Method Statement Package 3
Method Statement Package 3
: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
METHOD STATEMENTS
FOR
PACKAGE NO. 3
Revision
Issue Date Purpose of Issue Remarks
No.
0
Page | 1
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
INDEX
1.0 Purpose 3
2.0 Scope 3
3.0 Responsibilities 6
ANNEXURES
A Risk Assessment
1.0 PURPOSE
Page | 2
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
The purpose of this Method Statement is to identify the step by step procedure for the
Works for Package 3.
2.0 SCOPE
This method statement describes the procedure for the all the Works for Package 3 of HGH
Trauma & Emergency Expansion Phase 1 – Work Packages for Post Occupancy
Operational Changes. Scope of work is detailed below.
Page | 3
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
Page | 4
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
Page | 5
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
3.0 RESPONSIBILITIES
3.1 Organization, Responsibility & Supervision
The personnel stated below shall be responsible for the implementation of this
method statement and the procedures.
3.1.1 Position: Project Manager
Responsibilities:
Representative of for the project and the first person to interact
with HMC Representatives and Third Party Representatives.
Full authority and responsible for any aspects of the contract and
related agreements.
Overall execution and administration of the project as per the
contract requirements.
Ensure a comprehensive contract review.
Delegate responsibilities to his subordinate and direct organization
on site.
Coordinate with the Contractor representative for obtaining the
necessary resources for the project and deploy as required.
Submit progress reports as per contractual requirements.
Perform initial post-award and periodical contract review as and
when required throughout the execution of the project.
Project Manager shall be responsible for financial issues and
technical issues.
Reports to the contractor’s representative the progress and all
other matters regarding the project.
Page | 6
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
Page | 7
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
Page | 8
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
Page | 9
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
Page | 10
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
Page | 11
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
6.1.2 RESOURCES
6.1.2.1 Tools and Equipment
Page | 12
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
Page | 13
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
Page | 14
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
Page | 15
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
6.2.2 RESOURCES
6.2.2.1 Tools and Equipment
Power Supply
Scaffolding/Working Access
Drill Machines
Screw drivers
Measuring tape
Plumb line
Spirit level
Hammer
Shims
Screws
Levelling bar
6.2.2.2 Materials
Metal door frame and accessories
Metal door leaf
Ironmongeries
Anchors and fasteners
Page | 16
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
Page | 17
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
Page | 18
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
6.2.3.2.4 Grouting
Grouting can be done by filling the approved grout
material or approved PU foam on the back of the door
frames.
Protection either by masking tape or polythene sheet
will be done other than the filling area (back of frame)
to avoid the rework of frame primer/painting finish for
overflow or leakage of the grout or PU foam.
Page | 19
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
6.2.3.2.6 Adjustments
Before the commencing with the finishing work which
may inhibit adjustment, installers shall:
1. Check that clear openings between jambs are constant
within ± 1 mm from top to bottom of opening at both
faces of frame (not moved or twisted in tightening).
2. Fit hardware to supplier's instructions and check for
correct operation and even leaf I frame gaps.
3. Note that in some instances, fixings supplied by
subcontractor will supersede ironmongery supplier's
fixings and/ or instructions. Adjust as necessary.
Page | 20
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
Page | 21
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
6.2.3.3.2 Maintenance
Any scratches that occur should be treated with a rust
inhibitor and 'touched up'. Normal paintwork can be
incorporated into decoration program.
6.3.2 RESOURCES
6.3.2.1 Tools
Grooving machine
Hot air welding gun
Quarter moon knife
Hook knife
Straight knife
Measuring tape
Spatula
Metal roller
Page | 22
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
6.3.2.2 Manpower
Skilled workers from a specialist subcontractor
Helpers
6.3.2.3 Materials
RF-3 Sheet Vinyl, Forbo Flooring System
RF-1 Sheet Vinyl, Forbo Flooring System
Forbo Vinyl Adhesive
Vinyl coved skirting
6.3.3.3 STORAGE
The material will be stored in a covered warehouse to keep them
dry and protected against damage from weather, direct sun light
and construction traffic. Sub-floor to be flat since Vinyl Rolls to be
stored in vertical position. It shall be ensured that ambient
Page | 23
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
Page | 24
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
Take the exact measurements of the location and cut the skirting
at required length
Apply the recommended adhesive at wall, floor and at the back of
the skirting.
Start laying the Cove Cup Skirting to the wall and floor.
6.3.3.6 PROTECTION
Protection after carrying out vinyl flooring work shall be as per
manufacturer’s recommendations.
6.4.2 RESOURCES
6.4.2.1 Tools
Cutter / MITRE Saws &Drills
Angle Grinder
Festering Tools
Hand Tools
Ladder
6.4.2.2 Manpower
Skilled workers from a specialist subcontractor
Helpers
Page | 25
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
6.4.3.1 COORDINATION
Ensure coordinated reflected ceiling layouts are approved prior to
starting any work.
Examine soffits, areas and conditions under which false ceiling will
be applied with installer present for compliance with requirements.
Verify that all wall ceramic / gypsum board / bulkheads and MEP
works are completed.
Do not proceed with installation until unsatisfactory conditions
have been corrected.
Ensure proper coordination with MEP sub-contractors during
installation process for fixing of lighting diffuser etc.
6.4.3.2 PREPARATION
Ensure that all the necessary tools, equipment and material are
available.
Ensure that slab soffits are clean, dust free without any
protections of any of kind.
Make sure that the involved persons are aware of the technical
requirements concerning the use and application of all False
Ceiling materials.
Construct a suspended acoustical tile ceiling mock-up at the
location in the building designed by Client/Consultant. The mock-
up shall include lighting fixtures, mechanical grills, Diffusers etc.
etc.
Anchor Test: Test installed Anchor, selected at random by
(Client/Consultant) attached to the end of hanger or as per
specifications.
Ensure Mock-up is approved.
6.4.3.3 INSTALLATION
After receiving the area in clean condition, the subcontractor will
inspect and receive the area good for application. Mark the
desired level of false ceiling to the perimeter Walls/Bulkhead.
Page | 26
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
Page | 27
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
Page | 28
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
All work will be undertaken by qualified competent persons with experience of the
type of work described above, and in all cases in full accordance with safety
procedures specified in the companies’ health and safety Policy.
7.1 Scaffolds
Scaffolding is to be erected where it is required before any work is commenced,
so that good access is obtained to the whole of the working area and to allow
sufficient clearance for working. All workers working at height will have to wear
safety harnesses and lanyard.
Page | 29
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
Page | 30
Doc. Ref.: ARC-MST-P3-2021-01
METHOD STATEMENT Revision 00
Date 17 March 2021
Page | 31