TCS Q 113.02 R0
TCS Q 113.02 R0
TCS Q 113.02 R0
TABLE OF CONTENTS
1.0 SCOPE
2.0 DEFINITIONS
7.0 EXCAVATION
7.1 General
7.2 Excavation for Buildings and Structures
7.3 Utility Trenching
7.4 Bracing and Shoring
8.0 DEWATERING
8.1 Groundwater
8.2 Surface Runoff
10.1 Sub-grade
10.2 Backfill
10.3 Embankments
10.4 Test Section for Embankments
12.1 General
12.2 Improvement of Sabkhah Soils
12.3 Drainage Control
15.1 Bibliography
15.2 Appendices
16.0 FIGURES
1.0 SCOPE
This Transmission Construction Standard covers the mandatory requirements for the
construction of safe and reliable facilities by controlling earthwork in the system of Saudi
Electricity COMPANY (SEC). This Standard is applicable for all the works for the
COMPANY including, but not limited to, the following:
b. Excavation
d. Dewatering
g. Backfilling
h. Construction of embankment
i. Slope protection
2.0 DEFINITIONS
2.1 Backfill Refers to the construction of earth fill in confined spaces, such as the
refilling operations above concrete structures, or refilling in trenches
around pipes, direct buried cables, etc.
2.2 Base course The layer or layers of specified or selected material of designed
thickness placed on a sub-base or sub-grade to support surface course
such as asphalt concrete, aggregate surfacing or concrete pavement
2.3 Borrow Pit A site where earth material is removed by mechanical equipment and
transported to an off-site location for use in grading
2.4 Borrow Pit Boundary: The boundary for a Borrow Pit is defined in the Borrow Pit
permit
2.5 Controlled Fill This is defined as the placement of earthfill of specified engineering
properties (gradation, plasticity index, California Bearing Ratio,
thermal conductivity, etc.) and compacted to a required density.
2.8 Finished grade Finished grade is the final grade of the site, which conforms to the
approved plan by the COMPANY.
2.9 Grade Grade shall mean the vertical location of the ground surface
2.10 Grade Slope Refers to cut and fill side slope as per site requirements or as indicated
in the approved drawings. Standard for Cut=1:2 (vertical: horizontal)
and for Fill = 1:4. Berming system is also applicable for cut slope.
2.12 Rough Grade Refers to grading the construction site to approximate design contours
2.13 Select Fill Materials, obtained from a specified source such as a borrow area, of
acceptable quality having a specified characteristic to be used for a
specific purpose. The material, if not of acceptable quality, shall be
improved by mixing at site with suitable material to meet the specified
characteristics such as gradation, CBR, plasticity index, etc.
2.15 Sub-grade The existing underlying ground prepared and compacted for
supporting foundations of structures, embankments, pavements, etc.
3.1 Any conflicts between this Standard and other applicable Saudi Electricity Company
(SEC) Standards, Industry Standards, Codes, and forms shall be resolved in writing
by the COMPANY Representative.
3.2 Any request to deviate from this Standard shall be directed to the Manager of
Transmission Standards and Specifications.
4.1.1 All works performed and all materials furnished shall be in conformity with
the lines, grades, cross-sections, dimensions, and material requirements,
including tolerances, shown on the plans/drawings or indicated in the
specifications.
4.1.2 All materials to be incorporated into the work shall meet or exceed the
appropriate AASHTO, ASTM, or other Standard and specifications as
required by the plans/drawings and specifications but in no case shall be less
than the requirements of this Standard.
4.1.3 All materials shall be inspected, sampled, tested and accepted by the
COMPANY Representative before incorporation into the work.
4.1.4 Field and laboratory tests required to determine compliance with the
compaction requirements of this Standard shall be done by an Independent
Agency approved by the COMPANY.
4.1.5 No material, regardless of its source, shall be incorporated in the Work until
representative samples taken and tested by the SEC approved Independent
Laboratory have been reviewed and approved by the COMPANY
Representative.
4.1.6 Sub-grades or bottom of excavation for structures shall be firm, dense and
thoroughly compacted as specified under Construction Requirements. It shall
be free from mud and muck, and sufficiently stable to remain firm and intact
under the feet of the workmen.
