Executing Processes
Executing Processes
Executing Processes
3. During a meeting to negotiate a change to the contract, the seller states that
they have another meeting at three p.m. Negotiations will have to be over by
then. What kind of negotiation technique is this?
(A) Deadline
(B) Missing man
(C) Demand
(D) Delay
(A) Add two days to the schedule and inform management of the delay.
(B) Ask management for additional personnel because you cannot afford
the extra schedule time.
(C) Offer a bonus to the team member if he/she gets the training on
his/her own time.
(D) Include training in the project plan and include the unknown in a risk
analysis.
6. A customer is not happy with a project deliverable. What is your best course
of action?
(A) Expert
(B) Referent
(C) Manipulative
(D) Experience
8. Product verification is different than scope verification in that product
verification?
(A) Forcing
(B) Compromising
(C) Withdrawal
(D) Smoothing
(A) Rework
(B) Quality training
(C) Scrap
(D) Warranty costs
11. A project manager is finalizing the resources for the project team. All the
following will help the project manager complete this task EXCEPT?
12. The management theory that all people can direct their own efforts is:
(A) Herzberg's theory
(B) Theory Y
(C) Theory X
(D) Maslow's hierarchy
(A) You are the project manager responsible for the whole of the project.
To ensure you have control you remain firm and reprimand the foreman
and the team to ensure they do not slow down.
(B) You disregard the issue, acknowledging that what is done is done, and
develop a plan for moving forward.
(C) You meet with the foreman inquiring about what happened, and seek
to understand and solve the problem.
(D) You reprimand the foreman in private and ask that he keep you
better informed in the future.
(A) Timeliness
(B) Accuracy
(C) Completeness
(D) Acceptance
16. A software development project has been suffering through many major
project changes. Because of this, the project manager has not been able to do
much but complete change control forms. Which statement best describes the
other activities the project manager should be doing?
17. On his first project assignment as the project manager, the project manager
encounters disagreements among highly technical team members. How would
the project manager best deal with the conflict?
18. What theory proposes that efforts will lead to effective performance and will
be rewarded for accomplishments?
19. During a routine walk-through, you discover that a seller has neglected to
properly produce a major component of its deliverable. What should you do?
20. A project manager has just been hired and is trying to gain the cooperation
of others. What is the best form of power for gaining cooperation under these
circumstances?
(A) Penalty
(B) Expert
(C) Formal
(D) Referent
21. In a fixed price contract, which of the following might not be an output of
contract administration?
22. Which of the following can create the most misinterpretation in the
statement of work?
25. Under a seller agreement, formal, written correspondence with the seller is
required when:
26. A project team is worried that the integration of the components of the
project will result in uncovering flaws. Instead of continuing their work, they
are constantly looking for flaws to try to prevent their system from being the
only one found to have flaws during integration. It might be best for the project
manager to?
27. One of your team members informs you that he does not know which of the
many projects he is working on is the most important. Who should determine
the priorities among projects in a company?
(A) Sponsor
(B) Team
(C) Senior management
(D) Project manager
28. During execution a team member comes to the project manager because he is
not sure of what work he needs to accomplish on the project. Which of the
following documents contain detailed descriptions of work packages?
29. In planning a project, you notice that some of the materials required on the
project are only available from a seller that owns a patent on the material. What
should be one of your main concerns?
30. After the contract has been signed for the upgrade of 8,000 workstations, a
project manager is assigned. The proposal manager is relatively new and
doesn't have as much related knowledge as the project manager. The cost
analyst works from home and his price estimates are based on the details
outlined in the contract. The project manager thinks there was a flaw in the
logic determining the number of workstations that can be upgraded via remote
electronic software distribution. Which of the following is the best thing for the
project manager to do?
(A) Meet with the appropriate project team members to choose the best
solution
(B) Meet with the vendor to adjust the contract for the change
(C) Determine if the contingency budget will cover the additional cost of
more expensive visits
(D) Meet with the cost analyst and the proposal manager to determine
how they can amend the contract to accurately reflect the work that will
have to be done
31. A project team member comes to the project manager during project
execution to tell him that they feel the project cannot meet its quality standards.
The project manager calls a meeting of the affected stakeholders to work
through the problem. Which step of the quality management process is the
project manager in?
32. Your company just won a major new project. It will begin in three months
and is valued at US $2,000,000. You are the project manager for an existing
project. What is the FIRST thing you should do once you hear of the new
project?
(A) Security.
(B) Stability.
(C) Affection.
(D) Learning.
35. You are purchasing a major component for a new product from the company
that has the patent on the component. Under these circumstances, which of the
following should be your highest concern?
36. A parking lot fencing project was bid at US $11 per foot. The parking lot has
four equal sides of 125 feet and requires installing a six-foot diameter culvert on
one side. Fencing should take 100 feet per day, and the culvert installation will
cost US $500 and take one day to complete. The culvert must be installed before
work can begin on that side of the fence. After three days of work, one side is
complete, another has 75 feet installed, and the culvert is completely installed.
At this point, the client tells you that the culvert needs to be increased to a seven-
foot diameter. You determine that this will cost US $1000 and require two
additional days. What should you do FIRST?
(A) Review the scope of work for mention of the diameter of the culvert.
(B) Call a team meeting and determine if schedule and cost alternatives
can maintain the current cost and schedule requirements.
(C) Renegotiate the contract.
(D) Ask for a change order to cover the change.
37. For which of the following can the work breakdown structure be used?
38. During the project, you realize you need a consultant immediately to begin
working on a project. What is the most appropriate contract type in this
situation?
(A) personality.
(B) cost.
(C) priorities.
(D) schedules.
42. Which project management process group normally takes the most project
time and resources?
(A) Planning
(B) Design
(C) Integration
(D) Execution
43. A project team member has just completed work on the microprocessor for
the new human system performance monitor and is now finished with the
project. The project manager should:
44. You are asked to select tools and techniques to implement a quality
assurance program to supplement existing quality control activities. Which of
the following would you choose?
45. Out of the following list which is the highest point in Maslow's hierarchy of
needs?
(A) Social
(B) Physiological
(C) Esteem
(D) Safety
46. A project manager says to a team member, "If you cannot complete this task
according to the quality standards you set in place, I will remove you from the
team that is going to Venezuela for the milestone party with the customer."
What form of power is the project manager is using?
48. All the following are forms of power derived from the project manager's
position EXCEPT?
(A) Formal
(B) Reward
(C) Penalty
(D) Expert
50. A seller is awarded a contract to build a pipeline. The contract terms and
conditions require a work plan be issued for the buyer's approval prior to
commencing work but the seller fails to provide one. WHICH of the following
should the buyer's project manager do?
(A) Develop the work plan and issue it to the seller to move things along.
(B) Issue a stop work order to the seller until a work plan is prepared.
(C) Issue a default letter.
(D) File a letter of intent.
52. A project manager believes that modifying the project scope may provide
added value for the customer. What should the project manager do?
53. Employees who believe their efforts will lead to effective performance and
expect to be rewarded for their accomplishments remain productive as rewards
meet their expectations. This is called?
54. A project team member has been having a big disagreement with another
team member for over two months when the other team members become
involved. The issues are complex, but you have specific experience in the area
and know what needs to be done. The best choice would be to:
55. A project manager is assigned to a new, high priority project. There are only
five available resources because other resources are already committed to
projects. The resource's time available to complete the project is less than half
the time needed, and the project manager cannot convince management to
change the end date. The project manager should do which of the following?
(A) Coordinate with team members the overtime necessary to complete
the work.
