Activity Productivity Rate

The document provides details on activities, estimated durations, productivities, and resources for various phases of a construction project. It includes information on earthworks like excavation, disposal, filling, compaction and formation to receive fill material. The activities are broken down into multiple stages with details on equipment and labor units required to complete each task.

Uploaded by

Ahamed Ziyath
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
292 views21 pages

Activity Productivity Rate

The document provides details on activities, estimated durations, productivities, and resources for various phases of a construction project. It includes information on earthworks like excavation, disposal, filling, compaction and formation to receive fill material. The activities are broken down into multiple stages with details on equipment and labor units required to complete each task.

Uploaded by

Ahamed Ziyath
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 21

07-Mar-21 13:11

Activity ID Activity Name Estimated Productivity Budgeted Units Resource Name


Duration

Site Clearance 281 ---

Earthworks 166 ---


SA032.01. (1-6).CON.06.P1.S1 Phase 01: Stage 1 Carriage Way (Ch.1+000 to 1+550) 36 ---
WO.06.1630 Excavation | Disposal 21 3.05/d 64.00 Unskilled Labor
WO.06.1630 Excavation | Disposal 21 2.00/d 42.00 Shovel 966
WO.06.1630 Excavation | Disposal 21 6.10/d 128.00 Tipper 6 Wheel Truck
WO.06.1630 Excavation | Disposal 21 6.10/d 128.00 Excavator: Hammer
WO.06.1630 Excavation | Disposal 21 1.52/d 32.00 Excavator: Bucket
WO.06.1630 Excavation | Disposal 21 1.57/d 33.00 Charge Hand
WO.06.1630 Excavation | Disposal 21 485.71/d 10200.00 Excavated Un-Suitable Material
WO.06.1630 Excavation | Disposal 21 485.71/d 10200.00 Disposed Unsuitable Materials
WO.06.1810 Filling | Compaction 21 1.52/d 32.00 Water Tanker
WO.06.1810 Filling | Compaction 21 1.71/d 36.00 Unskilled Labor
WO.06.1810 Filling | Compaction 21 1.52/d 32.00 Bobcat
WO.06.1810 Filling | Compaction 21 0.30/d 6.25 JCB
WO.06.1810 Filling | Compaction 21 1.59/d 33.41 Roller Compactor: 2Ton
WO.06.1810 Filling | Compaction 21 0.14/d 3.00 Charge Hand
WO.06.1810 Filling | Compaction 21 14.79/d 310.69 Imported Fill
WO.06.1790 Formation to Receive Fill Material 21 1.52/d 32.00 Water Tanker
WO.06.1790 Formation to Receive Fill Material 21 3.05/d 64.00 Roller Compactor: 10Ton
WO.06.1790 Formation to Receive Fill Material 21 1.52/d 32.00 Grader
WO.06.1790 Formation to Receive Fill Material 21 1.59/d 33.41 Roller Compactor: 2Ton
WO.06.1790 Formation to Receive Fill Material 21 3.05/d 64.00 Unskilled Labor
WO.06.1790 Formation to Receive Fill Material 21 1.52/d 32.00 JCB
WO.06.1790 Formation to Receive Fill Material 21 1.52/d 32.00 Bobcat
WO.06.1790 Formation to Receive Fill Material 21 0.64/d 13.50 Charge Hand
WO.06.1790 Formation to Receive Fill Material 21 664.87/d 13962.31 Formated Excavated Area
WO.06.1790 Formation to Receive Fill Material 21 20.20/d 424.25 Formated Existing Ground
SA032.01. (1-6).CON.06.P1.S2 Phase 01: Stage 2 Carriage Way (Ch.1+550 to 1+908)38 ---
WO.06.3140 Excavation | Disposal 21 2.00/d 42.00 Unskilled Labor
WO.06.3140 Excavation | Disposal 21 2.00/d 42.00 Shovel 966
WO.06.3140 Excavation | Disposal 21 4.00/d 84.00 Tipper 6 Wheel Truck
WO.06.3140 Excavation | Disposal 21 9.00/d 189.00 Excavator: Hammer
WO.06.3140 Excavation | Disposal 21 3.00/d 63.00 Excavator: Bucket
WO.06.3140 Excavation | Disposal 21 0.50/d 10.50 Charge Hand
WO.06.3140 Excavation | Disposal 21 707.62/d 14860.00 Excavated Un-Suitable Material
WO.06.3140 Excavation | Disposal 21 707.62/d 14860.00 Disposed Unsuitable Materials
WO.06.3400 Filling | Compaction 19 1.00/d 19.00 Water Tanker
WO.06.3400 Filling | Compaction 19 2.00/d 38.00 Unskilled Labor
WO.06.3400 Filling | Compaction 19 1.00/d 19.00 Bobcat
WO.06.3400 Filling | Compaction 19 0.99/d 18.75 JCB
WO.06.3400 Filling | Compaction 19 1.04/d 19.84 Roller Compactor: 2Ton
WO.06.3400 Filling | Compaction 19 1.00/d 19.00 Charge Hand
WO.06.3400 Filling | Compaction 19 23.86/d 453.33 Imported Fill
WO.06.3390 Formation to Receive Fill Material 21 1.00/d 21.00 Water Tanker
WO.06.3390 Formation to Receive Fill Material 21 2.00/d 42.00 Roller Compactor: 10Ton
WO.06.3390 Formation to Receive Fill Material 21 1.00/d 21.00 Grader
WO.06.3390 Formation to Receive Fill Material 21 1.04/d 21.92 Roller Compactor: 2Ton
WO.06.3390 Formation to Receive Fill Material 21 2.00/d 42.00 Unskilled Labor
WO.06.3390 Formation to Receive Fill Material 21 1.00/d 21.00 JCB
WO.06.3390 Formation to Receive Fill Material 21 1.00/d 21.00 Bobcat
WO.06.3390 Formation to Receive Fill Material 21 1.00/d 21.00 Charge Hand
WO.06.3390 Formation to Receive Fill Material 21 970.12/d 20372.59 Formated Excavated Area
WO.06.3390 Formation to Receive Fill Material 21 29.48/d 619.02 Formated Existing Ground
SA032.01. (1-6).CON.06.P1.S3N Phase 01: Stage 3 (Ch.1+000 to 1+908) 31 ---
WO.06.7360 Excavation | Disposal 18 2.00/d 36.00 Unskilled Labor
WO.06.7360 Excavation | Disposal 18 1.00/d 18.00 Shovel 966
WO.06.7360 Excavation | Disposal 18 4.00/d 72.00 Tipper 6 Wheel Truck
WO.06.7360 Excavation | Disposal 18 6.00/d 108.00 Excavator: Hammer
WO.06.7360 Excavation | Disposal 18 2.00/d 36.00 Excavator: Bucket
WO.06.7360 Excavation | Disposal 18 0.58/d 10.50 Charge Hand
WO.06.7360 Excavation | Disposal 18 449.72/d 8095.00 Excavated Suitable Material
WO.06.7360 Excavation | Disposal 18 449.72/d 8095.00 Disposed Unsuitable Materials
WO.06.7350 Filling | Compaction 18 1.00/d 18.00 Water Tanker
WO.06.7350 Filling | Compaction 18 2.00/d 36.00 Unskilled Labor
WO.06.7350 Filling | Compaction 18 1.00/d 18.00 Bobcat
WO.06.7350 Filling | Compaction 18 1.00/d 18.00 JCB
WO.06.7350 Filling | Compaction 18 1.04/d 18.79 Roller Compactor: 2Ton
WO.06.7350 Filling | Compaction 18 1.06/d 19.00 Charge Hand

© Oracle Corporation Page 1 of 21


07-Mar-21 13:11
Activity ID Activity Name Estimated Productivity Budgeted Units Resource Name
Duration

WO.06.7350 Filling | Compaction 18 13.68/d 246.25 Imported Fill


WO.06.7370 Formation to Receive Fill Material 18 1.00/d 18.00 Water Tanker
WO.06.7370 Formation to Receive Fill Material 18 2.00/d 36.00 Roller Compactor: 10Ton
WO.06.7370 Formation to Receive Fill Material 18 1.00/d 18.00 Grader
WO.06.7370 Formation to Receive Fill Material 18 1.04/d 18.79 Roller Compactor: 2Ton
WO.06.7370 Formation to Receive Fill Material 18 2.00/d 36.00 Unskilled Labor
WO.06.7370 Formation to Receive Fill Material 18 1.00/d 18.00 JCB
WO.06.7370 Formation to Receive Fill Material 18 1.00/d 18.00 Bobcat
WO.06.7370 Formation to Receive Fill Material 18 1.17/d 21.00 Charge Hand
WO.06.7370 Formation to Receive Fill Material 18 614.82/d 11066.68 Formated Excavated Area
WO.06.7370 Formation to Receive Fill Material 18 18.68/d 336.26 Formated Existing Ground
SA032.01. (1-6).CON.06.P2.S1 Phase 02: Stage 1 Garrage Way (Ch.0+100 to 0+500) 49 ---
WO.06.7490 Excavation | Disposal 32 2.00/d 64.00 Unskilled Labor
WO.06.7490 Excavation | Disposal 32 1.00/d 32.00 Shovel 966
WO.06.7490 Excavation | Disposal 32 4.00/d 128.00 Tipper 6 Wheel Truck
WO.06.7490 Excavation | Disposal 32 4.00/d 128.00 Excavator: Hammer
WO.06.7490 Excavation | Disposal 32 1.00/d 32.00 Excavator: Bucket
WO.06.7490 Excavation | Disposal 32 1.03/d 33.00 Charge Hand
WO.06.7490 Excavation | Disposal 32 240.31/d 7690.00 Excavated Suitable Material
WO.06.7490 Excavation | Disposal 32 240.31/d 7690.00 Disposed Unsuitable Materials
WO.06.7480 Filling | Compaction 32 1.00/d 32.00 Water Tanker
WO.06.7480 Filling | Compaction 32 2.00/d 64.00 Unskilled Labor
WO.06.7480 Filling | Compaction 32 1.00/d 32.00 Bobcat
WO.06.7480 Filling | Compaction 32 0.20/d 6.25 JCB
WO.06.7480 Filling | Compaction 32 1.04/d 33.41 Roller Compactor: 2Ton
WO.06.7480 Filling | Compaction 32 0.09/d 3.00 Charge Hand
WO.06.7480 Filling | Compaction 32 7.31/d 233.86 Imported Fill
WO.06.7500 Formation to Receive Fill Material 32 1.00/d 32.00 Water Tanker
WO.06.7500 Formation to Receive Fill Material 32 2.00/d 64.00 Roller Compactor: 10Ton
WO.06.7500 Formation to Receive Fill Material 32 1.00/d 32.00 Grader
WO.06.7500 Formation to Receive Fill Material 32 1.04/d 33.41 Roller Compactor: 2Ton
WO.06.7500 Formation to Receive Fill Material 32 2.00/d 64.00 Unskilled Labor
WO.06.7500 Formation to Receive Fill Material 32 1.00/d 32.00 JCB
WO.06.7500 Formation to Receive Fill Material 32 1.00/d 32.00 Bobcat
WO.06.7500 Formation to Receive Fill Material 32 0.42/d 13.50 Charge Hand
WO.06.7500 Formation to Receive Fill Material 32 328.42/d 10509.56 Formated Excavated Area
WO.06.7500 Formation to Receive Fill Material 32 9.98/d 319.33 Formated Existing Ground
SA032.01. (1-6).CON.06.P2.S2 Phase 02: Stage 2 Garrage Way (Ch.0+500 to 1+000) 48 ---
WO.06.8050 Excavation | Disposal 32 1.31/d 42.00 Unskilled Labor
WO.06.8050 Excavation | Disposal 32 1.31/d 42.00 Shovel 966
WO.06.8050 Excavation | Disposal 32 2.63/d 84.00 Tipper 6 Wheel Truck
WO.06.8050 Excavation | Disposal 32 9.00/d 288.00 Excavator: Hammer
WO.06.8050 Excavation | Disposal 32 3.00/d 96.00 Excavator: Bucket
WO.06.8050 Excavation | Disposal 32 0.33/d 10.50 Charge Hand
WO.06.8050 Excavation | Disposal 32 622.97/d 19935.00 Excavated Suitable Material
WO.06.8050 Excavation | Disposal 32 622.97/d 19935.00 Disposed Unsuitable Materials
WO.06.8040 Filling | Compaction 32 0.59/d 19.00 Water Tanker
WO.06.8040 Filling | Compaction 32 1.19/d 38.00 Unskilled Labor
WO.06.8040 Filling | Compaction 32 0.59/d 19.00 Bobcat
WO.06.8040 Filling | Compaction 32 0.59/d 18.75 JCB
WO.06.8040 Filling | Compaction 32 0.62/d 19.84 Roller Compactor: 2Ton
WO.06.8040 Filling | Compaction 32 0.59/d 19.00 Charge Hand
WO.06.8040 Filling | Compaction 32 17.68/d 565.82 Imported Fill
WO.06.8060 Formation to Receive Fill Material 32 0.66/d 21.00 Water Tanker
WO.06.8060 Formation to Receive Fill Material 32 1.31/d 42.00 Roller Compactor: 10Ton
WO.06.8060 Formation to Receive Fill Material 32 0.66/d 21.00 Grader
WO.06.8060 Formation to Receive Fill Material 32 0.69/d 21.92 Roller Compactor: 2Ton
WO.06.8060 Formation to Receive Fill Material 32 1.31/d 42.00 Unskilled Labor
WO.06.8060 Formation to Receive Fill Material 32 0.66/d 21.00 JCB
WO.06.8060 Formation to Receive Fill Material 32 0.66/d 21.00 Bobcat
WO.06.8060 Formation to Receive Fill Material 32 0.66/d 21.00 Charge Hand
WO.06.8060 Formation to Receive Fill Material 32 794.62/d 25427.91 Formated Excavated Area
WO.06.8060 Formation to Receive Fill Material 32 24.14/d 772.63 Formated Existing Ground
SA032.01. (1-6).CON.06.P2.S3 Phase 02: Stage 3 (Ch.0+100 to 1+500) 31 ---
WO.06.8850 Excavation | Disposal 18 2.00/d 36.00 Unskilled Labor
WO.06.8850 Excavation | Disposal 18 1.00/d 18.00 Shovel 966
WO.06.8850 Excavation | Disposal 18 4.00/d 72.00 Tipper 6 Wheel Truck
WO.06.8850 Excavation | Disposal 18 4.00/d 72.00 Excavator: Hammer
WO.06.8850 Excavation | Disposal 18 1.00/d 18.00 Excavator: Bucket

© Oracle Corporation Page 2 of 21


07-Mar-21 13:11
Activity ID Activity Name Estimated Productivity Budgeted Units Resource Name
Duration

WO.06.8850 Excavation | Disposal 18 0.58/d 10.50 Charge Hand


WO.06.8850 Excavation | Disposal 18 261.28/d 4703.00 Excavated Suitable Material
WO.06.8850 Excavation | Disposal 18 261.28/d 4703.00 Disposed Unsuitable Materials
WO.06.8840 Filling | Compaction 18 1.00/d 18.00 Water Tanker
WO.06.8840 Filling | Compaction 18 2.00/d 36.00 Unskilled Labor
WO.06.8840 Filling | Compaction 18 1.00/d 18.00 Bobcat
WO.06.8840 Filling | Compaction 18 1.00/d 18.00 JCB
WO.06.8840 Filling | Compaction 18 1.04/d 18.79 Roller Compactor: 2Ton
WO.06.8840 Filling | Compaction 18 1.06/d 19.00 Charge Hand
WO.06.8840 Filling | Compaction 18 7.67/d 138.05 Imported Fill
WO.06.8860 Formation to Receive Fill Material 18 1.00/d 18.00 Water Tanker
WO.06.8860 Formation to Receive Fill Material 18 2.00/d 36.00 Roller Compactor: 10Ton
WO.06.8860 Formation to Receive Fill Material 18 1.00/d 18.00 Grader
WO.06.8860 Formation to Receive Fill Material 18 1.04/d 18.79 Roller Compactor: 2Ton
WO.06.8860 Formation to Receive Fill Material 18 2.00/d 36.00 Unskilled Labor
WO.06.8860 Formation to Receive Fill Material 18 1.00/d 18.00 JCB
WO.06.8860 Formation to Receive Fill Material 18 1.00/d 18.00 Bobcat
WO.06.8860 Formation to Receive Fill Material 18 1.17/d 21.00 Charge Hand
WO.06.8860 Formation to Receive Fill Material 18 10.47/d 188.51 Formated Excavated Area
WO.06.8860 Formation to Receive Fill Material 18 11.11/d 200.00 Formated Existing Ground

