000
17. A company has the capacity of production of 80000 units and presently it sells 20000
units at ₹100 each. The demand is sensitive to selling price and it has been observed
that every reduction of ₹10 in selling price the demand is doubled. What should be the
target cost at full capacity it profit margin on sales is taken at 25%?
(A) ₹58 lakhs
(B) ₹52 lakhs
(C) ₹48 lakhs
(D) ₹50 lakhs
18. The information relating to the direct material cost of a company is as follows:
Standard price per unit ₹7.20
Actual quantity purchased in units 1600
Standard quantity allowed for actual production in units 1450
Material price variance on purchase (Favourable) ₹480
What is the actual purchase price per unit?
(A) ₹7.50
(B) ₹6.40
(C) ₹6.50
(D) ₹6.90
20. The preparation and use of standard cost, their comparison with actual costs and the
measurement and analysis of variances to originating causes is defined as:
(A) Marginal Costing
(B) Standard Costing
(C) Throughput Costing
(D) Kaizen Costing
21. The following are cost data for two alternative ways of processing the clerical work for
legal cases brought before the district court:
Semi-Automatic Fully Automatic
Monthly Fixed Costs (₹)
Occupancy 15,000 15,000
Maintenance Contract 5,000 10,000
Equipment Lease 25,000 1,00,000
Unit Variable Cost (per Report) (₹)
Supplies 80 20
Labour 60 20
The cost indifference point will be:
(A) 800 cases
(B) 850 cases
(C) 750 cases
(D) 700 cases
22. The following figures are extracted from the books of a company:
Budgeted O/H ₹10,000 (Fixed ₹6,000, Variable ₹4,000)
Budgeted Hours 2000
Actual O/H ₹10,400 (Fixed ₹6,100, Variable ₹4,300)
Actual Hours 2100
Variable O/H cost variance and Fixed O/H cost variance will be:
(A) 100 (A) and 200 (A)
(B) 100 (F) and 200 (F)
(C) 100 (A) and 200 (F)
(D) 200 (A) and 100 (F)
23. A company produces a product which is sold at a price of ₹80. Its Variable cost is ₹32.
The company’s Fixed cost is ₹11,52,000 p.a. The company operates at a margin of
safety of 40%. The total sales of the company is:
(A) 4,000 units
(B) 40,000 units
(C) 30,000 units
(D) 20,000 units
24. The P/V ratio of a firm dealing in Electrical equipment is 50% and the margin of safety
is 40%. BEP of the firm at a sales volume of ₹50,00,000 will be
(A) ₹25,00,000
(B) ₹35,00,000
(C) ₹30,00,000
(D) ₹36,00,000
25. ABC Limited has current PBIT of ₹19.20 lakhs on total assets of ₹96 lakhs. The company
has decided to increase assets by ₹24 lakhs, which is expected to increase the
operating profit before depreciation by ₹8.40 lakhs. There will be a net increase in
depreciation by ₹4.80 lakhs. This will result in ROI
(A) to increase by 1%
(B) to decrease by 1%
(C) to decrease by 1.5%
(D) to remain the same
26. For a Learning Curve percentage of 72%, the time to be taken to complete the 4th unit
of a 12-unit job involved in the assembly line, if the initial unit requires 80 hours, will be
(A) 43.50 hrs
(B) 41.47 hrs
(C) 46.71 hrs
(D) 40.95 hrs
27. Marketing department of an organisation estimates that 40,000 of new mixers could be
sold annually at a price of ₹60 each. To design, develop and produce these new mixers
an investment of ₹40,00,000 would be required. The company desires a 15% return on
investment (ROI). Given these data, the target cost to manufacture, sell, distribute and
service one mixer will be
(A) ₹37.50
(B) ₹40.00
(C) ₹45.00
(D) ₹48.60
28. When you wait until the manufacture of a product has been completed and then
record all of the related issuances of inventory from stock that were required to create
the product, it is called
(A) Forensic Accounting
30. A company uses traditional standard costing system. The inspection and set-up costs
are actually ₹1,760 against a budget of ₹2,000. ABC system is being implemented and
accordingly the number of batches is identified as the cost driver for inspection and set
up. The budgeted production is 10,000 units in batches of 1,000 units whereas actually
9,000 units were produced in 11 batches. The cost per batch under ABC system will be
(A) ₹160
(B) ₹200
(C) ₹180
(D) ₹220
31. A company has the capacity of production of 80,000 units and presently sells 20,000
units at ₹100 each. The demand is sensitive to selling price and it has been observed
that with every reduction of ₹10 in selling price the demand is doubled. What should be
the target cost at full capacity if profit margin on sale is taken as 25%?
(A) ₹75
(B) ₹90
(C) ₹60
(D) ₹25
32. If the direct labour cost is reduced by 20% with every doubling of output, what will be
the cost of labour for the sixteenth unit produced as an approximate percentage of the
cost of the first unit produced?
