662061
662061
BY
SİMGE VURĞUN ÇELİKEL
JANUARY 2021
Enhanced Project Delivery From Construction to
Operations And BIM Use In Facility Management: Istanbul
Airport Case Study
Supervisor
Assist. Prof. Dr. Mehmet Sakin
By
Simge Vurğun Çelikel
January 2021
ii
© 2021 [Simge VURĞUN ÇELİKEL]
iii
APPROVAL FORM PAGE
iv
ABSTRACT
VURĞUN, Simge
M.Sc. in Civil Engineering
Supervisor: Assist. Prof. Dr. Mehmet SAKİN
January 2021
89 pages
v
ÖZET
Anahtar Kelimeler: Yapı Bilgi Modellemesi, Tesis Yönetimi, Proje Teslimi, Dijital
İkiz
vi
ACKNOWLEDGEMENTS
First of all, I would like to express my gratitude to all people, who in one way or
another contributed to the development of this research. I would like to express my
sincere appreciation to my thesis supervisor Dr. Mehmet Sakin for his guidance,
support and helpful critics throughout the progress of my thesis study.
I also would like specially thank to İstanbul Airport Management and BIM
Departmant, for supporting my research activities, sharing his experinces and offering
an employment opportunity.
Finally, I would like to dedicate my thesis to my dearest family. I cannot ignore their
motivating attitudes, encouragement during each phase and guidance throughout my
thesis and my life.
January 2021
Simge VURĞUN ÇELİKEL
vii
TABLE OF CONTENTS
ABSTRACT ................................................................................................................. v
ÖZET........................................................................................................................... vi
ACKNOWLEDGEMENTS ....................................................................................... vii
TABLE OF CONTENTS .......................................................................................... viii
LIST OF FIGURES ..................................................................................................... x
LIST OF TABLES ..................................................................................................... xii
LIST OF ABBREVIATIONS ................................................................................... xiii
CHAPTER 1 ................................................................................................................ 1
INTRODUCTION ....................................................................................................... 1
1.1. Background of the Research ............................................................................. 2
1.2. Problem Statement and Research Questions ..................................................... 3
1.3. Aims and Objectives of the Research ............................................................... 4
1.4. Research Methodology ..................................................................................... 4
1.5. Organization of the Thesis ................................................................................ 5
CHAPTER 2 ................................................................................................................ 6
REVIEW OF BIM IMPLEMENTATION IN BUILDING LIFECYCLE ................... 6
2.1. Definition of BIM ............................................................................................. 6
2.2. International Development of BIM ................................................................... 7
2.3. The Need for BIM ............................................................................................. 9
2.3.1. Benefits of BIM Implementation for Project Handover and FM ............ 11
2.3.2. Barriers of BIM Implementation for Project Handover and FM ............ 13
2.4. BIM Basics ...................................................................................................... 14
2.4.1. BIM Maturity Levels .............................................................................. 14
2.4.2. Dimensions of BIM ................................................................................. 16
2.4.3. Information and Model Development ..................................................... 18
2.5. Lifecycle of a Building ................................................................................... 21
2.5.1. Handover of Information Between Project Phases ................................. 23
2.5.2. Challenges in Construction to Operations Handover .............................. 24
2.6. BIM Enabled Construction Management........................................................ 25
2.7. BIM Enabled Facility Management ................................................................ 27
CHAPTER 3 .............................................................................................................. 29
RESEARCH METHODOLOGY ............................................................................... 29
3.1. Research Approach ......................................................................................... 29
3.1.1. Qualitative Approach .............................................................................. 29
viii
3.1.2. Quantitative Approach ............................................................................ 30
3.2. Research Strategy ............................................................................................ 30
3.3. Data Collection & Data Analysis .................................................................... 30
3.4. Research Design .............................................................................................. 31
CHAPTER 4 .............................................................................................................. 33
A CASE STUDY OF ISTANBUL AIRPORT PROJECT – HOW DIGITAL
AIRPORT BECOME A REALITY ? ........................................................................ 33
4.1. Project Information ......................................................................................... 33
4.2. BIM Execution in Istanbul Airport ................................................................. 36
4.3. Construction Management with BIM.............................................................. 40
4.3.1. Digital Site Engineering .......................................................................... 41
4.3.2. QA/QC and Project Control .................................................................... 45
4.3.3. 4D BIM to Schedule ............................................................................... 48
4.4. BIM for Sustainability..................................................................................... 50
4.5. Facility Management with BIM ...................................................................... 53
4.6. Construction to Operations Delivery .............................................................. 58
4.6.1. BIM Model Development ....................................................................... 58
CHAPTER 5 .............................................................................................................. 65
RESULTS AND FINDINGS ..................................................................................... 65
5.1. Framework Development ................................................................................ 65
5.1.1. Integration Management ......................................................................... 68
5.1.2. Project Execution .................................................................................... 68
5.1.3. Handover and Facility Management Integration..................................... 69
5.1.4. Operational Process Management ........................................................... 70
CHAPTER 6 .............................................................................................................. 71
CONCLUSION .......................................................................................................... 71
REFERENCES........................................................................................................... 73
ix
LIST OF FIGURES
xi
LIST OF TABLES
xii
LIST OF ABBREVIATIONS
INTRODUCTION
Building Information Modeling (BIM) concept contains the most promising
technologies in the sectors of architecture, engineering and construction (AEC). The
advantages it provides make many companies want to incorporate and use BIM in their
complex projects. This purpose, however, is not very easy to put into practice because
of the subject's creativity and because of the great complexity that implies moving
from conventional processes to BIM (Eastman, et al., 2011). All participating parties
in AEC industry is involved in BIM processes (Figure 1).
Digital technology for the definition and display of information needed in the planning
, design , construction and operation of built installations is supported by building
information modeling. This modeling methodology is increasingly expanding, from
1
civil infrastructure, services and public space, to cover all aspects of the built
environment. These are collectively referred to as construction procedures. This
approach to knowledge management puts together the various collections of records
used during the designed environment's life cycle into a single database environment,
reducing and even removing the need for the many types of paper documentation
already in use (International Organization for Standardization, 2016).
BIM is a master, intelligent data model, resulting in an as-built database that can be
conveniently supplied upon completion of commissioning to the building operator.
With the implementation of BIM, CAD data with product descriptions, submissions,
shop drawings, project records, as-built documents and details on operations can be
combined in a single multi-dimensional platform which makes conventionally written
O&M and system manuals obsolete. The smart buildings of tomorrow are supposed
to require the complex interaction of design and information systems. In order to
maintain an optimal environment, building materials and systems can sense internal
and external conditions, predict changes, and automatically make necessary
adjustments. (National Institute of Building Sciences, 2016)
For various daytime exposures, space lighting would be changed and window control
systems would adapt automatically, such as blinds, louvers, environmentally reactive
glass. To track efficiency and possible degradation over time, wireless sensors will be
installed in building envelope materials, and then give facility managers early warning
of potential issues.
In a construction project, the use of BIM has both the possible advantage of enhancing
product efficiency and the introduction of more sustainable building design (Eastman
et al. 2011).
