013 Emr en - 6
013 Emr en - 6
013 Emr en - 6
Semestral Report
Project number: 44458–013
Loan Numbers: 3025, 3026
July 2020
Period covered: January – June 2020
This semi-annual environmental monitoring report is a document of the borrower. The views expressed
herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may
be preliminary in nature. In preparing any country program or strategy, financing any project, or by
making any designation of or reference to a particular territory or geographic area in this document, the
Asian Development Bank does not intend to make judgments as to the legal or other status of any
territory or area.
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
Table of Contents
1 INTRODUCTION ................................................................................................ 1
1.1 Preamble ................................................................................................................. 1
1.2 Headline Information .............................................................................................. 1
2 PROJECT DESCRIPTION AND CURRENT ACTIVITIES ............................................. 2
2.1 Project Description .................................................................................................. 2
2.2 Project Contracts and Management ......................................................................... 2
2.3 Project Activities During Current Reporting Period ................................................... 5
2.4 Description of Any Changes to Agreed Construction methods .................................. 8
24. No changes to any construction processes have been observed during the
construction period. .......................................................................................................... 8
3 ENVIRONMENTAL SAFEGUARD ACTIVITIES ........................................................ 8
3.1 General Description of Environmental Safeguard Activities ...................................... 8
3.2 Site Audits ............................................................................................................... 9
3.3 Issues Tracking (Based on Non-Conformance Notices) ............................................ 13
3.4 Trends ................................................................................................................... 18
3.5 Unanticipated Environmental Impacts or Risks ...................................................... 18
4 RESULTS OF ENVIRONMENTAL MONITORING ...................................................19
4.1 Overview of Monitoring Conducted during Current Period ..................................... 19
4.1.1 Air Emissions and Ambient Air Quality ............................................................ 19
4.1.2 Wastewater and Ambient Water Quality ........................................................ 20
4.1.3 Noise .............................................................................................................. 20
4.2 Trends ................................................................................................................... 24
4.3 Summary of Monitoring Outcomes ........................................................................ 24
4.4 Material Resources Utilization ............................................................................... 24
4.4.1 Current Period ................................................................................................ 24
4.4.2 Cumulative Resource Utilization ..................................................................... 25
4.5 Waste Management .............................................................................................. 26
4.5.1 Current Period ................................................................................................ 27
4.5.2 Cumulative Waste Generation ........................................................................ 30
4.6 Health and Safety .................................................................................................. 30
4.6.1 Community Health and Safety......................................................................... 30
4.6.2 Worker Health and Safety ............................................................................... 30
4.7 Training ................................................................................................................. 31
i
15 July 2020
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
Annexes:
Annex III- Acoustic Report for Amu Bukhara 1 New Pump Station (ABISRP 01)
Construction Site
ii
15 July 2020
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
ABBREVIATIONS
iii
15 July 2020
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
1 INTRODUCTION
1.1 Preamble
1. This report represents the Semi - Annual Environmental Monitoring Review (SAEMR)
for AMU BUKHARA IRRIGATION SYSTEM REHABILIATION PROJECT.
a) Construction of one new pump station, and modernization and rehabilitation of four
existing ones;
b) Increase in the conveyance efficiency of the main canal of ABIS;
c) Increase in the capacity of Basin Irrigation System Administration (BISA), Irrigation
System Administrations (ISAs), water consumers’ associations (WCAs), and farmers to
adapt to climate change; and
d) Efficient management of project and ABIS
4. The Ministry of Agriculture and Water Resources (MAWR) has agreed to implement the
Environmental Management Plan (EMP) and submit regular reports on its
implementation. The Initial Environmental Examination Report (IEE), including the
EMP, has been published on the Asian Development Bank (ADB) website. During
project implementation, ADB and Japan International Cooperation Agency (JICA) will
each be responsible for safeguard compliance in their respective project activities.
15 July 2020 1
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
5. The Amu Bukhara Irrigation System (ABIS) Rehabilitation Project is located in the
central part of Uzbekistan on the right bank of Amu Darya River bordering to
Turkmenistan. Bukhara is 563 km far from the capital Tashkent. The project covers
lands of Bukhara and Navoi provinces. The ABIS is very important for the area and
gives life as an oasis.
6. The ABIS supplies water to already irrigated lands, cities, settlements, and industries
in Bukhara and Navoi provinces through a series of large cascading pump stations and
thousands of kilometers of conveyance canals. It also drains the excess water through
drainage system outside of the project area.
7. The ABIS, with a command area of 315,000 ha, serves the irrigated lands of the
Bukhara Zarafshan and Karakul oases and the Karaul Bazar massif. The population in
the ABIS command area is about 1,788,000 people, including 1,550,000 in Bukhara
and 239,000 in two districts of Navoi, of which 68% live in rural areas and fully rely on
irrigated agriculture. It is particularly important to supply reliable water to these people
in the region. ABIS also supplies water for municipal and industrial purposes.
8. The aim of the Project is to improve the irrigated agriculture and water resources
management in the ABIS, with the goal of promoting sustainable economic and
social welfare of communities dependent upon ABIS. The Project objectives are:
9. A list or table of main organizations involved in the project and relating to Environmental
Safeguards is Table 1 given below. It includes lender, borrower, PIU, Main Contractor/s
and significant sub-contractors, environmental staff of various organizations with their
names and contact details.
15 July 2020 2
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
Lender
Organization: Asian Development Bank
Staff Name Syed Asim Ali Sabzwari
Designation Environment Specialist, CWOD-PSG
E-mail [email protected]
Staff Name: Feruza Insavalieva
Designation Associate Safeguards Officer, URM
Email: [email protected]
Tel: + 998 78 1401920
Organization: ADB/RETA International Environmental
Staff Name: Keti Dgebuadze
Designation: Safeguards Consultant
E-mail: [email protected]
Tel: +995 322 250619
Borrower/PIU Ministry of Water Resources of Uzbekistan Republic
Organization: Project Implementation Unit
Environmental Staff: Mr. Sardor Pulatov
E-mail: [email protected]
Tel: +998 99 895 82 31
Supervision Consultant
Organization: JV Temelsu International Engineering Services Inc.
Sheladia Associates Inc
Environment Specialist (International): Mr. Saban Cimen
Email: [email protected]
Tel: +998 90 317 36 11
Environment Specialist (local): Mr. Sherzod Sunatulin
Email: [email protected]
Tel: +998 90 966 59 54
Contractors
Construction of Amu Bukhara 1 NEW Pump Station (ABISRP 01)
China National Technical Import and Export Corporation (CNTIC)
Environmental Staff: Mr. Yang Guo You
Email: -
Tel: -
Modernization and Rehabilitation of Amu Bukhara Main Canal Regulating Structure (ABISRP 02)
Consortium LLC “Kogon Suv Qurilish” and JSC “Amubukhorokanalkurilish”
Environmental Staff: -
Email: -
Tel: -
Modernization and Rehabilitation of Kuyu Mazar and Kizil Tepa Pump Stations (ABISRP 03)
Modernization & Rehabilitation of Kuyu Mazar Pump Station (ABISRP 03.01)
Hebei Construction Group Co., Ltd, Hebei Province, China
Environmental Staff: Mr. Miao Guowang
Email: [email protected]
Tel: +998972812666
Modernization & Rehabilitation of Kizil Tepa Pump Station (ABISRP 03.02)
Hebei Construction Group Co., Ltd, Hebei Province, China
Environmental Staff: Mr. Zhang Zehui
Email: [email protected]
15 July 2020 3
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
Tel: +998997568278
10. The following organizations and/or staff will be responsible for environmental
monitoring:
11. The key staff for the environmental management and monitoring activities is Mr. Sardor
Pulatov, as PIU’s Monitoring and Evaluation Specialist (M&ES). He has all
responsibilities and tasks related to environment, land, social (including involuntary
resettlement and indigenous people), and poverty and gender aspects in accordance
with the environment and social safeguard documents and Summary Poverty
Reduction and Social Strategy, all of which are project linked documents. Specifically,
PIU Monitoring and Evaluation Specialist:
12. Additionally, in relation to the environmental aspects, with the support from the
international consultant the PIU Environmental Monitoring and Evaluation Specialist
will:
15 July 2020 4
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
13. PIU as responsible IA for the project recruited a Supervision Consultant (SC) –
consortium: «Temelsu International Engineering Services Inc» and «Sheladia
Associates Inc.». The International environmental expert (Saban Cimen) and national
environmental specialist of Supervision Consultant (EEC) – Sherzod Sanatulin assist
M&ES of PIU in the supervision of the construction activities under the Project.