(A) 51.2%
(B) 40.96%
(C) 62%
(C) None of these
33. A company determines its selling price by marking up variable costs 60%. In addition,
the company uses frequent selling price mark down to stimulate sales. If the mark down
average 10%, what is the company’s contribution margin ratio?
(A) 30.6%
(B) 44%
(C) 86.4%
(D) None of these
34. B Ltd. Has earned net profit of ₹1 lakh, and its overall P/V ratio and margin of safety are
25% and 50% respectively. What is the total fixed cost of the company?
(A) ₹2,50,000
(B) ₹2,00,000
(C) ₹3,00,000
(D) ₹1,00,000
35. The total cost of manufacturing a component is as under at a capacity of 50,000 units
of production:
₹
Prime Cost 10.00
Variable Overheads 2.40
Fixed Overheads 4.00
16.40
The selling price is ₹21 per unit. The variable selling and administrative expenses is 60
paise per component extra. During the next quarter only 10,000 units can be produced
and sold. Management plans to shut down the plant estimating that the fixed
manufacturing cost can be reduced to ₹74,000 per quarter. When the plant is
operating, the fixed overheads are incurred at a uniform rate throughout the year.
Additional costs of plant shutdown for the quarter are estimated at ₹14,000. The shut
down pint for the quarter in units of product will be:
(A) ₹25,000
(B) ₹14,000
(C) ₹11,000
(D) ₹20,000
36. A company manufactures two products using common material handling facility. The
total budgeted material handling cost is ₹60,000. The other details are:
Product X Product Y
Number of Units Produced 30 30
Material moves per product line 5 15
Direct Labour hour per unit 200 200
Under activity based costing system the material handling cost to be allocated to
product X (per unit) would be:
(A) ₹1,000
(B) ₹500
(C) ₹1,500
(D) ₹2,500
37. A company operates throughput accounting system. The details of product X per unit
are as under.
Selling Price ₹50
Material Cost ₹20
Conversion Cost ₹15
Time on bottleneck resources 10 minutes
The return per hour for product X is:
(A) ₹210
(B) ₹300
(C) ₹180
(D) ₹90
38. The information relating to the direct material cost of a company is as under:
₹
Standard Price per unit 3.60
Actual quantity purchased in units 1,600
Standard quantity allowed for actual production in units 1,450
Material Price Variance on purchase (favourable) 240
What is the actual purchase price per unit?
(A) ₹3.45
(B) ₹3.75
(C) ₹3.20
(D) ₹3.25
39. If the time taken to produce the first unit of a product is 4000 hrs, what will be the total
time taken to produce the 5th to 8th unit of the product, when a 90% learning curve
applies?
(A) 10,500 hours
(B) 12,968 hours
(C) 9,560 hours
(D) 10,368 hours
40. A company has forecast sales and cost of sales for the coming year as ₹25 lakhs and
₹18 lakhs respectively.
The inventory turnover has been taken as 9 times per year. In case the inventory
turnover increases to 12 times and the short term interest rate on working capital is
taken as 10%, what will be saving in cost?
(A) ₹10,000
(B) ₹20,000
(C) ₹15,000
(D) ₹5,000
41. Which of the following would decrease unit contribution margin the most?
(A) 15% decrease in selling price
(B) 15% increase in variable costs
(C) 15% decrease in variable costs
(D) 15% decrease in fixed costs
42. A company produces two joint products, P and V. In a year, further processing costs
beyond split-off point spent were ₹8,000 and ₹12,000 for 800 units of P and 400 units of
V respectively. P sells at ₹25 and V sells at ₹50 per unit. A sum of ₹9,000 of joint cost
were allocated to product P based on the net realization method. What were the total
joint cost in the year?
(A) ₹20,000
(B) ₹10,000
(C) ₹15,000
(D) None of these
43. A company is to market a new product. It can produce up to 1,50,000 units of this
product. The following are the estimated cost data:
Fixed Cost Variable Cost
For Production upto 75,000 units ₹ 8,00,000 60%
Exceeding 75,000 units ₹12,00,000 50%
Sale price is expected to be ₹25 per unit.
How many units must the company sell to break even?
(A) 1,00,000 units
(B) 1,11,000 units
(C) 1,27,000 units
(D) 75,000 units
44. The following details relate to two competing companies, Alps and Himalayas, for
identical projects:
I. The net present value (NPV) of Alps is ₹20,000 and its internal rate of return (IRR) is
18%.
II. For the same life period, Himalayas estimated cash flows are:
Year ₹ ‘000
0 (450)
1 300
2 200
3 100
And its cost of capital is 15%.
Which one of the following combinations is correct concerning the NPV and the IRR of
the two projects?
Projects
Alps Himalayas
A) Higher NPV Higher IRR
B) Higher NPV Lower IRR
C) Lower NPV Higher IRR
D) Lower NPV Lower IRR
45. Nulook Ltd. Uses a JIT system and back flush accounting. It does not use a raw material
stock control account During May, 8000 units were produced and sold. The standard
cost per unit is ₹100; this includes materials of ₹45. During May, ₹4,80,000 of conversion
costs were incurred.
