Method Statement For Rebar, Formworks and Concrete Works
Method Statement For Rebar, Formworks and Concrete Works
Method Statement For Rebar, Formworks and Concrete Works
TABLE OF CONTENTS
FILE
PARAGRAPH
NO DESCRIPTION PAGE NO
NOS.
METHOD STATEMENT FOR REBAR, FORMWORKS
AND CONCRETE WORKS 1
TABLE OF CONTENTS 2
1 PROJECT UNDERSTANDING 3
2 SCOPE 3
3 PURPOSE 3
4 REFERENCES 3
5 DEFINITIONS 4
RESPONSIBILITIES 4
6
EQUIPMENTS 5
7
PROCEDURES
8 6
REBAR INSTALLATION
9 6
FORMWORKS INSTALLATION
10 6
CONCRETE WORKS
11 8
QUALITY INSPECTION
12 11
PRECAUTION AND SAFETY INSTRUCTION
13 12
1. PROJECT UNDERSTANDING
2. SCOPE :
2.1. Rebar installation, Formworks installation and concrete works for all type of structural
works mentioned in IFC drawings & Shop drawings.
3. PURPOSE :
This method statement defines the methodology for the rebar & formwork installation
and concrete works for all type of structure including Foundation, grade beams, grade
slab, Column, beams, Floor Slab, utilities foundation and all other similar structure
where applicable mentioned in IFC & Shop drawings.
4. REFERENCES :
4.1. Approved Issued for Construction (IFC) drawings and Shop Drawings.
4.2. Saudi Aramco Standards (Applicable as per Schedule B)
4.3. Project Specifications Division 3, Section 03100-Concrete Formwork
4.4. Project Specifications Division 3, Section 03200-Concrete Reinforcement
4.5. Project Specifications Division 3, Section 03300-Cast-in-Place Concrete
4.6. Project Specifications Section 01400-Quality Control Services
4.7. ACI-347 Recommended Practice for concrete Formwork
4.8. ACI-318 Building code Requirements for Reinforced concrete
4.9. ACI-117M-10 Specification for Tolerance for Concrete Construction & Materials.
4.10. SBC-Saudi Building Code
4.11. ACI-315 Details of concrete Reinforcement
4.12. ACI-301 Specifications for Structural Concrete
4.13. ASTM-615 Standards Specification for Deformed & Plain Bar.
4.14. IBC-2009 International Building Code
4.15. Contractor Site Safety Plan (CSSP)
5. DEFINITIONS :
6. RESPONSIBILITIES :
6.1. Site Surveyor: The Surveyor shall be fully responsible for formworks layout, rebar
installation layout, concrete pouring layout of the designated area as per IFC drawings and
Shop Drawings and will monitor all assigned works to complete the task. He will also be
responsible for the protection of bench mark and temporary bench mark.
6.2. Civil/Site Engineer: The Civil/Site Engineer shall responsible for the execution of all
rebar, formworks installation and concrete works as per IFC drawings, and project
specification under safe conditions and following the contractor site safety plan.
6.3. QC Inspector: The QC Inspector shall be responsible for all quality inspection
activities are carrying out as per latest revision of IFC drawings and to ensure compliance
with all requirements of relevant contract documents.
6.4. Construction Manager: The Construction Manager shall be responsible for executing
all constriction activities as per relevant project specification, in accordance with quality,
safety and schedule requirements.
6.5. Quality Control Manager: The Quality Control Manager (QCM) shall be responsible
for organizing and allocating inspection work to CQCI.
6.7. Safety Inspector: Safety inspector would be responsible for the following:
a) He will make sure all construction activities would be carried out under approved
CCSP.
b) He will make sure all site workers are following proper PPEs.
c) He will make sure all equipment have proper valid certificate before starting the site
works.
d) He will make sure the provision of flagman to assist the equipment operator and
warn people for any movement of equipment.
e) He will make sure the presence of work permit and list involved personnel at site
and work permit should have the clearance from electrical, Mechanical, instrument
department and also permits for succeeding work.
f) He will make sure that signals, signs and barricades will not be removed from site
until work finished.
6.8. Document Controller: Document Controller shall keep records of all documents to be
controlled in systematic order so that they can be accessed easily. Maintains clear
communication with all departments and ensures proper and effective flow of information.
8. PROCEDURES :
8.1.2. Methodology
Materials unloading should be in a proper way to avoid any scratching or
damaging and placing rebar with cover.
Reinforcing bars shall be hot rolled deformed in accordance with dimension
specified in the Bar Bending Schedule as mentioned in the IFC & Shop drawings.
Contractor will review all rebar bending details prior to fabrication to verify that
concrete cover and anchor bolt clearance can be maintained.
Bar cutting length shall be grouped with respect to their mark numbers by putting
tag identification.
Rebar should be keep by supporting timber dunnage rack.
Rebar shall be free from dirt, mill scale, rust scale, oil, grease and other foreign
matter.
Rebar should be placed as per spacing marked in IFC drawings.
Rebar should be binding properly with binding wire.
Chair shall be provided at regular inerval to support the rebar network.
Rebar spacer of approved material shall be placed at the bottom and to the sideds
where necessary to maintain the clear cover. For concrete clear cover of
reinforcement IFC drawings VA-ESGQ01-001-A shall be followed for minimum
cover requirements.
b) Methodology
Formworks lines, levels, and centers should be according to approved Issued for
Construction (IFC) drawings and Shop Drawings.
Formworks faces should be true flat and free from any corrugation/undulation that
may affect the concrete finish surface.
Formworks end should be braced perfectly so support all forms are maintained in
their desired position during and after concrete placing also build sufficiently tight
to prevent mortar leakage.
Formworks shall be tighten with sufficient braced in whole area in order to
resulting concrete surface conform to specified tolerence.