2
Even though BIM's financial and environmental advantages are generally recognized
(Eastman et al. 2011), The implementation of this new technology was sluggish
(Bernstein and Pittman 2005).
BIM is more commonly known in the construction industry because it interacts with
great visualization and planning in a software that can be easily reached by each
discipline. The construction industry has been faced with a paradigm change to
increase efficiency, infrastructure value, quality and sustainability and to reduce costs
and reworks by effective coordination and collaboration where the construction
managers faces a considerable amount of difficulty to successfully complete the
project. Building Information Modeling software can be a powerful new method for
facility managers to improve the efficiency of a building and more accurately manage
operations over the life of a building (Brinda & Prasanna, 2014).
How can BIM improve the efficiency on information and knowledge handover from
construction phase to the operations phase of a complex project?
What are the objectives to overcome success barriers for BIM implementation into the
building lifecycle of a complex project and how can we achieve those objectives?
3
What should be the effective approach to implement BIM for facility management in
a large scale project?
This thesis also analyses the adoption and execution of BIM in complex construction
projects with a case study of Istanbul Airport. The purpose of the research is to develop
the understanding of the benefits of BIM in such a large scale construction project in
terms of both construction to operations handover and airport operations management.
This thesis provides a conceptual guideline for implementation of BIM in the project
lifecycle.
This thesis also aims to describe the improvement of delivery, implementation and
execution of BIM in the Istanbul Airport.
The research will also outline the view on BIM within the complex construction,
identify the advantages that improve the quality, duration, cost, manufacturing,
planning and controlling with the help of BIM implementation.
4
implementation processes to the building lifecycle especially to facility management
phase together with it’s benefits and barriers. In order to create a strong ground for the
answers of the research questions and accomplishing the objectives of the thesis, a case
study was done about the execution, implementation and delivery stages of a complex
construction project, including the BIM based facility management activities and it’s
potential benefits. Details of the research methodology will be discussed further.
In Chapter 1, introduction and background about the research are given. Purpose of
the stduy and research objectives are explained briefly. Research methodology is
briefly explained which is given in detail in the following chapters.
In Chapter 4, a case study will be determined in terms of all aspects from design to
facility management stages.
In Chapter 6, a brief conclusion about the thesis and review of the thesis objectives are
given.
5
CHAPTER 2
A process for the sharing or disclosure of building details, including its construction,
operation, performance and maintenance. This has historically involved the sharing,
in paper or electronic format of drawings, schedules and manuals. The use of BIM will
improve performance and minimize errors. Until construction goes on site, simulated
structures are designed in three dimensions; the characteristics of all the components
of the building can be found in the model; and design issues can be defined and settled
instead of on site in the model, before the actual installations begin.
6
2.2. International Development of BIM
BIM principles can be traced back to the early days of computing in the 1960s, and in
the 1970s and 1980s, solid simulation systems started to appear. Many see the
development of the ArchiCAD software program in Hungary in 1982 as the true origin
of BIM, and the development of the Revit software program in 2000 saw a real change
towards the effective implementation of BIM (Bergin, 2010).
Although the technology underpinning BIM has been around for over two decades,
compared to industries such as manufacturing and engineering, BIM adoption and
take-up in the construction industry has been relatively slow. Over the past five years,
however, there has been a big change in momentum as technology and implementation
challenges progress and the industry recognizes the tremendous benefits to be achieved
by the use of this technology (RICS, 2013).
Industry Foundation Classes (IFCs) and aecXML (data structures for knowledge
representation) built by buildingSMART are often associated with BIM. IFC is ISO-
recognized and, since 2013, has become an official international standard, ISO 16739.
(BuildingSmart International, 2013)
7
By mandating its use on their programs, building customers and government agencies
are gradually becoming a driving force for the adoption of BIM, and technology and
implementation problems continue to improve. (Smith, 2014).
Countries that later implemented BIM mandates, especially the United Kingdom, have
developed mandates that specifically comply with the goal of reducing lifecycle costs;
potential adopters are likely to do the same; and countries with current mandates are
shifting their policies in this direction. (McGraw Hill Construction, 2014).
Together with those proposing a mandate, both countries mandating BIM want to
make sure that their construction industries keep pace with emerging innovations and
practices, believing them to be crucial to future success. In countries where BIM is not
yet required for public buildings, there is a general risk of falling behind competing
economies and a willingness to take advantage of business opportunities created by
BIM in robust construction markets, whether in the country or abroad (McGraw Hill
Construction, 2014). In Table 1, countries with national mandates are shown together
with the BIM data requirements and prerequisites for projects in order to be included
in the mandate.
8
Reduce errors and omissions
Norway: Statsbygg Architec- All national public Enhancing communications and
Statsbygg BIM Manual ture and projects collaboration
Gain efficiencies
1.2.1 handover Increase energy efficiency
data Use cutting edge research,
technologies and processes to
improve the built environment
Project
United lifecycle Reduce construction costs
Kingdom: The Govern- (architect- Reduce project delivery time
Cabinet Office of ment ure through All national public
Government Construc- O&M, projects Make UK's design and
Construction tion Strategy defined in constuction industry more
Board the U.K. As competitive
Help UK meet globally
carbon reduction
Level 2) targets for buildings
9
In addition to tracking the entire construction lifecycle, BIM-based systems will help
to track any single component of construction processes and operations (LetsBuild,
2019).
During the planning , programming, design , and construction stages, the knowledge
of a construction project gathered and generated by hte project parties offers a
tremendous resource of extremely useful information and data which may be used by
facility owners and managers to increase the efficiency of operations during the
building's lifecycle. The increasing use of BIM models for modeling, analysis,
construction planning, 4D coordination, and manufacturing offers an incentive for the
data in these models to be compiled and unified into an as-built model of facility
record.
10
The information in this model will facilitate the regular activities and planning needed
in order to ensure that the facility continues to function successfully and at peak
performance (Brinda & Prasanna, 2014). In Figure 2, a fully functional BIM aspects
can be seen.
Indeed, it is smart for clients and new adopters to settle for a partial BIM. But each of
the roles will carry and has much to learn from the common information pool. For any
single feature, most BIM-based projects do not implement overall BIM yet, but choose
the most suitable functions.
11
Table 2: Benefits of BIM Implementation for Project Handover and FM
Automating the process of data transfer and update: (Davtalaba and Delgadob, 2014)
12
Compared to conventional deployment and coordination approaches, the
implementation of BIM ventures involves a radical change of work processes and
habits (Carlsen, 2013).
In Figure 3, The MacLeamy Curve reflects the idea that the higher the cost of design
improvements, the more a project team is into the design process. For an integrative
design method, it makes a good argument. BIM mechanisms pull project partners
together faster than as in conventional methods, since before the model is assessed and
quality assured, all preparations must be done. This has a beneficial result, a benefit,
provided that the expense of improvements increases during the project process.
13
The existing BIM practice in FM scope, stakeholders do not completely implement
BIM in the FM industry and in existing FM operations that implemented BIM, most
functions are still performed manually even though the facility manager knows that
implementing BIM during operational construction will reduce the probability of
errors and increase efficiency (Becerik-Gerber et. al, 2014).