The debit balance on cost of goods sold account for May was
(A) ₹8,00,000
(B) ₹8,40,000
(C) ₹8,80,000
(D) ₹9,20,000
46. A company has estimated the selling prices and the variable costs of one of its products
as under:
Probability Selling Price (Per unit) Probability Variable Cost (Per unit)
0.25 60 0.25 30
0.45 75 0.40 45
0.30 90 0.35 60
The company will be able to produce and sell 4,000 units in a month irrespective of the
selling price. The selling price and variable cost per unit are independent of each other.
The specific fixed cost relating to this product is ₹20,000. The probability that the
monthly net profit of the product will be ≥ ₹1,20,000 is
(A) 0.2525
(B) 0.4512
(C) 0.3825
(D) 0.3075
47. In calculating the life cycle costs of a product, which of the following items would be
included?
A. Planning and concept design costs B. Preliminary and detailed design costs
C. Testing costs D. Production costs E. Distribution costs
(A) All of the above
(B) D and E
(C) B, D and E
(D) D
48. A Ltd., developing a new product, makes a model for testing and goes for regular
production. From past experience of similar models, it is known that a 90% learning
curve applies. If the time taken to make the model is 300 hours, what will be the total
time taken to produce 3rd to 4th unit of the product?
(A) 540 hours
(B) 486 hours
(C) 432 hours
(D) None of the above
49. A particular job required 800 kgs of material – P. 500 kgs. of the particular material is
currently in stock. The original price of the material – P was ₹300 but current resale value
of the same has been determined as ₹200. If the current replacement price of the
material – P is ₹0.80 per kg., the relevant cost of the material – P required for the job
would be:
(A) ₹640
(B) ₹440
(C) ₹300
(D) None of these
50. A company has 2000 units of an obsolete item which are carried in inventory at the
original purchase price of ₹30,000. If these items are reworked for ₹10,000, they can be
sold for ₹18,000. Alternatively, they can be sold as scrap for ₹3,000 in the market. In a
decision model used to analyze the reworking proposal, the opportunity cost should
be taken as:
(A) ₹8,000
(B) ₹12,000
(C) ₹3,000
(D) ₹10,000
51. When allocation service department cost to production departments, the method that
does not consider different cost behavior patterns is the
(A) Step method
(B) Reciprocal method
(C) Single rate-method
(D) Dual rate-method
52. ASHLIN LTD., has developed a new product just complete the manufacture of first four
units of the product. The fist unit took 2 hours to manufacture and the first four units
together took 5.12 hours to produce. The Learning Curve rate is
(A) 83.50%
(B) 80.00%
(C) 75.50%
(D) None of (A), (B) or (C)
53. ANKIT LTD. operates Throughput Accounting System. The details of product A per unit
are as under:
₹
Selling Price 75
Material Cost 30
Conversion Cost 20
Time to Bottleneck Resources 10 minutes
The return per hour for product A is
(A) ₹270
(B) ₹150
(C) ₹120
(D) ₹90
54. A company has a capacity to make 4,00,000 units of a product. It has noted from
market conditions that at a price of ₹50 per unit, it can sell 1,00,000 units but the
demand would double for each ₹5 fall in the selling price. A minimum margin of 25% is
required. The target cost for the company should be:
(A) ₹50
(B) ₹40
(C) ₹30
(D) ₹20
55. Division A of a company manufactures a single product and the following data are
provided:
Sales = 25,000 units Fixed Cost = ₹4,00,000
Depreciation = ₹2,00,000 Residual Income = ₹30,000
Net Assets = ₹10,00,000
Head Office assesses divisional performance by the method of Residual Income and
uses cost of capital of 12%
(A) ₹25
(B) ₹30
(C) ₹35
(D) None of these
56. A company makes components and sells internally to its subsidiary and also to external
market. The external market price is ₹24 per component, which gives a contribution of
40% of sales. For external sales, variable costs include ₹1.50 per unit for distribution
costs. This is, however not incurred in internal sales. There are no capacity constraints.
To maximize company profit, the transfer price to subsidiary should be:
(A) ₹9.60
(B) ₹12.90
(C) ₹14.40
(D) None of these
57. The information relating to the direct material cost of a company is as under:
₹
Standard Price per unit 3.60
Actual quantity purchased in units 1,600
Standard quantity allowed for actual production in units 1,450
Material Price Variance on purchase (favourable) 240
What is the actual purchase price per unit?
(A) ₹3.45
(B) ₹3.75
(C) ₹3.20
(D) ₹3.25
58. SUVAM Ltd., has the capacity of production of 80,000 units and presently sells 20,000
units at ₹100 each. The demand is sensitive to selling price and it has been observed
that with every reduction of ₹10 in selling price, the demand is doubled. What should
be the target cost at full capacity if profit margin on sale is taken as 25%?