Brace forms adequately to retain forms in position during concrete placement and
curing.
Provide morter-tight forms which conform to shapes, lines and dimension shown in
IFC drawings and produce smooth surface without fins and projections.
Foam tape should be fixed all joints in formworks and edges in order to prevent
the loss of cement slury.
Formworks faces to concrete shall be provide oil agent to easy removal of forms
after concrete and should not stuck in concrete while removing.
Formworks alignment should be straight and its maximum tolerence should not be
exceed as specified in ACI-117 forms and formed surfaces.
Coats forms with form release agent prior to placement of reinforcing steel. Form
release agent shall not apply where concrete surfaces require special finishes.
Conduit and pipes shall be embedded in accordance with project specification and
Block-outs, inserts, sleeves, anchors, and other embedded items should be
properly identified, positioned and secured.
Ensuring items to be embedded in concrete are free from oil and foreign
matterials. Ensure anchor bolts do not come in contact with reinforcing steel.
Pipes and other embedded items should be checking before concrete placement.
Constraction, expansion and construction joint shall be provided as specified in
IFC drawings and shop drawings.
Formworks external edges exposed to concrete shall be chamfered by inserting
25mm angles strips in the form, this case will not apply under ground concrete
portion.
Formworks shall not be removed until concrete has attained sufficient strength to
support its own weight and the imposed loads. Forms shall be removed when
safety and serviceability are not impaired.
Formworks removal should be conducted carefully as per project specification and
take extra attention that it should not disturnb the concrete surface smoothness.
Form sheets should not be thrown down to the ground directly. Extreme care shall
be taken so as not to damage the formworks.
After the carefull removal of formworks foreign materials should be clean carefully
such as sticks, boards, loose rocks, snad, debris, etc within forms.
Form sheets shall be properly segregated accroding to the size and stored under
the shelter for re-use.
Cut Back rods and ties in a manner preventing swelling.
Damaged formworks shall not be re-use for further activities and it should be
segregated separately.
e) Reject concrete delivered to job site that exceeds the time limit 90 mins or failed
field inspection test.
f) Workability shall comply with ACI or Aramco Standards.
g) Mixing and transportation concrete shall confirm to concreting procedure set in
ASTM C94, ACI 304R.
h) Concrete acceptance shall be sign delivery batch tickets to indicate concrete
acceptance and reject truck without have any batch tickets.
i) For concrete pouring the quality control inspector (Civil) shall check and make
sure that the activities have been fulfilled prior to placement of concrete.
v. The Field Technician shall obtain samples from the 1 st truck mixer during
discharge unless otherwise instructed by the CQCI. Slump and Cylinder test
samples shall be taken from the end of the mixture truck chute or at the
discharge point of the concrete pump hose.
vi. The Field Test of Slump, Concrete Temperature shall be record by Field
technician .
vii. Concrete cylinder sample set of 04 Nos. cylinders shall be marked with the
number, the casting date and designated letter for each cylinder sample of
the set.
viii. All structural concrete shall have a minimum cylinder compressive strength
should be following below unless otherwise noted;
f’c = 28 MPa for Footings, Grade Beams, Slab on Grade, Column &
Walls.
f’c= 35 MPa for Hollow core Slab, Topping, Concrete Slab and Beams.
ix. Lean Concrete beneath foundation, where specified on IFC Drawings, shall
have a minimum compressive strength of 14 MPa @ 28 days.
i. Deformed Bars: Reinforcing Bars - 420 Mpa, Yield grade 60, Black steel. Use
deformed bars complying with the requirements of ASTM A-615.
ii. Additional testing shall be carried out as and when instructed by the CQCI.
Such samples and test shall be additional to the routine samples and tests.
iii. After Sampling and initial set on-site curing, the cylinders shall be tested for
compressive strength in the laboratory at the age of 7 days (2 Samples) and 28
days (2 Samples) in accordance with Contracts.(Ref.: VE-000A03-B-Vol.004
Section 03300, under Sub-sec 3.07.) unless otherwise directed by the Saudi
Aramco Representatives.
iv. Sampling shall comply with ASTM C172 and perform tests specified for each
40 cubic meters of fresh concrete or fraction thereof, but not less than one set
of four to six cylinders for each day’s concreting.
9. Quality Inspection
Inspection test Plan (ITP) specific to project requirements shall be made and
inspection activites are recorded either on the forms as given under related
docuemtns.
Ensure that approved 60 grade of black steel is used at site.
Rebar shall be free from loose mill scale and any surface rust prior to placement in
position.
Binding wire shall be free from rust and conform to the project specification.
Lap length shall be provide as per IFC & Shop drawings.
Verify site activities to conform the approved IFC & Shop drawings plan.
All activities would be carried out under approved inspection test plan (ITP) to
meet the project quality pan.
QC inspector shall assure that accepted material to be used at site and documents
can be produced upon Saudi Aramco request.
All Formworks materials to be used in the works shall be in accordance with the
project specification.
Embedded parts (if any) should be checked carefully prior to fixing of formworks.
Both horizontal & vertical formworks reference layout and elevation should be
reflected as the reference control line during starting works and inspection.
Vertical and horizontal bracing of formworks shall be standard inerval and equal
distance.
Approved Controlled IFC drawings and Shop drawings shall be used.
Approved inspection checklist shall be followed during inspection.
Inspection of erected formwork, shoring, bracing to ensure work is in accordance
with formwork design and supports, fastenings, wedges, ties, and items prior to
concrete placement.
Always wear gloves for handling shuttering of formworks and other tools and must
be aware other people working around.
Trained concrete pump operator and banks man shall be engaged to control or
operate readymix truck and pump.
Experienced labour shall be engaged to hold the pump hose and equally
distributed the concrete by layer.
END