4.1.7 Adequate dewatering equipment to remove and dispose all surface and
groundwater entering the excavations and other parts of the work, shall be
provided at site and maintained properly.
4.2.2 Excavation by the use of explosives shall be with prior written approval from
the SEC.
4.2.3 The stability of adjacent structures or facilities including public safety shall
not be impaired or endangered by excavation works.
The latest revisions/amendments of the following Standard and specifications are intended as
guidance in providing an acceptable level of quality and practice. In case of conflict between
these Standards and the text of this Standard, the latter shall govern:
5.2.1 ASTM C 127 Test Method for Density, Relative Density (Specific
Gravity) and Absorption of Coarse Aggregates
5.2.2 ASTM D 421 Practice for Dry Preparation of Soil Samples for Particle-
Size Analysis and Determination of Soil Constants
5.2.5 ASTM D 854 Test Methods for Specific Gravity of Soil Solids by
Pycnometer
5.2.6 ASTM D 1194 Test Method for Bearing Capacity of Soil for Static Load
and Spread Footings
5.2.7 ASTM D 1556 Test Method for Density of Soil in place by the Sand-Cone
Method
5.2.9 ASTM D 1558 Test Method for Moisture Content Penetration Resistance
Relationships of Fine-Grained Soils
5.2.10 ASTM D 1586 Test Method for Penetration Test and Split Barrel
Sampling of Soils
5.2.11 ASTM D 1632 Practice for making and Curing Soil-Cement Compression
and Flexural Test Specimens in the Laboratory
5.2.12 ASTM D 1633 Test Method for Compressive Strength of Moulded Soil-
Cement Cylinders
5.2.13 ASTM D 1739 Test Method for Collection and Measurement of Dustfall
(Settleable Particulate Matter)
5.2.14 ASTM D 1883 Test Method for CBR (California Bearing Ratio) of
Laboratory-Compacted Soils
5.2.16 ASTM D 2922 Test Methods for Density of Soil and Soil-Aggregate in
Place by Nuclear Methods (Shallow Depth)
5.2.17 ASTM D 4253 Test Methods for Maximum Index Density and Unit
Weight of Soils Using a Vibratory Table
5.2.18 ASTM D 4254 Test Methods for Minimum Index Density and Unit
Weight of Soils and Calculation of Relative Density
5.2.19 ASTM D 4318 Test Methods for Liquid Limit, Plastic Limit, and Plasticity
Index of Soils
5.2.20 ASTM D 4791 Test Method for flat particles, elongated particles, or flat
particles and elongated particles in coarse Aggregate
5.2.21 AASHTO T-180 Test Method for Moisture-Density Relations of Soils Using
a 4.54 kg (10-lb) Rammer and 457 mm (18-in.) Drop
6.1.1 The site shall be cleared of all boulders, debris, decomposable materials such
as wood, grass, plants, tree stumps, etc., to the satisfaction of COMPANY
Representative.
6.1.3 Where structural support is required, the soil that softens due to rainfall,
groundwater, disturbance, exposure or any other cause shall be excavated and
replaced with controlled fill.
6.1.4 Burning of rubbish and organic materials, resulting from the site clearing
operations, shall not be permitted on the site or adjacent property.
6.1.5 All surplus materials, resulting from the site clearing operations, shall be
transported to and dumped in municipal approved dump areas, with prior
approval from the COMPANY Representative
6.1.6 Care shall be taken to protect existing utilities, site improvement works and
existing structures.
Rough grading shall be done to the approximate finished lines and grades shown on
approved drawings. This area shall then be inspected and approved by the
COMPANY Representative before commencing any work.
7.0 EXCAVATION
7.1 General
7.1.1 Prior to excavation, information about all existing underground services such
as gas, water, telephone lines, sewage lines, electric cables, etc., shall be
obtained from ministries, municipalities, utility companies and other affected
agencies. Excavation shall be carried out with special care and with proper
permissions to avoid any interference with these systems. Only manual
excavation shall be employed in locations where underground utilities are
present. Any damage caused shall be repaired expeditiously and restoration of
services shall be made without delay.
