Problem:
A project consists of 12 activities and their time estimates are shown below:
Requirements:
1|Page
Solution:
a. Network Diagram
Here, Optimistic time, a = to
Pessimistic time, b = tp
Most likely time, m = tm
Expected time, te = [(a+4m+b)/6] = [(to+4tm+tp)/6]
2|Page
3|Page
b. Critical Path
4|Page
c. Calculating Event Slack
Time Duration
V
Activity
to tp
1-2 4 10 1 1
2-4 6 20 2.3 5.4
4-5 2 5 0.5 0.25
5-6 1 6 0.83 0.69
6-7 1 6 0.83 0.69
Total 8.03
Standard deviation
5|Page
e. Calculating the probability of completing the project in 30 weeks
Here,