Main barriers of BIM implementation is listed in Table 3 which are derived from a
report by McGraw Hill Construction.
Table 3. BIM Implementation Barriers (adapted from McGraw Hill Construction, 2014)
Main Challenges
Training Investment
Cost/Funding/ Initial Investment
Buy-In Among Industry/ Adoption on Wider Scale
Not as Adaptable for Small Jobs
Lack of Standards for BIM Across the Industry
Lack of Skilled Users
14
Figure 4. BIM Maturity Levels (Source: bsi, PAS 1192-2:2013)
Level 0 It sure isn't BIM at all. This applies to the use of 2D CAD files for details on
design and development.
Level 1 is the first step towards true BIM and the use of 3D data to present concept is
the first step. At this stage, designers generally use managed CAD in 2D or 3D format
with shared resources to include a shared data environment where data structure and
interface specifications are used.
Level 2 is an structured 3D format with data attached, held in different BIM discipline
software resources. To correlate the work schedule, 4D BIM is used. Using costing
systems that use model data, 5D or cost-driven engineering is carried out and is
incorporated with BIM through proprietary interfaces.
15
2.4.2. Dimensions of BIM
BIM processes can be conceptualized by adding dimensions upon the virtual models
in 3D. Thus, The 3D model offers improved visualization, model operating, and
identification of clashes. The 4D model offers the opportunity to schedule, plan, track
and maintain a project. The 5D model allows for the calculation of quantity take-outs
and real-time and life cycle costs. The 6D model includes the measurement and
analysis of energy and discusses environmental distress. Facility operations, operation
and maintenance, and life-cycle analysis are given by the 7D model. BIM Dimensions
are listed in Figure 5 and detailed explanations are given in this section.
• Model Coordination
3D
• Time Management
4D
• Cost Management
5D
• Environmental Management
6D
BIM supports leaner building practices that can lead to higher prefabrication
consumption ratios, decreased inventories of engineered-to-order parts, increased
workflow stability, and improved coordination (Alarcón et al., 2013). Dimensions of
BIM are explained in detail in the following paragraphs.
3D Model: BIM's ultimate aims are to maximize productivity in terms of time, costs,
precision and thoroughness, to enhance coordination and to increase teamwork
(Hardin, 2009). In intelligent Building Information Models, an exact representation of
a completed project result may be visualized at an early level.
16
It is less difficult and more efficient to communicate design and engineering strategies
between stakeholders in the project. Models and their interconnected details are always
modified, and BIM makes changes and creation of real-time architecture. This usually
strengthens collaboration and lets disciplines move towards a shared purpose together
(Hattab and Hamzeh, 2013). Many potential contact errors are avoided by the model's
interoperability and the digital exchange of information. Digital Information Requests
(RFI) can be created by BIM, and in the model the installation of fabricated
components is noticeable (Hardin, 2009). Owing to the fact that all specialization
frameworks are merged under one core multidisciplinary model, rework and downtime
on site is minimized. This allows project partners the opportunity to measure the effect
of improvements more realistically and in real time on the final plan (Hattab and
Hamzeh, 2013). When using BIM, client engagement and customer loyalty are
improved. Involvement of the client in a BIM project would accurately translate the
value preposition of the client (Hattab and Hamzeh, 2013). And by using 3D printers,
the 3D model can be made into a physical manifestation in the future (Vandezande et
al., 2011).
5D Cost: The Stanford University Center for Advanced Facility Engineering revealed
that the use of BIM provides various advantages, including up to 40 percent removal
17
of unbudgeted improvements, 3 percent accuracy in cost calculation, up to 80 percent
reduction in cost estimate generation time, saving up to 10 percent of the contract value
by conflict detection, and up to 7 percent reduction in cost estimate generation time.
(Chien et al., 2014). With BIM, budget preparation and accumulated tracking expenses
can be carried out more effectively.
7D Facility Management: Prior to the delivery of the finished project output to the
owner, a final project review is carried out. (Hardin, 2009). For such jobs, BIM models
may be used as punch lists. A BIM model is a facilities resource with warranty,
specification and maintenance plan information that will ease the closure of the project
and make it a quicker operation (Bryde et al., 2013).
It should be recalled that BIM really works in the field of construction if it is fully
implemented. There is plenty of room for improvement and smoother interoperability
between field systems and tools, but contractors who choose not to use this technology
and leverage it to any or its fullest extent on the construction ground are losing a great
opportunity (Hardin, 2009).
18
LOD 100: Symbols or other common definitions may describe components. Because
of the type of results, only logical analyses can be performed.
LOD 200: The model involves elements of the model, generalized structures, and
assemblies in numbers, scale, form, and position that are estimated. It is possible to
build simpler forecasts and schedules showing the phasing of major components.
LOD 300: The level of production of the model is equivalent to that of LOD 200, but
the focus is on improved precision. At this point, the model can be used to create
building papers, shop drawings, more comprehensive cost forecasts, scheduling, and
performance-based analyses.
LOD350: The required coordination parts for the element are also presented in addition
to LOD300. Support and connections are provided in these parts.
LOD 400: With the purpose of ordering, assembling, mounting, and specifying, the
model has a much greater level of complexity. Virtual elements are very detailed and
adequate to reflect, forecast and planning costs based on the committed sales costs and
construction methods. LOD 400 shall be used during construction by general
contractors and subcontractors.
LOD 500: In terms of their geometries, components have been field-verified, and
reports of accumulated costs are available. Components can also contain design
characteristics and component details, which are useful for facility operation and
maintenance.
19
and windows, may be architectural model components. Abstract artifacts such as
rooms, spaces, and zones may, however, also be architectural model components. The
model elements must, as far as possible, include all product information as properties
of the model element for all architectural objects that represent tangible products and
physical structure. The model components must have the functionality commonly seen
in 2D schedules (GSA, 2016).
Foundations where it is important to completely model all the components of the base,
including but not limited to isolated pads, bearing and retaining footings, stem walls,
structural slabs, and piles.
Horizontal elements where it is important to completely model all beams, joists, slabs,
and precast slabs. Slab perimeters and structural edges must be demonstrated by the
model; penetrations for shafts, gaps, or other discontinuities of the slab; and
cantilevered sections.
20
Vertical elements where it is important to completely model all columns, walls, and
cross bracing. To allow load consistency, all connections and start/end points of such
elements must be modelled.
Inclined planes which any structural feature that is inclined, including, though not
limited to, non-plumb walls, stairs, ramps, and roofs.
Structural abstract components, including but not limited to loads and distributions of
loads. (GSA, 2016).
21
deployment at the level of the company. Enterprise BIM also promotes asset
management (Shoolestani et al. 2015). In Figure 6 a typical building lifecycle can be
seen where BIM is the main driver for all of the phases.