Unbound Pavment Material 142 ---


SA032.01. (1-6).CON.06.P1.S1 Phase 01: Stage 1 Carriage Way (Ch.1+000 to 1+550) 21 ---
WO.06.2300 Aggregate Road Base Formation 18 3.56/d 64.00 Unskilled Labor
WO.06.2300 Aggregate Road Base Formation 18 810.74/d 14593.27 Aggregate Road Base: 150mm
WO.06.2300 Aggregate Road Base Formation 18 3.71/d 66.82 Roller Compactor: 2Ton
WO.06.2300 Aggregate Road Base Formation 18 1.78/d 32.00 Bobcat
WO.06.2300 Aggregate Road Base Formation 18 1.78/d 32.00 Water Tanker
WO.06.2300 Aggregate Road Base Formation 18 3.56/d 64.00 Roller Compactor: 10Ton
WO.06.2300 Aggregate Road Base Formation 18 1.78/d 32.00 Grader
WO.06.2300 Aggregate Road Base Formation 18 1.74/d 31.25 JCB
WO.06.2300 Aggregate Road Base Formation 18 0.50/d 9.00 Charge Hand
WO.06.2300 Aggregate Road Base Formation 18 864.58/d 15562.47 Granular Sub - Base: 150mm
SA032.01. (1-6).CON.06.P1.S2 Phase 01: Stage 2 Carriage Way (Ch.1+550 to 1+908)21 ---
WO.06.4350 Aggregate Road Base Formation 18 2.00/d 36.00 Unskilled Labor
WO.06.4350 Aggregate Road Base Formation 18 2.09/d 37.58 Roller Compactor: 2Ton
WO.06.4350 Aggregate Road Base Formation 18 1.00/d 18.00 Bobcat
WO.06.4350 Aggregate Road Base Formation 18 1.00/d 18.00 Water Tanker
WO.06.4350 Aggregate Road Base Formation 18 2.00/d 36.00 Roller Compactor: 10Ton
WO.06.4350 Aggregate Road Base Formation 18 1.00/d 18.00 Grader
WO.06.4350 Aggregate Road Base Formation 18 0.63/d 11.25 JCB
WO.06.4350 Aggregate Road Base Formation 18 0.61/d 11.00 Charge Hand
WO.06.4350 Aggregate Road Base Formation 18 1182.96/d 21293.23 Aggregate Road Base: 150mm
WO.06.4350 Aggregate Road Base Formation 18 1261.52/d 22707.41 Granular Sub - Base: 150mm
SA032.01. (1-6).CON.06.P1.S3N Phase 01: Stage 3 (Ch.1+000 to 1+908) 14 ---
WO.06.4040 Aggregate Road Base Formation 12 2.09/d 25.06 Roller Compactor: 2Ton
WO.06.4040 Aggregate Road Base Formation 12 1.00/d 12.00 Bobcat
WO.06.4040 Aggregate Road Base Formation 12 8.00/d 96.00 Tipper 6 Wheel Truck
WO.06.4040 Aggregate Road Base Formation 12 2.00/d 24.00 PTR Roller
WO.06.4040 Aggregate Road Base Formation 12 2.00/d 24.00 Roller Compactor: 10Ton
WO.06.4040 Aggregate Road Base Formation 12 3495.83/d 41949.98 Asphaltic Wearing Course: 60/70 50mm
WO.06.4040 Aggregate Road Base Formation 12 2.00/d 24.00 Unskilled Labor
WO.06.4040 Aggregate Road Base Formation 12 1.00/d 12.00 Paver
WO.06.4040 Aggregate Road Base Formation 12 0.50/d 6.00 Charge Hand
WO.06.4040 Aggregate Road Base Formation 12 6313.18/d 75758.20 Bituminous Spray Tack Coat
SA032.01. (1-6).CON.06.P2.S1 Phase 02: Stage 1 Garrage Way (Ch.0+100 to 0+500) 21 ---
WO.06.7550 Aggregate Road Base Formation 18 3.56/d 64.00 Unskilled Labor
WO.06.7550 Aggregate Road Base Formation 18 610.25/d 10984.49 Aggregate Road Base: 150mm
WO.06.7550 Aggregate Road Base Formation 18 3.71/d 66.82 Roller Compactor: 2Ton
WO.06.7550 Aggregate Road Base Formation 18 1.78/d 32.00 Bobcat
WO.06.7550 Aggregate Road Base Formation 18 1.78/d 32.00 Water Tanker
WO.06.7550 Aggregate Road Base Formation 18 3.56/d 64.00 Roller Compactor: 10Ton
WO.06.7550 Aggregate Road Base Formation 18 1.78/d 32.00 Grader
WO.06.7550 Aggregate Road Base Formation 18 1.74/d 31.25 JCB
WO.06.7550 Aggregate Road Base Formation 18 0.50/d 9.00 Charge Hand
WO.06.7550 Aggregate Road Base Formation 18 650.78/d 11714.02 Granular Sub - Base: 150mm
SA032.01. (1-6).CON.06.P2.S2 Phase 02: Stage 2 Garrage Way (Ch.0+500 to 1+000) 21 ---
WO.06.8110 Aggregate Road Base Formation 18 2.00/d 36.00 Unskilled Labor
WO.06.8110 Aggregate Road Base Formation 18 2.09/d 37.58 Roller Compactor: 2Ton
WO.06.8110 Aggregate Road Base Formation 18 1.00/d 18.00 Bobcat

© Oracle Corporation Page 3 of 21


07-Mar-21 13:11
Activity ID Activity Name Estimated Productivity Budgeted Units Resource Name
Duration

WO.06.8110 Aggregate Road Base Formation 18 1.00/d 18.00 Water Tanker


WO.06.8110 Aggregate Road Base Formation 18 2.00/d 36.00 Roller Compactor: 10Ton
WO.06.8110 Aggregate Road Base Formation 18 1.00/d 18.00 Grader
WO.06.8110 Aggregate Road Base Formation 18 0.63/d 11.25 JCB
WO.06.8110 Aggregate Road Base Formation 18 0.61/d 11.00 Charge Hand
WO.06.8110 Aggregate Road Base Formation 18 1476.50/d 26577.00 Aggregate Road Base: 150mm
WO.06.8110 Aggregate Road Base Formation 18 1574.56/d 28342.10 Granular Sub - Base: 150mm
SA032.01. (1-6).CON.06.P2.S3 Phase 02: Stage 3 (Ch.0+100 to 1+500) 14 ---
WO.06.7560 Aggregate Road Base Formation 12 2.09/d 25.06 Roller Compactor: 2Ton
WO.06.7560 Aggregate Road Base Formation 12 1.00/d 12.00 Bobcat
WO.06.7560 Aggregate Road Base Formation 12 8.00/d 96.00 Tipper 6 Wheel Truck
WO.06.7560 Aggregate Road Base Formation 12 2.00/d 24.00 PTR Roller
WO.06.7560 Aggregate Road Base Formation 12 2.00/d 24.00 Roller Compactor: 10Ton
WO.06.7560 Aggregate Road Base Formation 12 1959.75/d 23517.02 Asphaltic Wearing Course: 60/70 50mm
WO.06.7560 Aggregate Road Base Formation 12 2.00/d 24.00 Unskilled Labor
WO.06.7560 Aggregate Road Base Formation 12 1.00/d 12.00 Paver
WO.06.7560 Aggregate Road Base Formation 12 0.50/d 6.00 Charge Hand
WO.06.7560 Aggregate Road Base Formation 12 3539.15/d 42469.80 Bituminous Spray Tack Coat

Asphalt Works 342 ---


SA032.01. (1-6).CON.06.P1.S1 Phase 01: Stage 1 Carriage Way (Ch.1+000 to 1+550)211 ---
WO.06.9040 Milling of Exixting Asphalt 6 3.33/d 20.00 Unskilled Labor
WO.06.9040 Milling of Exixting Asphalt 6 1.67/d 10.00 Charge Hand
WO.06.9040 Milling of Exixting Asphalt 6 1.67/d 10.00 Tipper 6 Wheel Truck
WO.06.9040 Milling of Exixting Asphalt 6 0.83/d 5.00 Bobcat
WO.06.9040 Milling of Exixting Asphalt 6 304.50/d 1827.00 Milled Bitmac
WO.06.9040 Milling of Exixting Asphalt 6 0.83/d 5.00 Milling Machine
WO.06.2600 Prime Coat | Base Course 18 10.67/d 192.00 Unskilled Labor
WO.06.2600 Prime Coat | Base Course 18 1.78/d 32.00 Paver
WO.06.2600 Prime Coat | Base Course 18 14.22/d 256.00 Tipper 6 Wheel Truck
WO.06.2600 Prime Coat | Base Course 18 3.71/d 66.82 Roller Compactor: 2Ton
WO.06.2600 Prime Coat | Base Course 18 1.78/d 32.00 Bobcat
WO.06.2600 Prime Coat | Base Course 18 3.56/d 64.00 PTR Roller
WO.06.2600 Prime Coat | Base Course 18 3.56/d 64.00 Roller Compactor: 10Ton
WO.06.2600 Prime Coat | Base Course 18 580.08/d 10441.39 Asphaltic Base Course: Class A 100mm
WO.06.2600 Prime Coat | Base Course 18 0.50/d 9.00 Charge Hand
WO.06.2600 Prime Coat | Base Course 18 580.06/d 10441.00 Bituminous Spray Prime Coat
WO.06.2600 Prime Coat | Base Course 18 467.50/d 8415.06 Asphaltic Base Course: Class A 80mm
238
SA032.01. (1-6).CON.06.P1.S2 Phase 01: Stage 2 Carriage Way (Ch.1+550 to 1+908) ---
WO.06.9050 Milling of Exixting Asphalt 5 4.00/d 20.00 Unskilled Labor
WO.06.9050 Milling of Exixting Asphalt 5 2.00/d 10.00 Charge Hand
WO.06.9050 Milling of Exixting Asphalt 5 2.00/d 10.00 Tipper 6 Wheel Truck
WO.06.9050 Milling of Exixting Asphalt 5 1.00/d 5.00 Bobcat
WO.06.9050 Milling of Exixting Asphalt 5 533.16/d 2665.80 Milled Bitmac
WO.06.9050 Milling of Exixting Asphalt 5 1.00/d 5.00 Milling Machine
WO.06.4400 Prime Coat | Base Course 18 6.00/d 108.00 Unskilled Labor
WO.06.4400 Prime Coat | Base Course 18 1.00/d 18.00 Paver
WO.06.4400 Prime Coat | Base Course 18 8.00/d 144.00 Tipper 6 Wheel Truck
WO.06.4400 Prime Coat | Base Course 18 2.09/d 37.58 Roller Compactor: 2Ton
WO.06.4400 Prime Coat | Base Course 18 1.00/d 18.00 Bobcat
WO.06.4400 Prime Coat | Base Course 18 2.00/d 36.00 PTR Roller
WO.06.4400 Prime Coat | Base Course 18 2.00/d 36.00 Roller Compactor: 10Ton
WO.06.4400 Prime Coat | Base Course 18 846.40/d 15235.17 Asphaltic Base Course: Class A 100mm
WO.06.4400 Prime Coat | Base Course 18 0.11/d 2.00 Charge Hand
WO.06.4400 Prime Coat | Base Course 18 846.39/d 15235.00 Bituminous Spray Prime Coat
WO.06.4400 Prime Coat | Base Course 18 682.14/d 12278.52 Asphaltic Base Course: Class A 80mm
SA032.01. (1-6).CON.06.P1.S3N Phase 01: Stage 3 (Ch.1+000 to 1+908) 27 ---
WO.06.8880 Prime Coat | Base Course 12 2.00/d 24.00 Roller Compactor: 2Ton
WO.06.8880 Prime Coat | Base Course 12 1.00/d 12.00 Bobcat
WO.06.8880 Prime Coat | Base Course 12 8.00/d 96.00 Tipper 6 Wheel Truck
WO.06.8880 Prime Coat | Base Course 12 2.00/d 24.00 PTR Roller
WO.06.8880 Prime Coat | Base Course 12 2.00/d 24.00 Roller Compactor: 10Ton
WO.06.8880 Prime Coat | Base Course 12 689.66/d 8275.96 Asphaltic Base Course: Class A 100mm
WO.06.8880 Prime Coat | Base Course 12 6.00/d 72.00 Unskilled Labor
WO.06.8880 Prime Coat | Base Course 12 1.00/d 12.00 Paver
WO.06.8880 Prime Coat | Base Course 12 0.21/d 2.50 Charge Hand
WO.06.8880 Prime Coat | Base Course 12 1245.58/d 14947.00 Bituminous Spray Tack Coat
WO.06.8880 Prime Coat | Base Course 12 555.82/d 6669.87 Asphaltic Base Course: Class A 80mm
WO.06.4550 Tack Coat | Wearing Course 12 2.09/d 25.06 Roller Compactor: 2Ton
WO.06.4550 Tack Coat | Wearing Course 12 1.00/d 12.00 Bobcat

© Oracle Corporation Page 4 of 21


07-Mar-21 13:11
Activity ID Activity Name Estimated Productivity Budgeted Units Resource Name
Duration

WO.06.4550 Tack Coat | Wearing Course 12 8.00/d 96.00 Tipper 6 Wheel Truck
WO.06.4550 Tack Coat | Wearing Course 12 2.00/d 24.00 PTR Roller
WO.06.4550 Tack Coat | Wearing Course 12 2.00/d 24.00 Roller Compactor: 10Ton
WO.06.4550 Tack Coat | Wearing Course 12 3495.83/d 41949.98 Asphalt Wearing Course
WO.06.4550 Tack Coat | Wearing Course 12 6.00/d 72.00 Unskilled Labor
WO.06.4550 Tack Coat | Wearing Course 12 1.00/d 12.00 Paver
WO.06.4550 Tack Coat | Wearing Course 12 0.21/d 2.50 Charge Hand
WO.06.4550 Tack Coat | Wearing Course 12 6313.18/d 75758.20 Bituminous Spray Tack Coat
SA032.01. (1-6).CON.06.P2.S1 Phase 02: Stage 1 Garrage Way (Ch.0+100 to 0+500)187 ---
WO.06.9060 Milling of Exixting Asphalt 10 4.00/d 40.00 Unskilled Labor
WO.06.9060 Milling of Exixting Asphalt 10 1.00/d 10.00 Charge Hand
WO.06.9060 Milling of Exixting Asphalt 10 2.00/d 20.00 Tipper 6 Wheel Truck
WO.06.9060 Milling of Exixting Asphalt 10 1.00/d 10.00 Bobcat
WO.06.9060 Milling of Exixting Asphalt 10 137.52/d 1375.20 Milled Bitmac
WO.06.9060 Milling of Exixting Asphalt 10 1.00/d 10.00 Milling Machine
WO.06.7570 Prime Coat | Base Course 18 10.67/d 192.00 Unskilled Labor
WO.06.7570 Prime Coat | Base Course 18 1.78/d 32.00 Paver
WO.06.7570 Prime Coat | Base Course 18 14.22/d 256.00 Tipper 6 Wheel Truck
WO.06.7570 Prime Coat | Base Course 18 3.71/d 66.82 Roller Compactor: 2Ton
WO.06.7570 Prime Coat | Base Course 18 1.78/d 32.00 Bobcat
WO.06.7570 Prime Coat | Base Course 18 3.56/d 64.00 PTR Roller
WO.06.7570 Prime Coat | Base Course 18 3.56/d 64.00 Roller Compactor: 10Ton
WO.06.7570 Prime Coat | Base Course 18 436.63/d 7859.33 Asphaltic Base Course: Class A 100mm
WO.06.7570 Prime Coat | Base Course 18 0.50/d 9.00 Charge Hand
WO.06.7570 Prime Coat | Base Course 18 436.61/d 7859.00 Bituminous Spray Prime Coat
WO.06.7570 Prime Coat | Base Course 18 351.89/d 6334.09 Asphaltic Base Course: Class A 80mm
SA032.01. (1-6).CON.06.P2.S2 Phase 02: Stage 2 Garrage Way (Ch.0+500 to 1+000)214 ---
WO.06.9070 Milling of Exixting Asphalt 10 4.00/d 40.00 Unskilled Labor
WO.06.9070 Milling of Exixting Asphalt 10 1.00/d 10.00 Charge Hand
WO.06.9070 Milling of Exixting Asphalt 10 2.00/d 20.00 Tipper 6 Wheel Truck
WO.06.9070 Milling of Exixting Asphalt 10 1.00/d 10.00 Bobcat
WO.06.9070 Milling of Exixting Asphalt 10 332.70/d 3327.00 Milled Bitmac
WO.06.9070 Milling of Exixting Asphalt 10 1.00/d 10.00 Milling Machine
WO.06.8130 Prime Coat | Base Course 18 6.00/d 108.00 Unskilled Labor
WO.06.8130 Prime Coat | Base Course 18 1.00/d 18.00 Paver
WO.06.8130 Prime Coat | Base Course 18 8.00/d 144.00 Tipper 6 Wheel Truck
WO.06.8130 Prime Coat | Base Course 18 2.09/d 37.58 Roller Compactor: 2Ton
WO.06.8130 Prime Coat | Base Course 18 1.00/d 18.00 Bobcat
WO.06.8130 Prime Coat | Base Course 18 2.00/d 36.00 PTR Roller
WO.06.8130 Prime Coat | Base Course 18 2.00/d 36.00 Roller Compactor: 10Ton
WO.06.8130 Prime Coat | Base Course 18 1056.43/d 19015.67 Asphaltic Base Course: Class A 100mm
WO.06.8130 Prime Coat | Base Course 18 0.11/d 2.00 Charge Hand
WO.06.8130 Prime Coat | Base Course 18 1056.44/d 19016.00 Bituminous Spray Prime Coat
WO.06.8130 Prime Coat | Base Course 18 851.41/d 15325.35 Asphaltic Base Course: Class A 80mm
SA032.01. (1-6).CON.06.P2.S3 Phase 02: Stage 3 (Ch.0+100 to 1+500) 30 ---
WO.06.8890 Prime Coat | Base Course 12 2.00/d 24.00 Roller Compactor: 2Ton
WO.06.8890 Prime Coat | Base Course 12 1.00/d 12.00 Bobcat
WO.06.8890 Prime Coat | Base Course 12 8.00/d 96.00 Tipper 6 Wheel Truck
WO.06.8890 Prime Coat | Base Course 12 2.00/d 24.00 PTR Roller
WO.06.8890 Prime Coat | Base Course 12 2.00/d 24.00 Roller Compactor: 10Ton
WO.06.8890 Prime Coat | Base Course 12 386.62/d 4639.47 Asphaltic Base Course: Class A 100mm
WO.06.8890 Prime Coat | Base Course 12 6.00/d 72.00 Unskilled Labor
WO.06.8890 Prime Coat | Base Course 12 1.00/d 12.00 Paver
WO.06.8890 Prime Coat | Base Course 12 0.21/d 2.50 Charge Hand
WO.06.8890 Prime Coat | Base Course 12 386.58/d 4639.00 Bituminous Spray Prime Coat
WO.06.8890 Prime Coat | Base Course 12 311.59/d 3739.10 Asphaltic Base Course: Class A 80mm
WO.06.8120 Tack Coat | Wearing Course 12 2.09/d 25.06 Roller Compactor: 2Ton
WO.06.8120 Tack Coat | Wearing Course 12 1.00/d 12.00 Bobcat
WO.06.8120 Tack Coat | Wearing Course 12 8.00/d 96.00 Tipper 6 Wheel Truck
WO.06.8120 Tack Coat | Wearing Course 12 2.00/d 24.00 PTR Roller
WO.06.8120 Tack Coat | Wearing Course 12 2.00/d 24.00 Roller Compactor: 10Ton
WO.06.8120 Tack Coat | Wearing Course 12 1959.75/d 23517.02 Asphalt Wearing Course
WO.06.8120 Tack Coat | Wearing Course 12 6.00/d 72.00 Unskilled Labor
WO.06.8120 Tack Coat | Wearing Course 12 1.00/d 12.00 Paver
WO.06.8120 Tack Coat | Wearing Course 12 0.21/d 2.50 Charge Hand
WO.06.8120 Tack Coat | Wearing Course 12 3539.15/d 42469.80 Bituminous Spray Tack Coat

Kerbs | Footways | Paved Areas 199 ---


SA032.01. (1-6).CON.06.P1.S1 Phase 01: Stage 1 Carriage Way (Ch.1+000 to 1+550) 37 ---
WO.06.4210 Road Kerbs: Foundation | Kerbs Installation 32 85.94/d 2750.00 Kerb Stone: 250x125