7.1.2 Safe working distances and overhead clearances shall be maintained at all
times when working near or under energized overhead lines or substation
structures to ensure safety of personnel and avoid accidental disruption of
power. Safe working distance shall be in accordance with Chapter 14 of
Construction Safety Manual (See Appendix II).
7.1.4 Excavation in all types of soil and rock shall be treated as unclassified
excavation.
Pits and trenches shall be excavated to grades and depths shown on the
approved drawings. Trenches and pits in loose earth shall be at least 300 mm
bigger in both plan dimensions than the size of foundations. Trenches and
pits for footings in stiff cohesive material or rock shall not be wider than
necessary for formwork and bracing.
Bottoms of excavations shall be smooth and free of loose earth or sand. Any
soft or loose spots of insufficient bearing shall be compacted to the density as
stipulated in Section 7.2.2 or they may be removed and replaced with concrete
or with compacted Select Fill materials (as specified). Excavation bottoms for
support of foundations shall be level or stepped and shall not be sloped.
Excavation slope (as shown in Figure 1) must be checked for stability. This is
applicable to all types of foundations.
7.3.2 Utility trenching shall follow strictly the approved alignment requirements.
Care shall be taken such that pipes, cables, and duct runs shall be made as
straight as possible, both horizontally and vertically, and if a deflection must
be made, it shall be along a smooth and gradual curve to avoid stressing the
ducts, cables or pipes.
7.3.3 All excavations shall be extended at least 150 mm below the bottom of pipe
or power cable to provide an all around 150 mm minimum clean sand bedding
(See Figure 2). The gradation of clean sand shall conform to Section 9.1.3.
The thermal conductivity of sand around power cables shall comply with
design requirements.
7.3.4 Trenches shall be excavated to the grade shown on the profile with a
minimum of 1000 mm and 500 mm earth cover over the top of the service line
in traffic areas and non-traffic areas, respectively (See Figure 2). Excess
excavation below required level shall be backfilled with selected fill materials
compacted to 95% of the maximum density as determined by ASTM D 1557
for soils containing more than 15% material passing the 75-micron sieve or
85% relative density (ASTM D 4253 and ASTM D 4254) for free draining
cohesionless soils containing less than 15% non-plastic material passing 75-
micron sieve.
7.3.5 Soft or loose spots in the trench shall be compacted to the density as per
Section 7.3.4 or the soft materials shall be removed and replaced with selected
fill materials that is compacted to the density per Section 7.3.4.
7.3.6 The trench bottom shall be continuous, smooth and free of loose debris and/or
sharp rocks which could damage the service line/power cable.
7.4.1 The sides of pits and trenches shall be sloped back to the natural angle of
repose of the soil to avoid caving. Sides which cannot be sloped, because of
space limitation due to adjacent structures, or unrestrained sand masses (loose
sand) shall be shored adequately to resist earth movement, protect workers,
and protect on-going work and existing property.
7.4.2 Shoring shall not be braced against forms. Forms shall be properly braced and
tied together, independent of shoring.
8.0 DEWATERING
8.1 Groundwater
In order to obtain a stable bottom of the excavation, dewatering should be carried out
in advance of excavation. Dewatering shall be performed by carefully installed well
point system which should be properly designed, having sufficient knowledge of
local condition. The problem of bottom “heave” can be anticipated by adopting a
designed dewatering system. A typical dewatering procedure could be as follows:
Excavate to near the anticipated ground level. The sides may be supported by sheet
piles.
The well points could be jetted or drilled into position. The well points should extend
below the excavation to a depth of at least about 1.5 times the excavation depth
below the ground water level. The well points should be spaced about two meters
center to center (other depth-spacing criteria may be adopted to suit the field
conditions).
Typical grain size distribution range of the soils encountered at the study area or from
the gradation charts shall be obtained. This should assist in the design of a well point
system, the size of the screening, the sand filter and the size of the vacuum pump, if
necessary.
Controlled fill shall be free of organic matters, rubbles, cobbles and boulders, and other
deleterious substances.
The following four (4) types of controlled fills are classified for earthworks.
