Advance Foundary and Welding
Advance Foundary and Welding
Advance Foundary and Welding
March 2021
SEMESTER & PROGRAM I Sem M Tech TIME 12:00 - 01:00 pm
(Production Engineering)
TIME ALLOWED 1 Hr. MARKS 20
COURSE NAME – (CODE) (PE5203T ) ADVANCE FOUNDARY &JOINING TECHNOLOGY
Q.01 a Differentiate the Pressurized and Non pressurized gating systems. CO2
b The casting product of size 150mmx210mmx120mm (LxBxH) it has hole of 100 mm. CO2
Calculate the dimensions of pattern used. Consider the shrinkage allowances to be
21mm/m.
Q.02 a A mold sprue is 20 cm long, and the cross-sectional area at its base is 2.5 cm2. The sprue CO4
feeds a horizontal runner leading into a mold cavity whose volume is 1560 cm3.
Determine: (a) velocity of the molten metal at the base of the sprue, (b) volume rate of
flow, and (c) time to fill the mold.
b What is permeability? Permeability is more important in the basic process of sand casting
than porosity. Give one important reason for this feature.
Q.04 a What is the Centrifugal casting? Explain the concept with neat diagram and give to CO2
practical example of products manufactured by this method
b An 92% Aluminum-8% Copper Alloy Casting Is Made In A Sand Mold Using A Sand Core
That Weighs 20 Kg. Determine The Buoyancy Force In Newtons Tending To Lift The Core
During Pouring.