(B) Provide the team with opportunities to do a great job on the work
that can be accomplished.
(C) Cut the scope of work by removing the work that cannot be
completed in the time provided.
(D) Use more experienced resources to complete the work faster.
56. You have been appointed manager of a project to convert multiple electronic
mail systems at a major financial institution to a single platform. Your
company's approach was not the client's first choice, and your firm was able to
be the lowest cost alternative by using funds provided to your company for a
different purpose. After the project is underway, the client specifies a new
approach that has never been used before. When the project is approaching the
originally-scheduled end date, it becomes clear that the technological approach
will have to be significantly altered. Although the client has been kept apprised
of developments throughout the project through regular status reports, and the
project plan has been followed, the client demands that the project be continued
without any increase in cost until all of the client's requirements are met. Your
firm feels that it has no choice but to comply with the client's demands, although
this will result in a substantial loss on the project. What was the MO
57. You are in the process of having work crews dig a trench to the customer
facilities to lay fiber for a high-speed connection. All of the work permits have
been obtained and funding has been approved. There have been several weather
related delays, but due to perseverance of the entire team, the project is on time.
It is the customer's responsibility to provide entrance facilities so the connection
into the building can be made. You discover the customer does not have
adequate facilities and will not have them in time. What should you do?
59. All the following are tools for scope verification EXCEPT?
60. You are a project manager working on a large software integration project
involving multiple sellers. One of your key sellers has informally requested a
change to its statement of work to account for some requirements she neglected
to address. You are relatively certain that the requested changes will add time
and cost to the project. What should you do in response to the seller's request?
(A) Analyze the requested changes and feed them back through project
planning and procurement processes.
(B) Work with your procurement office to obtain new bids from other
sellers on the scope of work.
(C) Reject the change request and insist that the seller perform to the
contract they signed.
(D) Negotiate a compromise with the seller.
61. Senior management regularly evaluates project performance to maintain
confidence in quality product standards. Which of the following best describes
this?
62. During project execution, a risk occurs and has a greater impact on the
project than was anticipated. The best thing to do would be to?
63. You have a choice of four ongoing projects that you can take over as project
manager. Project 1 has a BCR of 1.4, is a high priority project, and has a
critical path length of 16 months. Its CPI is 1.2. Project 2 has a SPI of 1.1, is
using three critical resources, has a low priority, and has a BCR of 1.1. Project 3
has a CPI of 1.2, and SPI of .893, a BCR of 1.6, and a critical path length of 19
months. Project 4 has a CPI of .82, a task with 33 days of float, a resource that is
hard to get assigned to task L, and a priority of keeping cost low. Based on the
above, which project would you prefer to take over?
(A) Project 1
(B) Project 2
(C) Project 3
(D) Project 4
64. Which motivational theorist said that people cannot ascend to the next level
until the levels below are fulfilled?
(A) Deming
(B) Maslow
(C) Herzberg
(D) McGregor
65. A project team is trying to decrease risk on the project. The project sponsor
has a good relationship with a seller who is experienced in areas that your
company is not experienced in. The sponsor wants all tasks with a US $50,000 or
higher risk to be transferred to the seller. The project sponsor believes that this
will remove their impact from the project. Why would this not be effective?
(A) The transference of a risk does not remove all impacts of the risk.
(B) The sponsors association with the seller is a conflict of interest for the
project.
(C) Working with sellers will add more than the US $50,000 of risk to the
project.
(D) You would have to go through the contracting process.
66. During project execution a project team member informs the project
manager that based on her observations, the project cannot meet the quality
standards set for it. The project manager meets with all parties concerned to
analyze the situation. In which step of the quality management process is the
project manager involved here?
67. A project manager is working on his first project with outside sellers. He is
familiar with project control systems but not contract control systems. In
explaining how a contract control system differs from a project control system, it
is best to point out that a contract control system:
69. You are negotiating with a seller. Time is of the essence but you have a
limited budget, and the seller knows this. What is your best negotiating strategy
under these circumstances?
70. Your contract states that the maximum charge for services from the seller
will be US $50,000 per month. However the actual invoices have been US
$100,000 for the past three months. Stopping the seller's service will impact the
project schedule. Under these circumstances, the best thing to do is to review
the:
(A) Terminate the seller for convenience and hire another seller
(B) Assign a group within your team to meet with the seller and reassign
project work so that the seller has easier work to accomplish
(C) Meet with the seller to discover the cause of the problem
(D) Provide some of your own staff to augment the seller's staff
72. While completing work on your contract, the seller is refused access to the
facility by your company's security force. If access to the facility is stipulated in
the contract, what should the project manager do?
73. You are managing a construction project that was contracted on a fixed price
plus incentives basis. The additional incentives for completing the project early
are very large. A not-for-profit cultural organization in the community has
raised some concern that the construction site might overlap with an
archeological site. As the project manager, you should?
(A) Stop the project immediately until the site can be validated.
(B) Quickly research the situation, understanding that your organization
is accountable for social or economic impacts resulting from a project.
(C) Change the facility design to incorporate the archaeological site.
(D) Contact the city council. It is the responsibility of the city council to
monitor social or environmental impacts.
75. You have decided to terminate a contract because you no longer need the
work from the seller. What is the best way to communicate this to the seller?
76. Which of the following best describes the project manager's role during
project planning?
(A) Coordinate the creation of a document that can be used to guide the
project.
(B) Following the plan set by management.
(C) Making a list of tasks the team members are required to perform.
(D) Creating a Gantt chart and getting management to approve it.
(A) McGregor's
(B) Herzberg's
(C) Maslow's hierarchy
(D) Theory Y
79. A new project manager has just been assigned a project that is in progress
and is two weeks behind the scheduled time. Your team members are about to
be distributed to another project based on original time estimates provided by
the functional manager. What is the FIRST step she should take?
(A) She should initially contact the steering committee and begin with a
new team.
(B) She should first revise the Gantt chart with new timelines.
(C) She should check the project plan for contingencies concerning
resources and talk to the functional manager.
(D) She should first show sympathy with the current team and delay
decision making for another week.
80. You work in a matrix organization when a team member comes to you to
admit he is having trouble with his task. Although not yet in serious trouble, the
team member admits he is uncertain of how to perform part of the work on the
task. He suggests a training class available next week. Where should the cost of
the training come from?
81. The need for _______________ is one of the major driving forces for
communication in a project.
(A) Integrity
(B) Optimization
(C) Differentiation
(D) Integration
82. Extensive use of which type of communication is most likely to aid in solving
complex problems?
(A) formal
(B) non-verbal
(C) verbal
(D) written
83. Management wants to be sure that the project is following defined quality
standards. Which of the following would they look at?
(A) WBS
(B) Risk management plan
(C) Quality audit
(D) Statement of work
84. During project execution, a project team delivers a project deliverable to the
customer. However, the customer neither acknowledges the deliverable nor says
if it is acceptable, although an approval is required. What is the best thing to
do?
88. You are managing a project with part-time resources in a weak matrix
organization. Several of the team members only attend team meetings and have
not completed assignments. At your next team meeting, the most important
agenda item would be:
89. You are a project manager for a major information systems project when
someone from the quality department comes to see you about beginning a
quality audit of your project. The team, already under pressure to complete the
project as soon as possible, objects to the audit. You should explain to the team
that the purpose of a quality audit is?
90. Team members are arguing about the location of specification limits on a
control chart. The discussion is becoming heated when the project manager
walks in and says, _It seems that the real problem here is that we do not have
enough information about the customer's specifications. Let's..." This is an
example of?
(A) Explain what will happen if the resources are not made available.