9.1.1 General Fill (Class D) shall meet the following gradation requirements:
b. Between 80% and 40% by weight passing the 2.0 mm mesh sieve
c. Not more than 15% by weight passing the 75 micron mesh sieve; less
than 4 plasticity index. Where binding effect is required between soil
particles as in uncontained embankments, a maximum of 20% by
weight material passing the 75 micron mesh sieve shall be provided.
9.1.2 Select Fill shall be a well graded granular material as shown in Table-I.
Table-I
50 100
19.0 95 to 80
2.0 80 to 50
0.250 50 to 25
0.075 20 to 5
Where free draining properties of the controlled fill are essential, such as
groundwater table being within 1.5 m depth below the bottom of foundations
or pavements, the material passing the 75 micron mesh sieve shall be between
5% and 10% by weight. Where groundwater is not a problem and binding
effect is required between soil particles, as in uncontained embankments and
surfaces exposed to erosion, near maximum limit of 20% by weight material
passing the 75 micron mesh sieve shall be provided.
9.1.3 Clean sand satisfying the following USA Standard sieve size gradation shall
be used for bedding around utilities as shown in Table II.
Table II
9.1.4 Aggregate sub-base and base course materials shall meet the following
gradation as shown on Table III and physical properties as shown on Table
IV.
Fine Aggregate 20 20 20 20 20
The COMPANY Representative shall approve the depth of the fill after the
availability of soil reports. Aggregate sub-base and base courses, if specified, shall
be used as fill material for access roads, substation yards, designated roadways,
parking lots, and material yards where heavy traffic load is expected.
Minimum depth of filling shall be 600 mm if the bottom of excavation reveals good
soil/ hard surface.
Sand shall be used for bedding around service lines such as pipes, conduits, and
cables. In all other instances, “General Fill” shall be used as sub-base unless
otherwise specified.
Fifty kilogram bag samples of each material to be used as controlled fill shall be
collected in the presence of COMPANY Representative and submitted for testing to
an independent soil testing laboratory, approved by the COMPANY, at least ten
(10) days prior to commencing controlled fill operations. The testing laboratory
shall perform at least one of each of the following tests on fill samples and submit
the test results to the COMPANY.
If the results from the above tests meet the specification requirements, the testing
laboratory shall determine the CBR, Sulphate and chloride content including the
compaction characteristic of the fill material by conducting one of the following tests
(item a or b below) that is applicable to the gradation, plasticity and drainage
characteristics of the fill material:
c. The California Bearing Ratio (CBR) for each class of fill materials
compacted in the laboratory after four (4) days soaking as determined by
ASTM D 1883 shall be as follows:
Table V
Note: The correlation of the soil ratings based on CBR values is given in
Figure 8.
d. The Sulfate and chloride contents of controlled fill for each class of fill
materials shall also be determined. Borrowed fill with greater Sulfate or
chloride content than the existing soil in the site shall not be used as
controlled fill for improvement of existing facility.
10.1 Sub-grade
10.1.1 The existing ground surface shall be proof-rolled by the same equipment that
will be used to compact the controlled fill materials prior to the placement of
first lift of controlled fill (sub-base). Compaction of the sub-grade may be
facilitated by maintaining its moisture content at or slightly wet or dry (±2 %)
of the optimum moisture content determined from laboratory tests.
Depending on the type of structure supported, sub-grade shall be compacted
to develop the following degrees of compaction to about 300 mm below the
ground surface:
Light Traffic Road, e.g., Plant Minimum of 80% relative density (ASTM D 4253
roads for operations and and ASTM D 4254) for free draining soils
maintenance only and not containing less than 15% by weight finer than 75
frequently subjected to traffic. micron sieve non plastic material or 92% of the
service lines/ power cables maximum density as determined by ASTM D 1557
below these roads for soils containing more than 15% materials
passing the 75 micron sieve.
Note: ASTM D 2922 can be used for testing the compaction of the soil at site if
permitted by the COMPANY Representative, provided the soil is uniform.
10.1.2 In case of filling Sabkhah or areas of high water table, the requirements for
proof-rolling the ground surface may be waived by the COMPANY
Representative if proof-rolling is not feasible. For modification to Sabkhahs,
refer Section 12.0. Dewatering shall be done for areas of high water table.