22
2.5.1. Handover of Information Between Project Phases
All relevant information is integrated before construction work starts in order to build
what is known as a digital twin of the construction. During the construction process,
all stakeholders then have access to the twin and, subsequently, to the latest
construction status and schedule. The digital twin becomes the property of the builder
after the construction process, who can use the data to run the facility management
cost-effectively. The information given by the digital twin can be used in the disposal
and recycling of raw materials, including in the case of a building being demolished.
BIM eventually rewards all stakeholders for this cause. (Wilo, n.d.)
Information and data gathering during a construction project, starting from its
programming and conceptual design phases is crucial for the later phases of the project
in terms of data development, documentation and ability to achieve historical data
interactions. Hence, handing over the gathered information and data to the next phase
carefully and successfully plays even more crucial role for a successfull building
lifecycle management, especially in the facility management phases.
23
during design and construction and produce a consolidated electronic O&M manual
with little to no extra effort. COBie data will then be imported, again at no expense,
directly into CMMS and asset management applications. The PDF, drawing, and BIM
model files that accompany COBie are arranged so that they can be quickly accessed
at the facilities management office using the protected server folders already in place
(East, 2016). The theory behind COBie is that the key knowledge is all drawn into one
format and shared among the construction team at designated stages of a project
(Hamil, 2018).
Bever, in an internet article of him, defines the informations handover challenges under
4 main reasons as follows;
24
The first issue to be solved is the the big bang approach to information handover from
the EPC to O&M staff. If data is not regularly assembled, distributed, and inspected
during the project, O / Os frequently experience unforeseen start-up delays.
The second issue is the use of unstructured formats of data exchange for the transfer
of knowledge from engineering to O&M employees.
The third issue is the proprietary handover information format for data exchange.
The final issue is the manual data exchange methods from Engineering and Building
Systems to O&M systems to solve.
Adoption of BIM is not only a change in technology; but also makes improvements to
productivity. BIM is a mechanism in order to improve progreses to reach certain goals.
25
In order to achieve successful BIM implementation during the construction phase of a
project, a structured approach should be taken for execution planning.
Ideally, a BIM model may offer detailed building information in an accurate 3D model
that offers graphic views of the elements of a building and the ability to extract
information on the quantity and product property to construction site supervisors and
engineers (Eastman et al., 2011).
As a result of improved quality designs and less defects and allowing higher rate of
prefabrication, building costs and schedules were reduced. A beneficial consequence
of the opportunity to create design details reasonably early in the project is that it often
prevents rework, which typically stems from unfinished details and incomplete
paperwork. It is possible to model temporary parts, such as equipment and formwork.
Both are essential to a project's sequencing and preparation.
A important feature of BIM is the potential during the project to make knowledge
accessible faster. The most valuable indicator of the importance of BIM is undoubtedly
the number of requests for information (RFIs). The number of RFIs can be predicted
to decrease dramatically with high-quality collaborative BIM. Since more RFI needs
26
work to be overcome, less RFIs equal more efficient time available for work and
improved planning, development and service. However, some industry analysts have
learned that RFIs are pushed to the front end of a project and do not diminish as much
as they had anticipated.
The ultimate goal of a BIM model is to use it in FM, regardless of whether the building
is new or an existing one, which has the ability to dramatically decrease life cycle costs
(Edirisinghe et. al., 2017). BIM has the option of providing a knowledge management
system with traceability. It is possible to classify both specific quantities and positions
of various items while the databases are related to the model. This helps personal
maintenance to know the exact location of malfunctioning facilities and link it to the
product details contained in the model-related databases. There are also opportunities
inside the buildings to provide programs related to particular events. In a hospital
setting, for example, there is a need to be able to track where such facilities have been,
such as beds, washing appliances, and so on, to trace the spread of contamination.
With increased pressure on building owners and operators to minimize energy use and
environmental effects, BIM allows for simulated pre-construction testing and review
of building systems to ensure that sufficient steps have been taken to ensure expected
efficiency and to modify underperforming systems before they are built.
Energy conservation and building performance are one area of significant concern
for GSA and the building industry in new construction, major reconstruction and
modernization, and building operations. In order to promote energy conservation,
Table 4 indicates several ways to use BIM-based energy modeling during design.
27
Table 4. BIM-Based Energy Modeling Opportunities by Project Type (GSA, 2015)
28
CHAPTER 3
RESEARCH METHODOLOGY
The topics for this section of the research include how this research was done. Details
on the methodology of research including research approach, strategy and techniques
of data collection are explained.
Prior to the case study, a wide range of resources were scanned and reviewed in terms
of literature review including academical journals, articles, books, internet blog
articles, whitepapers and case studies with the keywords especially including BIM and
Facility Management. Prior to the literature review, research questions and objectives
were defined in order to shape the structure of research and put an idea on the table.
Research approach and strategy then defined to supply this research with robust
information directly from the industry.
29
The findings of quantitative studies, such as significance tests, correlation and
regression analysis, are described in the form of descriptive or complex statistics.
Quantitative analysis is concerned with expressing results in a numerical manner, as
the name implies. (Wilkinson, 2000)
30
the research problem by clear method selection (Bryman and Bell, 2007). Data analysis
is specifically responsible for the reliability and legitimacy of research (Wood & Ross,
2010). Therefore the two types of data collected for a detailed analysis are the primary
data and secondary data for any study. In this analysis, primary data collection is
adopted through direct observation of qualitative approach, while the researcher also
worked as Senior BIM Engineer in the project and engaged in various executive
processes during the project. Qualitative evidence is collected from direct experience,
archive, one-to-one interviews and observation of processes.
• Research Design
Stage 2
• Data Collection
Stage 3
• Data Analysis
Stage 4
The best way to research what the researcher wants to know is to experience it for the
researcher themselves, the context of the events being researched is important and a
flexible approach to research is needed (Wilkinson & Birmingham, 2003).
31
In Figure 9, research objectives, case study, research methodology and data sources
are summarized. Case study is the main source of information for the outcomes of this
thesis. Together with the case study, a wide range review of literature is providing a
strong infrastructure for the thesis objectives.
Research Objectives:
>Develop an understanding of advantages of BIM usage for facility management
>Provide a guidance of BIM implementation into the building lifecycle effectively and
efficiently
>Examine the benefits of enabling BIM during the construction phase of a complex project
for the information handover from construction to operation phases
Case Study:
Istanbul Airport: a PPP structured project which is contracted as Design-
Build-Operate and considered to be one of the world’s largest airport
32
CHAPTER 4
4.1.Project Information
Istanbul Airport (IGA) is an international airport under construction on the European
side of Istanbul in the Arnavutköy area. The new airport is being built at the
intersection of the Arnavutköy, Göktürk and Çatalca highways, north of the European
side of Istanbul, between the Yeniköy and Akpınar regions of the Black Sea. Total
construction area is nearly 76 square km. There are old open-pit coal mines in the field,
which are to be filled with soil.
4 phases are defined by the project scope. The first phase entails the construction of
three runways, a terminal containing five piers covering an area of nearly 1.5 million
m2, a car park covering an area of nearly 700,000 m2 and other supporting facilities.
The critical assets of the main terminal structure, the runways and the associated
emergency runway/taxiway system will be accomplished within the framework of the
project. At the time of completion in 2018, with a gross floor area and the capacity to
accommodate 90 million passengers a year, Istanbul Airport has the world's biggest
terminal under one roof.