(B) Crash the project.
(C) Show how the resources were originally promised to your project and
request that they be moved back to your project.
(D) Re-plan the project without the resources.
1 C 26 A 51 B 76 A
2 B 27 C 52 B 77 B
3 A 28 B 53 D 78 C
4 A 29 B 54 A 79 C
5 D 30 A 55 C 80 B
6 A 31 C 56 B 81 D
7 A 32 B 57 D 82 D
8 D 33 A 58 B 83 C
9 A 34 D 59 B 84 C
10 B 35 C 60 A 85 B
11 B 36 A 61 A 86 A
12 B 37 B 62 A 87 B
13 C 38 A 63 A 88 D
14 D 39 D 64 B 89 A
15 C 40 A 65 A 90 A
16 A 41 D 66 D 91 A
17 C 42 D 67 C 92 A
18 C 43 A 68 A
19 B 44 D 69 A
20 C 45 C 70 B
21 A 46 A 71 A
22 D 47 D 72 A
23 A 48 D 73 B
24 D 49 A 74 C
25 A 50 C 75 D
1-When empowering followers through idealized attributes and behaviors, and effective
motivation; the leadership style is
A- Transactional
B- Transformational
C- Servant leader
D- Laissez-faire
A- Rules
B- Procedures
C- Norms
D- Project schedule
A- Internal EEF
B- External EEF
C- Internal OPAs
D- Strong matrix
5-Which of the following is not a category for the influences of the project manager?
A- Project
B- Organization
C- Industry
D- Media
6-Multiple factors interact within an individual organization creating a unique system that
impacts the project operating in that system; which of the following is considered a system
principal?
A- Governance frameworks
B- Management elements
C- Organizational structure types
D- Systems are dynamic
7-A system of practices, techniques, procedures, and rules used by those who work in a
discipline, is best described as:
A- A methodology
B- A guide
C- A good practice
D- A Standard
10-Guiding organizational investment decisions and selecting the optimal mix of programs and
projects to meet strategic objectives are features of?
A- Project management
B- Program management
C- Portfolio management
D- Operations management
11-Which of the following is not an organizational influence in the project manager sphere of
influence?
C- Market niches
D- Funding Priorities
12-Could the project be considered to be ended in all of the following cases except?
D- No more Funding
13-The knowledge, skills, and behaviors needed to guide, motivate, and direct a team. to help
an organization achieve its business goals, is best described as?
A- Leadership
B- Strategic management
C- Knowledge management
D- Communication skills
14-Managing project elements, such as cost, schedule, and risk, is related to which skills of the
project manager's skills?
A- Leadership
B- Strategic management
C- Business management
A- High
B- Moderate
C- Low
D- No control
16-Which development life cycle is applicable when the project scope is determined early in
the project life cycle, and time and cost estimates are routinely modified as the understanding
of the product increases?
17-When a team makes their own decisions and establish their own goals, also referred to as
taking a hands-off style, the leadership style is?
A- Transactional
B- Transformational
C- Servant leader
D- Laissez-faire
A- Guiding and collaborating is related to management; while directing using positional power is
related to leadership
B- Guiding and collaborating is related to leadership; while directing using positional power is
related to management
19-Lessons learned from previous projects, and historical information are considered a/an?
A- Internal EEF
B- External EEF
D- Constraint
20-The benefits could be tangible or intangible, which of the following is a tangible benefit?
A- Monetary assets
B- Trademarks
C- Strategic alignment
D- Reputation
21-In which project management process group is the project scope established?
A- Initiating
B- Planning
C- Executing
D- Closing
22-Which of the following knowledge areas is concerned with purchasing and acquiring
products, services, or results needed from outside the project team?
23-What are the not skill sets represented by the PMI talent triangle?
B- Meeting management
C- Leadership
24-Many is a project manager in MLK organization; he is a full time designated to the job, he
has total authority, and he manages the project the budget; the work groups in this
organization are arranged by project; what is the organizational structure type of this
organization?
A- Virtual
B- Matrix balanced
C- Hybrid
D- Project-oriented
25-The ability to think abstractly, to see things differently, and to innovate, is related to which
personality characteristic?
A- Authentic
B- Creative
C- Social
D- Pragmatic
26-What is the Project Management Office (PMO) type where the PMO is directly managing
the projects and has a high level of control?
A- Supportive PMO
B- Directive PMO
C- Controlling PMO
D- Balanced PMO
27-Project and ongoing operations could intersect at different points, such as?
A- Upgrading a product
D- Identifying risks
A- Project management
B- Program management
C- Portfolio management
D- Operations management
29-Assets that influence the management of the project, such as the plans, processes, policies,
procedures, and knowledge bases specific to and used by the performing organization, could
be referred to as:
C- Governance concept
D- Matrix-balanced
30-Ali is a project team member in GTH organization; in this organization, the role of the
project manager is more like a coordinator, while the functional manager manages the project
budget; what is the organizational structure type of this organization?
A- Matrix-Weak
B- Matrix balanced
C- Hybrid
D- PMO
1-one of the following isn't a characteristic of a project, that …?
A-it is permanent.
D-it is temporary.
A-cost management.
B-Integration management.
C-Quality management.
A-Planning.
B-Controlling.
C-Closing.
D-Monitoring.
A-project chart.
B- project scope.
C-project cost.
D- project time.
D-Verify Scope.
A- 47
B- 5
C-74
D- 10
7-Scope Verification is
A) Performed at the end of project planning
B) Essentially same as quality control
C) Primarily concerned with acceptance of the work results
D) Primarily concerned with correctness of the work results
8-You and several of your key team leader are really struggling with
estimating the overall cost of the project. The most probable cause for
this estimating difficulty can be
contributed to:
A. initial poor scope definition
B. lack of required resources.
C. insufficient funds.
D. problems with the overall schedule.
3 -Time Management.
4 -Cost Management.
2 -Scope Management.
5 -Quality Management.
1 -integration Management.
A- result.
B- services.
C-Plan.
D-Product.
A-Extended authority.
B-No authority.
C- Limited authority.
A- project scope.
B- project Schedule.
C- project procurement .
D- project start.
This is Called…………………………?
A-project planning.
B- project integration.
C-project initiation.
D- project manipulation.
A-Accounting.
HR Staff
Earned Value
Quality
Project Manager
True
False
an input
an output
an input & an output
a tool or technique
Three-point estimating
Bottom-up estimating
Parametric estimating
Analogous estimating
5- Project Quality Management has three main processes which
are planning quality , _____________ quality and controlling quality.
directing
monitoring
performing
closing
True
False
Cost Planning
Cost Estimation of a project/activity.
Estimating cost of a project done at other similar organization (benchmarking).
Budget Determination
9- What tool do you need to measure Schedule Efficiency
expressed as the ratio of earned value to planned value.
Organizational Structures
Organizational Process Assets
Enterprise Environmental Factors
Organizational history
Resource Levelling
Resource Balancing
Resource Approximation
Resource Labelling
Sellers
Sponsors
Business parteners
Activity sequences
True
False
AC - EV
AC x EV
EV / AC
EV - AC
True
False
21- ___________________ is the process of identifying and
documenting project roles, responsibilities, required skills,
reporting relationships, and creating a staffing management
plan.