(A) ₹67.50
(B) ₹60.00
(C) ₹45.00
(D) None of the above
59. A company makes and sells a single product. The selling price and marginal revenue
equations are:
Selling Price = ₹50 - ₹0.001X
Marginal Revenue = ₹50 - ₹0.002X
Where X is the product the company makes. The variable cost amount to 20 per unit
and the fixed costs are ₹1,00,000. In order to maximize the profit, the selling price should
be
(A) ₹25
(B) ₹30
(C) ₹35
(D) ₹40
60. A Company requires ₹85,00,000 in sales to meet its target net profit. Its contribution
margin is 30% and the fixed costs are ₹15,00,000. What is the target net profit?
(A) ₹10,50,000
(B) ₹19,50,000
(C) ₹25,50,000
(D) ₹35,00,000
61. In a factory where standard costing system is followed, the production department
consumed 1100 kgs of a material @ ₹8 per kg for product X resulting in material price
variance of ₹2200 (Fav) and material usage variance of ₹1000 (Adv). What is the
standard material cost of actual production of product X?
(A) 11,000
(B) 20,000
(C) 14,000
(D) 10,000
63. By making and selling 9,000 units of a product, a company makes a profit of ₹10,000,
whereas in the case of 7,000 units, it would lose ₹10,000 instead. The number of units to
break-even is
(A) 7,500 units
(B) 8,000 units
(C) 7,750 units
(D) 8,200 units
64. 1200 units of microchips are required to be sold to earn a profit of ₹1,06,000 in a
monopoly market. The fixed cost for the period is ₹74,000. The contribution in the
monopoly market is as high as 3/4th of its variable cost. Determine the target selling
price per unit.
(A) 450
(B) 325
(C) 400
(D) 350
65. An operation has a 90% learning curve and the first unit produced took 28 minutes. The
labour cost is ₹20 per hour. How much should the second unit cost?
(A) ₹9.80
(B) ₹7.60
(C) ₹8.40
(D) ₹6.60
66. If project A has a net present value (NPV) of ₹30,00,000 and project B has an NPV of
₹50,00,000, what is the opportunity cost if project B is selected?
(A) ₹23,00,000
(B) ₹30,00,000
(C) ₹20,00,000
(D) ₹50,00,000
67. A company operates an activity based costing (ABC) system to attribute its overhead
costs to cost objects. In its budget for the year - ending 31st August, 2018. The company
expected to place a total of 2000 purchase orders at a total cost of ₹1,00,000. This
activity and its related costs were budgeted to occur at a constant rate throughout the
budget year which is divided into 13 four week periods.
During the four week period ended 30th June 2017, a total of 200 purchase orders were
placed at a cost of ₹9,000. The over recovery of these costs for the four week period
was
(A) ₹2,000
(B) ₹3,000
(C) ₹1,500
(D) ₹1,000
68. Empire Hotel has a capacity of 100 single rooms and 20 double rooms. Average
occupancy is 70% for 365 days of the year. The rent for a double room is kept at 130%
of a single room. The total room occupancy days in a year in terms of single room is
(A) 32193
(B) 30660
(C) 31660
(D) 30993
70. A company has a break even point when sales are ` 3,20,000 and variable cost at that
level of sales are `2,00,000. How much would contribution margin increase or decrease
if variable expenses are dropped by 30,000?
`
(A) Increase by 27.5%
(B) Increase by 9.375%
(C) Decrease by 9.375%
(D) Increase by 37.5%
71. Twin Ltd. uses JIT and back flush accounting. It does not use a raw material stock control
account. During September 2018, 10000 units were produced and sold. The standard
cost per unit is `150 which includes materials of ` 60. During September 2018, ` 9,90,000
of conversion costs were incurred. The debit balance in cost of goods sold account for
September 2018 was
(A) ` 14,00,000
(B) ` 14,80,000
(C) ` 15,90,000
(D) `16,20,000
72. A company operates a standard absorption costing system. The budgeted fixed
production overheads for the company for last year were ` 3,30,000 and budgeted
output was 2,20,000 units. At the end of the company’s financial year, the total of the
fixed production overheads debited to the Fixed Production Overhead Control
Account was ` 2,60,000 and the actual output achieved was 2,00,000 units. The
under/over absorption of overhead was
(A) ` 40,000 over absorbed
73. A factory can make only one of the three products X, Y or Z in a given production
period. The following information are given:
Per unit ` X Y Z
Selling Price 1500 1800 2000
Variable Cost 700 950 1000
Assume that there is no constraint on resource utilization or demand and similar
resources are consumed by X, Y and Z. The opportunity cost of making one unit of Z is
(A) ` 850
(B) ` 800
(C) ` 1800
(D) ` 1500
75. S Ltd. manufactures a product whose time for the first unit is 1000 hours. It experience a
learning curve of 80%, What will be the total time taken in hours for unit 5 to 8?