The architectural design of the terminal at Istanbul Airport is closely related to the
character of the city and will serve as an excellent gateway to Istanbul and Turkey.
An early design sketch of Istanbul Airport can be seen in Figure 10.
33
Figure 10. Early Design Brief of İstanbul Airport
The terminal building, considering its scale, is constructed as one that sits quietly, with
a simple horizontal expression, in its background. Train, subway, bus, coach and
parking are smoothly integrated between the terminal and the planned Airport City
across a generous plaza and an accessible traffic forecourt on the landside.
34
A groundbreaking scheme will come to life at the completion of all stages, delivering
76 million square meters of airport field and 6 runways, accommodating 3,500 take-
offs and landings per day, 200 million passengers a year and access to 350 destinations
worldwide. IGA Master Planning phases can be seen in Figure 11.
The airport project includes runways, passenger terminals, Air Passenger Movement
(APM) Station, cargo terminal, maintenance hangars, cargo apron, Air Traffic Control
(ATC) Towers, ancillary buildings; general aviation buildings; VIP terminal, fuel
farm, fuel delivery jetty, fire services, a metro link; airport service, hotels & offices,
roads and airport connector roads.
35
Project levels are given in Figure 12 for Terminal, Piers and Carpark for use in accurate
design processes. Similarly, Pier Buldings and Carpark Buldings have subzones that
are listed in Figure 13.
There is an all-inclusive strategy for BIM execution which includes almost every
discipline for seamless coordination between parties for overall project delivery and
supply chain management. Considering the size and complexity of the project, using
conventional methods for project delivery is unimaginable. In Figure 15, a generalized
strategy flow for Istanbul Airport is illustrated. As seen in the figüre, structural,
architectural, mechanical, BHS (Baggage Handling System), electrical, infrastructural,
SAS (Special Airport Systems) and ICT (Information and Communication Systems)
disciplines are included in the BIM execution strategy. Since the ultimate aim to build
a BIM model is using it in the operational phase, all systems related to operational
phase are included in the BIM model.
37
BIM Integration includes IGA officials and subcontractors from all design disciplines
and QA/QC. The information and design deliverables (2D and/or 3D) from all
disciplines will be submitted to Vault in 2-week intervals. Document submissions will
be logged by Project Coordination Team and reported to BIM Management and
submitting discipline officials after each submission.
BIM has an important role for strategic processes by upholding the integration of all
related stakeholders and all relevant disciplines which are architecture, structure, MEP
(Mechanical, Electrical and Plumbing), BHS (Baggage Handling System), IT etc. at
such a major and complex infrastructure project. In Figure 16, LOD Matrix Index
sample can be seen which shows a grouped list of objects in the BIM Execution
Planning subject to LOD matrix data.
38
(As-Built). BoQ extraction from BIM model, clash detection and reporting, 4D
schedule simulation will be performed regularly.
Together with the LOD Matrix Index, all related systems and equipments are defined
in detail. In Figure 17, details of a sample equipment in each development phase of
the BIM model can be seen. This details include description of the model
development details for every LOD level inthe project.
BIM Management gathers project information from all disciplines through Vault and
Buzzsaw environments. BIM Management is responsible for BIM based project
coordination, BIM model management and integration of design, schedule, quantity
and as-built information. The coordination of the project is accomplished by weekly
BIM coordination meetings and workshops where critical issues and other project
problems are solved. Request for Information documents (RFIs) are an important part
of every project. It is evident that any time there is some improvement in the plan, it
is appropriate to lift any demand in terms of RFI project information requesting the
required details. It is effectively an authorized electronic format to keep track of all
changes and improvements and knowledge sharing. A basic procedure has been shown
below to track and manage all the RFI's and a cumulative log is kept that will be revised
weekly and mirrored in Buzzsaw as well.
39
The RFI format and response are described in Figure 18 for Terminal Building E level
MEP discipline together with snapshots of both 2D drawing and 3D model of the
subject area in the RFI. These snapshots are included in the relevant RFI in order for
the receipents to clearly understand the issue.
Figure 18. RFI example for MEP with answer and attachments
40
4.3.1. Digital Site Engineering
Coordination of all disciplines is extremely hard for Istanbl Airport Project because
of its complexity and scale of the Project without using BIM. Architecture, structure,
MEP and BHS coordination are not conducted in 2D environment. All clashes between
the disciplines are solved with the using navisworks manage software, then clash-free
model can be obtained shared with related departments/disciplines in order to progress
on site. In Figure 19, BIM centered relation and collaboration between project parties
are shown.
41
Figure 20. Clash Resolution Workflow
Before site installations begin, according to the construction planning, BIM Model is
getting clash-free for subcontractors and site teams to rely on a correct model. Clashes
are resolved in a structured manner which every step of the process is under record. In
Figure-21, a sample MEP vs Architecture clash report can be seen.
42
In Figure 22, a sample viewpoint of a clash and clash markup can be seen. These
clashes are coordinated between design teams and modelling teams and necessary
actions are taken. At some point if there is no re-routing option available, model is
used for engineering purposes.
Another helpful application is BIM360 Glue, which enables project teams to access
related project knowledge virtually anywhere, wherever, through cloud-based BIM
collaboration. BIM 360 Glue provides multi-disciplinary teamwork and coordination
analysis cycles to be carried out more efficiently by the project.
All updated layers of each discipline are checked and merged with each other. Then
the updated merge models are shared with field for engineers to control the project
situation and manufacturing by their tablets on site via BIM360 Glue. A sample view
of BIM360 Glue mobile application can be seen in Figure 23.
43
Figure 23. Layers (Arch/Strc/MEP-IT/BHS) and Section of TB1-2-B level in Glue
Site manufacturing and processing are checked by site engineers with the help of
shared model in BIM360 glue for all zones. The progress are compared with the
updated BIM models in site. An example comparison of site and model can be seen in
Figure 24.
44
4.3.2. QA/QC and Project Control
Technology, QA/QC and the use of technology are also very important, so that a
collaborative environment with subcontractors has been developed from the very
beginning of the project and mobile tablets have provided this very well on site. Since
all engineers are fully equipped with technologies, on a cloud network with BIM360
Area, they can reach the latest project models, making a major contribution to better
quality of engineering.
Notification for Inspection (NFI) with QA/QC checklists, approved Shop Drawings
(SD), Material Approval Form (MAF), Method of Statements (MS) are stored in
BIM360 Field Library. Besides, Test&Commissioning Request (TCR) will be applied
over the BIM360 Field for all the equipments which are in site.
In addition to NFI’s, issues and observations(obs.) which have significant impact for
site progress are created and checked with BIM360 system. Controls about the
observations are conducted by related engineers who are BIM Site engineers and
QA/QC engineers. Problems-issues are solved on site by the help of engineers, then
the obs is closed. Engineers are also checked Material Approval Form of equipments
from the BIM360 library, if there is any problem about the approval form of
equipments/materials, observation can be opened by engineers.