1-Ramy is a project manager of a construction project; being in the planning stage,
Ramy requested his team to participate with him in creating the Work"
"Breakdown Structure (WBS)when Waleed. one of the junior engineers asked him
""what is WBS? what is the best answer should Ramy select
A- WBS is a component of the scope management plan that helps in scope identification and
control
B- WBS Is a document that authorizes the project and presents the high-level project
information
D- Resources availability
B- Affinity diagrams
C- Context diagrams
D- Observation/conversation
B- Scope baseline
C- Project charter
D- WBS
5-The project manager of an IT project is currently documenting the project scope
description, major deliverables. assumptions, constraints, acceptance"? criteria,
and project exclusions; the project manager is currently preparing which document
A- Project charter
B- WBS
B- Business requirements describe the temporary capabilities that are needed: while
transition requirements describe the high-level needs of the organization
B- Control scope
C- Define scope
8- Samir is a project manager who has just been assigned for managing a new IT
development project in IMN organization; one of the project managers who has
managed previous similar projects in the same organization has advised Samir to
utilize agile scope planning approach: when is this approach is? considered useful
and effect
A- When scope is clear and well understood from the beginning of the project
B- Requirements documentation
10-Data analysis is a technique used in control scope process; variance analysis and
data analysis are two different techniques of data analysis, which answer?
describes variance analysis and trend analysis correctly
A- Variance analysis examines project performance over time to determine if progress is
deteriorating or improving, while trend analysis compares baseline to actual results and
determines if preventive actions or corrective actions are required
11- Which of the following are the outputs of collect requirements process ?
A- Scope management plan. and requirements management plan
12-How to measure the completion of the product scope and the project scope?
A- The completion of the product scope is measured against the scope management plan,
while the completion of project scope is measured against the requirements documentation
B- The completion of the product scope is measured against the scope management plan,
while the completion of project scope is measured against the requirements traceability
matrix
C- The completion of the product scope is measured against the project management plan,
while the completion of project scope is measured against the requirements documentation
D- The completion of the product scope is measured against the product requirements,
while the completion of project scope is measured against the project management plan
13-Which of the following are the main outputs of the plan scope management
process?
A- Requirements documentation, and requirements traceability matrix
B- Verified deliverables are input to validate scope process: while accepted deliverables are
the output of validating scope process
C- Both verified deliverables and accepted deliverables are inputs to validate scope process
D- Both verified deliverables and accepted deliverables are outputs to validate scope
process
C- Requirements documentation
16- What is the main difference between validate scope process and control
quality process?
A- Validate scope is mainly concerned with the correctness of the deliverables, while control
quality is mainly concerned with acceptance of the deliverables
B- Validate scope is mainly concerned with acceptance of deliverables, while control quality
is mainly concerned with the correctness of the deliverables and meeting the quality
requirements
D- Validate scope Is related to planning process group while control quality is related to
monitoring and controlling process group
17-Trends and emerging practices in project scope management mainly include:
A- Updating project management plan and project documents
B- Context diagrams
C- Affinity diagrams
D- Benchmarking
19-During the planning stage of a construction project. the project manager was
discussing with the team the importance of having a scope baseline, one of the"
junior engineers is confused about the components of the scope: baseline, which
of the following is NOT a component of the scope baseline
A- Project scope statement
C- WBS
D- WBS dictionary
B- The hierarchical decomposition of the total scope of work to be carried out by the project
team
"Your project's primary constraint is quality. To make certain the project team members
don't feel too pressed for time and to avoid schedule risk, you decide to use which of the
following activity estimating tools? "
Three-point estimates
Analogous estimating
Reserve analysis
Parametric estimating
You are working on a project that requires resources with expertise in the areas of
hospitality management and entertainment. You are preparing your project schedule
network diagram and know that you will use only finish-to-start dependencies. Which of
the following diagramming methods does this describe?
PDM
ADM
AON
Network template
All of the following statements describe the activity list except which one?
The activity list is an output of the Define Activities process.
The activity list includes all activities of the project.
The activity list is an extension of and a component of the WBS.
The activity list includes an identifier and description of the activity.
You are the project manager for Changing Tides video games. You have produced a project
schedule network diagram and have updated the activity list. Which process have you just
finished?
"The Define Activities process, which identifies all the specific activities of the project "
"The Sequence Activities process, which identifies all the activity dependencies "
"The Develop Schedule process, which diagrams project network time estimates "
"The Estimate Activity Durations process, which estimates activity durations "
You are a project manager for Picture Shades, Inc. Your company manufactures window
shades that have replicas of Renaissance-era paintings for hotel chains. Picture shades is
taking its product to the home market, and you're managing the new project. products at
retail stores as well as on its website. You're developing the project schedule for this
undertaking and have determined the critical path. Which of the following statements is
true? "
"You calculated the most likely start date and most likely finish dates, float time, and
weighted average estimates."
You calculated the activity dependency and the optimistic and pessimistic activity
duration estimates.
"You calculated the early and late start dates, the early and late finish dates, and float
times for all activities. "
"You calculated the optimistic, pessimistic, and most likely duration times, and the
float times for all activities."
You have been hired as a contract project manager for X company. It wants you to design
an Internet juice club for its customers. One of the activities for this project is the
installation and testing of several new servers. You know from past experience it takes
about 16 hours per server to accomplish this task. Since you're installing 10 new servers,
you estimate this activity to take 160 hours. Which of the estimating techniques have you
used?"
Parametric estimating
Analogous estimating
Bottom-up estimating
Reserve analysis
"You are the project manager for Design Your Web Site, Inc. Your company is designing the
website for a national grocery store chain. You have your activity Iist in hand and are ready
to diagram the activity dependencies using the PDM technique; Which of the following
statements is true? "
PDM is also the AON diagramming method and it uses one-time estimate.
PDM is also the AOA diagramming method and uses logical relationships.
PDM is also the ADM diagramming method and its most common logical relationship is
finish-to-start.
"PDM is also the GERT method, which allows for conditions, branches, and loops."
15 / Project body of knowledge includes all of the following areas except:
O Cost management
O integration management.
O Quality management.
O Product management
O Decision-making
O Simulation models
O Quality improvement
O Team discussions
o Colocation
o Ground Rules
o Team-building activity
O Project authority
O Control accounts
O Statement of work
O Planning HR
O Acquiring HR.
22 / The Actual Cost (AC) is the realized cost incurred for the work performed on an
O True
O False
24 / Which statement is true?
O A project manager should not have soft skills in order to lead the project
O A project manager must hide critical information that ma lead the project to financial loss.
O A project manager must disclose critical information that may lead the project to financial loss.
O A project manager should spend as more time as possible in each activity because the time isn't a
matter
25 / ……………is a technique that examines the project from each of the strengths, weaknesses, a threats
perspective to increase the breadth of identified risks by including internally generated risks
O PERT Chart
O Cost Analysis
O SWAT Analysis
O Delphi Technique.
O scope
O quality
O risk
O accuracy
28 / All of the following are codes of Professional Roles and Responsibility except
30 / The Tuckman ladder which identifies five stages of developing project teams includse all of
O Forming
O Storming
O Norming
O Performing
O Adjourning
O Time Control.
O Stakeholders Control
O Risk Control
O Impact Control
O Good Communicator
O Wealthy
O Enthusiastic
34 / The project manager can not get the outputs unless he…………….
35 / The project always aims, but not limited, to get all of the following except
O result.
O stakeholders
O services
O product.
36 / The project management process groups consist of several individual component processes which
turn project.
O materials
O inputs
O objects
O teams
37 / Which of the following is not a mean by which projects are initiated?