14. The part of the work of the Environmental Experts of the Consultant is to develop a
capacity building training program for Contractor’s Environmental Officers in order to
increase the implementation efficiency of environmental monitoring. The timing of this
program will be just before the commencement of civil works. Environmental Experts of
the Consultant will develop the content of training.
15. China National Technical Import and Export Corporation (CNTIC) Contractor of the
Construction of Amu Bukhara 1 New Pump Station (ABISRP 01) mobilized to the site
on 05/10/2019 has started project design, completed topographical and geotechnical
surveys, executed tests of model pump and started to construct working camp during
the previous reporting period. The construction works have started on the field on
24/May/2020. Construction of working camp could not be completed during the current
reporting period (January 2020 - June 2020). An impermeable sewage septic tank has
been constructed and received permission from the local environmental authorities of
15 July 2020 5
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
Bukhara Oblast. Topsoil stripping and earth removal from the slopes proceeds as from
the end of May and almost 240 000 m³ soil has been excavated.
16. Regarding to the Contract of the Modernization and Rehabilitation of Amu Bukhara Main
Canal Regulating Structure (ABISRP 02), the completion date of contract was extended
until 12/04/2020. The extended completion date as per the Addendum No 3 has expired
during this reporting period on 12.04.2020 whereas the works are still far from
completion. The progress achieved during the period of Addendum No 3 is 2.75% and
the total overall progress of about 4 years is only 41%. An Assessment Report was
issued by the Engineer on the outstanding matters and problems of the Project. The
extended completion time has expired on 12.04.2020 and no further time extension has
been granted to the Contract since then. At present, the Contract remains virtually in
suspension. The Employer now seeks for the possibility of a re-organization of the
Contractor to enable execution of the remaining work, which is about half of the original
Contract amount. Although the Contractor has not officially abandoned the site, there
is almost no construction activity ongoing in the Project area.
17. Under the Modernization and Rehabilitation of Kuyu Mazar and Kizil Tepa Pump
Stations (ABISRP 03) there are two contracts: Modernization & Rehabilitation of Kuyu
Mazar Pump Station (ABISRP 03.01) and Kizil Tepa Pump Station (ABISRP 03.2).
Contracts were signed and became effective by September 2017. The contractor of
both contracts is the same company named Hebei Construction Group Co.Ltd. The
construction works related on these contracts are in progress. In Kuyu Mazar PS all six
new pump units are in operation presently and in Kizil Tepa PS except the old pump
units six and seven, all other eight new pumps became operational during the reporting
period.
18. The main project activities carried out during the reporting period include the following:
Table 2-2 Construction Activities Carried out During Reporting Period (January 2020 -
June 2020)
Number of Workers
Site Construction Activity
Maximum Minimum
15 July 2020 6
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
Number of Workers
Site Construction Activity
Maximum Minimum
20. A map of construction sites during the reporting period are given at the Figure
2-1.
21. The construction works at Kuyu Mazar and Kizil Tepa Pump stations have been started
during the (6th) reporting period (January 2018 - June 2018) and has not been fully
completed yet.
Figure 2-1 Map of Construction Sites Showing Construction Activities Carried out
During Reporting Period (January 2020 -June 2020)
22. The construction work at Peresechenie area has been started during 9th (July 2019-
December 2019) reporting period. Construction works at the subproject area has not
been completed during this reporting period.
15 July 2020 7
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
23. No changes happened during the reporting period of the project design from that which
was assessed in the Impact Assessment phase of the project and is set out in the Initial
Environmental Examination/Environmental Impact Assessment.
24. No changes to any construction processes have been observed during the
construction period.
25. The activities carried out during the reporting period by the environmental staff who are
related to the project activities have been summarized at the following Table 3-1.
Table 3-1: Environmental Safeguards Activities Carried out During Reporting Period
(January 2020 - June 2020)
15 July 2020 8
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
26. Regular site monitoring visits were carried out during the reporting period by PIU and
Environmental Specialist of SC to check up realization of environmental protection
measures parallel to civil works inspection as indicated below:
Table 3-2: Environmental Inspections Carried out During Reporting Period (January
2020 - June 2020)
27. The contractor of Construction of Amu Bukhara 1 New Pump Station (ABISRP 01) has
submitted third version of Site Environmental Management Plan (SEMP) on 28th
January 2020 to PIU/SC. The comments given to SEMP by PIU/SC has been delivered
to the contractor on 4th February 2020. Fourth, updated version of the SEMP has been
received on 21st April 2020 and comments is given to the fourth version of the SEMP in
22nd April 2020. SEMP is expected to comply with the contract requirement at the next
submission.
28. It has been requested from the contractors to send monthly environmental monitoring
activities which could be integrated into the monthly progress report. During the
reporting period the environmental monitoring reports (EMR) which have been received
from the contractors have been indicated in the Table 3-1.
29. Modernization and Rehabilitation of Amu Bukhara Main Canal Regulating Structure
(ABISRP 02) Contractor has not submitted any EMR for months between January 2020
and June 2020. Based on the explanations made Paragraph 16 the extended
completion time of the ABISRP 02 Contractor has expired on 12.04.2020 and no further
time extension has been granted to the Contract since then. At present, the Contract
15 July 2020 9
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
remains virtually in suspension. The Employer now seeks for the possibility of a re-
organization of the Contractor to enable execution of the remaining work, which is about
half of the original Contract amount. Although the Contractor has not officially
abandoned the site, there is almost no construction activity ongoing in the Project area.
After re-commencement of the construction activity, the ABISRP 02 Contractor shall
certainly be compelled to comply with the requirements as to the environmental issues
and complete the outstanding issues.
30. Modernization and Rehabilitation of Kuyu Mazar Pump Station (ABISRP 03.1)
contractor has issued the EMR for January, February, March, April, May and June 2020
on time.
31. Modernization and Rehabilitation of Kizil Tepa Pump Station (ABISRP 03.2) contractor
has issued the EMR for January, February, March, April, May and June 2020 on time.
32. Mr. Miao Guowang is the Health, Safety and Environmental Manager of Kuyu Mazar
Pump Station (ABISRP 03.1) contractor. The local Health, Safety and Environmental
expert of the contactor is Mr. Aziz Juraev.
33. Mr. Zhang Zehui is the Health, Safety and Environmental Manager of Kizil Tepa Pump
Station (ABISRP 03.2) contractor in cooperation with local Health, Safety and
Environmental expert Mr. Aziz Juraev.
34. It has been declared by Construction of Amu Bukhara 1 New Pump Station
(ABISRP 01) contractor that, Mr. Yang Guo You will be in field as the Health, Safety
and Environmental Manager of the contractor. The contractor has already appointed
Mr. Egamov Murod Kuchkorovich as local Health, Safety and Environmental expert.
35. Environmental progress of the Modernization and Rehabilitation of Amu Bukhara Main
Canal Regulating Structure (ABISRP 02) Contractor considered to be minor. See
performance evaluation form at the Annex I. The construction activities in Agitma
Regulator, Dvoynik Regulator, Rostguy, Djilvan Regulator has been completed. In the
Kharkhur regulator area there are still minor works need to be completed. Construction
works in the Peresechenie regulator area in progress. (See Annex II).
36. Amu Bukhara Main Canal Regulating Structure (ABISRP 02): The workers camp and
equipment and vehicles exist in Peresechenie area. Sites are considered to be clean,
excess excavated material stored on site. The demounted gates remain in site which
need to be gathered and stored by the Canal authority. The concrete has been carried
form the existing concrete plants. Therefore, no chemical or hazardous material has
15 July 2020 10
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
been observed on site. Excavated materials and pipes have been stored at nearby
areas.
37. Environmental progress of the Modernization and Rehabilitation of Kuyu Mazar Pump
Station (ABISRP 03.1) contractor is moderate. The environmental record keeping
system has been formed but day by day recording has not been applied for health and
safety training records. Health and safety conditions, social leisure areas have been
created for the workers. Environmental and health and safety labelling has been
improved at the sites, nevertheless, needs observation. Hazardous waste management
storage area developed and separation of solid wastes in progress. See performance
evaluation form at the Annex I.
38. Environmental progress of the Modernization and Rehabilitation of Kizil Tepa Pump
Station (ABISRP 03.2) contractor is under progress. The environmental record keeping
system has been established, however daily recording has been applied for solid waste
records. Health and safety conditions, social leisure areas have been created for the
workers. Environmental and health and safety labelling has been improved at the sites,
nevertheless, needs observation. Hazardous waste management storage area
developed. Separation of solid wastes still is not actively applied. See performance
evaluation form at the Annex I.