© Oracle Corporation Page 5 of 21


07-Mar-21 13:11
Activity ID Activity Name Estimated Productivity Budgeted Units Resource Name
Duration

WO.06.4210 Road Kerbs: Foundation | Kerbs Installation 32 2.00/d 64.00 Unskilled Labor
WO.06.4210 Road Kerbs: Foundation | Kerbs Installation 32 2.09/d 66.82 Mason
WO.06.4210 Road Kerbs: Foundation | Kerbs Installation 32 2.00/d 64.00 Carpenter
WO.06.4210 Road Kerbs: Foundation | Kerbs Installation 32 0.56/d 18.00 Charge Hand
SA032.01. (1-6).CON.06.P1.S2 Phase 01: Stage 2 Carriage Way (Ch.1+550 to 1+908)52 ---
WO.06.4640 Road Kerbs: Foundation | Kerbs Installation 45 64.44/d 2900.00 Kerb Stone: 250x125
WO.06.4640 Road Kerbs: Foundation | Kerbs Installation 45 1.07/d 48.00 Unskilled Labor
WO.06.4640 Road Kerbs: Foundation | Kerbs Installation 45 1.11/d 50.11 Mason
WO.06.4640 Road Kerbs: Foundation | Kerbs Installation 45 1.07/d 48.00 Carpenter
WO.06.4640 Road Kerbs: Foundation | Kerbs Installation 45 0.27/d 12.00 Charge Hand
SA032.01. (1-6).CON.06.P1.S3N Phase 01: Stage 3 (Ch.1+000 to 1+908) 44 ---
WO.06.7380 Road Kerbs: Foundation | Kerbs Installation 18 358.33/d 6450.00 Kerb Stone: 250x125
WO.06.7380 Road Kerbs: Foundation | Kerbs Installation 18 2.00/d 36.00 Unskilled Labor
WO.06.7380 Road Kerbs: Foundation | Kerbs Installation 18 2.09/d 37.58 Mason
WO.06.7380 Road Kerbs: Foundation | Kerbs Installation 18 2.00/d 36.00 Carpenter
WO.06.7380 Road Kerbs: Foundation | Kerbs Installation 18 0.67/d 12.00 Charge Hand
WO.06.4750 Sub-base Formation | Sand Bedding | Interlock Paving 33 1.04/d 34.45 Plate Compactor
WO.06.4750 Sub-base Formation | Sand Bedding | Interlock Paving 33 1.00/d 33.00 Bobcat
WO.06.4750 Sub-base Formation | Sand Bedding | Interlock Paving 33 2.00/d 66.00 Unskilled Labor
WO.06.4750 Sub-base Formation | Sand Bedding | Interlock Paving 33 3.13/d 103.36 Mason
WO.06.4750 Sub-base Formation | Sand Bedding | Interlock Paving 33 666.91/d 22008.00 Paving Block
WO.06.4750 Sub-base Formation | Sand Bedding | Interlock Paving 33 0.50/d 16.50 Charge Hand
SA032.01. (1-6).CON.06.P2.S1 Phase 02: Stage 1 Garrage Way (Ch.0+100 to 0+500) 37 ---
WO.06.7590 Road Kerbs: Foundation | Kerbs Installation 32 62.50/d 2000.00 Kerb Stone: 250x125
WO.06.7590 Road Kerbs: Foundation | Kerbs Installation 32 2.00/d 64.00 Unskilled Labor
WO.06.7590 Road Kerbs: Foundation | Kerbs Installation 32 2.09/d 66.82 Mason
WO.06.7590 Road Kerbs: Foundation | Kerbs Installation 32 2.00/d 64.00 Carpenter
WO.06.7590 Road Kerbs: Foundation | Kerbs Installation 32 0.56/d 18.00 Charge Hand
SA032.01. (1-6).CON.06.P2.S2 Phase 02: Stage 2 Garrage Way (Ch.0+500 to 1+000) 52 ---
WO.06.8140 Road Kerbs: Foundation | Kerbs Installation 45 93.02/d 4186.00 Kerb Stone: 250x125
WO.06.8140 Road Kerbs: Foundation | Kerbs Installation 45 1.07/d 48.00 Unskilled Labor
WO.06.8140 Road Kerbs: Foundation | Kerbs Installation 45 1.11/d 50.11 Mason
WO.06.8140 Road Kerbs: Foundation | Kerbs Installation 45 1.07/d 48.00 Carpenter
WO.06.8140 Road Kerbs: Foundation | Kerbs Installation 45 0.27/d 12.00 Charge Hand
SA032.01. (1-6).CON.06.P2.S3 Phase 02: Stage 3 (Ch.0+100 to 1+500) 77 ---
WO.06.8870 Road Kerbs: Foundation | Kerbs Installation 36 111.50/d 4014.00 Kerb Stone: 250x125
WO.06.8870 Road Kerbs: Foundation | Kerbs Installation 36 1.00/d 36.00 Unskilled Labor
WO.06.8870 Road Kerbs: Foundation | Kerbs Installation 36 1.04/d 37.58 Mason
WO.06.8870 Road Kerbs: Foundation | Kerbs Installation 36 1.00/d 36.00 Carpenter
WO.06.8870 Road Kerbs: Foundation | Kerbs Installation 36 0.33/d 12.00 Charge Hand
WO.06.7580 Sub-base Formation | Sand Bedding | Interlock Paving 30 1.04/d 31.32 Plate Compactor
WO.06.7580 Sub-base Formation | Sand Bedding | Interlock Paving 30 1.00/d 30.00 Bobcat
WO.06.7580 Sub-base Formation | Sand Bedding | Interlock Paving 30 2.00/d 60.00 Unskilled Labor
WO.06.7580 Sub-base Formation | Sand Bedding | Interlock Paving 30 3.13/d 93.96 Mason
WO.06.7580 Sub-base Formation | Sand Bedding | Interlock Paving 30 762.23/d 22867.00 Paving Block
WO.06.7580 Sub-base Formation | Sand Bedding | Interlock Paving 30 0.55/d 16.50 Charge Hand

Traffic Signs | Markings | Studs 34 ---


SA032.01. (1-6).CON.06.P1.S3N Phase 01: Stage 3 (Ch.1+000 to 1+908) 13 ---
WO.06.5580 Surface Markings | Letters | Studs 12 1563.29/d 18759.50 Road Marking
WO.06.5580 Surface Markings | Letters | Studs 12 1.67/d 20.00 Unskilled Labor
WO.06.5580 Surface Markings | Letters | Studs 12 0.21/d 2.50 Charge Hand
WO.06.5580 Surface Markings | Letters | Studs 12 4.00/d 48.00 Painter
WO.06.4530 Traffic signs: Excavation | Foundation | Installation 12 2.00/d 24.00 Unskilled Labor
WO.06.4530 Traffic signs: Excavation | Foundation | Installation 12 11.50/d 138.00 Traffic Sign
WO.06.4530 Traffic signs: Excavation | Foundation | Installation 12 0.38/d 4.50 Charge Hand
SA032.01. (1-6).CON.06.P2.S3 Phase 02: Stage 3 (Ch.0+100 to 1+500) 13 ---
WO.06.8150 Surface Markings | Letters | Studs 12 1563.29/d 18759.50 Road Marking
WO.06.8150 Surface Markings | Letters | Studs 12 1.67/d 20.00 Unskilled Labor
WO.06.8150 Surface Markings | Letters | Studs 12 0.21/d 2.50 Charge Hand
WO.06.8150 Surface Markings | Letters | Studs 12 4.00/d 48.00 Painter
WO.06.8160 Traffic signs: Excavation | Foundation | Installation 12 2.00/d 24.00 Unskilled Labor
WO.06.8160 Traffic signs: Excavation | Foundation | Installation 12 11.50/d 138.00 Traffic Sign
WO.06.8160 Traffic signs: Excavation | Foundation | Installation 12 0.38/d 4.50 Charge Hand

Water Works 304 ---


SA032.01. (1-6).CON.06.P1.S1 Phase 01: Stage 1 Carriage Way (Ch.1+000 to 1+550) 22 ---
WO.06.1690 Backfilling | Compaction 4 129.75/d 519.00 Backfilling LM
WO.06.1690 Backfilling | Compaction 4 2.00/d 8.00 Unskilled Labor
WO.06.1690 Backfilling | Compaction 4 0.94/d 3.75 JCB
WO.06.1690 Backfilling | Compaction 4 1.04/d 4.18 Plate Compactor

© Oracle Corporation Page 6 of 21


07-Mar-21 13:11
Activity ID Activity Name Estimated Productivity Budgeted Units Resource Name
Duration

WO.06.1690 Backfilling | Compaction 4 1.04/d 4.18 Roller Compactor: 2Ton


WO.06.1690 Backfilling | Compaction 4 1.00/d 4.00 Charge Hand
WO.06.1820 Concrete Protection 4 2.00/d 8.00 Carpenter
WO.06.1820 Concrete Protection 4 2.00/d 8.00 Mason
WO.06.1820 Concrete Protection 4 2.00/d 8.00 Unskilled Labor
WO.06.1820 Concrete Protection 4 0.50/d 2.00 Charge Hand
WO.06.1240 Excavation | Disposal 10 1.00/d 10.00 Excavator: Hammer
WO.06.1240 Excavation | Disposal 10 1.00/d 10.00 Excavator: Bucket
WO.06.1240 Excavation | Disposal 10 51.90/d 519.00 Excavation LM
WO.06.1240 Excavation | Disposal 10 2.00/d 20.00 Unskilled Labor
WO.06.1240 Excavation | Disposal 10 0.40/d 4.00 Charge Hand
WO.06.1430 Fire Hydrant | Valve installation 1 2.00/d 2.00 Pipe Fitter
WO.06.1430 Fire Hydrant | Valve installation 1 2.00/d 2.00 Unskilled Labor
WO.06.1430 Fire Hydrant | Valve installation 1 0.50/d 0.50 Charge Hand
WO.06.1430 Fire Hydrant | Valve installation 1 1.00/d 1.00 Removing of Existing Fire Hydrants
WO.06.1300 Removal of Existing Line 5 2.00/d 9.97 Unskilled Labor
WO.06.1300 Removal of Existing Line 5 0.40/d 2.00 Charge Hand
WO.06.1300 Removal of Existing Line 5 104.15/d 519.00 Removal of Existing Portable Water DI Pipes : 400 m
SA032.01. (1-6).CON.06.P1.S3N Phase 01: Stage 3 (Ch.1+000 to 1+908) 34 ---
WO.06.3450 Backfilling | Compaction 5 34.80/d 174.00 Backfilling LM
WO.06.3450 Backfilling | Compaction 5 2.00/d 10.00 Unskilled Labor
WO.06.3450 Backfilling | Compaction 5 1.00/d 5.00 JCB
WO.06.3450 Backfilling | Compaction 5 1.04/d 5.22 Plate Compactor
WO.06.3450 Backfilling | Compaction 5 1.04/d 5.22 Roller Compactor: 2Ton
WO.06.3450 Backfilling | Compaction 5 0.50/d 2.50 Charge Hand
WO.06.3660 Concrete Protection 4 2.00/d 8.00 Carpenter
WO.06.3660 Concrete Protection 4 2.00/d 8.00 Mason
WO.06.3660 Concrete Protection 4 2.00/d 8.00 Unskilled Labor
WO.06.3660 Concrete Protection 4 1.00/d 4.00 Charge Hand
WO.06.2640 Excavation | Disposal 5 1.00/d 5.00 Excavator: Hammer
WO.06.2640 Excavation | Disposal 5 1.00/d 5.00 Excavator: Bucket
WO.06.2640 Excavation | Disposal 5 34.80/d 174.00 Excavation LM
WO.06.2640 Excavation | Disposal 5 2.00/d 10.00 Unskilled Labor
WO.06.2640 Excavation | Disposal 5 0.50/d 2.50 Charge Hand
WO.06.3080 Fire Hydrant | Valve installation 4 2.00/d 8.00 Pipe Fitter
WO.06.3080 Fire Hydrant | Valve installation 4 2.00/d 8.00 Unskilled Labor
WO.06.3080 Fire Hydrant | Valve installation 4 0.50/d 2.00 Charge Hand
WO.06.3080 Fire Hydrant | Valve installation 4 0.25/d 1.00 Removing of Existing Fire Hydrants
WO.06.2750 Leveling | Bedding 4 2.00/d 8.00 Unskilled Labor
WO.06.2750 Leveling | Bedding 4 43.50/d 174.00 Bedding LM
WO.06.2750 Leveling | Bedding 4 1.00/d 4.00 Charge Hand
WO.06.2820 Pipe Laying 4 2.00/d 8.00 Unskilled Labor
WO.06.2820 Pipe Laying 4 2.00/d 8.00 Pipe Fitter
WO.06.2820 Pipe Laying 4 43.50/d 174.00 Wet - Pipe Laying LM
WO.06.2820 Pipe Laying 4 1.00/d 4.00 Mobile Crane
WO.06.2820 Pipe Laying 4 1.00/d 4.00 Charge Hand
WO.06.2980 Removal of Existing Line 11 2.00/d 22.00 Unskilled Labor
WO.06.2980 Removal of Existing Line 11 1.00/d 11.00 Charge Hand
WO.06.2980 Removal of Existing Line 11 47.18/d 519.00 Removal of Existing Portable Water DI Pipes : 400 m
WO.06.3470 Surrounding works 9 2.00/d 18.00 Unskilled Labor
WO.06.3470 Surrounding works 9 19.33/d 174.00 Sand Surround LM
WO.06.3470 Surrounding works 9 1.00/d 9.00 Tipper 6 Wheel Truck
WO.06.3470 Surrounding works 9 1.04/d 9.40 Plate Compactor
WO.06.3470 Surrounding works 9 0.50/d 4.50 Charge Hand

Electricity Works 253 ---


SA032.01. (1-6).CON.06.P1.S1 Phase 01: Stage 1 Carriage Way (Ch.1+000 to 1+550) 21 ---
WO.06.1490 Duct Works: Electrical 18 18.50/d 333.00 Excavation LM
WO.06.1490 Duct Works: Electrical 18 2.00/d 36.00 Unskilled Labor
WO.06.1490 Duct Works: Electrical 18 1.00/d 18.00 Excavator: Hammer
WO.06.1490 Duct Works: Electrical 18 1.00/d 18.00 Excavator: Bucket
WO.06.1490 Duct Works: Electrical 18 0.28/d 5.00 Charge Hand
SA032.01. (1-6).CON.06.P1.S2 Phase 01: Stage 2 Carriage Way (Ch.1+550 to 1+908)35 ---
WO.06.7140 MV Work: Excavation | Cable Laying | Surround | Backfilling 30 5.00/d 150.00 Unskilled Labor
WO.06.7140 MV Work: Excavation | Cable Laying | Surround | Backfilling 30 0.60/d 18.00 Excavator: Hammer
WO.06.7140 MV Work: Excavation | Cable Laying | Surround | Backfilling 30 0.60/d 18.00 Excavator: Bucket
WO.06.7140 MV Work: Excavation | Cable Laying | Surround | Backfilling 30 0.17/d 5.00 Charge Hand
WO.06.7140 MV Work: Excavation | Cable Laying | Surround | Backfilling 30 7.33/d 220.00 Removal - MV cable
WO.06.7140 MV Work: Excavation | Cable Laying | Surround | Backfilling 30 4.00/d 120.00 Electrician
SA032.01. (1-6).CON.06.P1.S3N Phase 01: Stage 3 (Ch.1+000 to 1+908) 35 ---

© Oracle Corporation Page 7 of 21


07-Mar-21 13:11
Activity ID Activity Name Estimated Productivity Budgeted Units Resource Name
Duration

WO.06.7280 Duct Works: Electrical 18 18.50/d 333.00 Excavation LM


WO.06.7280 Duct Works: Electrical 18 2.00/d 36.00 Unskilled Labor
WO.06.7280 Duct Works: Electrical 18 1.00/d 18.00 Excavator: Hammer
WO.06.7280 Duct Works: Electrical 18 1.00/d 18.00 Excavator: Bucket
WO.06.7280 Duct Works: Electrical 18 0.28/d 5.00 Charge Hand
WO.06.3760 LV Work: Excavation | Cable Laying | Surround | Backfilling 30 5.00/d 150.00 Unskilled Labor
WO.06.3760 LV Work: Excavation | Cable Laying | Surround | Backfilling 30 4.00/d 120.00 Electrician
WO.06.3760 LV Work: Excavation | Cable Laying | Surround | Backfilling 30 0.13/d 4.00 Charge Hand
WO.06.3760 LV Work: Excavation | Cable Laying | Surround | Backfilling 30 24.00/d 720.00 Removal - LV cable
SA032.01. (1-6).CON.06.P2.S1 Phase 02: Stage 1 Garrage Way (Ch.0+100 to 0+500) 21 ---
WO.06.7410 Duct Works: Electrical 18 18.50/d 333.00 Excavation LM
WO.06.7410 Duct Works: Electrical 18 2.00/d 36.00 Unskilled Labor
WO.06.7410 Duct Works: Electrical 18 1.00/d 18.00 Excavator: Hammer
WO.06.7410 Duct Works: Electrical 18 1.00/d 18.00 Excavator: Bucket
WO.06.7410 Duct Works: Electrical 18 0.28/d 5.00 Charge Hand
SA032.01. (1-6).CON.06.P2.S2 Phase 02: Stage 2 Garrage Way (Ch.0+500 to 1+000) 21 ---
WO.06.8650 Duct Works: Electrical 18 18.50/d 333.00 Excavation LM
WO.06.8650 Duct Works: Electrical 18 2.00/d 36.00 Unskilled Labor
WO.06.8650 Duct Works: Electrical 18 1.00/d 18.00 Excavator: Hammer
WO.06.8650 Duct Works: Electrical 18 1.00/d 18.00 Excavator: Bucket
WO.06.8650 Duct Works: Electrical 18 0.28/d 5.00 Charge Hand
SA032.01. (1-6).CON.06.P2.S3 Phase 02: Stage 3 (Ch.0+100 to 1+500) 87 ---
WO.06.8770 Duct Works: Electrical 18 18.50/d 333.00 Excavation LM
WO.06.8770 Duct Works: Electrical 18 2.00/d 36.00 Unskilled Labor
WO.06.8770 Duct Works: Electrical 18 1.00/d 18.00 Excavator: Hammer
WO.06.8770 Duct Works: Electrical 18 1.00/d 18.00 Excavator: Bucket
WO.06.8770 Duct Works: Electrical 18 0.28/d 5.00 Charge Hand
WO.06.7910 MV Work: Excavation | Cable Laying | Surround | Backfilling 45 2.00/d 90.00 Unskilled Labor
WO.06.7910 MV Work: Excavation | Cable Laying | Surround | Backfilling 45 1.60/d 72.00 Electrician
WO.06.7910 MV Work: Excavation | Cable Laying | Surround | Backfilling 45 0.09/d 4.00 Charge Hand
WO.06.7910 MV Work: Excavation | Cable Laying | Surround | Backfilling 45 28.89/d 1300.00 Removal - LV cable
WO.06.7910 MV Work: Excavation | Cable Laying | Surround | Backfilling 45 0.40/d 18.00 Excavator: Hammer
WO.06.7910 MV Work: Excavation | Cable Laying | Surround | Backfilling 45 0.40/d 18.00 Excavator: Bucket