O Legal requirement
O Technological advance
38 / the following areas according to the degree of sequence, (e what comes first or before the other)
39 / All of the following are Quantitative Risk Analysis and Modeling Techniques except:
O Sensitivity analysis
O Interviewing
42 / …………..Management descrbes the processes and methods required to identity uantity and control
O Scope
O Cost
O Quality
O Risk
O Political climate
O deliverable
O Product
o output
o impact
45 / All of the following are Strategies for positive risks (or opportunities) except
O Exploit
O Enhance
O Avoid
O Share
47 / Resource ……….……..is the process of rescheduling on the project schedule activities that ha
resource usage.
O Preloading
O Downloading
o Loading
O Uploading
48 / One project manager had sequenced stages to do, but he What do you think the mistake he made ?
2 السؤال
"One of the team members in a development project is trying to define the
relation between two variables, which tool will be sufficient to carry out this
task?"
Histograms
Scatter diagram
Affinity diagram
Root cause analysis
3 السؤال
"An audit has been performed in a construction project, and its results
recommend that some team members should have training, in what category
of cost of quality (COQ) does the training exist?"
Internal failure costs
External failure costs
Appraisal costs
Prevention costs
4 السؤال
"In a construction project, during testing a deliverable, the results show that
there are several defects, the project manager advised the team members to
organize defects into groups in order to show areas to be focused on, which
tool/technique is requested to be used by the project manager ?"
Cause and effect diagram
Root cause analysis
Affinity diagram
Document analysis
5 السؤال
Keeping errors out of the process is the primary concern of ?
Inspection
Prevention
Attribute sampling
Variable sampling
6 السؤال
A collaborative environment is related to which of the following tailoring
considerations?
Policy compliance.
Stakeholder engagement.
Continuous improvement.
Standards compliance.
7 السؤال
Which of the following is not an emerging practice/trend in project quality
management?
Customer satisfaction.
Continual improvement.
Mutually beneficial partnership with suppliers.
Communication method.
8 السؤال
Which of the following techniques is considered a set of technical guidelines
that may be applied during product design and used for optimization of a
specific aspect of design?
Histograms
Checklists
Scatter diagram
Design for X
9 السؤال
Which of the following are considerations for applying project quality
management in the agile/ adaptive environment?
"Consider large work batches, fewer reviews, and check efficiency for the
applied process."
"Consider large work batches, frequent reviews, and check efficiency for
the applied process."
"Consider small work batches, fewer reviews, and check efficiency for the
applied process."
"Consider small work batches, frequent reviews, and check efficiency for
the applied process. "
10 السؤال
Which of the following are considered quality improvement methods?
"Six Sigma, and plan-act method"
"Six Sigma, and plan-do-act method"
"Six Sigma, and plan-do-check-act method"
"Six Sigma, and plan quality management"
11 السؤال
"In an IT project for developing an estimating software, the preliminary results
are shown to be inaccurate, all results have the same error percentage; Ali,
the project manager, advised Yasser, one of the team members, to search for
the underlying reason for this error as he believes that fixing this underlying
reason will result in accurate and correct results, what technique/tool is
requested to be used?"
Document analysis
Data analysis
Surveying
Root cause analysis
12 السؤال
What is the tool used in the figure below ?
Affinity diagram
Control chart
Scatter diagram
Benchmarking
13 السؤال
Which of the following is an output of plan quality management process ?
Quality management plan
Quality control measurements
Organizational quality policy
Completed checklists
14 السؤال
The specified range of acceptable results could be described as
___________________.
Tolerances
Control limits
Specification limits
Acceptable range
15 السؤال
Which of the following is an input to manage the quality process ?
Project charter
Cost estimates
Quality control measurements
Change requests
16 السؤال
"The type of sampling that represents the result in two categories only
(confirm, and not confirm) is called ______________________."
Statistical sampling
Attribute sampling
Variable sampling
Probabilistic sampling
17 السؤال
Abdullah is a quality manager in a construction project; he is cooperating with
project manager to define and document the quality standards and
requirements. Which process is currently carried out ?
Plan quality management
Manage quality
Control quality
Develop project management plan
18 السؤال
Which of the following tools is a financial used to determine the best
alternative regarding benefits provided by estimating the strengths and
weaknesses of alternatives?
What-if analysis
SWOT analysis
Cost-benefit analysis
Multi-criteria decision analysis
19 سؤال
Is the process, in the figure below, controlled or out of control?
The process is controlled.
The process is out of control because all the points fall outside the control
limits.
The process is out of control because all the points fall outside the
specification limits.
The process is out of control because one point falls outside the control
limits
20 السؤال
Meeting quality requirements could result in ______________ .
Less re-work decreased level of risk and increased profit.
"More re-work increased level of risk, and decreased profit."
"Less re-work increased level of risk, and decreased profit."
More re-work decreased level of risk and decreased profit.
السؤال1
"In an IT project, the project manager stated that a prototype should be developed to minimize the risk of
rejecting final product; what is the stated strategy?"
Accept
Transfer
Mitigate
Avoid
السؤال2
"ARABCO is an organization which is planning to start a new IT development project; the nature of this
project is entirely new to the organization, which is considered a negative risk. The organization's top
management has decided to build an agreement with a third party to manage the risk and to bear the
impact of the threat if occurs; what is the strategy used by the organization?"
Share risk
Transfer risk
Mitigate risk
Accept risk
السؤال3
"Samir is a project manager of a development project, during the project execution, Samir checks the
validity of the identified risks, analyses and identifying new risks, and checks the effectiveness of the risk
management process; these activities are related to which process of project risk management?"
السؤال4
Implementing agreed-upon risk responses is related to which project management process group?
Closing
Executing
Planning
Monitoring and controlling
السؤال5
Ahmed is a project manager of a construction project; he is currently working with risk manager to
prioritize risks based on the probability of occurrence and the impact of risks; what is the current risk
management process?
Monitor risks
Identify risks
Perform quantitative risk analysis
Perform qualitative risk analysis
السؤال6
"Determining if risk processes can be followed sequentially and iteratively, or otherwise is related to
which of the following tailoring considerations?"
Project complexity
Development approach
Project size
Standards compliance
السؤال7
"In an IT project, Mohamed, the project manager requested from Omar, one team members, to classify the
risks into priority groups considering their probability of occurrence and their impact; Omar asked
Mohamed about an appropriate perform this task; what could be Mohamed's answer?"
السؤال8
Which of the following is an output of identify risks process?
السؤال9
Which of the following are most likely to be the components of an initial risk register developed in the
early planning stages of the project?
السؤال10
Which of the following strategy is concerned with increasing the probability and/or impact of an
opportunity?
Exploit
Accept
Enhance
Escalate
السؤال11
Which of the following is an emerging practice/trend in project risk management?
Trial engagements
Mutually beneficial Partnership with suppliers
Communication method
Customer satisfaction
السؤال12
"In a construction project, risks have been identified and prioritized. The risk manager is currently
working with the project manager to numerically analyze the combined effect of individual risks to
determine the effect on the project objectives, what is the current process of project risk management?"
السؤال13
Which of the following is not a component of risk management plan?
السؤال14
Which of the following is an input to plan risk management process?
Change requests
Risk register
Risk management plan
Project charter
السؤال15
"After planning risk responses in a construction project; the project manager conducted a meeting with
the project manager; he mentioned that the only ways to eliminate a high priority threat that may affect
the project severely are to extend the schedule or to reduce the scope, what strategy is discussed by the
project manager?"
Mitigate
Accept
Transfer
Avoid
السؤال16
"During planning responses for identified risks, it was found that a risk is expected to remain after
implementing the agreed-upon risk responses, what is this risk called?"