10.2 Backfill
10.2.1 All formworks shall be completely removed but in no case less than 24 hours
after placing concrete. All debris shall be cleaned out and permission to
backfill shall be secured from the COMPANY Representative.
10.2.2 Trenches, pits and other excavations shall be backfilled with materials
described in Section 9.1. The location of each type of fill shall be governed
by Section 9.2. As far as possible, excavated materials shall be used as
backfill provided they meet the requirements of controlled fill specified in
this Standard.
10.2.4 Backfill materials shall be placed in uniform layers not exceeding 300 mm of
uncompacted thickness. Increased thickness may be permitted for non-
cohesive materials by the COMPANY representative if the specified
compacted density can be obtained.
10.2.6 Where controlled fill is placed adjacent to walls, which are not designed as
retaining walls, either the difference in elevation of the top of the controlled
fill on both sides of the wall shall not be more than 300 mm, or the wall is to
be adequately braced.
10.2.7 All utility lines shall be laid on a clean sand bed compacted to the density
criteria of Table VI. Sand shall conform to Section 9.1.3 and thermal
resistivity of sand around power cables shall comply with design
requirements. After utility lines have been laid, clean sand shall be carefully
placed and compacted beneath the bottom half of the service lines to assure
firm support. Careful backfilling and compaction by tamping or inundation
with water shall continue above the service lines.
10.2.8 Finished grades adjacent to structures shall slope away from the structures to
minimize ingress of precipitation and quickly drain away the surface runoff.
10.3 Embankments
10.3.1 Prior to placing the first layer of controlled fill, sub-grade shall be leveled, if
necessary moistened, compacted, tested and then scarified so that the surface
material of the sub-grade is as compact and well bonded with the first layer of
controlled fill as is specified for succeeding layers of controlled fill. Test
criteria for the sub-grade shall be as per Section 9.3. Bond between a sloping
sub-grade and controlled fill shall be improved by benching the sub-grade.
10.3.2 Unless otherwise specified, all controlled fill shall conform to soil gradation
specified in Section 9.1. The location of use of each type of controlled fill
shall be determined by provisions of Section 9.2.
10.3.3 Unless specified otherwise, all controlled fill shall be compacted to densities
indicated in Table VI.
10.3.4 Moisture content shall be uniform throughout the layer to be compacted and it
shall be as close as practicable to the optimum moisture content from
laboratory compaction tests, which will result in the maximum densification
of the material to be compacted.
10.4.1 On large earthwork projects, the COMPANY Representative shall direct for
the construction of a test section using the material and equipment to be used
on the project. This shall provide the basis for the most practicable processing
and placing procedures for representative soils under job conditions. By
varying the placement procedure within certain limits, by exercising rigid
control over the relatively small volume of the section, and by keeping
complete records of the tests, the most applicable procedures shall be
determined during the initial stages of construction. Results of field density
tests made on the test section shall provide the necessary information for
establishing construction control procedures consistent with design
requirements. This is to establish the moisture content of the borrow material;
methods for correcting borrow material’s moisture content if too wet or too
dry; roller characteristics; number of roller passes; thickness of layers; and
effectiveness of power tamping in places inaccessible or undesirable for roller
operation.
If the size of the project does not warrant a test section, then experience from
the initial placing operations shall be used to determine the above
characteristics.
All permanent slopes shall be designed based on the stability considerations of the
embankment and foundation materials.
b. A layer of hot asphalt concrete mix, conforming to surface course per Asphalt
Concrete Paving Standard, TCS-Q-113.01, shall be placed on clean,
compacted and primed embankment slope to provide a 50 mm minimum
compacted asphalt pavement thickness.
If the top surface of the embankment is paved, the increased runoff from
precipitation shall be collected by provision of curbing around edges of the
pavement and directing the flow of water down the slope through cement
grouted rip-rap gutters. Typical sections of curbs and gutters arrangement are
shown in the attached drawings (Figures 4, 5 and 6). Precast concrete gutter
units may be used if approved by COMPANY Representative.
The temporary slopes, when constructed, shall be maintained in a stable and firm
condition including proper surface drainage and control of erosion.