39. The dredged material excavated at the forebay area of the Kuyu Mazar Pump station
has been disposed to a site. A permission from the Novai Ecology and Environmental
Protection Headquarter obtained on 22/04/2019 by the Modernization and
Rehabilitation of Kuyu Mazar Pump Station (ABISRP 03.1) contractor for disposal of
the dredged material. The spoil deposit area should be levelled according to Chapter
11 on Architecture and Landscaping, Article 11.12 of the General Technical
Specification of Contract (GTS). Besides that, the conditions of depositing of dredged
material has been explained on this permission as “the spoil area should be levelled
and planted”. The contractor should settle the planting of the levelled spoil area with the
Novai Ecology and Environmental Protection Headquarter.
40. The dredged material excavated at the forebay area of the Kizil Tepa Pump station has
been disposed to a site. A permission from the Bukhara Ecology and Environmental
Protection Headquarter obtained on 21/02/2019 by the Modernization and
Rehabilitation of Kizil Tepa Pump Station (ABISRP 03.2) contractor for disposal of the
dredged material. The spoil deposit area should be levelled according to Chapter 11 on
Architecture and Landscaping, Article 11.12 of the General Technical Specification of
Contract (GTS). Besides that, the conditions of depositing of dredged material has been
15 July 2020 11
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
explained on the ecological report which is attached to this permission that “After
levelling, perennial decorative trees, such as elm, mulberries and spruce shall be
planted”. The contractor should settle the planting of the levelled spoil area with the
Bukhara Ecology and Environmental Protection Headquarter.
41. Status of non-compliances revealed for previous period are provided in the Table 3-3
below:
15 July 2020 12
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
42. During the previous reporting period (July 1st, 2019 - December 30th, 2019) the observed
Non-Conformance issues have been recorded and are given below in the table related
to the construction activities of project components. The following table gives the
present situation on these tracked non-conformance notices.
Non-Conformances Corrective measures Implementation
deadline
Construction of Amu Bukhara 1 New Pump Station (ABISRP 01)
15 July 2020 13
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
43. ABISRP 01 Contractor has prepared and submitted SEMP for the fourth time on
21/04/2020. Required revisions that are given to the ABISRP 01 Contractor by SC about
the SEMP are minor. Therefore, SEMP is expected to be approved at the next
submission.
44. Despite of repetitive warnings, ABISRP 02 Contractor doesn’t pay attention to correct
actions related to reporting the activity therefore this non-conformance issue remains
open, since 10/08/2020.
45. During the reporting period (January 1st, 2020- June 30th, 2020) Non-Conformance
issues of Modernization and Rehabilitation of Kuyu Mazar Pump Station (ABISRP 03.1)
and Modernization and Rehabilitation of Kizil Tepa Pump Station (ABISRP 03.2) have
been closed, except the levelling and planting of the dredged material storage area
which has still time till deadline agreed with the contractor.
15 July 2020 14
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
46. During the reporting period (January 1st ,2020 – June 30th, 2020) no new
Non- Conformance issues have been recorded, but there are non-conformance issues
which are lasting from the previous reporting periods. The contractors have been
informed about their non-conformances in written manner including the deadline agreed
with the contractor, when these non-conformances have been detected. These lasting
Non-Conformance issues are about the construction activities of Amu Bukhara 1 NEW
Pump Station (ABISRP 01) Amu Bukhara Main Canal Regulating Structure (ABISRP
02), Modernization and Rehabilitation of Kuyu Mazar Pump Station (ABISRP 03.1) and
Modernization and Rehabilitation of Kizil Tepa Pump Station (ABISRP 03.2) contracts.
See the table below.
31/01/20
SEMP not completed Finalize SEMP
(Open)
Modernization and Rehabilitation of Amu Bukhara Main Canal Regulating Structure (ABISRP 02)
10/08/18
EMR of the Contractor not prepared Prepare EMP
(Open)
Modernization and Rehabilitation of Kuyu Mazar and Kizil Tepa Pump Stations (ABISRP 03)
47. During this reporting period (January 1st ,2020 – June 30th, 2020) no new
Non- Conformance issues have been recorded. Six issues have been closed from
15 July 2020 15
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
48. The distribution of Non-Conformance issues based on priority is shown at the Figure
3-1 and non-conformance level at the Figure 3-2.
15 July 2020 16
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
49. Duration to close any issue takes approximately 5 months. The distribution of days
required to close any issue has been shown in Figure 3-3.
15 July 2020 17
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
3.4 Trends
50. Based on the record time, the trends of issues closed has been given at the following.
Total Number of
Semi-annual % of issues closed % of issues closed
Issues opened at
Report No on time late
Reporting Period
6 6 60% 40%
7 6 60% 40%
8 7 15% 15%
9 7 40% 60%
10 0 44% 56%
51. During the reporting period (January 1st ,2020 – June 30th, 2020) the outbreak of
Coronavirus Disease (COVID-19) was first identified in Wuhan, China, in December
2019 and news about the extensive case has been reported in January 2020 and
implementation of entry restrictions on 18, February 2020 as well as additional anti-
COVID 19 measures have been considered as unanticipated environmental impact.
15 July 2020 18
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
52. When the outbreak of Coronavirus Disease (COVID-19) was first identified in Wuhan,
China, in December 2019 and news about the extensive case has been reported in
January 2020, PIU/SC agreed to inform the Chinese Contractors for taking measures to
avoid spreading out the COVID-19. It has been requested from the Chinese Contractors
to perform medical inquiry of the staff who returned from China on last week of January.
Uzbek authorities implemented entry restrictions on 18, February 2020 and extended
these restrictions until 01/08/2020. The Chinese contactors have started to apply the
training, health and safety procedures and disinfected the working camp, vehicles,
construction area within the scope of COVID-19 protection measures.
53. According to EMP, Contractors are responsible for conduction of environmental
monitoring activities for environmental impacts caused during the construction. These
monitoring activities are based on visual observations. There are no more requirements
on environmental monitoring included in EMP and as following in SEMP’s submitted by
the Contractors. Submitted EMR of each contractor includes the monitoring results of
environmental and health and safety activities. Contractor of Construction of Amu
Bukhara 1 NEW Pump Station (ABISRP 01) has not submitted any EMR since its SEMP
hasn’t approved yet. The Contractor of Modernization and Rehabilitation of Amu
Bukhara Main Canal Regulating Structure (ABISRP 02) does not submit any EMR. The
Contractor of modernization and Rehabilitation of Kuyu Mazar and Kizil Tepa Pump
Stations (ABISRP 03) submits regularly EMR for Kuyu Mazar and Kizil Tepa Pump
Station construction sites.
54. During the reporting period no complaints were received from people living in nearby
residential areas for any construction site. In case of receiving such complains, further
elaboration in environmental monitoring activities and solving and or settling the
problematic issues needed.
55. At all the construction sites appropriate measures were taken to prevent the pollution of
atmospheric air, to limit the dust level from working vehicles and enforce strict
observance of safety rules at main road crossing, along main roads, the mahalla streets
and near sub-project construction sites.
56. While excavation and transportation of excavating materials, additional environmental
requirements were followed: Schedule transportation activities by avoiding peak traffic
15 July 2020 19
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
periods; Use tarpaulins to cover loose material that is transported to and from the site
by truck.
57. Inspection of exhaust emissions of vehicles and machinery used has been controlled in
Uzbekistan with a regulation named “Implementation of Mandatory Technical Inspection
of Vehicles the Machinery” and numbered 54 which is in force since January 31st, 2003.
Each Contractor should hold a valid permission for the vehicles and machineries used
in the construction activities. Therefore, the vehicles and machineries used in
construction activities do not exceed limits as far as they hold a valid permission from
relevant Government authorities.
58. According to the IEE the nature of the project activities, will not generate significant
quantities of emissions, therefore visual monitoring of dust has been envisaged at the
Environmental Management Plan of the project. Since there is not any change in the
main project activities, no need for monitoring of air quality except the method stated in
Environmental Management Plan given at IEE:
59. The Contractor of Construction of Amu Bukhara 1 NEW Pump Station (ABISRP 01) is
constructing the working camp area with septic tanks and toilet facilities. Temporary
toilets exist in the field.
60. The toilet facilities for Contract ABISRP 02 exist in the Peresechenie regulator area. But
their conditions are poor. Since the number of workers are less in number, the
wastewater produced during the daily activities have been directly filtered to the ground.