Residual risk
Remaining risk
Secondary risk
Unknown risk
السؤال17
Escalating is concerned with risks which are ................................. .
within the project level of control and outside the project level of control
within the project level of control
outside the project level of control
only opportunities
السؤال18
What is the use of bubble chart in risk management?
"It models three dimensions of data, where each individual risk is represented as a bubble, and the three
parameters are modelled by the xaxis value, the y-axis value, and the bubble size."
"It models two dimensions of data, where each individual risk is represented by the x-axis value and the y-
axis value."
السؤال19
"Saud is a project manager of a project of constructing a residential compound; one of the agreed-upon
risk responses is to have a contingent supplier to provide a required material if the main supplier faces
any problems, if the contingent supplier is utilized, the required material may cost more than that
originally agreed upon with the main supplier; what is described in this case?"
Residual risk
Secondary risk
Issue/Problem
Unknown risk
السؤال20
Which of the following is a consideration for applying project risk management in the agile/adaptive
environment?
Buyer
Owner
Seller
Customer
Agreements.
Bid documents
3- In an IT project, and due to adaptive nature of the project, the buyer and the seller did not agree regarding
payments related to a specific requirement, the project manager of the seller organization is planning to claim the
issue at the court, one of his colleagues stated that this not the correct way and that he must follow another Path,
what should be this path
Missing information
Negotiation only
4- The collaborative working relationship is an effective consideration for applying procurement management in
agile / adaptive environments. what should this feature include
Mitigating risks
Avoiding risks
Accepting risks
5- During inspections and auditing in a construction project. It was found that the contractor performance is
inferior and not as expected, what is the first step to do
6- A sort of discussion targeting mutual satisfaction of the parties of discussion before signing a contract could be
referred to as
Informal Communication
Negotiation.
Claims administration
Dispute resolution
7- Which type of contract is most appropriate for staff augmentation, acquisition of experts: “and any outside
support when a precise statement? of work cannot be quickly prescribed
Incentive contracts
Fixed price
Cost reimbursable
8- Which of the following could best describe the complexity of procurement tailoring consideration of
Contractors availability
9- "Building Information Modeling (BIM) is an emerging practice / trend, which category could have BIM"
Advance in tools
Cost reimbursable
Fixed price
Conduct Procurements.
Close Procurements
Control procurements
12- In a construction project, the performing organization decided to acquire a contractor to carry out concrete
works instead of using the organizational resources, during the executing phase, it was found that the incurred
costs are very high and could result in substantial losses, what should have been done to prevent this
Bidder conference
Independent estimates
13- Closing out the contract is done in which procurement management process
Control procurements.
Conduct Procurements
Validate procurement
When more information on the goods and services to be acquired is needed from the sellers
. When there is a problem with the project, and the solution is not easy to determine
o When more information is needed on how vendors would satisfy the requirements and / or how much it will
cost
16- Which contract type is appropriate for considering changed condition, such as inflation
17- What is contract type that allows the seller to be reimbursed for all legitimate costs, but the majority of the fee
is earned based on the satisfaction of specific broad subjective performance criteria that are defined into the
contract ?
Fixed price
18- Which of the following is not a component of procurement statement of work (SOW
Quality levels
Specifications
Formal agreement
Quantity desiredo
19- During a bidding process, one of the prospective sellers stated that one seller receives preferential treatment
what should have been done to "prevent this
Project charter
21- In an IT project, the following stakeholders have been identified: Hamed, Adel, and Gamal; "Supportive is the
desired engagement levels of Adel, while" Leading "is the desired engagement level of Hamed and Gamal. During
the project execution, it was found that the current engagement level of Adel is" Neutral, "Hamed was found to
be" unaware, "while Gamal was found to be" Leading ". who has the most massive communication gap?
Gamal
Adel
Hamed
22-." Tarek is a project manager of a construction manager; he is currently defining and documenting appropriate
approaches for involving stakeholders based on their needs, interests, and impact on the project; what process is
Tarek currently involved in?
Identify stakeholders
23-Which of the following are the tailoring considerations for applying project stakeholder management?
"Stakeholder diversity, the complexity of stakeholder stakeholders' relationships, and time of stakeholder
engagement.
. Stakeholder diversity, the complexity of stakeholders 'relationships, and budget of stakeholder engagement.
24- which of the following statements is not accurate regarding brainstorming and brainwriting ?
25-. All of the following are characteristics of stakeholder engagement plan except?
Its level of details depends on the project needs and stakeholders' expectations.
It should be formal.
27- During the process of stakeholders in a new construction project, the project manager has identified
the mayor of the city in the stakeholder register, this mayor has a low interest regarding the project,
what action should be defined to manage this stakeholder effectively?
Monitor
Keep satisfied
Keep informed
Manage closely
28- Mahmoud is a project manager of an IT project with an adaptive environment; Samir, a project
manager in the same organization who managed previous similar projects advised Mahmoud to focus
on effective engagement of project stakeholders in order to maintain their support and commitment,
what should Mahmoud do to achieve this?
29- "Co - creation concept is considered one of the emerging practices and trends in project
stakeholder engagement, what is co - creation?
"Consulting with stakeholders who are most impacted by the project work or outcomes, a include
them as partners in the team
31-. Which of the following is the primary concern of project stakeholder engagement?
Stakeholder register.
Change requests
34-. Which of the following is used to identify the underlying cause of not achieving desired results?
Status meetings
. Alternative analysis.
36- Which of the following is not a project management process related to project stakeholder
management knowledge area?
Identify stakeholders
37- In the execution phase of a construction project, a new group of people started to have a
substantial impact on the project work, Sameh, the project manager, decided to proceed in the
required procedures to update the stakeholder register, when Ahmed, one of the project team
members, stated that the stakeholder register is created at the beginning of the project and it can't
be updated during the execution phase, is Ahmed's statement correct?
"No, the stakeholder register should be initially developed during the execution phase."
No, the stakeholder register can be updated when a change in the stakeholder's community occur
" Yes, the stakeholder register is an output of family stakeholder process, which is related to
initiating process group, so no way to update the stakeholder register during execution.
Project charter
Agreements
Project schedule
39-. During the stakeholders in a project, one of the team members proposed to use a technique /
tool that considers the level of authority, and the level of concern, which tool does he mean?
Salience model
. 40- Which tool / technique for customer stakeholders considers combining grid elements into a 3D
model, and providing a model with multiple dimensions?
Directions of influence.
Stakeholder cube
Salience model
41 - What type of negotiations is considered when negotiating for specific resources inside a functional
organization?
42 - Which of the following documents establishes the operating guidelines for the team and builds clear
expectations regarding the acceptable behavior by project team members?
Project charter
Team charter
43 "When do team members begin to work together and adjust their work habits and behaviors to support the
team, what this stage is called in Tuckman ladder?
" Forming
Storming
Norming
Performing
44 - Which of the following data representation techniques is the most effective when describing the team
member role and responsibilities in details?
Hierarchical charts
Text-oriented formats
Assignment matrix
RACI chart
Project team
Project sponsor
Project manager
46 - Estimate activity resource identified resource requirements which are then effectively used in?
Sequencing activities
Defining activities
Creating WBS
47 - Which of the following is an emerging practice / trend in project resource management?
Customer satisfaction
trial engagements
Team charter
Project charter
Change requests
Team charter
50- "During acquiring resources, the project manager highlighted that a specific sub - contractor had been
nominated in the project charter, this could be referred to as?
Sole subcontractor
Pre - assignment
Resource acquisition
51 - Which of the following is a consideration for applying project resource management in the agile / adaptive
environment?
52- In a research project, it was recommended to utilize virtual teams to perform the required work, which of the
following is not a characteristic of virtual teams?