12.1 General
These soils are either situated along the coasts (Coastal Sabkhahs) or farther inland
(Continental Sabkhahs).
The bearing capacity and compressibility characteristics of these soils in the virgin
state rarely meet routine design requirements. Therefore, before any construction
activity, the soil has to be either treated, or replaced, or the foundation loads must be
transferred through end bearing piles to the underlying dense soil or rock.
Measures to enhance the properties of Sabkhah must be taken before any construction
takes place on the soil. Control of groundwater rise is a vital corrective measure, in
conjunction with soil densification. If various densification and drainage control
techniques fail to improve the soil properties, i.e., the required bearing capacity and
warranted settlement, pile foundations shall be used, if Sabkhah site cannot be
abandoned altogether.
The detailed report about the Sabkhah soil and the recommended methods of
improvement shall be submitted to The COMPANY. The selection of the type of
improvement shall be done by the COMPANY Representative.
This procedure is used for access roads and pavements, and when
subsurface conditions favor displacement. Filling proceeds from one
end of the area to be developed, by building a rolling surcharge fill,
which penetrates and displaces the Sabkhah soil to a certain depth.
The Sabkhah in front of the surcharge fill is excavated to a firm base
and the rolling surcharge is pushed forward to displace any Sabkhah
material that may have squeezed in after excavation. This is continued
until the entire filling procedure is completed.
a. Vibration Methods
i. Vibroflotation:
ii. Vibro-compaction:
iii. Vibro-replacement:
iv. Blasting:
b. Displacement Methods
Preloading:
In order to protect the Sabkhah itself (against salt dissolution), as well as the
embedded substructures against brine saturation due to capillarity, it is vital to
implement effective drainage control measures in conjunction with soil densification
techniques.
Radial and horizontal sand/gravel drains are effective means of controlling drainage
in Sabkhah. However, these drains may become clogged if the Sabkhah contains a
large proportion of fines.
c. Cofferdams
d. Electro-osmosis
e. Electrolysis
Mechanical tamping when used around structures, along abutments, and in areas not
accessible to the rolling equipment, shall be checked by frequent density tests.
The areas of low density, and any other faults, shall be identifed by ascertaining the
causes and shall be rectified on instructions from COMPANY Representative by
sprinkling, scarifying, removal, or re-rolling, as required. As a minimum, one field
density test (ASTM D 1556 or ASTM D 2922) shall be made as follows:
13.2 Reports
14.1 At the end of all construction work, all holes, ruts, settlements and depressions shall
be filled and the whole area graded to final design elevations. All areas disturbed by
construction shall be restored to their original condition to the satisfaction of the
COMPANY Representative.
14.2 All debris, waste, excavated spoils and surplus articles and materials shall be
transported and/or discarded in a manner approved by the COMPANY
Representative.
15.1 Bibliography
5. Soil Survey for Engineering by ABA Brink, TC Partridge & AAB Williams
12. Chemical Stabilization of Soils Using Cement and Lime, by Dr. Omer
Sayeed Baghbara Al-Amoudi, K.F.U.P.M.
16. Foundation Analysis and Design, by Joseph E. Bowles McGraw Hills Co.,
Inc,. U.S.A.
15.2 APPENDICES
II. Construction Safety: Special Manual Chapter No. 14: Electrical Hazards.
6.0 EXCAVATION.
6.1 Introduction
Accidents due to excavations may involve injuries that are minor, serious, disabling
or fatal as well as property damage. It is essential that appropriate precautions be
taken to prevent collapse of any excavated structure or area.
Excavation work done in urban areas and cities usually involve the presence of
underground facilities such as utility lines (water, electricity, gas or telephone),
tanks, process piping, and drainage systems. If they are dug into, undercut, or
damaged in any way injury or death may result. Interruption of service,
contamination of water, disruption of processes, or extensive delay of Government
projects may also occur. These accidents will cause direct and indirect losses to the
COMPANY.
6.3.9 Position of any underground utilities such as water, gas, electric and
telephone lines
A work permit should be obtained from the Operations Supervisor of SEC before
any excavation work in a restricted area is started. Normally, a separate work permit
is required for each excavation. Refer to SEC General Instruction LP-002/83 or
Chapter 13 of this manual for Work Permit procedures.