The contamination risk of these effluents to the canals are low.
61. Closed septic tanks exit both for Kuyu Mazar Pump Station (ABISRP 03.1) and
Modernization and Rehabilitation of Kizil Tepa Pump Station (ABISRP 03.2) camp sites.
The collected sewage has been transferred by septic tank trucks to disposal site. In the
working field workers use toilets located at the existing pump stations.
62. During the canal cleaning works it is unavoidable to form temporary turbidity and
sediment problems. Existing water quality of the irrigation water turbid and high in
sediment amount, therefore this temporary effect could not be differentiated, unless the
sediment amount is measured before and during the cleaning activity.
4.1.3 Noise
63. The contractors have fit the daily regular working hours. It has been reported in EMR of
Contractors to use new equipment and vehicle which is appropriate for the Occupational
Health and Safety Noise levels. Since no grievance has been received from the public
it has been considered that noise level does not have any effect on public.
15 July 2020 20
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
64. The Uzbek national construction noise norms that are relevant to all stages of the
construction phase are provided by law KMK 2.01.08-96 ―Protection from noise
detailed in Table 4-1.
Table 4-1. Uzbek construction noise norms (KMK 2.01.08 96 ―Protection from noise)
1000
2000
4000
8000
31,5
Premises and territories Sound,
125
250
500
63
(dBA)
15 July 2020 21
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
1000
2000
4000
8000
31,5
Premises and territories Sound,
125
250
500
63
(dBA)
65. The Sanitarian Rules and Norms on providing allowed noise level into the living building,
public building and territory of living area (SanR&N No.0267-09) establish the maximum
admissible noise level into the living areas, both inside and outside buildings, given in
the Table 4-2.
Table 4-2. Admissible noise level into the living area, both inside and outside the
buildings (SanR&N No.0267-09)
2000
4000
8000
(dBA)
125
250
500
63
Daytime
Living room of flats, 63 52 45 39 35 32 30 28 40
07:00-23:00
bedrooms of resorts
Night-time
(inside) 55 44 35 29 25 22 20 18 30
23:00-07:00
Daytime
75 66 59 54 50 47 45 43 55
Territories adjacent to 07:00-23:00
living houses (outside) Night-time
67 57 49 44 40 37 35 33 45
23:00-07:00
66. The World Bank’s “Environmental, Health and Safety General Directives, 2007 (EHS)”
is functional instead of PPAH. EHS stipulates that noise at any activity shall not exceed
the levels given in the Table 4-3 for given receptors, nor shall they result in a greater
increase of ambient noise than 3 dB at the nearest receiving area outside the site.
Industrial; commercial 70 70
15 July 2020 22
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
Table 4-4. Comparison of Equivalent Sound Levels with the National and International
Standards
69. SEMP’s of both Kuyu Mazar Pump Station (ABISRP 03.1) construction site
Modernization and Rehabilitation of Kizil Tepa Pump Station (ABISRP 03.2) and
prospective SEMP of Amu Bukhara 1 New Pump Station (ABISRP 01) states that
“monthly noise measurement shall be done if required”. According to the results given
above it is not necessary to make monthly noise measurements.
70. During the assembling and disassembling of pumps at Kuyu Mazar Pump Station
(ABISRP 03.1) and Kizil Tepa Pump Station (ABISRP 03.2) construction sites, due to
working of existing pumps, noise formed. The working staff exposed to this noise
15 July 2020 23
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
produced. Therefore, PPE like earplugs shall be used and this will be checked by HSE
staff of the Contractors and SC:
4.2 Trends
71. Based on the visual inspection and EMR reports the air, noise and water quality
conditions has not considerably changed during the project construction span. The
existing performance of the Contractors has been evaluated based on the
Environmental Management Plan (EMP) of the overall project and attached to Annex I.
72. The established monitoring system is advice to be kept as they are it is early to make
any comments on ceasing/altering monitoring since the construction activities already
has been started.
73. The utilization of electricity, water and other materials for Amu Bukhara 1 New Pump
Station (ABISRP 03.1) construction site is given Table 4-5.
Table 4-5 Material Resources Utilization at Amu Bukhara 1 New Pump Station
Construction Site
74. The utilization of electricity, water and other materials for Amu Bukhara Main Canal
Regulating Structure (ABISRP 02) construction sites is given Table 4-6.
Table 4-6 Material Resources Utilization at Amu Bukhara Main Canal Regulating
Structure Construction Sites
15 July 2020 24
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
75. The utilization of electricity, water and other materials for Kuyu Mazar Pump Station
(ABISRP 03.1) and Kizil Tepa Pump Station (ABISRP 03.2) construction sites is given
Table 4-7 and Table 4-8, respectively.
Table 4-7 Material Resources Utilization at Kuyu Mazar Pump Station Construction Site
Table 4-8 Material Resources Utilization at Kizil Tepa Pump Station Construction Site
76. In previous reporting period the resource utilization records have not been kept. The
following data given at Table 4-8 covers cumulative material resource utilization at Amu
Bukhara 1 New Pump Station (ABISRP 03.1) construction site for the current reporting
period.
Table 4-9 Cumulative Material Resources Utilization at Amu Bukhara 1 New Pump
Station Construction Site
10th
Resources Reporting Total
Period
Water (m³) 20 20
Cement (tons) 40 40
Iron (tons)
Fuel (m³) 15 15
Electricity (kwh) 7000 7000
Sand (m³) 65 65
77. In previous reporting period the resource utilization records have not been kept. The
following data given at Table 4-10 covers cumulative material resource utilization at Amu
Bukhara Main Canal Regulating Structure (ABISRP 02) construction sites for the current
reporting period.
15 July 2020 25
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
Table 4-10 Cumulative Material Resources Utilization at Amu Bukhara Main Canal
Regulating Structure Construction Sites
10th
Resources Reporting Total
Period
Water (m³) 13 13
Cement (tons) 840 840
Iron (tons) 6.4 6.4
Fuel (m³) 12 12
Electricity (kwh) 1700 1700
Sand (m³) 912 912
78. In previous reporting period the resource utilization records have not been kept. The
following data given at Table 4-11 and Table 4-12 covers cumulative material resource
utilization at Kuyu Mazar Pump Station (ABISRP 03.1) and in Kizil Tepa Pump Station
(ABISRP 03.2) construction sites for the current reporting period.
Table 4-11 Cumulative Material Resources Utilization at Kuyu Mazar Pump Station
Construction Site
10th
Resources Reporting Total
Period
Water (m³) 334 334
Cement (tons) 372 372
Iron (tons) 89 89
Fuel (m³) 355 355
Electricity (kwh) 2392 2392
Sand (m³) 155 155
Table 4-12 Cumulative Material Resources Utilization at Kizil Tepa Pump Station
Construction Site
10th
Resources Reporting Total
Period
Water (m³) 549 549
Cement (tons) 73 73
Iron (tons) 12 12
Fuel (m³) 19 19
Electricity (kwh) 3108 3108
Sand (m³) 129 129
4.5 Waste Management
79. Amu Bukhara Main Canal Regulating Structure (ABISRP 02) Contractor has not signed
any contract related to the waste disposal. The waste originated from their construction
and worker’s daily activities disposed to the municipal solid waste disposal areas by
their own trucks/tractors.
15 July 2020 26
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
80. The Contractor of Modernization and Rehabilitation of Kuyu Mazar Pump Station
(ABISRP 03.1) has submitted a Waste Management Plan on 11th May 2018 and
Hazardous Materials Management Plan on 10th May 2018 (Semi-annual EMR R.06).
81. The solid waste disposal area of Contractor of Modernization and Rehabilitation of Kuyu
Mazar Pump Station (ABISRP 03.1) has been declared as Kuyu Mazar Solid Waste
Disposal area which is approximately 3 km away from the Kuyu Mazar Pumping Station.
82. The Contractor of Modernization and Rehabilitation of Kuyu Mazar Pump Station
(ABISRP 03.1) has extended the period of the protocol signed with Toza-Khudud firm
for collection, transfer, and disposal of the domestic solid waste. The protocol is valid
until the 31st December 2020.
83. The Contractor of Modernization and Rehabilitation of Kizil Tepa Pump Station (ABISRP
03.2) has submitted a Waste Management Plan on 11th May 2018 and Hazardous
Materials Management Plan on 10th May 2018 (Semi-annual EMR R.06).
84. The solid waste disposal area of Contractor of Modernization and Rehabilitation of Kizil
Tepa Pump Station (ABISRP 03.2) has been declared a local Solid Waste Disposal area
which is approximately 6 km away from the Kizil Tepa Pumping Station.