Ooredoo Works 149 ---


SA032.01. (1-6).CON.06.P1.S1 Phase 01: Stage 1 Carriage Way (Ch.1+000 to 1+550) 20 ---
WO.06.1890 Duct Works: Ooredoo 18 2.00/d 36.00 Mason
WO.06.1890 Duct Works: Ooredoo 18 2.00/d 36.00 Pipe Fitter
WO.06.1890 Duct Works: Ooredoo 18 2.00/d 36.00 Unskilled Labor
WO.06.1890 Duct Works: Ooredoo 18 2.00/d 36.00 Carpenter
WO.06.1890 Duct Works: Ooredoo 18 0.72/d 13.00 Charge Hand
WO.06.1890 Duct Works: Ooredoo 18 3.33/d 60.00 Ooredoo Duct
SA032.01. (1-6).CON.06.P1.S2 Phase 01: Stage 2 Carriage Way (Ch.1+550 to 1+908)21 ---
WO.06.7150 Duct Works: Ooredoo 18 2.00/d 36.00 Mason
WO.06.7150 Duct Works: Ooredoo 18 2.00/d 36.00 Pipe Fitter
WO.06.7150 Duct Works: Ooredoo 18 2.00/d 36.00 Unskilled Labor
WO.06.7150 Duct Works: Ooredoo 18 2.00/d 36.00 Carpenter
WO.06.7150 Duct Works: Ooredoo 18 0.72/d 13.00 Charge Hand
WO.06.7150 Duct Works: Ooredoo 18 3.33/d 60.00 Ooredoo Duct
SA032.01. (1-6).CON.06.P1.S3N Phase 01: Stage 3 (Ch.1+000 to 1+908) 21 ---
WO.06.7270 Duct Works: Ooredoo 18 2.00/d 36.00 Mason
WO.06.7270 Duct Works: Ooredoo 18 2.00/d 36.00 Pipe Fitter
WO.06.7270 Duct Works: Ooredoo 18 2.00/d 36.00 Unskilled Labor
WO.06.7270 Duct Works: Ooredoo 18 2.00/d 36.00 Carpenter
WO.06.7270 Duct Works: Ooredoo 18 0.72/d 13.00 Charge Hand
WO.06.7270 Duct Works: Ooredoo 18 3.33/d 60.00 Ooredoo Duct
SA032.01. (1-6).CON.06.P2.S1 Phase 02: Stage 1 Garrage Way (Ch.0+100 to 0+500) 21 ---
WO.06.7400 Duct Works: Ooredoo 18 2.00/d 36.00 Mason
WO.06.7400 Duct Works: Ooredoo 18 2.00/d 36.00 Pipe Fitter
WO.06.7400 Duct Works: Ooredoo 18 2.00/d 36.00 Unskilled Labor
WO.06.7400 Duct Works: Ooredoo 18 2.00/d 36.00 Carpenter
WO.06.7400 Duct Works: Ooredoo 18 0.72/d 13.00 Charge Hand
WO.06.7400 Duct Works: Ooredoo 18 3.33/d 60.00 Ooredoo Duct
SA032.01. (1-6).CON.06.P2.S2 Phase 02: Stage 2 Garrage Way (Ch.0+500 to 1+000) 21 ---
WO.06.8640 Duct Works: Ooredoo 18 2.00/d 36.00 Mason
WO.06.8640 Duct Works: Ooredoo 18 2.00/d 36.00 Pipe Fitter
WO.06.8640 Duct Works: Ooredoo 18 2.00/d 36.00 Unskilled Labor
WO.06.8640 Duct Works: Ooredoo 18 2.00/d 36.00 Carpenter
WO.06.8640 Duct Works: Ooredoo 18 0.72/d 13.00 Charge Hand
WO.06.8640 Duct Works: Ooredoo 18 3.33/d 60.00 Ooredoo Duct

© Oracle Corporation Page 8 of 21


07-Mar-21 13:11
Activity ID Activity Name Estimated Productivity Budgeted Units Resource Name
Duration

SA032.01. (1-6).CON.06.P2.S3 Phase 02: Stage 3 (Ch.0+100 to 1+500) 21 ---


WO.06.8760 Duct Works: Ooredoo 18 2.00/d 36.00 Mason
WO.06.8760 Duct Works: Ooredoo 18 2.00/d 36.00 Pipe Fitter
WO.06.8760 Duct Works: Ooredoo 18 2.00/d 36.00 Unskilled Labor
WO.06.8760 Duct Works: Ooredoo 18 2.00/d 36.00 Carpenter
WO.06.8760 Duct Works: Ooredoo 18 0.72/d 13.00 Charge Hand
WO.06.8760 Duct Works: Ooredoo 18 3.33/d 60.00 Ooredoo Duct

Road Drainage 309 ---


SA032.01. (1-6).CON.06.P1.S1 Phase 01: Stage 1 Carriage Way (Ch.1+000 to 1+550)147 ---
WO.06.2310 Backfilling | Compaction 52 21.15/d 1100.00 Backfilling LM
WO.06.2310 Backfilling | Compaction 52 2.00/d 104.00 Unskilled Labor
WO.06.2310 Backfilling | Compaction 52 0.24/d 12.50 JCB
WO.06.2310 Backfilling | Compaction 52 1.04/d 54.29 Plate Compactor
WO.06.2310 Backfilling | Compaction 52 1.04/d 54.29 Roller Compactor: 2Ton
WO.06.2050 Backfilling | Compaction 20 2.00/d 40.00 Unskilled Labor
WO.06.2050 Backfilling | Compaction 20 0.19/d 3.75 JCB
WO.06.2050 Backfilling | Compaction 20 1.04/d 20.88 Plate Compactor
WO.06.2050 Backfilling | Compaction 20 1.04/d 20.88 Roller Compactor: 2Ton
WO.06.2230 Backfilling | Compaction 30 2.00/d 60.00 Unskilled Labor
WO.06.2230 Backfilling | Compaction 30 0.38/d 11.25 JCB
WO.06.2230 Backfilling | Compaction 30 1.04/d 31.32 Plate Compactor
WO.06.2230 Backfilling | Compaction 9 1.04/d 9.40 Roller Compactor: 2Ton
WO.06.2050 Backfilling | Compaction 20 0.10/d 2.00 Charge Hand
WO.06.2230 Backfilling | Compaction 30 0.20/d 6.00 Charge Hand
WO.06.2310 Backfilling | Compaction 52 0.13/d 6.50 Charge Hand
WO.06.2230 Backfilling | Compaction 30 20.33/d 610.00 Backfilling LM
WO.06.2050 Backfilling | Compaction 20 1.05/d 21.00 SWD: Manhole Backfilling
WO.06.1860 Bedding | Pipe Laying | Surrounding 30 2.00/d 60.00 Unskilled Labor
WO.06.1860 Bedding | Pipe Laying | Surrounding 30 0.40/d 12.00 Charge Hand
WO.06.1860 Bedding | Pipe Laying | Surrounding 30 20.33/d 610.00 Pipes : Nomibal bore 200mm
WO.06.1970 Blinding | Waterproofing 30 2.00/d 60.00 Unskilled Labor
WO.06.1970 Blinding | Waterproofing 30 1.00/d 30.00 Mason
WO.06.1970 Blinding | Waterproofing 30 0.50/d 15.00 Charge Hand
WO.06.1730 Concrete for Foundation Manhole 30 2.00/d 60.00 Unskilled Labor
WO.06.1730 Concrete for Foundation Manhole 30 2.00/d 60.00 Carpenter
WO.06.1730 Concrete for Foundation Manhole 30 0.70/d 21.00 Manhole - Concrete Base
WO.06.1730 Concrete for Foundation Manhole 30 2.00/d 60.00 Mason
WO.06.1730 Concrete for Foundation Manhole 30 4.00/d 120.00 Steel Fixer
WO.06.1730 Concrete for Foundation Manhole 30 0.30/d 9.00 Charge Hand
WO.06.1850 Concrete for Wall Manhole 30 2.00/d 60.00 Unskilled Labor
WO.06.1850 Concrete for Wall Manhole 30 2.00/d 60.00 Carpenter
WO.06.1850 Concrete for Wall Manhole 30 2.00/d 60.00 Mason
WO.06.1850 Concrete for Wall Manhole 30 4.00/d 120.00 Steel Fixer
WO.06.1850 Concrete for Wall Manhole 30 0.30/d 9.00 Charge Hand
WO.06.1850 Concrete for Wall Manhole 30 0.70/d 21.00 SWD: MH Wall
WO.06.1270 De-watering Works 105 2.00/d 210.00 Unskilled Labor
WO.06.1410 Excavation | Disposal 68 16.18/d 1100.00 Excavation LM
WO.06.1410 Excavation | Disposal 68 2.00/d 136.00 Unskilled Labor
WO.06.1410 Excavation | Disposal 68 3.00/d 204.00 Excavator: Hammer
WO.06.1410 Excavation | Disposal 68 1.00/d 68.00 Excavator: Bucket
WO.06.1590 Excavation | Disposal 96 2.00/d 192.00 Unskilled Labor
WO.06.1590 Excavation | Disposal 96 1.00/d 96.00 Excavator: Hammer
WO.06.1590 Excavation | Disposal 96 1.00/d 96.00 Excavator: Bucket
WO.06.1410 Excavation | Disposal 68 0.19/d 13.00 Charge Hand
WO.06.1590 Excavation | Disposal 96 0.19/d 18.00 Charge Hand
WO.06.1590 Excavation | Disposal 96 0.22/d 21.00 Manhole Excavation
WO.06.1950 Excavation | Gully Installation 30 2.00/d 60.00 Unskilled Labor
WO.06.1950 Excavation | Gully Installation 30 1.00/d 30.00 Mason
WO.06.1950 Excavation | Gully Installation 30 0.20/d 6.00 Charge Hand
WO.06.1950 Excavation | Gully Installation 30 1.47/d 44.00 Gully: Precast
WO.06.1980 External Waterproofing 20 2.00/d 40.00 Unskilled Labor
WO.06.1980 External Waterproofing 20 1.00/d 20.00 Mason
WO.06.1980 External Waterproofing 20 0.90/d 18.00 Charge Hand
WO.06.2220 Installation of Concrete Slab Cover 20 2.00/d 40.00 Unskilled Labor
WO.06.2220 Installation of Concrete Slab Cover 20 0.45/d 9.00 Charge Hand
WO.06.2220 Installation of Concrete Slab Cover 20 1.05/d 21.00 SWD: Concrete Slab Cover
WO.06.2720 Installation of DI Cover 20 2.00/d 40.00 Mason
WO.06.2720 Installation of DI Cover 20 2.00/d 40.00 Unskilled Labor
WO.06.2720 Installation of DI Cover 20 0.23/d 4.50 Charge Hand

© Oracle Corporation Page 9 of 21


07-Mar-21 13:11
Activity ID Activity Name Estimated Productivity Budgeted Units Resource Name
Duration

WO.06.2720 Installation of DI Cover 20 1.05/d 21.00 SWD: DI Cover


WO.06.2030 Installation of Gully Cover | Frame 30 2.00/d 60.00 Mason
WO.06.2030 Installation of Gully Cover | Frame 30 2.00/d 60.00 Unskilled Labor
WO.06.2030 Installation of Gully Cover | Frame 30 1.00/d 30.00 Mobile Crane
WO.06.2030 Installation of Gully Cover | Frame 30 0.20/d 6.00 Charge Hand
WO.06.2030 Installation of Gully Cover | Frame 30 1.47/d 44.00 Gully Cover | Frame
WO.06.2480 Internal Finishing 25 2.00/d 50.00 Unskilled Labor
WO.06.2480 Internal Finishing 25 2.00/d 50.00 Mason
WO.06.2480 Internal Finishing 25 0.72/d 18.00 Charge Hand
WO.06.1510 Leveling | Bedding 52 2.00/d 104.00 Unskilled Labor
WO.06.1510 Leveling | Bedding 52 21.15/d 1100.00 Bedding LM
WO.06.1510 Leveling | Bedding 52 0.13/d 6.50 Charge Hand
WO.06.2200 Pipe Laying 52 2.00/d 104.00 Unskilled Labor
WO.06.2200 Pipe Laying 52 2.00/d 104.00 Pipe Fitter
WO.06.2200 Pipe Laying 52 21.15/d 1100.00 Wet - Pipe Laying LM
WO.06.2200 Pipe Laying 52 1.00/d 52.00 Mobile Crane
WO.06.2200 Pipe Laying 52 0.39/d 20.50 Charge Hand
WO.06.2280 Surrounding works 52 2.00/d 104.00 Unskilled Labor
WO.06.2280 Surrounding works 52 21.15/d 1100.00 Sand Surround LM
WO.06.2280 Surrounding works 52 1.04/d 54.29 Plate Compactor
WO.06.2280 Surrounding works 52 1.00/d 52.00 Tipper 6 Wheel Truck
WO.06.2280 Surrounding works 52 0.13/d 6.50 Charge Hand
WO.06.1770 Trench Excavation | Dis posal 30 2.00/d 60.00 Unskilled Labor
WO.06.1770 Trench Excavation | Dis posal 30 1.00/d 30.00 Excavator: Hammer
WO.06.1770 Trench Excavation | Dis posal 30 1.00/d 30.00 Excavator: Bucket
WO.06.1770 Trench Excavation | Dis posal 30 0.20/d 6.00 Charge Hand
WO.06.1770 Trench Excavation | Dis posal 30 20.33/d 610.00 Excavation LM
161
SA032.01. (1-6).CON.06.P1.S2 Phase 01: Stage 2 Carriage Way (Ch.1+550 to 1+908) ---
WO.06.3310 Backfilling | Compaction 21 47.81/d 1004.00 Backfilling LM
WO.06.3310 Backfilling | Compaction 21 2.00/d 42.00 Unskilled Labor
WO.06.3310 Backfilling | Compaction 21 0.18/d 3.75 JCB
WO.06.3310 Backfilling | Compaction 21 1.04/d 21.92 Plate Compactor
WO.06.3310 Backfilling | Compaction 21 1.04/d 21.92 Roller Compactor: 2Ton
WO.06.3580 Backfilling | Compaction 21 2.00/d 42.00 Unskilled Labor
WO.06.3580 Backfilling | Compaction 21 0.18/d 3.75 JCB
WO.06.3580 Backfilling | Compaction 21 1.04/d 21.92 Plate Compactor
WO.06.3580 Backfilling | Compaction 21 1.04/d 21.92 Roller Compactor: 2Ton
WO.06.4250 Backfilling | Compaction 18 2.00/d 36.00 Unskilled Labor
WO.06.4250 Backfilling | Compaction 18 0.28/d 5.00 JCB
WO.06.4250 Backfilling | Compaction 18 1.04/d 18.79 Plate Compactor
WO.06.4250 Backfilling | Compaction 4 1.04/d 4.31 Roller Compactor: 2Ton
WO.06.3310 Backfilling | Compaction 21 0.10/d 2.00 Charge Hand
WO.06.3580 Backfilling | Compaction 21 0.10/d 2.00 Charge Hand
WO.06.4250 Backfilling | Compaction 18 0.28/d 5.00 Charge Hand
WO.06.3580 Backfilling | Compaction 21 1.05/d 22.00 SWD: Manhole Backfilling
WO.06.4250 Backfilling | Compaction 18 40.72/d 733.00 Backfilling LM
WO.06.3240 Bedding | Pipe Laying | Surrounding 18 2.00/d 36.00 Unskilled Labor
WO.06.3240 Bedding | Pipe Laying | Surrounding 18 0.14/d 2.50 Charge Hand
WO.06.3240 Bedding | Pipe Laying | Surrounding 18 40.72/d 733.00 Pipes : Nomibal bore 200mm
WO.06.2990 Blinding | Waterproofing 21 2.00/d 42.00 Unskilled Labor
WO.06.2990 Blinding | Waterproofing 21 1.00/d 21.00 Mason
WO.06.2990 Blinding | Waterproofing 21 0.50/d 10.50 Charge Hand
WO.06.3380 CCTV Test 21 2.00/d 42.00 Unskilled Labor
WO.06.3380 CCTV Test 21 0.02/d 0.50 Charge Hand
WO.06.3160 Concrete for Foundation Manhole 21 2.00/d 42.00 Unskilled Labor
WO.06.3160 Concrete for Foundation Manhole 21 2.00/d 42.00 Carpenter
WO.06.3160 Concrete for Foundation Manhole 21 2.00/d 42.00 Mason
WO.06.3160 Concrete for Foundation Manhole 21 4.00/d 84.00 Steel Fixer
WO.06.3160 Concrete for Foundation Manhole 21 0.50/d 10.50 Charge Hand
WO.06.3160 Concrete for Foundation Manhole 21 1.05/d 22.00 Manhole - Concrete Base
WO.06.3300 Concrete for Wall Manhole 21 2.00/d 42.00 Unskilled Labor
WO.06.3300 Concrete for Wall Manhole 21 0.12/d 2.50 Charge Hand
WO.06.3300 Concrete for Wall Manhole 21 1.05/d 22.00 SWD: MH Wall
WO.06.3360 Concreting Protection - Capping 21 2.00/d 42.00 Carpenter
WO.06.3360 Concreting Protection - Capping 21 2.00/d 42.00 Unskilled Labor
WO.06.3360 Concreting Protection - Capping 21 2.00/d 42.00 Mason
WO.06.3360 Concreting Protection - Capping 21 0.02/d 0.50 Charge Hand
WO.06.2900 De-watering Works 21 2.00/d 42.00 Unskilled Labor
WO.06.2900 De-watering Works 21 1.00/d 21.00 Charge Hand

© Oracle Corporation Page 10 of 21


07-Mar-21 13:11
Activity ID Activity Name Estimated Productivity Budgeted Units Resource Name
Duration