(A) 4096 hours
(B) 3200 hours
(C) 1536 hours
(D) 2000 hours
76. H Group has two divisions, Division P and Division Q. Division P manufactures an item
that is transferred to Division Q. The item has no external market and 6000 units
produced are transferred internally each year. The costs of each division are as
follows?
Division P Division Q
Variable Cost ` 100 per unit ` 120 per unit
Fixed cost each year ` 1,20,000 ` 90,000
Head Office management decided that a transfer price should be set that provides a
profit of ` 30,000 to Division P. What should be the transfer price per unit?
(A) ` 145
(B) ` 125
(C) ` 120
(D) ` 135
77. In the context of Critical Path Analysis, the portion of the float of an activity which
cannot be consumed without affecting adversely the float of the subsequent activities
is called
(A) Free float
(B) Interfering float
(C) Independent float
(D) Total float
78. In CPA (Critical Path Analysis) which of the following is not a correct step in sequence?
(A) Understanding the logic of the system under consideration
(B) Constructing the net work
(C) Providing estimates for activity duration
(D) Implementing and controlling the net work
79. XYZ Ltd. has the following alternative planned activity levels.
Level E F G
Total cost ₹ 1,00,000, ₹ 1,50,000, ₹ 2,00,000
No. of units produced 5000 10000 15000
If fixed overhead remains constant, then fixed overhead cost per unit at Level E is
(A) ₹ 20
(B) ₹ 15
(C) ₹ 13.33
(D) ₹ 10
80. T Ltd. produces and sells a product. The company expects the following revenues and
costs in 2018:
Revenues (400 sets sold @ ₹600 per product) ₹ 2,40,000
Variable costs ₹ 1,60,000
Fixed costs ₹ 50,000
What amount of sales must T Ltd. have to earn a target net income of ₹63,000 if they
have a tax rate of 30%?
(A) ₹ 4,20,000
(B) ₹ 4,29,000
(C) ₹ 3,00,000
(D) ₹ 4,89,000
81. Excel Products Ltd. manufactures four products e.g. Product E, Product F, Product G and
Product H using same raw materials. The input requirements for Products E, F, G and H
are 1kg, 2kgs, 5kgs and 7kgs, respectively. Product-wise Selling Price and Variable
Cost data are given hereunder:
Products E F G H
Selling Price (₹) 100 150 200 300
Variable Cost (₹) 50 70 100 125
Assuming raw material availability is a limiting factor, the correct ranking of the
products would be:
(A) E, F, G & H
(B) E, F, H & G
(C) F, E, G & H
(D) F, E, H & G
82. S Ltd. recently sold an order of 50 units having the following costs:
₹
Direct materials 1,500
Direct labour (1000 hours @ ₹ 8.50) 8,500
Variable overhead (1000 hours @ ₹ 4.00)1 4,000
Fixed overhead2 1,400
15,400
1 Allocated on the basis of direct labour-hours.
2 Allocated at the rate of 10% of variable cost.
The company has now been requested to prepare a bid for 150 units of the same
product.
If an 80% learning curve is applicable, Stone Isle’s total cost on this order would be
(A) ₹ 38,500
(B) ₹ 37,950
(C) ₹ 26,400
(D) ₹ 31,790
84. AB Ltd. uses standard cost system. The following information pertains to direct labour
for Product X for the month of March, 2019:
Standard rate per hour ₹8
Actual rate per hour ₹ 8.40
Standard hours allowed for actual production 2000 hours
Labour Efficiency variance ₹ 1,600 (Adverse)
What were the actual hours worked?
(A) 1,800
(B) 1,810
(C) 2,200
(D) 2,190
85. X Ltd. has 1000 units of an obsolete item which are carried in inventory at the original
price of ₹50,000. If these items are reworked for ₹20,000, they can be sold for ₹36,000.
Alternatively, they can be sold as a scrap for ₹6,000 in the market. In a decision model
used to analyse the reworking proposal, the opportunity cost should be taken as
(A) ₹ 16,000
(B) ₹ 6,000
(C) ₹ 30,000
(D) ₹ 20,000
86. Uniform Costing may not be successfully applied in the following case:
(A) In a single enterprise having a number of branches, each of which manufactures
the same set of products with the same facilities
(B) In a number of entities in the same industry bound by a trade association
(C) In a number of units across different geographical locations manufacturing one or
more of a given set of products
(D) In different branches of the same company, each branch making a different
product using a unique process
87. Which of the following is a valid constraint for a linear programming problem?
(A) 3x2 + 4x + 1 = 0
(B) 5xt + 2x2 ≤ 10
(C) 4xx + 3x2 > 7
(D) (12x1 + 4x2)/3x2 ≤ 8x1
88. The shadow price of skilled labour for SD Ltd. is currently ₹ 10 per hour. What does this
mean?