85. The Contractor of Modernization and Rehabilitation of Kizil Tepa Pump Station (ABISRP
03.2) has extended the period of the protocol signed with Toza-Khudud firm for
collection, transfer, and disposal of the domestic solid waste. The protocol is valid until
the 31st December 2020.
86. At the prospective SEMP of the Contractor of Amu Bukhara 1 New Pump Station
(ABISRP 01) a Waste Management Plan on 11th May 2018 and Hazardous Materials
Management Plan have been provided. In the same SEMP it has been indicated that
contracts will be signed with the licensed companies in order to transport and dispose
the solid and hazardous wastes.
87. Amu Bukhara Main Canal Regulating Structure (ABISRP 02) Contractor has no record
about the type, quantity of waste produced and disposed. Any domestic solid waste has
not been observed at the construction and or camping sites.
88. During the previous reporting period (1st July – 30th December 2019) the Contractor of
Modernization and Rehabilitation of Kuyu Mazar Pump Station (ABISRP 03.1) was not
able to provide the solid waste disposal records. However, the transfer and disposal of
solid waste has been realized by Toza-Khudud firm. The contractor has been asked to
provide the relevant data until 04/01/2020. The Contractor provided the data on
10/01/2020. Based on the provided data during the previous reporting period (1st July –
30th December 2019) ten times of solid waste disposal has been realized by the Toza-
Khudud firm. The contractor of Modernization and Rehabilitation of Kuyu Mazar Pump
15 July 2020 27
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
Station (ABISRP 03.1) have recorded solid waste disposal data for the current reporting
period (1st January 2020 – 30th June 2020) also. During the current reporting period
fourteen times solid waste has been dumped by the same firm. The following table
summarizes the solid waste disposal data for the previous reporting period (1st July –
30th December 2019) and current reporting period (1st January 2020 – 30th June 2020).
Slightly Hazardous
Nearly No Hazard
Medium Hazard
Very Hazardous
Hazardous
Date of Solid Waste
Type IV
Type III
Type V
Type II
Storage Area
Transfer Type I
15 July 2020 28
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
89. During the current reporting period (1st January 2020 – 30th June 2020) the Contractor
of Modernization and Rehabilitation of Kizil Tepa Pump Station (ABISRP 03.2) has
dumped twenty two times domestic solid waste to the site defined at Paragraph 84. The
recorded disposals are given in the following table below. The transfer and disposal of
domestic solid waste has been realized by Toza-Khudud firm.
Slightly Hazardous
Nearly No Hazard
Medium Hazard
Very Hazardous
Hazardous
Date of Solid Waste
Type IV
Type III
Type V
Type II
Storage Area
Type I
Transfer
8, January,2020 7 Toza-Khudud
8, January,2020 14 Toza-Khudud
1, March,2020 7 Toza-Khudud
7, April,2020 6 Toza-Khudud
5, June,2020 3 Toza-Khudud
15 July 2020 29
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
90. During the current reporting period (1st January 2020 – 30th June 2020) totally 201.50
m³ of solid waste has been originated within the scope of Amu Bukhara Irrigation System
Rehabilitation Project. The cumulative solid waste generation volume reached to
457.90 m³ during the current reporting period (1st January 2020 – 30th June 2020).
Approximately 9% of cumulative waste volume has been restored for reuse and
recycling purposes at the premises of ABMK Kizil Tepa storage areas. The progress in
solid waste disposal has been shown in the below table.
Volume (m³)
EMR Kuyu Mazar Kizil Tepa Total
Report Recycled
Number Recycled Recycled
Disposed Disposed Disposed or
or Reused or Reused
Reused
6 3.00 0 3.90 0 6,90 0
7 42.62 0 12.00 42,00 54,62 42.00
8 11.88 0 18.00 0,00 29,88 0
9 53.00 0 70.00 0 123.00
10 53.50 0 148.00 0 201.50
Total 57,50 0 251.90 42.00 415.90 42.00
4.6 Health and Safety
4.6.1 Community Health and Safety
91. During the current reporting period (1st January – 30th June 2020) there were only one
accident on March 2020 at the Kizil Tepa Pump Station (ABISRP 03.2). In the former
accident (March 2020), one Chinese worker who worked at height fell down at the
working site. The worker was injured at his rebar. He was sent to the hospital and
immediately treated. The Uzbek National Authorities carried out investigation at site and
reported that the accident was a minor one. There is no responsibility attributed to the
Contractor by the investigators. No corrective actions were requested from the
Contractor for this accident. It should be noted that the engineer should prepare
corrective action plans and take necesssary measures to ensure such accidentts do not
happen in future, in timely manner. At other construction sites there were no incidents
occurred within the scope of Community Health and Safety issues, including the traffic
accidents.
92. As stated in paragraph 52 when the outbreak of Coronavirus Disease (COVID-19) was
first identified in Wuhan, China, in December 2019 and news about the extensive case
15 July 2020 30
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
has been reported in January 2020, PIU/SC agreed to inform the Chinese Contractors
for taking measures to avoid spreading out the COVID-19. It has been requested from
the Chinese Contractors to perform medical inquiry of the staff who returned from China
on last week of January. HSE Plan / SSEMP has not been updated with COVID-19 risk
assessment yet. Contractor was requested to update both plans in Q3 2020 and reflect
accordingly in the next SAEMR due in January 2021. The measures have been
successfully applied by the Contractors. Besides that, when Uzbek authorities declared
the measures to control COVID-19 the Chinese contactors have started to apply the
training, health and safety procedures and disinfection at the working camp, vehicles,
construction area within the scope of COVID-19 protection measures.
93. Amu Bukhara Main Canal Regulating Structure (ABISRP 02) Contractor have carried
out the construction activities in the Hydraulic structure "Peresecheniye" discharge
"Vodovypusk". Working staff use PPE due to, daily check, and immediate cautions to
the Contractor of the SC team.
94. Kuyu Mazar Pump Station (ABISRP 03.1) contractor and Kizil Tepa Pump Station
(ABISRP 03.2) contractor has trained staff during the current reporting period (1st
January – 30th June 2020) for site access, environmental education, occupational health
and safety education including the safety measures to applied to protect from
COVID- 19 pandemic.
95. During the site visit it has been observed that the health and safety instruction posters
have been attached to a board in the working site. Kuyu Mazar Pump Station (ABISRP
03.1) contract and Kizil Tepa Pump Station (ABISRP 03.2) contract.
96. During site audit during the previous report in 28/December/2019 it had been observed
that the implementation of safety rules is poor in Kuyu Mazar Pump Station (ABISRP
03.1) construction site. Since one of the technical staff was smoking at the fuel storage
area. It has been advised to HSE manager Mr. Miao Guowang to conduct a safety
training until 31/January/2020. Mr. Miao Guowang has conducted an additional safety
training on 10/January/2020 on this aspect. Besides that, it has been reported that the
smoker has been punished.
4.7 Training
97. Mr. Miao Guowang as the Health and Safety Specialist of Kuyu Mazar Pump Station
(ABISRP 03.1) contract has conducted regular HSE, environmental, site access and
COVID-19 protection trainings for the Chinese staff working at the Kuyu Mazar
construction site during the current reporting period (1st January 2020 – 30tht June 2020).
98. Mr. Zhang Zehui as the Health and Safety Specialist of Kizil Tepa Pump Station
(ABISRP 03.2) contract has conducted regular HSE, environmental, site access and
15 July 2020 31
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
COVID-19 protection trainings for the Chinese staff working at the Kizil Tepa
construction site during the current reporting period (1st January 2020 – 30tht June 2020).
99. Mr. Aziz Juraev as local HSE administrator of Kuyu Mazar Pump Station (ABISRP 03.1)
contract and Kizil Tepa Pump Station (ABISRP 03.2) contract has conducted regular
HSE, environmental, site access and COVID-19 protection trainings for the local staff
working at both sites during the reporting period (1st January 2020 – 30tht June 2020).
15 July 2020 32
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
100. The fourth revision of SEMP about the Amu Bukhara 1 New Pump Station (ABISRP 01)
have been submitted on 21/April/2020. The comments have been provided to the
contractor to revise and submit the final SEMP as soon as possible on 22/April/2020.
101. Amu Bukhara Main Canal Regulating Structure (ABISRP 02) Contractor has submitted
the SEMP just to fulfil its administrative obligations. However, the contractor acts as
unaware of existence of SEMP which has been submitted third revision on 24th January
2017 and has received conditionally no objection on date 20th December 2016) and does
not submit EMR accordingly. Unfortunately, repetitive cautions have not cared by the
Amu Bukhara Main Canal Regulating Structure (ABISRP 02) Contractor.