WO.06.2660 Excavation | Disposal 30 33.47/d 1004.00 Excavation LM


WO.06.2660 Excavation | Disposal 30 1.40/d 42.00 Unskilled Labor
WO.06.2660 Excavation | Disposal 30 2.10/d 63.00 Excavator: Hammer
WO.06.2660 Excavation | Disposal 30 0.70/d 21.00 Excavator: Bucket
WO.06.2890 Excavation | Disposal 21 2.00/d 42.00 Unskilled Labor
WO.06.2890 Excavation | Disposal 21 1.00/d 21.00 Excavator: Hammer
WO.06.2890 Excavation | Disposal 21 1.00/d 21.00 Excavator: Bucket
WO.06.2660 Excavation | Disposal 30 0.13/d 4.00 Charge Hand
WO.06.2890 Excavation | Disposal 21 0.24/d 5.00 Charge Hand
WO.06.2890 Excavation | Disposal 21 1.05/d 22.00 SW-Manholes
WO.06.3810 Excavation | Gully Installation 18 2.00/d 36.00 Unskilled Labor
WO.06.3810 Excavation | Gully Installation 18 1.00/d 18.00 Mason
WO.06.3810 Excavation | Gully Installation 18 0.31/d 5.50 Charge Hand
WO.06.3810 Excavation | Gully Installation 18 2.94/d 53.00 Gully: Precast
WO.06.3420 External Waterproofing 21 2.00/d 42.00 Unskilled Labor
WO.06.3420 External Waterproofing 21 1.00/d 21.00 Mason
WO.06.3420 External Waterproofing 21 0.12/d 2.50 Charge Hand
WO.06.3500 Installation of Concrete Slab Cover 21 2.00/d 42.00 Unskilled Labor
WO.06.3500 Installation of Concrete Slab Cover 21 0.12/d 2.50 Charge Hand
WO.06.3500 Installation of Concrete Slab Cover 21 1.05/d 22.00 SWD: Concrete Slab Cover
WO.06.3850 Installation of DI Cover 4 2.00/d 8.00 Mason
WO.06.3850 Installation of DI Cover 4 2.00/d 8.00 Unskilled Labor
WO.06.3850 Installation of DI Cover 4 5.50/d 22.00 DI Cover
WO.06.3850 Installation of DI Cover 4 1.00/d 4.00 Charge Hand
WO.06.4230 Installation of Gully Cover | Frame 11 2.00/d 22.00 Unskilled Labor
WO.06.4230 Installation of Gully Cover | Frame 11 1.00/d 11.00 Charge Hand
WO.06.4230 Installation of Gully Cover | Frame 11 4.82/d 53.00 Gully Cover | Frame
WO.06.3720 Internal Finishing 5 2.00/d 10.00 Unskilled Labor
WO.06.3720 Internal Finishing 5 2.00/d 10.00 Mason
WO.06.3720 Internal Finishing 5 1.00/d 5.00 Charge Hand
WO.06.2800 Leveling | Bedding 21 2.00/d 42.00 Unskilled Labor
WO.06.2800 Leveling | Bedding 21 47.81/d 1004.00 Bedding LM
WO.06.2800 Leveling | Bedding 21 0.24/d 5.00 Charge Hand
WO.06.2920 Pipe Laying 21 2.00/d 42.00 Unskilled Labor
WO.06.2920 Pipe Laying 21 2.00/d 42.00 Pipe Fitter
WO.06.2920 Pipe Laying 21 47.81/d 1004.00 Wet - Pipe Laying LM
WO.06.2920 Pipe Laying 21 1.00/d 21.00 Mobile Crane
WO.06.2920 Pipe Laying 21 0.24/d 5.00 Charge Hand
WO.06.3170 Surrounding works 21 2.00/d 42.00 Unskilled Labor
WO.06.3170 Surrounding works 21 47.81/d 1004.00 Sand Surround LM
WO.06.3170 Surrounding works 21 1.04/d 21.92 Plate Compactor
WO.06.3170 Surrounding works 21 1.00/d 21.00 Tipper 6 Wheel Truck
WO.06.3170 Surrounding works 21 0.10/d 2.00 Charge Hand
WO.06.3070 Trench Excavation | Dis posal 18 2.00/d 36.00 Unskilled Labor
WO.06.3070 Trench Excavation | Dis posal 18 1.00/d 18.00 Excavator: Hammer
WO.06.3070 Trench Excavation | Dis posal 4 1.00/d 4.13 Excavator: Bucket
WO.06.3070 Trench Excavation | Dis posal 18 0.28/d 5.00 Charge Hand
WO.06.3070 Trench Excavation | Dis posal 18 40.72/d 733.00 Excavation LM
SA032.01. (1-6).CON.06.P1.S3N Phase 01: Stage 3 (Ch.1+000 to 1+908) 38 ---
WO.06.8920 Backfilling | Compaction 18 2.00/d 36.00 Unskilled Labor
WO.06.8920 Backfilling | Compaction 18 0.28/d 5.00 JCB
WO.06.8920 Backfilling | Compaction 18 1.04/d 18.79 Plate Compactor
WO.06.8920 Backfilling | Compaction 4 1.04/d 4.31 Roller Compactor: 2Ton
WO.06.8920 Backfilling | Compaction 18 0.28/d 5.00 Charge Hand
WO.06.8920 Backfilling | Compaction 18 45.94/d 827.00 Backfilling LM
WO.06.8950 Bedding | Pipe Laying | Surrounding 18 2.00/d 36.00 Unskilled Labor
WO.06.8950 Bedding | Pipe Laying | Surrounding 18 0.14/d 2.50 Charge Hand
WO.06.8950 Bedding | Pipe Laying | Surrounding 18 45.94/d 827.00 Pipes : Nomibal bore 200mm
WO.06.8930 Excavation | Gully Installation 18 2.00/d 36.00 Unskilled Labor
WO.06.8930 Excavation | Gully Installation 18 1.00/d 18.00 Mason
WO.06.8930 Excavation | Gully Installation 18 0.31/d 5.50 Charge Hand
WO.06.8930 Excavation | Gully Installation 18 3.33/d 60.00 Gully: Precast
WO.06.8960 Installation of Gully Cover | Frame 11 2.00/d 22.00 Unskilled Labor
WO.06.8960 Installation of Gully Cover | Frame 11 1.00/d 11.00 Charge Hand
WO.06.8960 Installation of Gully Cover | Frame 11 5.45/d 60.00 Gully Cover | Frame
WO.06.8940 Trench Excavation | Dis posal 18 2.00/d 36.00 Unskilled Labor
WO.06.8940 Trench Excavation | Dis posal 18 1.00/d 18.00 Excavator: Hammer
WO.06.8940 Trench Excavation | Dis posal 4 1.00/d 4.13 Excavator: Bucket
WO.06.8940 Trench Excavation | Dis posal 18 0.28/d 5.00 Charge Hand

© Oracle Corporation Page 11 of 21


07-Mar-21 13:11
Activity ID Activity Name Estimated Productivity Budgeted Units Resource Name
Duration

WO.06.8940 Trench Excavation | Dis posal 18 45.94/d 827.00 Excavation LM


SA032.01. (1-6).CON.06.P2.S1 Phase 02: Stage 1 Garrage Way (Ch.0+100 to 0+500)146 ---
WO.06.7750 Backfilling | Compaction 30 2.00/d 60.00 Unskilled Labor
WO.06.7750 Backfilling | Compaction 30 0.13/d 3.75 JCB
WO.06.7750 Backfilling | Compaction 30 1.04/d 31.32 Plate Compactor
WO.06.7750 Backfilling | Compaction 30 1.04/d 31.32 Roller Compactor: 2Ton
WO.06.7830 Backfilling | Compaction 30 2.00/d 60.00 Unskilled Labor
WO.06.7830 Backfilling | Compaction 30 0.38/d 11.25 JCB
WO.06.7830 Backfilling | Compaction 30 1.04/d 31.32 Plate Compactor
WO.06.7830 Backfilling | Compaction 9 1.04/d 9.40 Roller Compactor: 2Ton
WO.06.7750 Backfilling | Compaction 30 0.07/d 2.00 Charge Hand
WO.06.7830 Backfilling | Compaction 30 0.20/d 6.00 Charge Hand
WO.06.7750 Backfilling | Compaction 30 0.40/d 12.00 SWD: Manhole Backfilling
WO.06.7830 Backfilling | Compaction 30 11.67/d 350.00 Backfilling LM
WO.06.7620 Backfilling | Compaction | Concreting Protection 35 14.29/d 500.00 Backfilling LM
WO.06.7620 Backfilling | Compaction | Concreting Protection 35 2.00/d 70.00 Unskilled Labor
WO.06.7620 Backfilling | Compaction | Concreting Protection 35 0.36/d 12.50 JCB
WO.06.7620 Backfilling | Compaction | Concreting Protection 35 1.04/d 36.54 Plate Compactor
WO.06.7620 Backfilling | Compaction | Concreting Protection 35 1.04/d 36.54 Roller Compactor: 2Ton
WO.06.7620 Backfilling | Compaction | Concreting Protection 35 0.19/d 6.50 Charge Hand
WO.06.7860 Bedding | Pipe Laying | Surrounding 30 2.00/d 60.00 Unskilled Labor
WO.06.7860 Bedding | Pipe Laying | Surrounding 30 0.40/d 12.00 Charge Hand
WO.06.7860 Bedding | Pipe Laying | Surrounding 30 11.67/d 350.00 Pipes : Nomibal bore 200mm
WO.06.7780 Blinding | Waterproofing 30 2.00/d 60.00 Unskilled Labor
WO.06.7780 Blinding | Waterproofing 30 1.00/d 30.00 Mason
WO.06.7780 Blinding | Waterproofing 30 0.50/d 15.00 Charge Hand
WO.06.7720 Concrete for Foundation Manhole 30 2.00/d 60.00 Unskilled Labor
WO.06.7720 Concrete for Foundation Manhole 30 2.00/d 60.00 Carpenter
WO.06.7720 Concrete for Foundation Manhole 30 0.40/d 12.00 Manhole - Concrete Base
WO.06.7720 Concrete for Foundation Manhole 30 2.00/d 60.00 Mason
WO.06.7720 Concrete for Foundation Manhole 30 4.00/d 120.00 Steel Fixer
WO.06.7720 Concrete for Foundation Manhole 30 0.30/d 9.00 Charge Hand
WO.06.7740 Concrete for Wall Manhole 30 2.00/d 60.00 Unskilled Labor
WO.06.7740 Concrete for Wall Manhole 30 2.00/d 60.00 Carpenter
WO.06.7740 Concrete for Wall Manhole 30 2.00/d 60.00 Mason
WO.06.7740 Concrete for Wall Manhole 30 4.00/d 120.00 Steel Fixer
WO.06.7740 Concrete for Wall Manhole 30 0.30/d 9.00 Charge Hand
WO.06.7740 Concrete for Wall Manhole 30 0.40/d 12.00 SWD: MH Wall
WO.06.8610 De-watering Works 51 2.00/d 102.00 Unskilled Labor
WO.06.8610 De-watering Works 51 0.50/d 25.50 Charge Hand
WO.06.7630 Excavation | Disposal 35 14.29/d 500.00 Excavation LM
WO.06.7630 Excavation | Disposal 35 2.00/d 70.00 Unskilled Labor
WO.06.7630 Excavation | Disposal 35 3.00/d 105.00 Excavator: Hammer
WO.06.7630 Excavation | Disposal 35 1.00/d 35.00 Excavator: Bucket
WO.06.7770 Excavation | Disposal 30 2.00/d 60.00 Unskilled Labor
WO.06.7770 Excavation | Disposal 30 1.00/d 30.00 Excavator: Hammer
WO.06.7770 Excavation | Disposal 30 1.00/d 30.00 Excavator: Bucket
WO.06.7630 Excavation | Disposal 35 0.37/d 13.00 Charge Hand
WO.06.7770 Excavation | Disposal 30 0.60/d 18.00 Charge Hand
WO.06.7770 Excavation | Disposal 30 0.40/d 12.00 Manhole Excavation
WO.06.7840 Excavation | Gully Installation 30 2.00/d 60.00 Unskilled Labor
WO.06.7840 Excavation | Gully Installation 30 1.00/d 30.00 Mason
WO.06.7840 Excavation | Gully Installation 30 0.20/d 6.00 Charge Hand
WO.06.7840 Excavation | Gully Installation 30 0.90/d 27.00 Gully Cover | Frame
WO.06.7760 External Waterproofing 30 2.00/d 60.00 Unskilled Labor
WO.06.7760 External Waterproofing 30 1.00/d 30.00 Mason
WO.06.7760 External Waterproofing 30 0.60/d 18.00 Charge Hand
WO.06.7730 Installation of Concrete Slab Cover 30 2.00/d 60.00 Unskilled Labor
WO.06.7730 Installation of Concrete Slab Cover 30 0.30/d 9.00 Charge Hand
WO.06.7730 Installation of Concrete Slab Cover 30 0.40/d 12.00 SWD: Concrete Slab Cover
WO.06.7800 Installation of DI Cover 25 2.00/d 50.00 Mason
WO.06.7800 Installation of DI Cover 25 2.00/d 50.00 Unskilled Labor
WO.06.7800 Installation of DI Cover 25 0.48/d 12.00 DI Cover
WO.06.7800 Installation of DI Cover 25 0.18/d 4.50 Charge Hand
WO.06.7870 Installation of Gully Cover | Frame 30 2.00/d 60.00 Mason
WO.06.7870 Installation of Gully Cover | Frame 30 2.00/d 60.00 Unskilled Labor
WO.06.7870 Installation of Gully Cover | Frame 30 1.00/d 30.00 Mobile Crane
WO.06.7870 Installation of Gully Cover | Frame 30 0.20/d 6.00 Charge Hand
WO.06.7870 Installation of Gully Cover | Frame 30 0.90/d 27.00 Gully Cover | Frame

© Oracle Corporation Page 12 of 21


07-Mar-21 13:11
Activity ID Activity Name Estimated Productivity Budgeted Units Resource Name
Duration

WO.06.7790 Internal Finishing 25 2.00/d 50.00 Unskilled Labor


WO.06.7790 Internal Finishing 25 2.00/d 50.00 Mason
WO.06.7790 Internal Finishing 25 0.72/d 18.00 Charge Hand
WO.06.7640 Leveling | Bedding 35 2.00/d 70.00 Unskilled Labor
WO.06.7640 Leveling | Bedding 35 14.29/d 500.00 Bedding LM
WO.06.7640 Leveling | Bedding 35 0.19/d 6.50 Charge Hand
WO.06.7600 Pipe Laying 35 2.00/d 70.00 Unskilled Labor
WO.06.7600 Pipe Laying 35 2.00/d 70.00 Pipe Fitter
WO.06.7600 Pipe Laying 35 14.29/d 500.00 Wet - Pipe Laying LM
WO.06.7600 Pipe Laying 35 1.00/d 35.00 Mobile Crane
WO.06.7600 Pipe Laying 35 0.59/d 20.50 Charge Hand
WO.06.7610 Surrounding works 35 2.00/d 70.00 Unskilled Labor
WO.06.7610 Surrounding works 35 14.29/d 500.00 Sand Surround LM
WO.06.7610 Surrounding works 35 1.04/d 36.54 Plate Compactor
WO.06.7610 Surrounding works 35 1.00/d 35.00 Tipper 6 Wheel Truck
WO.06.7610 Surrounding works 35 0.19/d 6.50 Charge Hand
WO.06.7850 Trench Excavation | Dis posal 30 2.00/d 60.00 Unskilled Labor
WO.06.7850 Trench Excavation | Dis posal 30 1.00/d 30.00 Excavator: Hammer
WO.06.7850 Trench Excavation | Dis posal 30 1.00/d 30.00 Excavator: Bucket
WO.06.7850 Trench Excavation | Dis posal 30 0.20/d 6.00 Charge Hand
WO.06.7850 Trench Excavation | Dis posal 30 11.67/d 350.00 Excavation LM
SA032.01. (1-6).CON.06.P2.S2 Phase 02: Stage 2 Garrage Way (Ch.0+500 to 1+000)158 ---
WO.06.8200 Backfilling | Compaction 30 55.27/d 1658.00 Backfilling LM
WO.06.8200 Backfilling | Compaction 30 2.00/d 60.00 Unskilled Labor
WO.06.8200 Backfilling | Compaction 30 0.13/d 3.75 JCB
WO.06.8200 Backfilling | Compaction 30 1.04/d 31.32 Plate Compactor
WO.06.8200 Backfilling | Compaction 30 1.04/d 31.32 Roller Compactor: 2Ton
WO.06.8340 Backfilling | Compaction 30 2.00/d 60.00 Unskilled Labor
WO.06.8340 Backfilling | Compaction 30 0.13/d 3.75 JCB
WO.06.8340 Backfilling | Compaction 30 1.04/d 31.32 Plate Compactor
WO.06.8340 Backfilling | Compaction 30 1.04/d 31.32 Roller Compactor: 2Ton
WO.06.8420 Backfilling | Compaction 30 2.00/d 60.00 Unskilled Labor
WO.06.8420 Backfilling | Compaction 30 0.17/d 5.00 JCB
WO.06.8420 Backfilling | Compaction 30 1.04/d 31.32 Plate Compactor
WO.06.8420 Backfilling | Compaction 4 1.04/d 4.31 Roller Compactor: 2Ton
WO.06.8200 Backfilling | Compaction 30 0.07/d 2.00 Charge Hand
WO.06.8340 Backfilling | Compaction 30 0.07/d 2.00 Charge Hand
WO.06.8420 Backfilling | Compaction 30 0.17/d 5.00 Charge Hand
WO.06.8340 Backfilling | Compaction 30 1.30/d 39.00 SWD: Manhole Backfilling
WO.06.8420 Backfilling | Compaction 30 27.00/d 810.00 Backfilling LM
WO.06.8450 Bedding | Pipe Laying | Surrounding 30 2.00/d 60.00 Unskilled Labor
WO.06.8450 Bedding | Pipe Laying | Surrounding 30 0.08/d 2.50 Charge Hand
WO.06.8450 Bedding | Pipe Laying | Surrounding 30 27.00/d 810.00 Pipes : Nomibal bore 200mm
WO.06.8370 Blinding | Waterproofing 30 2.00/d 60.00 Unskilled Labor
WO.06.8370 Blinding | Waterproofing 30 1.00/d 30.00 Mason
WO.06.8370 Blinding | Waterproofing 30 0.20/d 6.00 Charge Hand
WO.06.8190 CCTV Test 30 2.00/d 60.00 Unskilled Labor
WO.06.8190 CCTV Test 30 0.02/d 0.50 Charge Hand
WO.06.8310 Concrete for Foundation Manhole 30 2.00/d 60.00 Unskilled Labor
WO.06.8310 Concrete for Foundation Manhole 30 2.00/d 60.00 Carpenter
WO.06.8310 Concrete for Foundation Manhole 30 2.00/d 60.00 Mason
WO.06.8310 Concrete for Foundation Manhole 30 4.00/d 120.00 Steel Fixer
WO.06.8310 Concrete for Foundation Manhole 30 0.08/d 2.50 Charge Hand
WO.06.8310 Concrete for Foundation Manhole 30 1.30/d 39.00 Manhole - Concrete Base
WO.06.8330 Concrete for Wall Manhole 30 2.00/d 60.00 Unskilled Labor
WO.06.8330 Concrete for Wall Manhole 30 0.08/d 2.50 Charge Hand
WO.06.8330 Concrete for Wall Manhole 30 2.00/d 60.00 Mason
WO.06.8330 Concrete for Wall Manhole 30 1.30/d 39.00 SWD: MH Wall
WO.06.8210 Concreting Protection - Capping 30 2.00/d 60.00 Carpenter
WO.06.8210 Concreting Protection - Capping 30 2.00/d 60.00 Unskilled Labor
WO.06.8210 Concreting Protection - Capping 30 2.00/d 60.00 Mason
WO.06.8210 Concreting Protection - Capping 30 0.02/d 0.50 Charge Hand
WO.06.8600 De-watering Works 30 2.00/d 60.00 Unskilled Labor
WO.06.8600 De-watering Works 30 0.50/d 15.00 Charge Hand
WO.06.8220 Excavation | Disposal 30 55.27/d 1658.00 Excavation LM
WO.06.8220 Excavation | Disposal 30 2.00/d 60.00 Unskilled Labor
WO.06.8220 Excavation | Disposal 30 3.00/d 90.00 Excavator: Hammer
WO.06.8220 Excavation | Disposal 30 1.00/d 30.00 Excavator: Bucket
WO.06.8360 Excavation | Disposal 30 2.00/d 60.00 Unskilled Labor