(A) The cost of obtaining additional skilled labour is ₹ 10 per hour
(B) There is a hidden cost of ₹ 10 for each hour of skilled labour actively worked
(C) Contribution will be increased by ₹10 per hour for each extra hour of skilled labour
that can be obtained
(D) The total costs will be reduced by ₹10 for each additional hour of skilled labour that
can be obtained
89. The break-even point of a manufacturing company is ₹1,60,000. Fixed cost is ₹48,000.
Variable cost is ₹ 12 per unit. The PV ratio will be:
(A) 20%
(B) 40%
(C) 30%
(D) 25%
90. A factory has a key resource (bottleneck) of Facility A which is available for 31,300
minutes per week. The time taken by per unit of Product X and Y in Facility A are 5
minutes and 10 minutes respectively. Last week’s actual output was 4750 units of
product X and 650 units of Product Y. Actual factory cost was ₹ 78,250. The throughput
cost for the week would be:
(A) ₹ 75,625
(B) ₹ 76,225
(C) ₹ 77,875
(D) ₹ 79,375
91. In a PERT network, the optimistic time for a particular activity is 9 weeks and the
pessimistic time is 21 weeks. Which one of the following is the best estimate of the
standard deviation for the activity?
(A) 12
(B) 9
(C) 6
(D) 2
93. X is a factory making a certain product where learning curve ratio of 80% and 90%
apply respectively for two equally paid workers, A and B
(A) The labour cost of manufacturing the 4th product will be more for A
(B) The labour cost of manufacturing the 4th product will be more for B
(C) The labour cost is the same for the fourth product
(D) Nothing can be said about the specific product since learning applies ratio to the
average quantity of the product
94. What is the opportunity cost of making a component part in a factory given no
alternative use of the capacity?
(A) The variable manufacturing cost of the component
(B) The total manufacturing cost of the component
(C) The total variable cost of the component
(D) Zero
95. The product of XYZ company is sold at a fixed price of ₹1,500 per unit. As per company’s
estimate, 500 units of the product is expected to be sold in the coming year. If the value
of investments of the company is ₹ 15 lakh and it has a target ROI of 15%, the target
cost would be:
(A) ₹ 930
(B) ₹ 950
(C) ₹ 1050
(D) ₹ 1130
96. Max Ltd. fixes the inter divisional transfer prices for its products on the basis of cost plus
a return on investment in the division. The budget for division X for 2019 – 20 appears as
under -
₹
Fixed assets 5,00,000
Current assets 3,00,000
Debtors 2,00,000
Annual fixed cost of the division 8,00,000
Variable cost per unit of the product 10
Budgeted volume 4,00,000 units per year
Desired ROI 28%
Transfer price for division X is
(A) ₹ 12.70
(B) ₹ 10.70
(C) ₹ 8.70
(D) ₹ 14.70
98. A manufacturing company uses two types of materials. X and Y, for manufacture of a
standard product. The following information is given:
Standard Mix Actual mix
Materials X 120 Kg @ ₹5 = 600 112 Kg @ ₹5 = 560
Y 80 Kg @ ₹10 = 800 88 Kg @ ₹10 = 880
200 1400 200 1440
30% loss 60 25% loss 50
140 1400 150 1440
Direct Materials Mix Variance is:
(A) ₹ 40 (fav.)
(B) ₹ 40 (unfav.)
(C) ₹ 80 (fav.)
(D) ₹ 80 (unfav.)
Answer Key:
(1) (A) Resale Value
The resale value is normally referred to as the ‘exchange value’
(2) (A) Batch production
Batch production uses stocks to supply customers whilst other products are being
produced. Stocks are avoided in a JIT system. Jobbing production makes products to
customer order and is ideal for JIT.
(3) (B) Internal price transfer price
The internal price is just another name for the TP. So it is not a method of transfer pricing.
(4) (B) If the product is new and different
Here market skimming would be more appropriate. A high price could be changed to
the ‘opinion leaders’ who want to be seen to have the new product and are prepared
to pay a high price.
(5) (B) (A), (B) and (C) only
At first inspection all four appear to be methods of arriving at selling price. However,
target costing is a method to arrive at the cost at which a product should be produced
for having worked backwards from the price already set for the product.
(6) (C) 45%
To generate a contribution greater than $20,000 it is necessary to earn a unit
contribution greater than ₹ 20. Consider each of the feasible combinations:
Sales = ₹50,00,000
Less: Margin of safety 40% on sales = ₹20,00,000
Break even sales = ₹30,00,000
(25) (B) to decrease by 1%
Before installing new assets After installing new assets
PBIT ₹19.20 lakhs = ₹19.20 lakhs +(₹8.40 lakhs – ₹4.80 lakhs
= ₹22.80 lakhs
Value of Assets ₹96.00 lakhs =₹96.00 lakhs + ₹24.00 lakhs
= ₹120.00 lakhs
ROT = 20% = 19%
Conclusion: There will be a decrease of 1% in ROI under the proposed dispensation.
(26) (B) 41.47 hrs
At 72% Learning Curve, T-4 - Time taken by the 4th Unit = 80 (.72)(.72) = 41.47 hrs.