53- "During the execution phase of a project, Kamal is comparing the actual number of excavators to the
corresponding planned number in order to." Identify the gap and recommend a recovery action, what process is
described?
Manage team
Manage resources
Control resources
54-. "In a development project, a conflict has occurred between two of the team members, they failed to solve the
conflict by themselves, but no solution has been reached, they reached the project manager to resolve this
conflict, what should the project manager do first?
"Transfer one of the two team members to another work site to prevent future conflicts.
Try to apply collaboration and problem - solving techniques to reach an appropriate solution
Withdraw the problem to another time in order not to waste the work time.
. 55 - Nassir is a project manager of a construction project; he is currently working on improving the team
environment and competences; which process is currently described?
Acquire resource
Develop team
Manage team
Control resources
56- "Ahmed and Mahmoud are two team members in a construction project, where Tarik is the project manager,
and Sami is the project sponsor; during the executing phase, a personal conflict occured between Ahmed and
Mahmoud , who is / are the responsible person / persons to resolve this conflict as a first step ?
Tarik
Sami
57 - Which of the following tailoring considerations is concerned with the team's background?
Physical location
Diversity
Standards Compliance
Project charter
Team charter
Change requests
59 - in an IT project, where Ayman is the project manager, Hussain is one of the team members; he is arguing with
Ayman regarding an ambiguous part of the scope; Ayman told Hussain to stop this discussion and do only what
Ayman sees it is c orrect; what techniques have been utilized by Ayman?
"Smooth
Collaborate
Force
Withdraw
60 - Which resource management process is concerned with resolving conflicts and issues?
Acquire resources
Develop team
Manage team
Control resources
61 - The inclusion of stakeholders in project reviews is an emerging practice in project communications
management, all of ""? The following are also emerging practices / trends except
62- Network problems, different language, and surrounding sounds that could prevent and reduce understanding
could be "? referred to as
Noise
Barriers
Problems
Negative causes
Push communications
Pull communications
Interactive communication
64 - Waleed is a team member participating with Sami, the project manager, in developing the communication
management plan; "during discussion , Waleed stated that the stakeholder register is not needed to develop the
communication management plan, Sami rejected this statement and stated that stakeholder register is a core
input in communication planning: who has the correct *? opinion
Both Waleed and Sami have a correct opinion as it is not mandatory to use stakeholder register in communication
planning
65- ?" A project consists of 10 members, what is the number of the communication channels
35
45
55
10
66- A developer intends to develop a web - site for e - learning, what communication method is the most
appropriate for this case
Push
Pull
Interactive
Meeting
* Project communications
68 - What could be interpreted from the following statement the receiver provides feedback to the sender
regarding his "? Message
The receiver agrees with the sender about the message content
69 - During the execution phase, one of the stakeholders stated that he is not receivjr a progress report, based on
this, "one of the team members was going to gp him the required report, but the project manager told him that
he missed an "? essential step, what could be this step
Apologize for the stakeholder for the delay in sending the report
70 -... Ali of the following are examples of format communications except ÉÉÉ
Reports
Briefings
Meeting minutes
Emails
71 - Ameer is a project manager of an IT project; Ameer's team contains ten members, one of them, Wael, is
performing not as ""? expected. What is the best way that could be done by Amr to communicate with Wael
regarding this issue
Formal - verbal
Informal - verbal
Formal - written
Informal - written
72-? Who is the primary responsible person for the communication management success
Project sponsor
Project manager
Customer
Team leaders
73-? Which communication dimension focuses on stakeholders within the project and within the organization
Internal
Formal
External
Hierarchical focus
74 - For the same data in question 10, after conducting the informal - verbal communication, Ameer found that
Wael's ""? performance did not improve, but it stills poor, how should Ameer communicate with Wael this time
* Formal - verbal
* Informal – verbal
* Formal - written
* Informal – written
Decoding
Encoding
Active thinking
Active listening
76 - All of the following are considerations for applying project communication management in agile / adaptive
environment except?
Streamlining team member access to information
77 - Omar is a team member in an IT project who is responsible for managing information flow between team
members and stakeholders, the project has a virtual environment. The change control board has just approved a
change request, Omar will send this approved change to several team members in different locations by email,
what communication method will Omar "? Use
Push
Pull
Interactive
Two – way
Interactive communication
79- "? Misunderstanding is the most common communication problem, how it could be reduced
80 - During the execution of a construction project, one of the team members has discovered an issue which will
have a substantial negative impact on the project, he contacted the responsible person several times, but nothing
was changed, what "? should he do next
.He should proceed according to escalation procedures defined in the communication management plan
.Contact the responsible person again, maybe he will solve the problem
81-You have received estimates for activity costs associated with one work package of the WBS. Additional
contingencies have been added to the estimates to account for cost uncertainty. Which of the following tools and
techniques of Estimate Costs does this describe?
Reserve analysis
Three-point estimates
Analogous estimates
Funding requirements
Cost baseline
Cost estimates
Expenditures to date
83- "You are the project manager for a custom-home-building construction company. You are working on the
model home project for the upcoming Show Homes Tour. The model home includes Internet connections in every
room, talking appliances, and wiring for home theatres. You are working on the Determine Budget process. All of
the following statements are true except which one?
" You document the funding limit reconciliation to include a contingency for unplanned risks.
You discover that updates to the risk register are needed as a result of performing this process
. You document that funding requirements are based on a quarterly basis and are derived from the cost baseline.
The performance measurement baseline will be used to perform earned value management calculations.
84- You are a project manager working for iTrim Central and you're preparing your cost management plan. You
know that all of the following are true regarding this plan except for which one?
"Units of measure should be described in the plan usually as hours, days, weeks, or lump sum.
"Control thresholds should be described in the plan as to how estimates will adhere to founding ($100 or $1,000,
and so on)."
85-All of the following are tools and techniques of the Determine Budget process except for which one?
Reserve analysis
Expert judgment
Historical relationships
Cost of quality
86-"You have received the following estimates for a complex activity that is critical to the success of your project.
The three-point estimates are: most likely estimate is $42, the optimistic estimate is $35, and the pessimistic
estimate is $54 What is the expected activity cost of this activity using the beta distribution formula (rounded to
the nearest dollar)?"
49
39
43
44
87-Your project sponsor has requested a cost estimate for the project. She would like the cost estimate to be as
accurate as possible because this might be her one and only chance to secure the budget for this project because
of recent cuts in special projects. You decide to use ____________
88-All of the following are inputs of the Estimate Costs process except for which one?
Resource calendars
Scope baseline
Project schedule
89- You want to improve your activity cost estimates by taking into account estimation uncertainty and risk. Which
of the following tools and techniques will you use?
Analogous estimates
Three-point estimating
Parametric estimates
Bottom-up estimates
90- "This document is used to establish the criteria for planning, estimating, budgeting, and controlling costs."
" "Performance management baseline, an output of the Plan Cost Management process."
91- All of the following are true regarding the Project Cost Management Knowledge Area processes except for
which one?
The primary concern of the Project Cost Management Knowledge Area is determining the amount of resources
needed to complete project activities.
The Estimate Costs and Determine Budget processes can be combined into one process for small projects.
The Estimate Cost process is closely linked with the Estimate Activity Resources process.
"General management techniques such as ROI, discounted cash flow, and payback analysis can be used to help
derive cost estimates. "
1-which of the following is an output of performing integrated change control process
B- Change request
D- On-demand Scheduling
3-what is the process group that contains manage project knowledge process?