© Oracle Corporation Page 13 of 21


07-Mar-21 13:11
Activity ID Activity Name Estimated Productivity Budgeted Units Resource Name
Duration

WO.06.8360 Excavation | Disposal 30 1.00/d 30.00 Excavator: Hammer


WO.06.8360 Excavation | Disposal 30 1.00/d 30.00 Excavator: Bucket
WO.06.8220 Excavation | Disposal 30 0.13/d 4.00 Charge Hand
WO.06.8360 Excavation | Disposal 30 0.17/d 5.00 Charge Hand
WO.06.8360 Excavation | Disposal 30 1.30/d 39.00 SW-Manholes
WO.06.8430 Excavation | Gully Installation 30 2.00/d 60.00 Unskilled Labor
WO.06.8430 Excavation | Gully Installation 30 2.33/d 70.00 Mason
WO.06.8430 Excavation | Gully Installation 30 2.13/d 64.00 Gully: Precast
WO.06.8430 Excavation | Gully Installation 30 0.18/d 5.50 Charge Hand
WO.06.8350 External Waterproofing 30 2.00/d 60.00 Unskilled Labor
WO.06.8350 External Waterproofing 30 1.00/d 30.00 Mason
WO.06.8350 External Waterproofing 30 0.08/d 2.50 Charge Hand
WO.06.8320 Installation of Concrete Slab Cover 30 2.00/d 60.00 Unskilled Labor
WO.06.8320 Installation of Concrete Slab Cover 30 0.08/d 2.50 Charge Hand
WO.06.8320 Installation of Concrete Slab Cover 30 1.30/d 39.00 SWD: Concrete Slab Cover
WO.06.8390 Installation of DI Cover 30 2.00/d 60.00 Mason
WO.06.8390 Installation of DI Cover 30 2.00/d 60.00 Unskilled Labor
WO.06.8390 Installation of DI Cover 30 1.30/d 39.00 DI Cover
WO.06.8390 Installation of DI Cover 30 0.13/d 4.00 Charge Hand
WO.06.8460 Installation of Gully Cover | Frame 30 2.00/d 60.00 Unskilled Labor
WO.06.8460 Installation of Gully Cover | Frame 30 0.37/d 11.00 Charge Hand
WO.06.8460 Installation of Gully Cover | Frame 30 2.13/d 64.00 Gully Cover | Frame
WO.06.8380 Internal Finishing 30 2.00/d 60.00 Unskilled Labor
WO.06.8380 Internal Finishing 30 2.00/d 60.00 Mason
WO.06.8380 Internal Finishing 30 0.17/d 5.00 Charge Hand
WO.06.8230 Leveling | Bedding 30 2.00/d 60.00 Unskilled Labor
WO.06.8230 Leveling | Bedding 30 55.27/d 1658.00 Bedding LM
WO.06.8230 Leveling | Bedding 30 0.17/d 5.00 Charge Hand
WO.06.8170 Pipe Laying 30 2.00/d 60.00 Unskilled Labor
WO.06.8170 Pipe Laying 30 2.00/d 60.00 Pipe Fitter
WO.06.8170 Pipe Laying 30 55.27/d 1658.00 Wet - Pipe Laying LM
WO.06.8170 Pipe Laying 30 1.00/d 30.00 Mobile Crane
WO.06.8170 Pipe Laying 30 0.17/d 5.00 Charge Hand
WO.06.8180 Surrounding works 30 2.00/d 60.00 Unskilled Labor
WO.06.8180 Surrounding works 30 55.27/d 1658.00 Sand Surround LM
WO.06.8180 Surrounding works 30 1.04/d 31.32 Plate Compactor
WO.06.8180 Surrounding works 30 1.00/d 30.00 Tipper 6 Wheel Truck
WO.06.8180 Surrounding works 30 0.07/d 2.00 Charge Hand
WO.06.8440 Trench Excavation | Dis posal 30 2.00/d 60.00 Unskilled Labor
WO.06.8440 Trench Excavation | Dis posal 30 1.00/d 30.00 Excavator: Hammer
WO.06.8440 Trench Excavation | Dis posal 4 1.00/d 4.13 Excavator: Bucket
WO.06.8440 Trench Excavation | Dis posal 30 0.17/d 5.00 Charge Hand
WO.06.8440 Trench Excavation | Dis posal 30 27.00/d 810.00 Excavation LM
SA032.01. (1-6).CON.06.P2.S3 Phase 02: Stage 3 (Ch.0+100 to 1+500) 57 ---
WO.06.8990 Backfilling | Compaction 18 2.00/d 36.00 Unskilled Labor
WO.06.8990 Backfilling | Compaction 18 0.28/d 5.00 JCB
WO.06.8990 Backfilling | Compaction 18 1.04/d 18.79 Plate Compactor
WO.06.8990 Backfilling | Compaction 4 1.04/d 4.31 Roller Compactor: 2Ton
WO.06.8990 Backfilling | Compaction 18 0.28/d 5.00 Charge Hand
WO.06.8990 Backfilling | Compaction 18 52.22/d 940.00 Backfilling LM
WO.06.8970 Bedding | Pipe Laying | Surrounding 18 2.00/d 36.00 Unskilled Labor
WO.06.8970 Bedding | Pipe Laying | Surrounding 18 2.00/d 36.00 Pipe Fitter
WO.06.8970 Bedding | Pipe Laying | Surrounding 18 0.14/d 2.50 Charge Hand
WO.06.8970 Bedding | Pipe Laying | Surrounding 18 52.22/d 940.00 Pipes : Nomibal bore 200mm
WO.06.9000 Excavation | Gully Installation 18 2.00/d 36.00 Unskilled Labor
WO.06.9000 Excavation | Gully Installation 18 1.00/d 18.00 Mason
WO.06.9000 Excavation | Gully Installation 18 4.17/d 75.00 Gully: Precast
WO.06.9000 Excavation | Gully Installation 18 0.31/d 5.50 Charge Hand
WO.06.9030 Installation of Gully Cover | Frame 18 2.00/d 36.00 Unskilled Labor
WO.06.9030 Installation of Gully Cover | Frame 18 0.61/d 11.00 Charge Hand
WO.06.9030 Installation of Gully Cover | Frame 18 4.17/d 75.00 Gully Cover | Frame
WO.06.9010 Trench Excavation | Dis posal 18 2.00/d 36.00 Unskilled Labor
WO.06.9010 Trench Excavation | Dis posal 18 1.00/d 18.00 Excavator: Hammer
WO.06.9010 Trench Excavation | Dis posal 4 1.00/d 4.13 Excavator: Bucket
WO.06.9010 Trench Excavation | Dis posal 18 0.28/d 5.00 Charge Hand
WO.06.9010 Trench Excavation | Dis posal 18 52.22/d 940.00 Excavation LM

Treated Sewer Effluent (TSE) 354 ---


SA032.01. (1-6).CON.06.P1.S1 Phase 01: Stage 1 Carriage Way (Ch.1+000 to 1+550) 38 ---
WO.06.2250 Backfilling | Compaction 22 25.00/d 550.00 Backfilling LM

© Oracle Corporation Page 14 of 21


07-Mar-21 13:11
Activity ID Activity Name Estimated Productivity Budgeted Units Resource Name
Duration

WO.06.2250 Backfilling | Compaction 22 2.00/d 44.00 Unskilled Labor


WO.06.2250 Backfilling | Compaction 22 0.57/d 12.50 JCB
WO.06.2250 Backfilling | Compaction 22 1.04/d 22.97 Plate Compactor
WO.06.2250 Backfilling | Compaction 22 1.04/d 22.97 Roller Compactor: 2Ton
WO.06.2250 Backfilling | Compaction 22 0.30/d 6.50 Charge Hand
WO.06.1910 Concreting Ducts 18 1.67/d 30.00 Unskilled Labor
WO.06.1910 Concreting Ducts 18 2.00/d 36.00 Mason
WO.06.1910 Concreting Ducts 18 0.14/d 2.50 Charge Hand
WO.06.1910 Concreting Ducts 18 5.78/d 104.00 TSE Duct
WO.06.1480 Excavation | Disposal 18 30.56/d 550.00 Excavation LM
WO.06.1480 Excavation | Disposal 18 2.00/d 36.00 Unskilled Labor
WO.06.1480 Excavation | Disposal 18 3.00/d 54.00 Excavator: Hammer
WO.06.1480 Excavation | Disposal 18 1.00/d 18.00 Excavator: Bucket
WO.06.1480 Excavation | Disposal 18 0.78/d 14.00 Charge Hand
WO.06.1320 Leveling | Bedding 24 1.25/d 30.00 Unskilled Labor
WO.06.1320 Leveling | Bedding 24 22.92/d 550.00 Bedding LM
WO.06.1320 Leveling | Bedding 24 0.10/d 2.50 Charge Hand
WO.06.1760 Pipe Laying 20 2.00/d 40.00 Unskilled Labor
WO.06.1760 Pipe Laying 20 2.00/d 40.00 Pipe Fitter
WO.06.1760 Pipe Laying 20 27.50/d 550.00 Wet - Pipe Laying LM
WO.06.1760 Pipe Laying 20 1.00/d 20.00 Mobile Crane
WO.06.1760 Pipe Laying 20 0.35/d 7.00 Charge Hand
WO.06.1960 PressureTest 21 1.17/d 24.00 Unskilled Labor
WO.06.1960 PressureTest 21 2.00/d 41.00 Pipe Fitter
WO.06.1960 PressureTest 21 0.15/d 3.00 Charge Hand
WO.06.2180 Surrounding Works 19 2.00/d 38.00 Unskilled Labor
WO.06.2180 Surrounding Works 19 28.95/d 550.00 Sand Surround LM
WO.06.2180 Surrounding Works 19 1.04/d 19.84 Plate Compactor
WO.06.2180 Surrounding Works 19 1.00/d 19.00 Tipper 6 Wheel Truck
WO.06.2180 Surrounding Works 19 0.34/d 6.50 Charge Hand
168
SA032.01. (1-6).CON.06.P1.S2 Phase 01: Stage 2 Carriage Way (Ch.1+550 to 1+908) ---
WO.06.3770 Backfilling | Compaction 32 21.88/d 700.00 Backfilling LM
WO.06.3770 Backfilling | Compaction 32 2.00/d 64.00 Unskilled Labor
WO.06.3770 Backfilling | Compaction 32 0.12/d 3.75 JCB
WO.06.3770 Backfilling | Compaction 32 1.04/d 33.41 Plate Compactor
WO.06.3770 Backfilling | Compaction 32 1.04/d 33.41 Roller Compactor: 2Ton
WO.06.3770 Backfilling | Compaction 32 0.13/d 4.00 Charge Hand
WO.06.3560 Concreting Ducts 32 2.00/d 64.00 Carpenter
WO.06.3560 Concreting Ducts 32 0.94/d 30.00 Unskilled Labor
WO.06.3560 Concreting Ducts 32 2.00/d 64.00 Mason
WO.06.3560 Concreting Ducts 32 0.08/d 2.50 Charge Hand
WO.06.3560 Concreting Ducts 32 3.25/d 104.00 TSE Duct
WO.06.2790 Excavation | Disposal 60 11.67/d 700.00 Excavation LM
WO.06.2790 Excavation | Disposal 60 0.80/d 48.00 Unskilled Labor
WO.06.2790 Excavation | Disposal 60 1.60/d 96.00 Excavator: Hammer
WO.06.2790 Excavation | Disposal 60 0.53/d 32.00 Excavator: Bucket
WO.06.2790 Excavation | Disposal 60 0.13/d 8.00 Charge Hand
WO.06.2830 Leveling | Bedding 32 0.75/d 24.00 Unskilled Labor
WO.06.2830 Leveling | Bedding 32 21.88/d 700.00 Bedding LM
WO.06.2830 Leveling | Bedding 32 0.13/d 4.00 Charge Hand
WO.06.3320 Pipe Laying 32 1.38/d 44.00 Unskilled Labor
WO.06.3320 Pipe Laying 32 2.00/d 64.00 Pipe Fitter
WO.06.3320 Pipe Laying 32 21.88/d 700.00 Wet - Pipe Laying LM
WO.06.3320 Pipe Laying 32 1.00/d 32.00 Mobile Crane
WO.06.3320 Pipe Laying 32 0.34/d 11.00 Charge Hand
WO.06.3510 PressureTest 32 0.50/d 16.00 Unskilled Labor
WO.06.3510 PressureTest 32 2.00/d 64.00 Pipe Fitter
WO.06.3510 PressureTest 32 0.06/d 2.00 Charge Hand
WO.06.3710 Surrounding Works 32 0.63/d 20.00 Unskilled Labor
WO.06.3710 Surrounding Works 32 21.88/d 700.00 Sand Surround LM
WO.06.3710 Surrounding Works 32 1.04/d 33.41 Plate Compactor
WO.06.3710 Surrounding Works 32 1.00/d 32.00 Tipper 6 Wheel Truck
WO.06.3710 Surrounding Works 32 0.16/d 5.00 Charge Hand
SA032.01. (1-6).CON.06.P1.S3N Phase 01: Stage 3 (Ch.1+000 to 1+908) 60 ---
WO.06.4020 Backfilling | Compaction 5 2.00/d 10.00 Unskilled Labor
WO.06.4020 Backfilling | Compaction 5 0.80/d 4.00 JCB
WO.06.4020 Backfilling | Compaction 4 1.04/d 3.92 Plate Compactor
WO.06.4020 Backfilling | Compaction 5 1.04/d 5.22 Roller Compactor: 2Ton
WO.06.4020 Backfilling | Compaction 5 0.80/d 4.00 Charge Hand

© Oracle Corporation Page 15 of 21


07-Mar-21 13:11
Activity ID Activity Name Estimated Productivity Budgeted Units Resource Name
Duration