102. Currently SEMP of Modernization and Rehabilitation of Kuyu Mazar Pump Station
(ABISRP 03.1) (14th February 2018 is submission date of third revision and 20th
February 2018 no objection date) and Modernization and Rehabilitation of Kizil Tepa
Pump Station (ABISRP 03.2) (14th February 2018 is submission date of third revision
and 20th February 2018 no objection date) considered to fit the environmental
requirements of the construction activities. No revisions required on the existing SEMP
of Kuyu Mazar Pump Station (ABISRP 03.1) and SEMP of Kizil Tepa Pump Station
(ABISRP 03.2) due to construction activities.
103. SSEMP has not been updated with COVID-19 risk assessment yet. Contractor was
requested to update SSEMP in Q3 2020 and reflect accordingly in the next SAEMR due
in January 2021
15 July 2020 33
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
104. Prior to the declaration of COVID-19 as pandemic disease all over the world by WHO
and in Uzbekistan, the project administration PIU/SC has considered the possible
COVID-19 infections of the Chinese workers who travelled from China and requested
the contractors apply hygiene control and inspection measures for their staff.
105. After the designation of the environmental staff by the Amu Bukhara 1 New Pump
Station (ABISRP 01) Contractor a training program is proposed to be conducted by SC.
The subject of the training program will cover environmental, occupational health and
safety trainings of the contractor’s staff, monitoring, recording, and reporting
responsibilities of the contractor.
15 July 2020 34
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
7.1 Summary
106. During the current reporting period (1st January 2020- 30th June 2020) the following
environmental safeguard activities have been performed:
• Preparation of third version of SEMP of Amu Bukhara 1 New Pump Station (ABISRP
01) by China National Technical Import & Export Corporation (CNTIC) on
28/January/2020 and review of it by Saban Cimen on 29/January/2020. Fourth
version of SEMP has been submitted on 21/April/2020 and reviewed on 22/April/2020
by Saban Cimen.
• Routine daily site visits by Site Engineers of Supervision Consultant including
environmental, occupational health and safety issues.
7.2 Recommendations
107. Conduct environmental audit by SC on Site environmental and health and safety
conditions of the Contractor ABISRP 02, ABISRP 03.01 and 02 sites till the end of next
reporting period (Q3-Q4, 2020).
108. The Contractor of Modernization and Rehabilitation of Kuyu Mazar Pumping Station
(ABISRP 03.1) shall leave the disposal site of the dredged material as “levelled and
planted” which is defined in the permission obtained from the Novai Ecology and
Environmental Protection Headquarter on 21st February 2019. The levelling of the
disposal site is part of the contract which is defined at Article 11.12 of Chapter 11 on
Architecture and Landscaping. Planting of this site is an issue to be resettled with the
Novai Ecology and Environmental Protection Headquarter. Since the priority of this
issue compared to the completion of work is less therefore the deadline of the
implementation is agreed as 19th September 2020.
109. The Contractor of Modernization and Rehabilitation of Kizil Tepa Pumping Station
(ABISRP 03.2) shall leave the disposal site of the dredged material as “levelled and
planted” which is defined in the permission obtained from the Bukhara Ecology and
Environmental Protection Headquarter on 22nd April 2019. The levelling of the disposal
site is part of the contract which is defined at Article 11.12 of Chapter 11 on Architecture
and Landscaping. Planting of this site is an issue to be resettled with the Bukhara
Ecology and Environmental Protection Headquarter. Since the priority of this issue
compared to the completion of work is less therefore the deadline of the implementation
is agreed as 19th September 2020.
15 July 2020 35
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
110. It has been requested from China National Technical Import & Export Corporation
(CNTIC) to finalize the SEMP of Amu Bukhara 1 New Pump Station (ABISRP 01) until
31/January/2020, which could not be realized. Finalization of SEMP becomes an urgent
issue.
111. PPE usage at the all construction sites of Amu Bukhara Main Canal Regulating Structure
(ABISRP 02) Contractor is an issue to be monitored regularly by SC and reported in
next EMR report. This will be continuous monitoring activity.
112. Contractor to update H&S Plan and SSEMP with COVID-19 risk assessment and
relevant mitigation measures – Q3 2020.
15 July 2020 36
ANNEX I - PERFORMANCE EVAULATION OF ENVIRONMENTAL MONITORING
OF ABISRP
Achievement from Commencement of
Data Source Frequency Responsibility Project Till end of Reporting Period
(Yes(Y)/No(N)/Not Applicable(N/A))
ABISRP 03
INDICATORS
How it will be How often it will Who will
ABISRP 01
ABISRP 02
ABISRP 04
measured? be measured? measure it?
General
Lot Lot
1 2
PRE-CONSTRUCTION PHASE
By the activities of
Once in the initial
Has the Consultant reviewed IEE? PIU Technical EEC Y N/A N/A N/A N/A N/A
phase of project.
Assistance Team
If the IEE has been updated has it been sent
to the ADB for approval?
By the activities of
Once in the initial
PIU Technical EEC Y N/A N/A N/A N/A N/A
phase of project.
Assistance Team
AI-1
15 July 2020
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
ABISRP 03
INDICATORS
How it will be How often it will Who will
ABISRP 01
ABISRP 02
ABISRP 04
measured? be measured? measure it?
General
Lot Lot
1 2
Has the PIU submitted IEE assessment
report for approval to the National
Authorities?
By the activities of
Once in the initial
PIU Technical PIU Y N/A N/A N/A N/A N/A
phase of project.
Assistance Team
AI-2
15 July 2020
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
ABISRP 03
INDICATORS
How it will be How often it will Who will
ABISRP 01
ABISRP 02
ABISRP 04
measured? be measured? measure it?
General
Lot Lot
1 2
Has the Consultant included the EMP as a
special Condition in the Bid Document?
By the activities of
Once in the initial
PIU Technical PEC Y N/A N/A N/A N/A N/A
phase of project.
Assistance Team
AI-3
15 July 2020
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
ABISRP 03
INDICATORS
How it will be How often it will Who will
ABISRP 01
ABISRP 02
ABISRP 04
measured? be measured? measure it?
General
Lot Lot
1 2
Does the Contractor's design provide safety Once in the review
By technical
guards on the areas exposed to the of design MEC N/A N/A N/A Y Y N/A
review
machinery? documents
Once in the review
Does the Contractor's design have any By technical
of design CEC N/A N/A Y Y Y Y
drainage facility to lower ground water? review
documents
Does the design consider critical periods for Once in the review
By technical
biological life and adhere any avoidance of design EEC N/A N/A N/A N/A N/A N/A
review
plan? documents
Does the Contractor have proper survey N/A
equipment? Once in the review
By technical
of design CEC N/A Y Y Y Y
review N/A
documents
Does the design ensure free access to the Once in the review
By technical
facilities and availability of roads to them of design CEC N/A N/A Y Y Y Y
review
for O&M? documents
AI-4
15 July 2020
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
ABISRP 03
INDICATORS
How it will be How often it will Who will
ABISRP 01
ABISRP 02
ABISRP 04
measured? be measured? measure it?
General
Lot Lot
1 2
Does the design take care the placement of Once in the review
By technical
building and facilities considering fire of design MEC N/A N/A N/A Y Y N/A
review
breaks? documents
Once in the review
Does the design consider Corrosion By technical
of design CEC N/A N/A Y Y Y Y
protection of buildings by ground water? review
documents
Once in the review
Does the design care the fireproof materials By technical
of design CEC N/A N/A N/A Y Y N/A
where necessary? review
documents
Has the Contractor checked the desilting Once in the review
By technical
efficiency of inlet canal design and desilting of design CEC N/A N/A Y Y Y Y
review
basins? documents
Once in the review
Has the Contractor developed inlet having By technical
of design CEC/MEC N/A N/A Y Y Y Y
sand trap and/or other alternative devices? review
documents
Once in the review
Does the design consider oil separators to By technical
of design CEC/MEC N/A N/A N/A Y Y N/A
have oil concentration less than 0.3 mg/l? review
documents
Does the Contractor develop a Worker Once in the review
By technical
Safety Plan in compliance with Uzbekistan of design EEC N/A N/A Y Y Y Y
review
Labor Code? documents
AI-5
15 July 2020
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
ABISRP 03
INDICATORS
How it will be How often it will Who will
ABISRP 01
ABISRP 02
ABISRP 04
measured? be measured? measure it?