Note: In the arithmetic method followed above, every time the number the number of
repetitions doubles, the time to perform the activity is reduced by the Learning Curve
Coefficient.
(27) (C) ₹45.00
Projected sales (40,000 mixers X ₹60 per mixer) (A) = ₹24,00,000
Less desired profit (15% of ₹40,00,000) (B) = ₹6,00,000
Target Cost for 40,000 mixers (A - B) = ₹18,00,000
Target cost per mixer (₹18,00,000 / 40,000 mixer) = ₹45.00 per unit
(28) (B) Back-flush Accounting
(29) (C) A-2, B-3, C-1, D-4
(30) (B) ₹200
Number of batches under ABC = 9000 ÷ 1000 = 9
Std. Cost under ABC = Budget Cost / Batch × ABC number of batches
= ₹200 × 9 = ₹1800
Production 9000 Units
Number of batches 9
Cost /Batch ₹200
(31) (C) ₹60
Demand Price (₹)
20,000 100
40,000 90
80,000 80
Target Cost = ₹80 – (25% of ₹80) = ₹80 – ₹20 = ₹60
(32) (B) 40.96%
Units Average Time (hours)
1st 100%
2nd 80% x 100%
4th 80% of 2nd
8th 80% of 4th
16th 80% of 8th = 0.80 x 0.80 x 0.80 x 0.80 = 40.96%
Say, 41% of the time required for the 1st Unit.
(33) (A) 30.6%
When V (Var. cost) = 100, SP = 160, M.Cost/SP = 60/100
SP after 10% mark down of SP = 144, Cost = 60-16=44
Contribution Margin Ratio = 44/144=0.3056=30.6%
(34) (D) ₹1,00,000
MS=Profit/PV Ratio = ₹4 Lakh: MS=50%; BE Sales = (1 - 0.50) = 0.50 Hence BES = ₹4 lakh
Fixed Cost 25% of ₹4,00,000 = ₹1,00,000
(35) (B) ₹14,000
Contribution per unit of component ₹ ₹
Variable Prime Cost 10.00
Variable Overhead 2.40
Selling / Administrative Expenses 0.60 13.00
Contribution 8.00
Avoidable fixed cost per quarter
= total fixed cost - (unavoidable fixed cost + additional shut down cost)
= (50,000 x ₹4) (₹74,000 + ₹14,000) = ₹1,12,000.
The required shut down point for the quarter = ₹1,12,000 / ₹8 = 14,000 units.
(36) (B) ₹500
Total moves in material handling = 5+15=20
Percentage move for Product A = 5/20 = 25%
Material handling cost to be allocated to Product A = ₹60,000/25% = ₹15,000
i.e., ₹15,000/30 = ₹500 per unit.
(37) (C) ₹180
(Selling Price - Material Cost)/ Time of bottleneck resource
= [(₹50 - ₹20)/10 minutes] x 60 = ₹180 per hour.
(38) (A) ₹3.45
Actual quantity bought x standard price = 1,600 x ₹3.60 = ₹5,760
Deduct favorable price variance = 240
Actual quantity x actual price = 5,520 Or, 1,600 x actual price = ₹5,520
So, Actual price ₹5,520/1,600 = ₹3.45
(39) (D) 10,368 hours
Units Average Time (hours) Total Time (hours)
1 4000 4000
2 3600 7200
4 3240 12960
8 2916 23328
Total Time for 5th to 8 units = 23328 – 12960 = 10,368 hrs.
(40) (D) ₹5,000
18,00,000 10 18,00,000 10
Saving Cost = × - ×
9 100 12 100
(41) (A) 15% decrease in selling price
A given percentage change in unit sale price must have greater effect on contribution
margin than any other factor affected by the same percentage change.
(42) (C) ₹15,000
Products P V Total
Units 800 400
S.P. (₹) 25 50
Sales (₹) 20,000 20,000
Further costs (₹) 8,000 12,000
NRV (₹) 12,000 8,000 20,000
Joint cost appropriated ₹9,000
Total Joint Cost = (9,000/12,000) x 20,000 = ₹15,000
(43) (B) 1,11,000 units
At a production of 75,000 units or less the fixed costs amount to ₹8 lakh
Contribution is ₹10 per unit (₹25 - 60% of ₹25).
Production will however, be more than this level. Total fixed cost is then ₹12 lakh.
Contribution for first 75,000 units = ₹7,50,000
Hence, to meet ₹12 lakh fixed cost, further ₹4,50,000 contribution is required.
Contribution beyond 75,000 units is ₹12.5 (₹25 - 50% of ₹25).
Additional units to be sold = ₹4,50,000 / ₹12.50 = 36,000) units = 1,11,000 units
(44) (C) Lower NPV; Higher IRR
Working for Himalayas
NPV 28 (3)
Hence IRR = 20% (approx.)