WO.06.4020 Backfilling | Compaction 5 2.00/d 10.00 TSE Chamber Backfilling


WO.06.3210 Blinding | Waterproofing 25 2.00/d 50.00 Unskilled Labor
WO.06.3210 Blinding | Waterproofing 25 0.10/d 2.50 Charge Hand
WO.06.3430 Concrete for Foundation Chamber 25 1.20/d 30.00 Unskilled Labor
WO.06.3430 Concrete for Foundation Chamber 25 2.00/d 50.00 Carpenter
WO.06.3430 Concrete for Foundation Chamber 25 4.00/d 100.00 Steel Fixer
WO.06.3430 Concrete for Foundation Chamber 25 2.00/d 50.00 Mason
WO.06.3430 Concrete for Foundation Chamber 25 0.10/d 2.50 Charge Hand
WO.06.3430 Concrete for Foundation Chamber 25 0.40/d 10.00 TSE Chamber base
WO.06.3600 Concrete for Wall Chamber 25 1.20/d 30.00 Unskilled Labor
WO.06.3600 Concrete for Wall Chamber 25 2.00/d 50.00 Carpenter
WO.06.3600 Concrete for Wall Chamber 25 2.00/d 50.00 Mason
WO.06.3600 Concrete for Wall Chamber 25 4.00/d 100.00 Steel Fixer
WO.06.3600 Concrete for Wall Chamber 25 0.10/d 2.50 Charge Hand
WO.06.3600 Concrete for Wall Chamber 25 0.40/d 10.00 TSE Chamber wall
WO.06.3020 Excavation | Disposal 25 0.96/d 24.00 Unskilled Labor
WO.06.3020 Excavation | Disposal 25 1.00/d 25.00 Excavator: Hammer
WO.06.3020 Excavation | Disposal 25 1.00/d 25.00 Excavator: Bucket
WO.06.3020 Excavation | Disposal 25 0.16/d 4.00 Charge Hand
WO.06.3020 Excavation | Disposal 25 0.40/d 10.00 TSE Chamber
WO.06.3780 External Waterproofing 2 2.00/d 4.00 Unskilled Labor
WO.06.3780 External Waterproofing 2 1.00/d 2.00 Mason
WO.06.3780 External Waterproofing 2 2.00/d 4.00 Charge Hand
WO.06.4090 Fitting | Valves Installation | Internal Finishing 5 1.60/d 8.00 Unskilled Labor
WO.06.4090 Fitting | Valves Installation | Internal Finishing 5 0.80/d 4.00 Charge Hand
WO.06.3910 Installation of Concrete Slab Cover 2 2.00/d 4.00 Unskilled Labor
WO.06.3910 Installation of Concrete Slab Cover 2 2.00/d 4.00 Charge Hand
WO.06.3910 Installation of Concrete Slab Cover 2 5.00/d 10.00 TSE Chamber Cover Slab
WO.06.4270 Installation of DI Cover 2 2.00/d 4.00 Mason
WO.06.4270 Installation of DI Cover 2 2.00/d 4.00 Unskilled Labor
WO.06.4270 Installation of DI Cover 2 2.00/d 4.00 Charge Hand
WO.06.4270 Installation of DI Cover 2 5.00/d 10.00 TSE DI Cover
SA032.01. (1-6).CON.06.P2.S1 Phase 02: Stage 1 Garrage Way (Ch.0+100 to 0+500) 58 ---
WO.06.7680 Backfilling | Compaction 22 20.45/d 450.00 Backfilling LM
WO.06.7680 Backfilling | Compaction 22 2.00/d 44.00 Unskilled Labor
WO.06.7680 Backfilling | Compaction 22 0.57/d 12.50 JCB
WO.06.7680 Backfilling | Compaction 22 1.04/d 22.97 Plate Compactor
WO.06.7680 Backfilling | Compaction 22 1.04/d 22.97 Roller Compactor: 2Ton
WO.06.7680 Backfilling | Compaction 22 0.30/d 6.50 Charge Hand
WO.06.7690 Concreting Ducts 18 1.67/d 30.00 Unskilled Labor
WO.06.7690 Concreting Ducts 18 2.00/d 36.00 Mason
WO.06.7690 Concreting Ducts 18 0.14/d 2.50 Charge Hand
WO.06.7690 Concreting Ducts 18 5.83/d 105.00 TSE Duct
WO.06.7700 Excavation | Disposal 18 25.00/d 450.00 Excavation LM
WO.06.7700 Excavation | Disposal 18 2.00/d 36.00 Unskilled Labor
WO.06.7700 Excavation | Disposal 18 3.00/d 54.00 Excavator: Hammer
WO.06.7700 Excavation | Disposal 18 1.00/d 18.00 Excavator: Bucket
WO.06.7700 Excavation | Disposal 18 0.78/d 14.00 Charge Hand
WO.06.7710 Leveling | Bedding 24 1.25/d 30.00 Unskilled Labor
WO.06.7710 Leveling | Bedding 24 18.75/d 450.00 Bedding LM
WO.06.7710 Leveling | Bedding 24 0.10/d 2.50 Charge Hand
WO.06.7650 Pipe Laying 20 2.00/d 40.00 Unskilled Labor
WO.06.7650 Pipe Laying 20 2.00/d 40.00 Pipe Fitter
WO.06.7650 Pipe Laying 20 22.50/d 450.00 Wet - Pipe Laying LM
WO.06.7650 Pipe Laying 20 1.00/d 20.00 Mobile Crane
WO.06.7650 Pipe Laying 20 0.35/d 7.00 Charge Hand
WO.06.7670 PressureTest 21 1.17/d 24.00 Unskilled Labor
WO.06.7670 PressureTest 21 2.00/d 41.00 Pipe Fitter
WO.06.7670 PressureTest 21 0.15/d 3.00 Charge Hand
WO.06.7660 Surrounding Works 19 2.00/d 38.00 Unskilled Labor
WO.06.7660 Surrounding Works 19 23.68/d 450.00 Sand Surround LM
WO.06.7660 Surrounding Works 19 1.04/d 19.84 Plate Compactor
WO.06.7660 Surrounding Works 19 1.00/d 19.00 Tipper 6 Wheel Truck
WO.06.7660 Surrounding Works 19 0.34/d 6.50 Charge Hand
SA032.01. (1-6).CON.06.P2.S2 Phase 02: Stage 2 Garrage Way (Ch.0+500 to 1+000) 83 ---
WO.06.8270 Backfilling | Compaction 32 26.88/d 860.00 Backfilling LM
WO.06.8270 Backfilling | Compaction 32 2.00/d 64.00 Unskilled Labor
WO.06.8270 Backfilling | Compaction 32 0.12/d 3.75 JCB
WO.06.8270 Backfilling | Compaction 32 1.04/d 33.41 Plate Compactor

© Oracle Corporation Page 16 of 21


07-Mar-21 13:11
Activity ID Activity Name Estimated Productivity Budgeted Units Resource Name
Duration

WO.06.8270 Backfilling | Compaction 32 1.04/d 33.41 Roller Compactor: 2Ton


WO.06.8270 Backfilling | Compaction 32 0.13/d 4.00 Charge Hand
WO.06.8280 Concreting Ducts 32 2.00/d 64.00 Carpenter
WO.06.8280 Concreting Ducts 32 0.94/d 30.00 Unskilled Labor
WO.06.8280 Concreting Ducts 32 2.00/d 64.00 Mason
WO.06.8280 Concreting Ducts 32 0.08/d 2.50 Charge Hand
WO.06.8280 Concreting Ducts 32 3.28/d 105.00 TSE Duct
WO.06.8290 Excavation | Disposal 32 26.88/d 860.00 Excavation LM
WO.06.8290 Excavation | Disposal 32 1.50/d 48.00 Unskilled Labor
WO.06.8290 Excavation | Disposal 32 3.00/d 96.00 Excavator: Hammer
WO.06.8290 Excavation | Disposal 32 1.00/d 32.00 Excavator: Bucket
WO.06.8290 Excavation | Disposal 32 0.25/d 8.00 Charge Hand
WO.06.8300 Leveling | Bedding 32 0.75/d 24.00 Unskilled Labor
WO.06.8300 Leveling | Bedding 32 26.88/d 860.00 Bedding LM
WO.06.8300 Leveling | Bedding 32 0.13/d 4.00 Charge Hand
WO.06.8240 Pipe Laying 32 1.38/d 44.00 Unskilled Labor
WO.06.8240 Pipe Laying 32 2.00/d 64.00 Pipe Fitter
WO.06.8240 Pipe Laying 32 26.88/d 860.00 Wet - Pipe Laying LM
WO.06.8240 Pipe Laying 32 1.00/d 32.00 Mobile Crane
WO.06.8240 Pipe Laying 32 0.34/d 11.00 Charge Hand
WO.06.8260 PressureTest 32 0.50/d 16.00 Unskilled Labor
WO.06.8260 PressureTest 32 2.00/d 64.00 Pipe Fitter
WO.06.8260 PressureTest 32 0.06/d 2.00 Charge Hand
WO.06.8250 Surrounding Works 32 0.63/d 20.00 Unskilled Labor
WO.06.8250 Surrounding Works 32 26.88/d 860.00 Sand Surround LM
WO.06.8250 Surrounding Works 32 1.04/d 33.41 Plate Compactor
WO.06.8250 Surrounding Works 32 1.00/d 32.00 Tipper 6 Wheel Truck
WO.06.8250 Surrounding Works 32 0.16/d 5.00 Charge Hand
SA032.01. (1-6).CON.06.P2.S3 Phase 02: Stage 3 (Ch.0+100 to 1+500) 84 ---
WO.06.8500 Backfilling | Compaction 5 2.00/d 10.00 Unskilled Labor
WO.06.8500 Backfilling | Compaction 5 0.80/d 4.00 JCB
WO.06.8500 Backfilling | Compaction 4 1.04/d 3.92 Plate Compactor
WO.06.8500 Backfilling | Compaction 5 1.04/d 5.22 Roller Compactor: 2Ton
WO.06.8500 Backfilling | Compaction 5 0.80/d 4.00 Charge Hand
WO.06.8500 Backfilling | Compaction 5 2.40/d 12.00 TSE Chamber Backfilling
WO.06.8530 Blinding | Waterproofing 25 0.40/d 10.00 Unskilled Labor
WO.06.8530 Blinding | Waterproofing 25 0.10/d 2.50 Charge Hand
WO.06.8470 Concrete for Foundation Chamber 25 1.20/d 30.00 Unskilled Labor
WO.06.8470 Concrete for Foundation Chamber 25 2.00/d 50.00 Carpenter
WO.06.8470 Concrete for Foundation Chamber 25 4.00/d 100.00 Steel Fixer
WO.06.8470 Concrete for Foundation Chamber 25 2.00/d 50.00 Mason
WO.06.8470 Concrete for Foundation Chamber 25 0.10/d 2.50 Charge Hand
WO.06.8470 Concrete for Foundation Chamber 25 0.48/d 12.00 TSE Chamber base
WO.06.8490 Concrete for Wall Chamber 25 1.20/d 30.00 Unskilled Labor
WO.06.8490 Concrete for Wall Chamber 25 2.00/d 50.00 Carpenter
WO.06.8490 Concrete for Wall Chamber 25 2.00/d 50.00 Mason
WO.06.8490 Concrete for Wall Chamber 25 4.00/d 100.00 Steel Fixer
WO.06.8490 Concrete for Wall Chamber 25 0.10/d 2.50 Charge Hand
WO.06.8490 Concrete for Wall Chamber 25 0.48/d 12.00 TSE Chamber wall
WO.06.8520 Excavation | Disposal 25 0.96/d 24.00 Unskilled Labor
WO.06.8520 Excavation | Disposal 25 1.00/d 25.00 Excavator: Hammer
WO.06.8520 Excavation | Disposal 25 1.00/d 25.00 Excavator: Bucket
WO.06.8520 Excavation | Disposal 25 0.16/d 4.00 Charge Hand
WO.06.8520 Excavation | Disposal 25 0.48/d 12.00 TSE Chamber
WO.06.8510 External Waterproofing 2 2.00/d 4.00 Unskilled Labor
WO.06.8510 External Waterproofing 2 2.00/d 4.00 Charge Hand
WO.06.8540 Fitting | Valves Installation | Internal Finishing 5 1.60/d 8.00 Unskilled Labor
WO.06.8540 Fitting | Valves Installation | Internal Finishing 5 0.80/d 4.00 Charge Hand
WO.06.8480 Installation of Concrete Slab Cover 2 2.00/d 4.00 Unskilled Labor
WO.06.8480 Installation of Concrete Slab Cover 2 2.00/d 4.00 Charge Hand
WO.06.8480 Installation of Concrete Slab Cover 2 6.00/d 12.00 TSE Chamber Cover Slab
WO.06.8550 Installation of DI Cover 2 2.00/d 4.00 Mason
WO.06.8550 Installation of DI Cover 2 2.00/d 4.00 Unskilled Labor
WO.06.8550 Installation of DI Cover 2 2.00/d 4.00 Charge Hand
WO.06.8550 Installation of DI Cover 2 6.00/d 12.00 TSE DI Cover

QAF 146 ---


SA032.01. (1-6).CON.06.P1.S1 Phase 01: Stage 1 Carriage Way (Ch.1+000 to 1+550) 21 ---
WO.06.2320 Duct Works: QAF 18 0.21/d 3.75 JCB
WO.06.2320 Duct Works: QAF 18 1.04/d 18.79 Plate Compactor

© Oracle Corporation Page 17 of 21


07-Mar-21 13:11
Activity ID Activity Name Estimated Productivity Budgeted Units Resource Name
Duration

WO.06.2320 Duct Works: QAF 18 1.04/d 18.79 Roller Compactor: 2Ton


WO.06.2320 Duct Works: QAF 18 2.00/d 36.00 Unskilled Labor
WO.06.2320 Duct Works: QAF 18 1.00/d 18.00 Bobcat
WO.06.2320 Duct Works: QAF 18 0.22/d 4.00 Charge Hand
WO.06.2320 Duct Works: QAF 18 1.22/d 22.00 QAF Ducts
SA032.01. (1-6).CON.06.P1.S2 Phase 01: Stage 2 Carriage Way (Ch.1+550 to 1+908)21 ---
WO.06.7160 Duct Works: QAF 18 0.21/d 3.75 JCB
WO.06.7160 Duct Works: QAF 18 1.04/d 18.79 Plate Compactor
WO.06.7160 Duct Works: QAF 18 1.04/d 18.79 Roller Compactor: 2Ton
WO.06.7160 Duct Works: QAF 18 2.00/d 36.00 Unskilled Labor
WO.06.7160 Duct Works: QAF 18 1.00/d 18.00 Bobcat
WO.06.7160 Duct Works: QAF 18 0.22/d 4.00 Charge Hand
WO.06.7160 Duct Works: QAF 18 1.22/d 22.00 QAF Ducts
SA032.01. (1-6).CON.06.P1.S3N Phase 01: Stage 3 (Ch.1+000 to 1+908) 21 ---
WO.06.7260 Duct Works: QAF 18 0.21/d 3.75 JCB
WO.06.7260 Duct Works: QAF 18 1.04/d 18.79 Plate Compactor
WO.06.7260 Duct Works: QAF 18 1.04/d 18.79 Roller Compactor: 2Ton
WO.06.7260 Duct Works: QAF 18 2.00/d 36.00 Unskilled Labor
WO.06.7260 Duct Works: QAF 18 1.00/d 18.00 Bobcat
WO.06.7260 Duct Works: QAF 18 0.22/d 4.00 Charge Hand
WO.06.7260 Duct Works: QAF 18 1.22/d 22.00 QAF Ducts
SA032.01. (1-6).CON.06.P2.S1 Phase 02: Stage 1 Garrage Way (Ch.0+100 to 0+500) 21 ---
WO.06.7390 Duct Works: QAF 18 0.21/d 3.75 JCB
WO.06.7390 Duct Works: QAF 18 1.04/d 18.79 Plate Compactor
WO.06.7390 Duct Works: QAF 18 1.04/d 18.79 Roller Compactor: 2Ton
WO.06.7390 Duct Works: QAF 18 2.00/d 36.00 Unskilled Labor
WO.06.7390 Duct Works: QAF 18 1.00/d 18.00 Bobcat
WO.06.7390 Duct Works: QAF 18 0.22/d 4.00 Charge Hand
WO.06.7390 Duct Works: QAF 18 1.22/d 22.00 QAF Ducts
SA032.01. (1-6).CON.06.P2.S2 Phase 02: Stage 2 Garrage Way (Ch.0+500 to 1+000) 21 ---
WO.06.8630 Duct Works: QAF 18 0.21/d 3.75 JCB
WO.06.8630 Duct Works: QAF 18 1.04/d 18.79 Plate Compactor
WO.06.8630 Duct Works: QAF 18 1.04/d 18.79 Roller Compactor: 2Ton
WO.06.8630 Duct Works: QAF 18 2.00/d 36.00 Unskilled Labor
WO.06.8630 Duct Works: QAF 18 1.00/d 18.00 Bobcat
WO.06.8630 Duct Works: QAF 18 0.22/d 4.00 Charge Hand
WO.06.8630 Duct Works: QAF 18 1.22/d 22.00 QAF Ducts
SA032.01. (1-6).CON.06.P2.S3 Phase 02: Stage 3 (Ch.0+100 to 1+500) 21 ---
WO.06.8750 Duct Works: QAF 18 0.21/d 3.75 JCB
WO.06.8750 Duct Works: QAF 18 1.04/d 18.79 Plate Compactor
WO.06.8750 Duct Works: QAF 18 1.04/d 18.79 Roller Compactor: 2Ton
WO.06.8750 Duct Works: QAF 18 2.00/d 36.00 Unskilled Labor
WO.06.8750 Duct Works: QAF 18 1.00/d 18.00 Bobcat
WO.06.8750 Duct Works: QAF 18 0.22/d 4.00 Charge Hand
WO.06.8750 Duct Works: QAF 18 1.22/d 22.00 QAF Ducts

QNBN 142 ---


SA032.01. (1-6).CON.06.P1.S1 Phase 01: Stage 1 Carriage Way (Ch.1+000 to 1+550) 20 ---
WO.06.2780 QNBN Chambers | Ducts 18 2.00/d 36.00 Carpenter
WO.06.2780 QNBN Chambers | Ducts 18 2.00/d 36.00 Mason
WO.06.2780 QNBN Chambers | Ducts 18 2.00/d 36.00 Unskilled Labor
WO.06.2780 QNBN Chambers | Ducts 18 0.78/d 14.00 Charge Hand
WO.06.2780 QNBN Chambers | Ducts 18 5.17/d 93.00 QNBN Duct
SA032.01. (1-6).CON.06.P1.S2 Phase 01: Stage 2 Carriage Way (Ch.1+550 to 1+908)21 ---
WO.06.7170 QNBN Chambers | Ducts 18 2.00/d 36.00 Carpenter
WO.06.7170 QNBN Chambers | Ducts 18 2.00/d 36.00 Mason
WO.06.7170 QNBN Chambers | Ducts 18 2.00/d 36.00 Unskilled Labor
WO.06.7170 QNBN Chambers | Ducts 18 0.78/d 14.00 Charge Hand
WO.06.7170 QNBN Chambers | Ducts 18 5.17/d 93.00 QNBN Duct
SA032.01. (1-6).CON.06.P1.S3N Phase 01: Stage 3 (Ch.1+000 to 1+908) 21 ---
WO.06.7290 QNBN Chambers | Ducts 18 2.00/d 36.00 Carpenter
WO.06.7290 QNBN Chambers | Ducts 18 2.00/d 36.00 Mason
WO.06.7290 QNBN Chambers | Ducts 18 2.00/d 36.00 Unskilled Labor
WO.06.7290 QNBN Chambers | Ducts 18 0.78/d 14.00 Charge Hand
WO.06.7290 QNBN Chambers | Ducts 18 5.17/d 93.00 QNBN Duct
WO.06.7290 QNBN Chambers | Ducts 18 0.11/d 2.00 QNBN Chamber
SA032.01. (1-6).CON.06.P2.S1 Phase 02: Stage 1 Garrage Way (Ch.0+100 to 0+500) 21 ---
WO.06.7880 QNBN Chambers | Ducts 18 2.00/d 36.00 Carpenter
WO.06.7880 QNBN Chambers | Ducts 18 2.00/d 36.00 Mason
WO.06.7880 QNBN Chambers | Ducts 18 2.00/d 36.00 Unskilled Labor

© Oracle Corporation Page 18 of 21


07-Mar-21 13:11
Activity ID Activity Name Estimated Productivity Budgeted Units Resource Name
Duration

WO.06.7880 QNBN Chambers | Ducts 18 0.78/d 14.00 Charge Hand


WO.06.7880 QNBN Chambers | Ducts 18 5.17/d 93.00 QNBN Duct
SA032.01. (1-6).CON.06.P2.S2 Phase 02: Stage 2 Garrage Way (Ch.0+500 to 1+000) 21 ---
WO.06.8660 QNBN Chambers | Ducts 18 2.00/d 36.00 Carpenter
WO.06.8660 QNBN Chambers | Ducts 18 2.00/d 36.00 Mason
WO.06.8660 QNBN Chambers | Ducts 18 2.00/d 36.00 Unskilled Labor
WO.06.8660 QNBN Chambers | Ducts 18 0.78/d 14.00 Charge Hand
WO.06.8660 QNBN Chambers | Ducts 18 5.17/d 93.00 QNBN Duct
SA032.01. (1-6).CON.06.P2.S3 Phase 02: Stage 3 (Ch.0+100 to 1+500) 21 ---
WO.06.8780 QNBN Chambers | Ducts 18 2.00/d 36.00 Carpenter
WO.06.8780 QNBN Chambers | Ducts 18 2.00/d 36.00 Mason
WO.06.8780 QNBN Chambers | Ducts 18 2.00/d 36.00 Unskilled Labor
WO.06.8780 QNBN Chambers | Ducts 18 0.78/d 14.00 Charge Hand
WO.06.8780 QNBN Chambers | Ducts 18 5.17/d 93.00 QNBN Duct
WO.06.8780 QNBN Chambers | Ducts 18 0.17/d 3.00 QNBN Chamber