6.5.2 Mechanical excavators should not be used within 3m (10 ft.) of known
underground utilities and obstructions.
6.6.1 Shoring should be used immediately, or the sides sloped to a safe angle, if
there is a possibility of the sides of an excavation collapsing.
6.6.4 A careful inspection of the excavation area and the shoring system should be
made each day by the Contractor and the SEC Project Management Team.
6.6.7 Trenches should not be used. for dumping materials and rubbish
6.6.9 Any excavation made in public roads, streets and sidewalks should be cleared
in advance with Government Relations and have the approval of relevant
authorities- See Paragraph 6.4 or Chapter 13 of this manual.
6.6.11 Excavation of hard rock that requires drilling and blasting activities shall be
covered by a special permit. SEC Government Relations, Industrial Security
Department, and Project Management must be consulted and informed before
any blasting work.
14.1 Introduction
As a source of power, electricity is in some ways less hazardous than steam or other
sources of energy. If used properly it is a most versatile form of energy. However, if
one fails to take suitable precautions in its use the result may be bodily harm or
property damage as there are hazards in installing, maintaining, and using electrical
equipment. Control of most of these hazards is neither difficult nor expensive but
ignoring or neglecting them may lead to serious accidents. Current flow is the factor
that causes injury in: electric shock. The severity of the shock is determine4 by the
amount of current flow through the victim. Other factors affecting the severity of
injuries are the parts of the body injured, duration of current flow through the victim,
the frequency of the alternating current.
14.2.4 OSHA Regulations and Standards, Part 1926, Safety and Health Regulations
for Construction
Serious shock is not entirely dependent, upon the voltage of the power source. The
ratio of the voltage to the resistance determines the current flow and the resulting
hazard. This ratio is presented in the following formula
Current through the body = Voltage applied to the body divided by. Resistance of
the body
The Contractor will have to make temporary electrical installations within the
construction site and other nearby facilities on most big construction projects. As
construction activities increases more electrical equipment, tools, and wiring are
installed to meet the increase in work volume. Regardless of the changes that occur,
good safety advice requires that all temporary electrical facilities be made in
accordance with established safety code and engineering standards. The following
rules apply
14.4.1 The Contractor is responsible for temporary electrical facilities within the
construction site as specified in the contract. Connections should be made
with the existing SEC power supply and in coordination with SEC Power
Operations and the Area Affairs Organizations
14.4.3 All electrical supply, communication lines, and equipment shall be of suitable
design and construction, for the services and conditions under which they are
to be operated
14.4.5 All work on or near electrical equipment or lines shall be carried out by, or
under the immediate supervision of, a qualified craftsman. Whenever
possible the equipment or line shall be de-energized. A Work permit is
needed for this type of work
14.4.6 All temporary wiring shall be installed in safe locations to prevent their
damage. The installation should not pose a tripping hazard in the construction
site
14.5.2 Employees shall not work alone on live equipment nor on energized lines.
Another electrician, lineman, or helper should be standing by to give
assistance if needed. Lead men, supervisors, or a foreman should be present
to monitor the job
14.5.3 The power supply shall be checked to know the exact voltage. This will
determine the type of safety protection required to accomplish the job safely.
The following should be followed
Employees shall not approach or take any conductive object, except with
approved devices, any closer to unguarded live parts than as shown in the
following table
2.1-15 0.61
15.1-35 0.71
35.1-72 0.91
72.1-121 1.02
121.1-169 1.12
169.1-242 1.52
16.0 FIGURES
30°
FINISHED GRADE
Minimum Earth
cover (See Section Compacted backfill conforming to
7.3.4 ) local municipal requirements
and/ or TCS-Q-113.02.
Service Line/
Power Cable Minimum 150 mm clean sand
bedding on all sides
WELL POINTS
Header
(N.T.S)
2 3 4 5 6 7 8 9 10 15 20 30 40 50 60 70 80 90 100
GW
OH CH GM-u GM-d
MH OL GC
CL SW
ML SM-d
SC
SM-u GP
SP
Base Acceptable
Fig- 8 Approximate correlation of soil ratings based on CBR values for use in pavements.