Projects
Alpas Himalayas
Lower NPV Higher IRR
(45) (B) ₹8,40,000
`
Cost of goods sold 8,00,000
(Less) Material Cost (3,60,000)
Conversion Cost Allocated 4,40,000
Conversion Cost incurred 4,80,000
Excess charged to cost of goods sold 40,000
account
Total debit on cost of goods sold account = ₹8,00,000 + ₹40,000 = ₹8,40,000
(46) (D) 0.3075
The sales demand is 4,000 units per month. The monthly contribution must absorb the
fixed costs of ₹20,000 and leave at least a surplus of ₹1,20,000 profit. So, the contribution
per unit must be ₹1,40,000/4,000 units = ₹35 in the minimum.
The following selling price and variable cost pairs will produce a contribution of more
than ₹35.
Selling Price Variable Cost Contribution Joint Probability of SP & VC
75 30 45 0.45 x 0.25 = 0.1125
90 30 60 0.30 x 0.25 = 0.0750
90 45 45 0.30 x 0.40 = 0.1200
0.3075
If B is chosen, only A is being foregone and hence the NPV of 30,00,000 is the present
value of the opportunity lost.
(67) (D) ₹1,000
For 2,000 purchase orders, cost budgeted is 1 lac.
For 200, corresponding amount would be 10,000.
But actual = 9,000. Hence over recovered is 10,000 – 9000 = 1000.
Or
Cost driver rate for order = 1,00,000 / 2,000 = 50 per order.
Cost recovered = 50 × 200 = 10,000.
Actual = 9,000
Over recovery = 1000
(68) (A) 32193
1 double room = 1.3 single in terms of revenue.
Capacity = 100 + 1.3 × 20 = 100 + 26 = 126 equivalent single rooms.
Total Room Occupancy p.a. = 126 × 365 × 70% = 32193 days.
Note: This can be arrived at by other ways also, taking for example 70% of only single
rooms and then double rooms, etc.
(69) (A) There can be one or more activities without a predecessor in a network.
More than 1 activity can begin at the first node, say 1 – 2, 1 – 3, 1 – 4, etc.
Each of these will have no predecessor.
(70) (B) Increase by 9.375%
S – V = C = `3,20,000 – 2,00,000 = `1,20,000
, ,
c/s ratio = x 100 = 37.5%
, ,
New VC = ` 1,70,000,
C = `1,50,000
, ,
c/s ratio = x 100 = 46.875% %
, ,
% increase in c = 46.875 – 37.5% = 9.375%
(71) (C) ` 15,90,000
Standard cost of goods sold 15,00,000
(10,000 units @ `150)
Less : Std. material cost 6,00,000
(10,000 @ ` 60) 9,00,000
Standard conversion cost
Conversion cost incurred 9,90,000
Excess charged to cost of goods .
sold a/c. (debit) 90,000
Total debit balance of cost of goods sold
Account = `15,00,000 + 90,000 = `15,90,000
(72) (A) `40,000 over absorbed
` 3,30,000
Overhead Absorption Rate =
2,20,000 units = `1.50/unit
=
` 50,000 + 90, 000
`
1
3
= ` 4,20,000
(81) (B) E, F, H & G
Ranking of products would in order of contribution per limiting factor, in relative value.
E F G H
SP (₹) 100 150 200 300
VC (₹) 50 70 100 125
Contribution per unit 50 80 100 175
RM/unit (kg) 1 2 5 7
Contribution per kg of RM (₹) 50 40 20 25
Rank 1 2 4 3
Correct Order of ranking : E, F, H & G
(82) (C) ₹26,400
Cumulative hours 200 × (20×0.8×0.8) = 2560
Less: 50×20 = 1000
Net hours for 150 units = 1560
Cost : Direct Materials 150×30 = 4,500
Direct Labour 1560 × 8.50 =13,260
Variable Overhead 1560 × 4 = 6,240
Total Variable Cost = 24,000
Allocated Fixed OH = 10% = 2400
Estimated Cost of the Order = 26,400
(83) (D) ₹1,10,280
Indirect costs per machine: `
Material handling ₹8 × 50 = 400
Machining ₹68 × 12 = 816
Assembly ₹75 × 15 = 1,125
Inspection ₹104 × 4 = 416
= 2,757
= ₹1,500 – ₹450
= ₹1,050 per unit.
(96) (A) ₹12.70
Per unit (₹)
VC 10.00
FC (₹ 8, 00,000 ÷ 4, 00,000) 2.00
Investment: (FA + CA + Debtors) = ₹10, 00,000
``10, 00, 000 × 0.28
Return = 0.70
4, 00, 000
TP for Div. X 12.70
(97) (D) Inspection, Machine hours
Inspection hours, and not machine hours, drive the cost of inspection.
(98) (B) ₹40 (unfav.)
Direct Materials Mix Variance is: ₹ 40 (unfav.)
SP (SQ – AQ)
X ₹ 5 (120 – 112) = ₹40 (fav.)
Y ₹10 (80 – 88) = ₹80 (unfav)
= ₹40 (unfav)