MCC - Remaining Works To Complete

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

REMAINING WORKS TO COMPLETE AS OF FEBRUARY 27, 2021

FEB MAR APR


ACTIVITIES 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 REMARKS
Project Name : Design, Fabrication and Installation of Receiving Lines Nos. 3 and 4, etc.
Contractor : MECHATRENDS CONTRACTORS CORPORATION
Location : MC MAI Bulk Chemical Terminal, Calaca, Batangas

1. Fabrication and installation of Receiving Lines :


1.1. Rectification of section of 8"dia line as per CISC
1.2. RT at section of rectified 8"dia line only
1.3. Hydrotesting
1.4. Airblowing
1.5. Painting works
1.6. Application of anti-corrosion tape system
1.7. FDT and concreting at the other half of lane of road
1.8. Backfilling and compaction
1.9. Modification of inspection pits
1.10. Restoration of various concrete pavements, ect
2. Fabrication and installation of Tank 2 Cargo line :
2.1. Installation of PRV and line
2.2. Hydrotesting
2.3. Airblowing
2.4. Painting works
3. Fabrication and installation of Tank 2 Service line :
3.1. Fabrication and installation of tank-to-pump line
3.2. Fabrication and installation of pump-to-embedded line
3.3. Fabrication and installation of embedded-to-gantry line
3.4. Hydrotesting
3.5. Airblowing
3.6. Painting works
4. Electrical Works :
4.1. Replacement of pump' motor #1, #2 and #3 and testing
4.2. Electrical wiring works MCC to pump shed and testing includes installation of fixtures
4.3. Electrical wiring works MCC to gantry and testing retapping of existing flowmeters, switch of loading arm
4.4. Tapping of pump #4, grounding system and testing
4.5. Labelling
5. Repair of pump shed concrete slab
6. Construction and installation of lighting posts :
5.1. Excavation, rebarworks, formworks and concreting of footings
5.2. Rebarworks, formworks and concreting of pedestals
5.3. Supply and delivery of galvanized lighting posts
5.4. Erection of lighting post
5.5. Cabling works and testing
5.6. Installation of lighting fixtures awaiting MC MAI supplied lighting fixtures
7. Construction and installation of lightning arrester :
6.1. Excavation, rebarworks, formworks and concreting of footing
6.2. Rebarworks, formworks and concreting of pedestal
6.3. Supply and delivery of steel post awaitng for delivery
6.4. Erection of steel post
6.5. Installation of fixtures and testing
8. Replacement of tank gauge :
7.1. Removal of existing tank gauge
7.2. Delivery of new ATG Estimated delivery of ATG to Calaca : Mar 31, 2021
7.3. Installation of various supports of new ATG
7.4. Installation of new ATG

Project Name : Design and Construction of Water Tank


Contractor : MECHATRENDS CONTRACTORS CORPORATION
Location : MC MAI Bulk Chemical Terminal, Calaca, Batangas
1. Hydrotesting of tank to full height
2. Grouting/Tapping of foundation and construction of landing
3. Construction of grounding pit
4. Testing of grounding system
5. Painting retouch
6. Tank labelling

You might also like