A- Initiating
B- Planning
C- Executing
A- Leading and performing the work defined in the project management plan implementing
approved changes to achieve the projects objectives
B- Defining, preparing, and coordinating all plan components and consolidating them into an
integrated project management plan
C- Developing a document that formally authorizes the existence of a project and provides the
project manager with authority to apply organizational resources to project activities
D- Tracking, reviewing, and reporting overall progress to meet the performance objectives
defined in the project management plan
B- High-level requirements
A- Lessons learned
B- Stability of requirements
C- Resource availability
B- Schedule baseline
C- Risk register
9-Ibrahim is a project manager of an IT project; during the project execution, after defining all
requirements and approving all plans, one of the key stakeholders stated verbally that he
wants to add more features to the software: what should Ibrahim do?
A- Ibrahim should request the stakeholder to submit a change request, and he should also
evaluate the impact of this request on the project objectives
10-At the final stages of an IT project, the project manager is working with the project team to
create a document that include the summary of any risks or issues encountered on the project
and how they were addressed, what is this document?
A- Project charter
C- Final report
D- Change log
11-who is responsible for approving, or rejecting the submitted change requests?
A- Project manager
B- Functional manager
C- PMO manager
A- Change log
D- Issue log
13-during a kick-off meeting of a construction project, one of the key stakeholders stated that
the items being discussed are not appropriate to be discussed in a kick-off meeting; which of
the following could be those items which are not a purpose of the kick-off meeting?
D- Defining the project scope and creating the work breakdown structure
14-in the execution stage of a construction project, the project manager requested a team
member to provide him with a specific work performance data; which of the following could
be this work performance data?
15-A product, service, or result, once delivered by the project, may be handed over to a
different group or organization that will operate, maintain, and support it throughout its life
cycle; in what project management process this could happen?
A- Corrective action
B- Preventive action
C- Defect repair
17-in a construction project, and after recording lessons learned and preparing a final report,
the project manager is currently working on the release of team resources; in which project
management process the team resources are released?
20-which of the following is an output of direct and manage project work process?
A- Deliverables
B- Verified deliverables
C- Accepted deliverables
D- Project charter
1- PMP stands for
5- The PMI is
• Project Management Industry
• Project Management Information
• Project Management Institute
• Project Marketing Institute
11- Project integration management takes care thoroughly for all of the following except:
o Project costs.
o Project schedule.
o Project procurement.
Project scope.
12- ……. is the way of comparing the value of either producing needs or outsourcing the
Cost - benefit Analysis
Data Analysis
O Brainstorming
Recruitment
13- Stakeholders must know all technical details about the project.
True
False
16- Which area of knowledge is concerned with organizing employees within the project.
Scope Management
Integration Management
Resource Management
Cost Management
18- ……….. Authorizes the project to proceed, outlines funding status, and provides an overview of
the project from the organizational point of view.
Project Risk Register
Project Charter
Project Stakeholder Register
Project venders list
20- In a weak organizational structure of a project, the project manager has ÉÉÉÉ .. command of a
project."
Extended authority
wide - ranged delegation.
Limited to narrow power authority.
No authority at all.
22- The sender of a message is responsible for confirming the message is understood.
True
False
23- ……….. is the way of comparing the value of either producing beer
Cost - benefit Analysis
Data Analysis
Brainstorming
Recruitment
24- Generally, a bid differs from a proposal in that the term bid is use hat the term bid is used when
the seller selection decision will be based on price."
True
False
25- Examples of interpersonal skills that a project manager uses most often include all of the
following indicators EXCEPT:
Leadership
Influencing
Governance
Effective decision making
27- Which one of the following is not a side (rib) of the PM Talent Triangle?
Gaining & developing soft skills
Technical Project Management
Leadership
Strategic and Business Management
33- Performing integration is a cornerstone skill for all project managers; the following describe the
three different levels of performing integration EXCEPT
Cognitive level
Process level.
Complexity level.
context level.
35- It refers to the act of bringing together a group of people to create new knowledge ensuring
that the session's participants work together wey
Facilitation
Baseline
Work Breakdown Structure
Delegation
36- "All of the following are sub plans that integrated into a single unified project plan, EXCEPT:"
OPAős plan
Cost plan
Time plan
Scope plan
38- ……… are used to perform analysis to find current performance against to the expected level for
a specific activity in established time - phase. They are, generally, approved by project
management team and those are used to measure and control of project activities.
Facilitation
Baselines
Work Breakdown Structure
Delegation
39- "The management style differs from one project to another, and that is due to the difference
within project's nature."
True
False
40- There is no need to gather information for decision - making in project management.
True
False
41- The project always aims but not limited to get all of the following except:
Result.
services.
plan.
product.
product & service as well.
42- Select the estimating techniques used to determine project costs and duration:
Bottom - up Estimating
Bottom - Bottom Estimatingi
Parametric Estimating
Analogous Estimating
Parametric Analogous Estimating
3 - Point Estimating
Life - Cycle Estimating
43- Tools and techniques to acquire resources include all of the following EXCEPT:
o Decision making.
Acquisition.
Interpersonal and team skills.
Pre – assignment
44- "When the organization assessment is based on comparing to other similar one in the same field
of industry, what kind of assessment is that?
Analysis charting
Benchmarking
colocation
baselines
48- Select the knowledge areas of project management from the following list. Make sure you can
choose more than one answer
Integration Management
Scope Management
Communications Management
Cost Management
Stakeholder Management
Experts Management
50- ………. is the method used to expect the cost based on previous projects costs.
Bottom - up Estimating
Bottom - Bottom Estimating
Parametric Estimating
Analogous Estimating
52- Strategies typically used to deal with threats or risks that may have negative impacts on project
objectives if they occur include all of the following EXCEPT:
Interpreting.
Mitigating
Avoiding
Transferring
53- A program is a:
O Group of related tasks lasting one year or less.
O "Group of related projects, subsidiary programs, and program acti
O Large projects with significant cost and resource requirements.
Sequence of activities constituting a major project.
54- Which of the following tools best helps in finding out the root of the problem at work.
Fishbone Chart
Gantt Chart
Pareto Chart
Scattered Diagram Chart
55- All of the following are stakeholders EXCEPT:
Information Technology
Suppliers
Employees
Customers
56- "In communication, the receiver decodes the messages based on all the following EXCEPT;"
Language
Knowledge
Culture
Distance
57- The three main constraints that restrict the project implementation are all of the following
except:
project charter
project scope.
project cost.
project time.
58- Classification of the engagement levels of stakeholders includes all of the following EXO
Manipulative
Supportive
Neutral
Resistant
60- "The systematic processing for any process is built on inputs, tools & techniques, and outputs."
True
False
62- Project body of knowledge includes all of the following areas except:
Cost management.
Integration management.
Quality management.
Project product management.
64- ……….. is a process that involves activities needed to resolve different kinds of disputes by
conducting consultation between the involved parties to reach an agreement.
Manipulation
Traceability Matrix
Negotiation
Contract
65- ‘’ CASE: Your customer ask for a small change in the project, which was not budgeted in the
project. It is a project and you need the goodwill for a multimillion Riyals on the pipeline. You
will …………………
- Refuse to do the work
- Agree to do the work at no charge
- Assess the cost and schedule impact and tell them you will formalize the change request.
- Do the work and bill him later.
66- What is the expected error if the project manager could not express the project success even
though it is not?
- Lack of communication
- Lack of resources
- Lack of budget
- Lack of manpower
67- …………… is a process that involves activities need to resource consultations between the
involved parties to reach an agreement.
- Manipulation
- Traceability Matrix
- Negotiation
- Contract