An example about BIM Site Engineering Report & QA/QC Report details can be seen
in Figure 25.
45
Figure 25. QA/QC Observation Details on BIM360 Field
Besides QA/QC issues, site engineering teams also use mobile BIM environment to
track non-conformancies of site installations regarding to BIM model. In Figure-26 a
sample site engineering report can be seen where BIM Site Engineers and construction
responsibles can digitally cooperate in the resolution of an issue.
46
Figure 26. BIM Site Engineering Observation Details on BIM360 Field
These reports are executively reported weekly to the top management of the project in
order to provide transparency. There is also a huge benefit of fully digitalized site
engineering and QA/QC processes which at every desired point of time, a detailed
report for subcontractor performances on site can be derived from the system. It can
even be automatically created and delivered to the desired e-mails of project
responsibles, weekly or monthly. Observations status summary created by BIM360
Field system, a sample can be seen in Figure 27. This reports are shared with other
disciplines responsibles in order for everyone to see the latest situation and progress
periodically.
47
Figure 27. QA/QC Observation Status Summary
Examples of 4D simulation Master Model snapshots are seen in the Figure 28 with
the date of 08.08.2016.
4D Model is integrated not only for structural and architectural elements, but also
MEP-IT and BHS systems all the activities are linked to the BIM model to obtain a
simulation for those disciplines. In Figure 29, a sample view from Pier-1 Level D of
49
the Terminal Building for planned construction start and finish simulation can be seen
in a screenshot of the 4D model.
The IGA BIM executives notes that time and cost estimation provides better
understanding of construction documents in terms of job sequencing and helps with
executive level site planning.
50
Energy modelling, detailed analysis of energy needs of the structure and
analysis of renewable energy options such as solar energy.
Building orientation providing best building orientation option that leads to
minimum energy cost.
Reducing time and expenses for energy analysis allowing change of many
design parameters fast.
Access to recent data for unit energy costs and weather via using an internet
server.
Green Building Studio(GBS) and Insight 360 are used for energy analysis in the
Project. Revit 2016 & 2017 versions are suitable for using Insight 360 which works in
an integrated fashion with GBS server.
Green Building Studio (GBS): It is a web-based energy analysis service that helps users
early in the design stage to determine the environmental effect of individual building
components. Primary analysis capabilities of the program include energy and thermal
analysis, analysis of lighting and shading, and analysis of value/cost. Energy/thermal
analysis assesses the consumption of energy, carbon emissions, ventilation and
airflow. Lifecycle evaluations and lifecycle costs are determined by the value and price
functions.
Insight 360: Current workflows including Revit Energy Analysis and Lighting
Analysis for Revit are incorporated by Insight 360. In addition to understanding PV
energy output and saving and comparing design scenarios to monitor performance
spanning the construction lifecycle, it enables simulation of solar radiation on mass or
building element surfaces with new solar analysis workflows.
All analysis conducted with GBS and Insight 360 with the help of Revit 2016 software
for;
51
And sustainability analysis can be obtained at the end of the process. According to end
value of Sustainability Analysis, Via a decent optimization and project defaults
assumptions and determinations, it has succeeded to analyze all Terminal and Pier
Buildings and found annual and monthly data –both in energy units and in monetary
units- of total energy. In means of energy, annual and monthly monetary and energy
equivalents of space heating, space cooling, area lighting, hot water supplies have been
generated graphically which enables us to foresee future energy consumption of airport
buildings. Furthermore, the iterative data we get from the energy analysis process will
lead us to take retrofitting decisions in the design of the airport. Overall, with the
implementation of sustainability analysis, İGA are executing the application of 6D of
BIM. Having considered this, please check the following sample outputs taken from
GBS dashboard (Figure 30).
Figure 30: Energy Cost in Energy Units & Energy Cost in Monetary Units
Lastly, solar analysis result sample of a single Pier of Istanbul Airport is given in
Figure 31 visually.
52
4.5. Facility Management with BIM
It is one of the key objectives of extending Istanbul Airport's life-cycle efficiency and
sustainability by using BIM in the next phases for facility management and operations.
Facility documentation integrated in the BIM model and BIM model is handed over to
clients for their facility management. The handover was seamless and data loss was
minimum since BIM has been used in all project phases including design and
construction. Exceptional visualization and reporting capabilities of BIM platform was
beneficial during the commissioning to handover stages of equipments.
As defined by Cotts et al. (2009, quoted in Arayici, Onyenobi & Egbu, 2012), Facilities
Management is a "multi-disciplinary field comprising multi-disciplines to ensure the
functionality of the built environment through the integration of people, location,
process and technology." The BIM methodology explains the use of BIM tools and
techniques to strengthen the conventional business process and add value to projects.
(McGraw-Hill 2012). Planning, design, construction, facility maintenance and
operations are included in the BIM processes. The possibilities for using BIM for
facility operations are convincing, but in the design and development stages, the
application of BIM for facility management lags behind BIM adoption (Akcamete et
al. 2010). A analysis by the U.S. The National Institute of Standards and Technology
(NIST) has shown that the annual cost of insufficient information system
interoperability is $15.8 billion (Gallaher et al. 2004). As a consequence of continuous
facility operation and maintenance operations, two-thirds of this expense was
generated (Shen et al. 2010). This concern occurs because knowledge has to be
collected repeatedly at multiple points. In the use of BIM, data can be captured only
and used during the life cycle of the facility. In comparison, at an earlier level, certain
maintenance issues are much simpler to fix and cost less. While BIM is designed to be
a shared platform, communication databases do exist in practice. In order to reach a
consensus on BIM-FM practice, a bridge should also be built to close the distance. The
experience and knowledge required to implement BIM for FM are missing in many
facility managers; designers and architects are not aware about what FM data should
be collected and what FM requirements should be taken into account in their BIM
activities. (Liu 2012; Liu and Issa 2013b). A knowledge workflow for project lifecycle
is given in Figure 32 for facility management implementation that shows
maintainability issues in BIM implementation.
53
Figure 32. Knowledge database for maintainability issues (adapted from Liu & Issa, 2013a)
In IGA, the aim is to connect various databases with existing BIM database which
includes visual and non-visual data. In aviation, measurement is very crucial for
management, in most of the operational aspects of the industry. Aircraft, people and
bags must be moving all the time and a great passenger experience shall be maximized
through the highest utilization of technology and people as possible.
54
technology (IFMA, 2016). There are many databases that can be integrated with BIM
to work seamlessly and controlled over a single dashboard. Those databases can be
listed as IWMS, CAFM, CMMS, BMS, BAS, SCADA, GIS and ERP systems (Figure
33).
As BIM technology advances and is used over its life cycles to enhance asset
management, asset owners will need to fully understand the knowledge required after
completion of construction and the relationship between BIM, asset management and
maintenance management systems.
55
in local server in Airport Data Center. A screenshot for alarm viewer dashboard for
facility operations can be seen in Figure 34.
Figure 34. Alarm viewer dashboard for Facility Management & Operations
There is also a sample view of demo dashboard for assets in Figure 35. Assets can be
tracked and managed through this smart platform fully integrated with BIM model.
