Coronavirus: A Force Majeure Event Under Swiss Law?
Coronavirus: A Force Majeure Event Under Swiss Law?
Coronavirus: A Force Majeure Event Under Swiss Law?
LAW?
INTRODUCTION
Many states and corporations have taken drastic measures to contain the rapid
spread of the epidemic, and the corresponding confinement/quarantine measures
affect economic operators around the world. 2 In many instances, parties will
encounter difficulties whilst performing existing contracts: work force might be
unavailable, distribution networks disrupted, and orders cancelled. The question
is whether such epidemic and/or related government measures might in some
circumstances constitute a valid excuse for non-performance under the force
majeure doctrine. Contractual parties engaged in economic activities that may be
impacted by the recent coronavirus outbreak will have to assess whether their
contract specifically or implicitly addresses the issue of force majeure and
whether it covers coronavirus-related issues. Parties to such contracts should
carefully review governing law clauses, to ascertain under which law their
contractual obligations, including any force majeure clause, will be interpreted.
As many cross-border transactions and international contracts are governed by
1
http://country.eiu.com/article.aspx?articleid=1087995092
2
In Switzerland, see for e.g.: https://www.rts.ch/info/suisse/11127134-dizaines-d-evenements-
touches-par-l-interdiction-des-manifestations-de-plus-de-1000-personnes.html
Swiss substantive law, by agreement of the parties, Swiss law is of utmost
importance as regards these issues.
Here are our four key recommendations, under Swiss law, to tackling this
epidemic and its consequences efficiently (in addition to washing your hands
often!):
If epidemics are not explicitly listed in the force majeure clause, or otherwise
addressed in the contract, operators must analyse whether such epidemic cases
are covered by the general definition of force majeure events (which is to be
found in the force majeure clause) or under another category of circumstances
specifically mentioned. While the contract might not mention the epidemic,
emergency measures to address or contain an outbreak may be listed or covered
under general terms such as civil unrest, quarantines, lockouts, or governmental
injunctions.
Under Swiss law, the debtor can be excused from liability for non-performance
if it can prove an absence of fault on its part. Such absence of fault is constituted
where the performance of the debtor’s contractual obligation becomes
“objectively” impossible by circumstances not attributable to the obligor.
In a nutshell, under Swiss law, an epidemic like the coronavirus-related one,
despite its possibly higher mortality rate, may not necessarily amount to an
objective impossibility. An objective impossibility requires that an entire
segment of the economy or all operators in a given category be affected. That
being said, should such an epidemic lead to state authorities issuing bans or
prohibitions with a direct impact on an operator (or a defined category of
2
operators) to perform a contract, then a much closer analysis should be
undertaken as to whether there would be an objective impossibility to perform.
The consequences of a force majeure event will depend on what has been
negotiated. Under Swiss law, in case of force majeure and unless otherwise stated
in the contract, both parties would be immediately released from their respective
obligations. In long-term international contracts, however, force majeure usually
has a suspensive effect, at least initially. Indeed, many force majeure clauses
stipulate that the right to terminate may only be exercised if performance remains
impossible at the end of a fixed time limit. Such force majeure clauses generally
suspend performance of both parties’ obligations. A drastic remedy for drastic
situations.