Road Lighting 129 ---


SA032.01. (1-6).CON.06.P1.S2 Phase 01: Stage 2 Carriage Way (Ch.1+550 to 1+908)21 ---
WO.06.7200 Duct Works: Street Lighting 18 2.00/d 36.00 Carpenter
WO.06.7200 Duct Works: Street Lighting 18 2.00/d 36.00 Mason
WO.06.7200 Duct Works: Street Lighting 18 2.00/d 36.00 Unskilled Labor
WO.06.7200 Duct Works: Street Lighting 18 0.78/d 14.00 Charge Hand
WO.06.7200 Duct Works: Street Lighting 18 17.89/d 322.00 Street lighting Duct
SA032.01. (1-6).CON.06.P1.S3N Phase 01: Stage 3 (Ch.1+000 to 1+908) 75 ---
WO.06.4710 Cable Pulling | Earthing 12 2.00/d 24.00 Unskilled Labor
WO.06.4710 Cable Pulling | Earthing 12 4.00/d 48.00 Electrician
WO.06.4710 Cable Pulling | Earthing 12 569.33/d 6832.00 LV- Lighting Cable
WO.06.4710 Cable Pulling | Earthing 12 0.75/d 9.00 Charge Hand
WO.06.3620 Concrete Foundation Works 21 2.62/d 55.00 Lighting Poles Nos-Foundation
WO.06.3620 Concrete Foundation Works 21 2.00/d 42.00 Unskilled Labor
WO.06.3620 Concrete Foundation Works 21 2.00/d 42.00 Carpenter
WO.06.3620 Concrete Foundation Works 21 2.00/d 42.00 Mason
WO.06.3620 Concrete Foundation Works 21 4.00/d 84.00 Steel Fixer
WO.06.3620 Concrete Foundation Works 21 0.14/d 3.00 Charge Hand
WO.06.3860 Excavation | Disposal 21 2.00/d 42.00 Unskilled Labor
WO.06.3860 Excavation | Disposal 21 2.00/d 42.00 Excavator: Hammer
WO.06.3860 Excavation | Disposal 21 1.00/d 21.00 Excavator: Bucket
WO.06.3860 Excavation | Disposal 21 1.00/d 21.00 Bobcat
WO.06.3860 Excavation | Disposal 21 0.36/d 7.50 Charge Hand
WO.06.3860 Excavation | Disposal 21 2.62/d 55.00 Street Ligting Excvation
WO.06.4080 Junction Box | Feeder Pillar 12 4.00/d 48.00 Electrician
WO.06.4080 Junction Box | Feeder Pillar 12 2.00/d 24.00 Unskilled Labor
WO.06.4080 Junction Box | Feeder Pillar 12 0.33/d 4.00 Charge Hand
WO.06.4080 Junction Box | Feeder Pillar 12 0.17/d 2.00 Feedrer Piller
WO.06.3940 Removal of Existing Poles 12 4.00/d 48.00 Unskilled Labor
WO.06.3940 Removal of Existing Poles 12 1.00/d 12.00 Charge Hand
WO.06.3940 Removal of Existing Poles 12 1.00/d 12.00 Boom Truck
WO.06.3940 Removal of Existing Poles 12 0.50/d 6.00 Mobile Crane
WO.06.5060 Road Lighting Poles | Luminaries 12 1.00/d 12.00 Mobile Crane
WO.06.5060 Road Lighting Poles | Luminaries 12 2.00/d 24.00 Unskilled Labor
WO.06.5060 Road Lighting Poles | Luminaries 12 0.25/d 3.00 Charge Hand
WO.06.5060 Road Lighting Poles | Luminaries 12 4.58/d 55.00 Road Lighting Pole
SA032.01. (1-6).CON.06.P2.S2 Phase 02: Stage 2 Garrage Way (Ch.0+500 to 1+000) 21 ---
WO.06.8690 Duct Works: Street Lighting 18 2.00/d 36.00 Carpenter
WO.06.8690 Duct Works: Street Lighting 18 2.00/d 36.00 Mason
WO.06.8690 Duct Works: Street Lighting 18 2.00/d 36.00 Unskilled Labor
WO.06.8690 Duct Works: Street Lighting 18 0.78/d 14.00 Charge Hand
WO.06.8690 Duct Works: Street Lighting 18 17.89/d 322.00 Street lighting Duct
SA032.01. (1-6).CON.06.P2.S3 Phase 02: Stage 3 (Ch.0+100 to 1+500) 63 ---
WO.06.7930 Cable Pulling | Earthing 12 2.00/d 24.00 Unskilled Labor
WO.06.7930 Cable Pulling | Earthing 12 4.00/d 48.00 Electrician
WO.06.7930 Cable Pulling | Earthing 12 569.33/d 6832.00 LV- Lighting Cable
WO.06.7930 Cable Pulling | Earthing 12 0.75/d 9.00 Charge Hand
WO.06.7920 Concrete Foundation Works 21 2.67/d 56.00 Lighting Poles Nos-Foundation
WO.06.7920 Concrete Foundation Works 21 2.00/d 42.00 Unskilled Labor
WO.06.7920 Concrete Foundation Works 21 2.00/d 42.00 Carpenter
WO.06.7920 Concrete Foundation Works 21 2.00/d 42.00 Mason
WO.06.7920 Concrete Foundation Works 21 4.00/d 84.00 Steel Fixer
WO.06.7920 Concrete Foundation Works 21 0.14/d 3.00 Charge Hand
WO.06.7940 Excavation | Disposal 21 2.67/d 56.00 Street Ligting Excvation

© Oracle Corporation Page 19 of 21


07-Mar-21 13:11
Activity ID Activity Name Estimated Productivity Budgeted Units Resource Name
Duration

WO.06.7940 Excavation | Disposal 21 2.00/d 42.00 Unskilled Labor


WO.06.7940 Excavation | Disposal 21 2.00/d 42.00 Excavator: Hammer
WO.06.7940 Excavation | Disposal 21 1.00/d 21.00 Excavator: Bucket
WO.06.7940 Excavation | Disposal 21 1.00/d 21.00 Bobcat
WO.06.7940 Excavation | Disposal 21 0.36/d 7.50 Charge Hand
WO.06.7420 Junction Box | Feeder Pillar 12 4.00/d 48.00 Electrician
WO.06.7420 Junction Box | Feeder Pillar 12 2.00/d 24.00 Unskilled Labor
WO.06.7420 Junction Box | Feeder Pillar 12 0.33/d 4.00 Charge Hand
WO.06.7420 Junction Box | Feeder Pillar 12 0.17/d 2.00 Feedrer Piller
WO.06.8560 Removal of Existing Poles 12 2.00/d 24.00 Unskilled Labor
WO.06.8560 Removal of Existing Poles 12 0.08/d 1.00 Charge Hand
WO.06.7950 Road Lighting Poles | Luminaries 12 1.00/d 12.00 Mobile Crane
WO.06.7950 Road Lighting Poles | Luminaries 12 2.00/d 24.00 Unskilled Labor
WO.06.7950 Road Lighting Poles | Luminaries 12 0.25/d 3.00 Charge Hand
WO.06.7950 Road Lighting Poles | Luminaries 12 4.67/d 56.00 Road Lighting Pole

Traffic Signals 101 ---


SA032.01. (1-6).CON.06.P1.S2 Phase 01: Stage 2 Carriage Way (Ch.1+550 to 1+908)70 ---
WO.06.7230 Cabling and Backfilling 12 2.00/d 24.00 Unskilled Labor
WO.06.7230 Cabling and Backfilling 12 0.79/d 9.50 Charge Hand
WO.06.7230 Cabling and Backfilling 12 315.00/d 3780.00 Cable Laying LM
WO.06.7180 Duct Works: Traffic Signal 18 2.00/d 36.00 Carpenter
WO.06.7180 Duct Works: Traffic Signal 18 2.00/d 36.00 Mason
WO.06.7180 Duct Works: Traffic Signal 18 2.00/d 36.00 Unskilled Labor
WO.06.7180 Duct Works: Traffic Signal 18 0.78/d 14.00 Charge Hand
WO.06.7180 Duct Works: Traffic Signal 18 27.61/d 497.00 Traffic Signal Poles 3.7m long (Foundations:CLASS
WO.06.7220 Gantry Foundation 18 1.04/d 18.79 Plate Compactor
WO.06.7220 Gantry Foundation 18 1.78/d 32.00 Unskilled Labor
WO.06.7220 Gantry Foundation 18 0.44/d 8.00 Charge Hand
WO.06.7220 Gantry Foundation 18 0.22/d 4.00 Traffic Signal - Gantry Foundation
WO.06.7240 Gantry Installation 8 1.04/d 8.35 Roller Compactor: 2Ton
WO.06.7240 Gantry Installation 8 2.00/d 16.00 Unskilled Labor
WO.06.7240 Gantry Installation 8 0.94/d 7.50 JCB
WO.06.7240 Gantry Installation 8 1.04/d 8.35 Plate Compactor
WO.06.7240 Gantry Installation 8 0.50/d 4.00 Charge Hand
WO.06.7240 Gantry Installation 8 0.50/d 4.00 Gantries
WO.06.7250 Install Signal Heads | Loop Detector | Feeder Pillar 12 4.00/d 48.00 Unskilled Labor
WO.06.7250 Install Signal Heads | Loop Detector | Feeder Pillar 12 0.79/d 9.50 Charge Hand
WO.06.7250 Install Signal Heads | Loop Detector | Feeder Pillar 12 4.25/d 51.00 Signal Heads
WO.06.7250 Install Signal Heads | Loop Detector | Feeder Pillar 12 0.17/d 2.00 Feedrer Piller
WO.06.7250 Install Signal Heads | Loop Detector | Feeder Pillar 12 2.83/d 34.00 Signal - Loop Detector
WO.06.7250 Install Signal Heads | Loop Detector | Feeder Pillar 12 4.00/d 48.00 Electrician
WO.06.7210 Pole Foundation | Chamber Works 18 2.11/d 38.00 Traffic Signal Chamber
WO.06.7210 Pole Foundation | Chamber Works 18 2.00/d 36.00 Unskilled Labor
WO.06.7210 Pole Foundation | Chamber Works 18 1.00/d 18.00 Excavator: Hammer
WO.06.7210 Pole Foundation | Chamber Works 18 1.00/d 18.00 Excavator: Bucket
WO.06.7210 Pole Foundation | Chamber Works 18 0.44/d 8.00 Charge Hand
WO.06.7210 Pole Foundation | Chamber Works 18 1.17/d 21.00 Signal Poles
SA032.01. (1-6).CON.06.P2.S2 Phase 02: Stage 2 Garrage Way (Ch.0+500 to 1+000) 80 ---
WO.06.8710 Cabling and Backfilling 12 2.00/d 24.00 Unskilled Labor
WO.06.8710 Cabling and Backfilling 12 0.79/d 9.50 Charge Hand
WO.06.8710 Cabling and Backfilling 12 315.00/d 3780.00 Cable Laying LM
WO.06.8670 Duct Works: Traffic Signal 18 27.67/d 498.00 Carpenter
WO.06.8670 Duct Works: Traffic Signal 18 2.00/d 36.00 Mason
WO.06.8670 Duct Works: Traffic Signal 18 2.00/d 36.00 Unskilled Labor
WO.06.8670 Duct Works: Traffic Signal 18 0.78/d 14.00 Charge Hand
WO.06.8670 Duct Works: Traffic Signal 18 0.80/d 14.40 Traffic Signal Poles 3.7m long (Foundations:CLASS
WO.06.8730 Gantry Foundation 18 1.04/d 18.79 Plate Compactor
WO.06.8730 Gantry Foundation 18 1.78/d 32.00 Unskilled Labor
WO.06.8730 Gantry Foundation 18 0.44/d 8.00 Charge Hand
WO.06.8730 Gantry Foundation 18 0.22/d 4.00 Traffic Signal - Gantry Foundation
WO.06.8740 Gantry Installation 8 1.04/d 8.35 Roller Compactor: 2Ton
WO.06.8740 Gantry Installation 8 2.00/d 16.00 Unskilled Labor
WO.06.8740 Gantry Installation 8 0.94/d 7.50 JCB
WO.06.8740 Gantry Installation 8 1.04/d 8.35 Plate Compactor
WO.06.8740 Gantry Installation 8 0.50/d 4.00 Charge Hand
WO.06.8740 Gantry Installation 8 0.80/d 6.40 Gantries
WO.06.8700 Install Signal Heads | Loop Detector | Feeder Pillar 12 4.00/d 48.00 Unskilled Labor
WO.06.8700 Install Signal Heads | Loop Detector | Feeder Pillar 12 0.79/d 9.50 Charge Hand
WO.06.8700 Install Signal Heads | Loop Detector | Feeder Pillar 12 4.17/d 50.00 Signal Heads

© Oracle Corporation Page 20 of 21


07-Mar-21 13:11
Activity ID Activity Name Estimated Productivity Budgeted Units Resource Name
Duration

WO.06.8700 Install Signal Heads | Loop Detector | Feeder Pillar 12 0.17/d 2.00 Feedrer Piller
WO.06.8700 Install Signal Heads | Loop Detector | Feeder Pillar 12 2.83/d 34.00 Signal - Loop Detector
WO.06.8700 Install Signal Heads | Loop Detector | Feeder Pillar 12 4.00/d 48.00 Electrician
WO.06.8720 Pole Foundation | Chamber Works 18 2.11/d 38.00 Traffic Signal Chamber
WO.06.8720 Pole Foundation | Chamber Works 18 2.00/d 36.00 Unskilled Labor
WO.06.8720 Pole Foundation | Chamber Works 18 1.00/d 18.00 Excavator: Hammer
WO.06.8720 Pole Foundation | Chamber Works 18 1.00/d 18.00 Excavator: Bucket
WO.06.8720 Pole Foundation | Chamber Works 18 0.44/d 8.00 Charge Hand
WO.06.8720 Pole Foundation | Chamber Works 18 1.17/d 21.00 Signal Poles

ITS Network 112 ---


SA032.01. (1-6).CON.06.P1.S2 Phase 01: Stage 2 Carriage Way (Ch.1+550 to 1+908)21 ---
WO.06.7190 Duct Works: ITS 18 2.00/d 36.00 Carpenter
WO.06.7190 Duct Works: ITS 18 2.00/d 36.00 Mason
WO.06.7190 Duct Works: ITS 18 2.00/d 36.00 Unskilled Labor
WO.06.7190 Duct Works: ITS 18 0.78/d 14.00 Charge Hand
WO.06.7190 Duct Works: ITS 18 78.89/d 1420.00 ITS Duct
SA032.01. (1-6).CON.06.P1.S3N Phase 01: Stage 3 (Ch.1+000 to 1+908) 58 ---
WO.06.4310 Cable Pulling | Poles Installation 12 2.00/d 24.00 Unskilled Labor
WO.06.4310 Cable Pulling | Poles Installation 12 4.00/d 48.00 Electrician
WO.06.4310 Cable Pulling | Poles Installation 12 0.50/d 6.00 Charge Hand
WO.06.4310 Cable Pulling | Poles Installation 12 419.50/d 5034.00 Fiber Optic Cable
WO.06.4430 CCTV | LAN Network installation 8 2.00/d 16.00 Unskilled Labor
WO.06.4430 CCTV | LAN Network installation 6 4.00/d 24.00 Electrician
WO.06.4430 CCTV | LAN Network installation 8 0.50/d 4.00 Charge Hand
WO.06.4430 CCTV | LAN Network installation 8 0.13/d 1.00 CCTV
WO.06.4390 Chamber Works 21 0.10/d 2.00 Unskilled Labor
WO.06.4390 Chamber Works 21 0.05/d 1.00 Charge Hand
WO.06.4390 Chamber Works 21 0.95/d 20.00 ITS Chamber
WO.06.4110 Trench Excavation | Duct | Backfilling 30 2.00/d 60.00 Unskilled Labor
WO.06.4110 Trench Excavation | Duct | Backfilling 30 0.50/d 15.00 Charge Hand
WO.06.4110 Trench Excavation | Duct | Backfilling 30 94.67/d 2840.00 Excavation LM
SA032.01. (1-6).CON.06.P2.S2 Phase 02: Stage 2 Garrage Way (Ch.0+500 to 1+000) 21 ---
WO.06.8680 Duct Works: ITS 18 2.00/d 36.00 Carpenter
WO.06.8680 Duct Works: ITS 18 2.00/d 36.00 Mason
WO.06.8680 Duct Works: ITS 18 2.00/d 36.00 Unskilled Labor
WO.06.8680 Duct Works: ITS 18 0.78/d 14.00 Charge Hand
WO.06.8680 Duct Works: ITS 18 78.89/d 1420.00 ITS Duct
SA032.01. (1-6).CON.06.P2.S3 Phase 02: Stage 3 (Ch.0+100 to 1+500) 67 ---
WO.06.8570 Cable Pulling | Poles Installation 12 2.00/d 24.00 Unskilled Labor
WO.06.8570 Cable Pulling | Poles Installation 12 4.00/d 48.00 Electrician
WO.06.8570 Cable Pulling | Poles Installation 12 0.50/d 6.00 Charge Hand
WO.06.8570 Cable Pulling | Poles Installation 12 419.50/d 5034.00 Fiber Optic Cable
WO.06.8580 CCTV | LAN Network installation 8 2.00/d 16.00 Unskilled Labor
WO.06.8580 CCTV | LAN Network installation 6 4.00/d 24.00 Electrician
WO.06.8580 CCTV | LAN Network installation 8 0.50/d 4.00 Charge Hand
WO.06.8580 CCTV | LAN Network installation 8 0.13/d 1.00 CCTV
WO.06.8620 Chamber Works 21 0.90/d 19.00 ITS Chamber
WO.06.8620 Chamber Works 21 0.05/d 1.00 Charge Hand
WO.06.8620 Chamber Works 21 2.00/d 42.00 Unskilled Labor
WO.06.7890 Trench Excavation | Duct | Backfilling 28 2.14/d 60.00 Unskilled Labor
WO.06.7890 Trench Excavation | Duct | Backfilling 28 0.54/d 15.00 Charge Hand
WO.06.7890 Trench Excavation | Duct | Backfilling 28 101.43/d 2840.00 Excavation LM