56
BIM for facility management provides visualization and access to the accurate
location. Therefore, relationship of building systems and equipments/materials can be
accessible in an easy way to observe the conditions. In addition to this, BIM provides
several benefits over traditional 2D drawings in terms of facility management and
operations. BIM objects contain the information of what they are and where they are
located. Integrated tools identify areas service that are supplied by which components.
For instance, mechanical room 1 and 2 are supplied by Air Handling Unit A or
electrical room 7 and 8 are supplied from circuit panel S-2. This information shall
provide more flexilibility to technical staff over controlling the systems and identifying
problems. Sample views of integrated BIM model for facility management software
can be seen in Figure 36.
57
4.6.Construction to Operations Delivery
In Istanbul Airport project, a development strategy in a timely manner has been applied
in terms of BIM model development. Together with the development of the BIM
model, successful data handover has a crucial role on delivering necessary and
validated data to the next phase of the project. Two main topics for successful project
delivery from construction to operations are the BIM Model Development and BIM
Model Validation processes. Accordingly, integration of the Facility Management
platform also called as virtual platform will be examined in the following topics.
58
The BIM Model Development of IGA is a part of this challenge. Since the main
approach in IGA is to adopt the “plan, simplify and execute“, the model phasing is
broken up to three main steps which are construction model, commissioning model
and operational model. Each of these model phases contain only necessary data for
each project phase. In Figure 38, BIM Model Phases and their details are given.
Between each transition of the model phases, there is a structured planning for
additional data entry to the model, in order to execute necessary workflows for every
project phase. Owners system classification, asset type, asset category, unique ID,
manufacturer, parts number, installation date Floor, location, room, warranty
information, maintenance frequency, supplier, expected life, costNaming conventions;
Omniclass for materials are used.
IGA BIM and technical departments collaboratively worked together to agree on the
necessary attribute data for equipments to be populated in the model database.
59
4.6.1.1.1. Validation of Non-Graphical Data
In order to validate data, a software for BIM Model validation is used to ensure any
misinformation or defects in the model are corrected in IGA.
As seen in the workflow given in Figure 39, BIM Models are synched from Revit to
validation software directly in cloud environment with an add-in inside the Revit.
When models are reviewed in the software platform, they are checked with rules that
have been created by IGA to match the project requirements and pre-defined attribute
information.
60
Models are populated asset by asset and discipline by discipline in the software
platform as seen in the screenshot in Figure 40. Once the models are checked by the
rules created, results are exported to an excel report and reports are reviewed to update
and revise the models. This processes can also be followed through the software
platform dashboard.
Figure 40. Rule based QC Check for Equipment and object attributes
All equipmens can be grouped and filtered by rules for data validation as seen in Figure
41. Checking BIM models on time for collaborative data validation is the key for a
successful handover of information that owner and facility management teams need.
This is achieved by creating a structured workflows for quality checking for the
necessary data in the model.
61
4.6.1.1.2. Validation of Graphical Data
High compatibility of site installations with the BIM model is achieved by full
implementation of BIM in design and construction processes in IGA. Creating a fully
engineered and clash-free coordination model and delivering the model for fabrication
and site installations together with digital QA-QC and commissioning, almost every
defect and non-conformancy is under record. However, for full confidence of graphical
accuracy in the operational phase, validation of the model objects are done for
technical rooms by using a laser scanner to gather point clouds with the ease of mobile
applications. In Figure 42, a view of a point cloud from Autodesk Recap and point
cloud embedded Revit Model can be seen. As seen in the view, BIM model is validated
to ensure the model is as-built and fully compatible with the site conditions.
Figure 42. ReCap view of a mecanical room point cloud (above), point cloud
embedded Revit Model (below) (Source: IGA)
62
BIM Team captured the real as-built and commissioned environment and created point
clouds after a registration period for all mechanical rooms. Raw data of point clouds
after first registration was exported to Autodesk Recap for second registration and
indexing in order for them to be embedded in Revit Models in true coordinates for
validating object locations, sizes and possible additional objects. Other technical
rooms including electrical and ICT is planned to be scanned.
In IGA, several demo platforms were prepared for showcasing and testing of digital
twin integration into facility operations. A specification has been prepared by
involving various departments of the airport management including procurement,
technical services, inventory management, finance and so on. A sample screenshot of
the virtual platform demo including BIM model integration in asset lifecycle
management and work order management can be seen in Figure 43.
Figure 43. Virtual Platform Demo for BIM Model Integration for FM
63
It is possible to integrate BMS system to exchange real-time data of equipments by
sensors, enabling the user journeys and operational ease for work order management
and incident management. A sample view of an operation center dashboard of a Pier
Building together with various asset and alarm pins attached can be seen in Figure 44.
With the ease of model navigation, it is possible to reach any graphical or non-
graphical information of an asset, control over the asset and dispatch technical staff
for maintenance.
Figure 44. Virtual operation center dashboard demo for a Pier Building
64
CHAPTER 5
During design and development, BIM has proved its worth, some owners still see the
possible benefits of integrating BIM model data into facilities management systems.
Early adopters of BIM for facilities management are seeing a range of benefits, from
eliminating the need for reentry of equipment-related data into current FM systems to
creating more model-based virtual environments for preparation and implementation
of operations and maintenance activities. (McGraw Hill, 2014). The end purpose of a
BIM model is to use it in FM, whether the building is new or an old one, which will
significantly minimize the expense of the facility life cycle (Edirisinghe et. Al, 2017)
5.1.Framework Development
In consideration of the research objectives, it is necessary to establish a framework for
overall BIM integration and project execution, which is necessary for creating an
effective BIM database for operational use. A framework is established with a step by
step approach including both processes and methodologies given in a structured
manner to explain BIM based project delivery and facility management (Figure 45).
This can also be seen as a roadmap for BIM implementation especially for projects
with high complexity or relatively larger projects which generally involves thousands
of people in the lifecycle of the building. Hence, this framework can also be seen as a
guidance for any kind of construction project which BIM is to be used to some degree.
In the framework there are four sections including Integration Management, Project
65
Execution, Handover and Facility Management Integration and Operational Process
Management. These sections are explained in detail in the following topics.
Further research and review of industry practices shall be done to develop this
framework for overall improvement and increase of the business value.
66
Figure 45. A Framework for BIM Based Smart Facility Management
67
5.1.1. Integration Management
For the purpose of operational use of BIM it is very important to effectively plan and
successfully execute it’s processes. In the first hand, successful BIM integration can
be achieved by understanding the project needs including employer requirements and
project specific conditions. It is also very important to keep in mind that transofmation
of mindsets to a digital working environment by educating and
Process planning starts from the contractual issues which may include BIM Protocols
and directs the parties by defining obligations of BIM use which is very crucial for
BIM integration in a project. Creating a contentful BIM execution plan concerning
every party in the project is also very crucial for successful BIM implementation. It
may be created seperately for the facility management phase of the project. In order to
manage key project processes, effective and efficient workflows including roles and
processes to get the best outcomes shall be defined with relevant project teams.