General
Lot Lot
1 2
Once in the review
Does the design consider protection By technical
of design MEC N/A N/A N/A N/A N/A N/A
measures for pipes laid in saline areas? review
documents
Does the design consider safety conditions
Once in the review
of crossing, bridges that will be used for By technical
of design CEC N/A N/A Y N Y Y
transportation of vehicles, equipment, and review
documents
staff?
Does the design consider landscaping Once in the review
By technical
convenient to the prevailing natural of design EEC N/A N/A Y N/A N/A Y
review
conditions? documents
Does the design consider training of O&M Once in the review
By technical
staff on mechanical and electrical of design EEC N/A N/A N/A Y Y Y
review
equipment? documents
Once in the review
Does the design consider supplying By technical
of design ElEC N/A N/A N/A Y Y N/A
transformers free of PCB? review
documents
Once in the review
Is the EMP attached to the Contract to form By technical
of design PEC Y Y Y Y Y Y
a part of Contract Documents? review
documents
AI-6
15 July 2020
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
ABISRP 03
INDICATORS
How it will be How often it will Who will
ABISRP 01
ABISRP 02
ABISRP 04
measured? be measured? measure it?
General
Lot Lot
1 2
Once in the review
Does the design consider the irrigational By technical
of design MEC N/A N/A Y Y Y Y
and drinking water requirements? review
documents
Once in the review
Has PIU evaluated the bidder by checking By technical
of design PEC N/A Y Y Y Y Y
EMP requirements? review
documents
Once in the review
Has the Contractor prepared an acceptable By technical
of design CEC Y N Y Y Y Y
EMP based on the Approved IEE? review
documents
Once in the review
Has the Contractor developed Contingency By technical
of design EEC N/A N Y Y Y Y
Plan for accidents including spill of fuel? review
documents
Once in the review
Has the Contractor submitted the Site By technical
of design EEC N/A Y Y Y Y Y
Environmental Management Plan? review
documents
Once in the initial
Does the Contractor publish a public notice
phase of
regarding the nature and location of the Questionnaires C N/A N/A N N/A N/A N
construction
project?
project.
AI-7
15 July 2020
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
ABISRP 03
INDICATORS
How it will be How often it will Who will
ABISRP 01
ABISRP 02
ABISRP 04
measured? be measured? measure it?
General
Lot Lot
1 2
Once according to
By the activities of
Has the Consultant conducted training the time schedule
PIU Technical EEC Y N/A N/A N/A N/A N/A
program for WCA? of the training
Assistance Team
program
Once according to
By the activities of
Has the Consultant conducted training the time schedule
PIU Technical EEC/MEC N N/A N/A N/A N/A N/A
program for BISA? of the training
Assistance Team
program
Once before the
Has the EMP been explained to the By the activities of
commencement of
Contractor before the commencement of PIU Technical PMC/EEC/PIU N/A Y Y Y Y Y
construction
works? Assistance Team
project.
Once in bid
Has the Contractor defined Safety Officer? Biding Documents C N/A Y N Y Y N
evaluation phase
CONSTRUCTION PHASE
AI-8
15 July 2020
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
ABISRP 03
INDICATORS
How it will be How often it will Who will
ABISRP 01
ABISRP 02
ABISRP 04
measured? be measured? measure it?
General
Lot Lot
1 2
Does the Contractor handle the protected
plant species, trees taking care of
Questionnaires monthly C N/A N/A Y Y Y Y
environmental concerns and/or
permissions?
Does the Contractor excavate and preserve
Questionnaires monthly C N/A Y N N/A N/A N
the topsoil?
AI-9
15 July 2020
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
ABISRP 03
INDICATORS
How it will be How often it will Who will
ABISRP 01
ABISRP 02
ABISRP 04
measured? be measured? measure it?
General
Lot Lot
1 2
Has the Contractor take measures for
providing water continuously during Questionnaires monthly C N/A N/A Y N/A N/A Y
construction work?
AI-10
15 July 2020
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
ABISRP 03
INDICATORS
How it will be How often it will Who will
ABISRP 01
ABISRP 02
ABISRP 04
measured? be measured? measure it?
General
Lot Lot
1 2
Has the Contractor taken noise prevention
measures for staff using noisy equipment, Questionnaires monthly C N/A Y N Y Y N
vehicles?
Is the nearest residential area affected by
Questionnaires monthly C N/A Y N N N N
the noise level?
Has the working activities limited by
Questionnaires monthly C N/A N Y N N Y
daylight hours?
Does the Contractor have a water tanker for
Questionnaires monthly C N/A N N N N Y
spraying water to roads?
Does the Contractor suppress the dust by
Questionnaires monthly C N/A Y Y Y Y Y
watering?
AI-11
15 July 2020
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
ABISRP 03
INDICATORS
How it will be How often it will Who will
ABISRP 01
ABISRP 02
ABISRP 04
measured? be measured? measure it?
General
Lot Lot
1 2
AI-12
15 July 2020
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
ABISRP 03
INDICATORS
How it will be How often it will Who will
ABISRP 01
ABISRP 02
ABISRP 04
measured? be measured? measure it?
General
Lot Lot
1 2
AI-13
15 July 2020
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
ABISRP 03
INDICATORS
How it will be How often it will Who will
ABISRP 01
ABISRP 02
ABISRP 04
measured? be measured? measure it?
General
Lot Lot
1 2
Does security staff exist in the working
Questionnaires monthly C N/A N/A Y Y Y Y
area?
Does the working area have fencing in order
Questionnaires monthly C N/A N/A N Y Y N
to protect intrusion?
Has the Contractor defined solid waste
Questionnaires monthly C N/A N/A Y Y Y Y
storage area?
Has the Contractor defined the area for
Questionnaires monthly C N/A N/A N Y Y N
used material storage?
Does the Contractor apply solid waste
Questionnaires monthly C N/A N/A N Y Y N
separation for recyclable solid waste?
Does the Contractor keep any record for the
Questionnaires monthly C N/A N/A N Y Y N
waste recycled?
Does the Contractor keep any record for the
Questionnaires monthly C N/A N/A N Y Y N
solid waste disposed?
Does the Contractor keep any record for the
Questionnaires monthly C N/A N/A N Y Y N
hazardous waste disposed?
Does the Contractor use the local public
roads even the avoidance from these Questionnaires monthly C N/A N/A Y Y N/A Y
road(s) possible?
Has the Contractor collected and disposed
Questionnaires monthly C N/A N/A Y Y Y Y
the solid waste regularly?
AI-14
15 July 2020
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
ABISRP 03
INDICATORS
How it will be How often it will Who will
ABISRP 01
ABISRP 02
ABISRP 04
measured? be measured? measure it?
General
Lot Lot
1 2
Does the Contractor discharge the
Questionnaires monthly C N/A N/A N N/A N/A N
sewerage after treatment?
Does the Contractor avoid the peak hours of
local traffic in case of use of local public Questionnaires monthly C N/A N/A Y N/A N/A Y
roads?
Does the material carried on public roads
Questionnaires monthly C N/A N/A Y Y Y Y
covered?
AI-15
15 July 2020
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
ABISRP 03
INDICATORS
How it will be How often it will Who will
ABISRP 01
ABISRP 02
ABISRP 04
measured? be measured? measure it?
General
Lot Lot
1 2
Has the Contractor removed the soil if they
Questionnaires monthly C N/A N/A Y Y Y Y
contaminated?
Has the Contractor left the working area as
defined in Landscape section of the Bidding Questionnaires monthly C N/A N/A Y N/A N/A Y
Documents?
Has the Operating Personnel signed and
accepted all work sites, labor camps,
Questionnaires monthly C N/A N/A N N N N
storage areas and temporary dumping
areas?
Interview with the
Number of grievances about the
relevant monthly BISA N/A N/A 0 0 0 0
Contractor?
authorities
Interview with the
Number of grievances solved by the
relevant monthly BISA N/A N/A 0 0 0 0
Contractor?
authorities
Has the Contractor provided the training on Once when the
the safe use of electricity and pumps for Questionnaires project activities ElEC N/A N/A N/A Y Y N/A
operational staff? completed
Once when the
Has the Contractor evaluated the trained
Questionnaires project activities MEC/ElEC N/A N/A N/A N/A N/A N/A
O&M staff?
completed
AI-16
15 July 2020
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
ABISRP 03
INDICATORS
How it will be How often it will Who will
ABISRP 01
ABISRP 02
ABISRP 04
measured? be measured? measure it?