68
construction schedule, project needs and employer requirements. Therefore a solid and
understandable BIM modelling guideline is needed to set the specifications of
modelling for every party to rely on. The BIM model must be finalized including all
design decisions and delivered to site on-time to related people in order for site
installations to be accurate. It is important to decide on which asset information is
needed by the building operators for operational use to develop the BIM model.
In terms of design coordination BIM brings a collaborative workspace for all parties.
Together with digital collaborative environment it is possible to connect all parties
across the world and let them focus on the work itself. Design workshops using BIM
models are an efficient tool for taking fast and effective design decisions. Those
decisions can be applied and distributed to the related parties with cloud based
collaboration tools such as BIM360. The shop drawings derived from the BIM models
can be digitally reviewed for quality checking and validating the compliance with the
BIM model.
Finalized BIM models can be used for design document deliverables such as shop
drawings and detail drawings. Effective delivery of the finalized and approved design
documents including 2D drawings and 3D models to construction site is possible with
cloud based construction management tools and mobile tablets. On construction site,
it is easy for site engineers to reach final design documents to track site installations
for QA/QC and project control and commissioning.
BIM model when delivered to facility owners, need to be maintained throughout the
lifecycle of the building. There may be various operations that requiers an update in
the BIM model such as changes of design, additional installations, part replacements,
69
equipment replacements. These changes need to be tracked and integrated into the
BIM model accordingly.
There is also many opportunities and potential uses such as creating simulations for
operational uses and training, automation of aviation processes with BIM and GIS for
airports, machine learning and artificial intelligance developments.
70
CHAPTER 6
CONCLUSION
In this study, to obtain the implementation and benefits of Building Information
Modelling in Complex Construction Projects which is İstanbul Airport Project were
examined. The summarizes of this report conclusions will enable the other
Construction Projects how BIM based Project management can be achieved and how
it is executed for all phases from design to operation.
The motivation of implementing BIM involves to direct designing advantages that lead
to expanded efficiency for the engineering process and most relevant benefits being
the increased participation and team work with different disciplines. Besides, clash
detection & resolution, sustainability & energy analysis, planning, QA/QC and facility
management are the most common uses of BIM in the Project. Better services and
solutions are provided by BIM based Project management. Most significant outcomes
are better visualization with all parts and accessibility from everywhere with
Field&Glue apps.
Literature states that there are numerous profits associated with using BIM. Better
communication with other parties along the supply chain is being reported, and BIM
is proving a useful tool in fabricating and scheduling construction.
Database is coordinated and managed in all other parts, shared, preserved and reused
by BIM implementation. Through the application of information technology to the
problem of describing a building in software, they enable higher quality work, speed,
and cost efficiency for the design, construction, and operation of buildings.
There is fast increase in the interest for adopting BIM within the industry’s
professionals. According to NBS, 2013 statistics results shows that, the level of BIM
awareness has increased from 57% in 2010 to 84% in 2012 and the level of BIM usage
from 13% to 39% in the same period. BIM will be the main method in which buildings
are constructed and operated.
71
The BIM adoption process has already accelerated in Turkey as the İstanbul Airport
project has become a key learning hub not only for Turkish construction industry but
also global landmark for digital construction and related project delivery.
Given the fact that 85 percent of a building's life-cycle costs arise after completion of
construction (Arayici et al., 2012; Jordani, 2010; Lewis et al., 2010), In the
construction planning process, facilities managers are hardly interested, thereby
rendering the maintenance policy focused on the "as built" state until construction is
delivered.
Sharing details relating to the development of a comprehensive facilities management
strategy, creating meaningful key performance indicators, measuring the return on
investment, and developing the contract language and documentation will become
increasingly necessary for airports to facilitate the complete implementation of BIM
(Building Information Modelling for Airports 2016 ).
These objectives were achieved in this thesis. The first objective is met by defining the
advantages of BIM usage for facility management through a wide range of literature
review and showcasing industry practices.
Third objective is met by the explanation of project delivery form design to the facility
management including handover of project information to create an accurate BIM
model for FM use, including the BIM graphical and non-graphical data validation
together with its benefits throughout the project.
72
REFERENCES
Chıen, K.-F., Wu, Z.-H. & Huang, S.-C. 2014. Identifying and Assessing Critical
Risk Factors for BIM Projects: Empirical Study. Automation in Construction, 45, 1-
15.
73
Eastman, Chuck, et al. 2011. BIM Handbook, A guide to building information
modellin for owners, managers, designers, engineers and contractors, Second edition.
s.l. : Wiley, 2011.
Fischer, M., Kunz, J. 2006. The Scope and Role of Information Technology in
Construction. Available at: http://cife.stanford.edu/online.publications/TR156.pdf
Hardın, B. 2009. BIM and construction management: proven tools, methods, and
workflows, Indianapolis: Wiley Pub.
Harrıs, B. & Alves, T. D. C. L. 4D Building Information Modeling and Field
Operations:An Exploratory Study. 21st Annual Conference of the Internation Group
for Lean Construction, 2013 Fortaleza, Brazil. 811-820.
Howell, I., and B. Batcheler. 2005 "Building Information Modelling Two Years
Later–Huge Potential, Some Success and Several Limitations Retrieved." Available
from: LaiserinLetter< http://www. laiserin. com/features/bim/newforma_bim. pdf>
International Organization for Standardization. 2016. ISO 29481-1:2016 Building
information models — Information delivery manual — Part 1: Methodology
and format.
Kensek, K. M. 2014. Building information modeling, Abingdon ; New York,
Routledge.
Khemlani, L. (November 22, 2007). “Top Criteria for BIM Solutions”, AECbytes,
October issue. : http://www.aecbytes.com.
McGraw Hill Construction. 2014. The Business Value of BIM for Owners.
Messner, J., Anumba, C., Dubler, C., Goodman, S., Kasprzak, C., Kreider, R.,
Leicht, R., Saluja, C., and Zikic, N. 2019. BIM Project Execution Planning Guide,
Version 2.2. Computer Integrated Construction Research Program, The Pennsylvania
State University, University Park, PA, USA, Available at http://bim.psu.edu.
NBS. 2013. National BIM Report 2013 - National BIM Survey 2013 . s.l. : Royal
Institute of British Architects, 2013.
Sacks, R., Koskela, L., Dave, B. A. & Owen, R. 2010. Interaction of Lean and
Sciences, N. I. 2016. Information Technologies Engineering. Retrieved from Whole
Building Design Guide: https://www.wbdg.org/design-disciplines/information-
technologies-engineering
74
The BIM project execution planning guide 2009. BIM: operate.construct.design.plan.
The Computer Integrated Construction Research Group, The Pennsylvania State
University
Construction Products Association. 2013. The BIM for the terrified a guide for
manufacturers
Vandezande, J., Read, P. & Krygıel, E. 2011. Mastering Autodesk Revit
architecture 2012, Indianapolis, IN, Wiley.
Vanlande, R,. Nicolle, C,. Cruz, C,. (2008). IFC and building lifecycle management.
Automation in Construction, 18, 70-78
75