General
Lot Lot
1 2
Has the Consultant trained the WCA, BISA Once when the
staff for irrigation canal and drainage canal Questionnaires project activities EEC Y N/A N/A N/A N/A N/A
management? completed
Once when the
Has the Consultant evaluated the trained
Questionnaires project activities EEC Y N/A N/A N/A N/A N/A
WCA, BISA staff?
completed
Once when the
Has the Oil Separator regularly checked and
Questionnaires project activities EEC N/A N/A N/A N/A N/A N/A
properly maintained?
completed
Once when the
Has the relevant organizations observed the
Questionnaires project activities EEC N N/A N/A N/A N/A N/A
irrigation water quality?
completed
Once when the
Has the relevant organizations observed the
Questionnaires project activities EEC N N/A N/A N/A N/A N/A
ground water level in the irrigation area?
completed
Once when the
Have the farmers applied crop rotation? Questionnaires project activities BISA N N/A N/A N/A N/A N/A
completed
Once when the
Have the farmers applied environmentally
Questionnaires project activities BISA N N/A N/A N/A N/A N/A
friendly agricultural production techniques?
completed
AI-17
15 July 2020
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
ABISRP 03
INDICATORS
How it will be How often it will Who will
ABISRP 01
ABISRP 02
ABISRP 04
measured? be measured? measure it?
General
Lot Lot
1 2
Once when the
Has the fertility and productivity been
Questionnaires project activities BISA N N/A N/A N/A N/A N/A
enhanced?
completed
Once when the
Has the O&M staff applies the national
Questionnaires project activities C N/A N/A N Y Y N
Worker Safety Plan?
completed
Has the Contractor made facilities available Once when the
in the operational building with the clean Questionnaires project activities C N/A N/A Y Y Y Y
drinking water? completed
Has the Contractor made facilities available Once when the
in the operational building with sewerage Questionnaires project activities C N/A N/A N Y Y N
disposal/handling? completed
Once when the
Has the international agreements about the
Questionnaires project activities EEC N/A N/A N/A N/A N/A N/A
water abstraction been fitted?
completed
GENERAL ENVIRONMENTAL IMPACTS OF THE PROJECT ON THE ENVIRONMENT
Flow amount of water in channels? Measurement Monthly BISA/WCA N N/A N/A N/A N/A N/A
Irrigated Area (ha) Measurement Monthly BISA/WCA N N/A N/A N/A N/A N/A
Amount of water used for irrigation
Measurement Monthly BISA/WCA N N/A N/A N/A N/A N/A
purposes.
AI-18
15 July 2020
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
ABISRP 03
INDICATORS
How it will be How often it will Who will
ABISRP 01
ABISRP 02
ABISRP 04
measured? be measured? measure it?
General
Lot Lot
1 2
Amount of water used for irrigation Health Statistics of PIU from local
Yearly N N/A N/A N/A N/A N/A
purposes. Local Authorities MoH
Monthly
Electricity Consumed before the project by Electricity Meter
Consumed, yearly BISA N N/A N/A N/A N/A N/A
pumping? Records
total
Monthly
Electricity Consumed after the project by Electricity Meter
Consumed, yearly BISA N N/A N/A N/A N/A N/A
pumping? Records
total
AI-19
15 July 2020
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 - June 2020)
ABISRP 03
INDICATORS
How it will be How often it will Who will
ABISRP 01
ABISRP 02
ABISRP 04
measured? be measured? measure it?
General
Lot Lot
1 2
Water quantity pumped before Flow Monthly, average
BISA N N/A N/A N/A N/A N/A
rehabilitation/reconstruction? Measurement flow
Water quantity pumped after Flow Monthly, average
BISA N N/A N/A N/A N/A N/A
rehabilitation/reconstruction? Measurement flow
Once based on
Reduction in % of GHG by implementation yearly energy Calculated by
Calculations N/A N/A N/A N/A N/A N/A
of project? consumption PIU CCMS
amounts
BISA : Basin Irrigation System Authority of Regions
C: Contractor of any Subcomponent
CEC: Civil Engineer of Consultant
CCMS: Climate Change Mitigation Specialist
EEC: Environmental Expert of Consultant
ElEC: Electrical Engineer of Consultant
EMR: Environmental Monitoring Report
MEC: Mechanical Engineer of Consultant
MoH : Ministry of Health
MRoC: Monthly Report of the Contractor about the Implementation of EMP
PEC: Procurement Expert of Consultant
PMC: Project Manager of Consultant
PIU: Project Implementation Unit
WCA: Water Consumer Associations
AI-20
15 July 2020
Amu Bukhara Irrigation System Rehabilitation Project
Environmental Monitoring Report (January 2020 – June 2020)
Excavation Works
AII-1
15 July 2020
COVID -19 Training
Training of COVID-19
April 2020
AII-2
15 July 2020
Modernization & Rehabilitation of Amu Bukhara Main Canal Regulation Structures
(ABISRP 02)
AII-3
15 July 2020
Modernization and Rehabilitation of Kuyu Mazar Pump Station (ABISRP 03.1)
Hazardous /Recyclable Solid Waste Storage Occupational Health and Safety Training
Containers 10 January 2020
10 January 2020
AII-4
15 July 2020
Training of COVID-19
April 2020
AII-5
15 July 2020
Modernization and Rehabilitation of Kizil Tepa Pump Station (ABISRP 03.2)
AII-6
15 July 2020
Training of COVID-19 Disinfection due to COVID-19
April 2020 April 2020
AII-7
15 July 2020
ANNEX III
ACOUSTIC REPORT
FOR
AMU BUKHARA 1 NEW PUMP STATION
(ABISRP 01) CONSTRUCTION SITE
1 GENERAL KNOWLEDGE
Amu Bukhara 1 New Pump Station (ABISRP 01) Construction site has been located
approximately 1.3 km away from northwest of Dengizkul Lake.
To ensure acceptable levels of sound pressure and sound levels in rooms, workplaces,
industrial sites, in residential and public buildings, living areas of cities and other settlements
the project must comply with a couple of Uzbek legislations.
The Uzbek national construction noise norms that are relevant to all stages of the construction
phase are provided by law KMK 2.01.08-96 ―Protection from noiseǁ and detailed in Table 1
below.
Table 1- Uzbek construction noise norms (KMK 2.01.08 96 ―Protection from noise)
Equivalent sound pressure levels, Leq (dB)
Level of
Premises and territories Sound,
1000
2000
4000
8000
31,5
(dBA)
125
250
500
63
AIII-1
15 July 2020
Equivalent sound pressure levels, Leq (dB)
Level of
Premises and territories Sound,
1000
2000
4000
8000
31,5
(dBA)
125
250
500
63
6. Class premises, exercise
rooms, auditoriums of
schools and other
educational facilities,
82 63 52 45 39 35 32 30 28 40
conference halls, audience
halls of theatres, clubs,
cinemas, halls for court
sessions and meetings.
7. Administration working
premises, working premises
of design and engineering 86 71 61 54 49 45 42 40 38 50
organizations, scientific and
research institutes
8. Café, restaurant, canteen
halls, lobby of theatres and 89 75 66 59 54 50 47 45 43 55
cinemas
9. Trading halls of shops,
sport halls, waiting halls of
airports and transport
93 79 70 63 58 55 52 50 49 60
stations, reception centers of
housekeeping/ municipal
services
The ―Sanitarian Rules and Norms on providing allowed noise level into the living building,
public building and territory of living areaǁ (SanR&N No.0267-09) establish the maximum
admissible noise level into the living areas, both inside and outside buildings, given at
Table 2. In this Norm daytime is defined as time span between 07:00 and 23:00, whereas
nighttime is defined as time span between 23:00 and 07:00.
Table 2 Admissible noise level into the living area, both inside and outside the buildings
(SanR&N No.0267-09)
Level of sound pressure, octave bands
with average geometric mean frequencies
(dB) Level of
Name of Location Sound,
(dBA)
1000
2000
4000
8000
125
250
500
63
Daytime
Living room of flats, 63 52 45 39 35 32 30 28 40
07:00-23:00
bedrooms of resorts
Nighttime
(inside) 55 44 35 29 25 22 20 18 30
23:00-07:00
Daytime
75 66 59 54 50 47 45 43 55
Territories adjacent to 07:00-23:00
living houses (outside) Nighttime
67 57 49 44 40 37 35 33 45
23:00-07:00
AIII-2
15 July 2020
2.2. International Standards
Amu Bukhara Irrigation System Rehabilitation Project shall comply with Environmental
Assessment Guidelines of Asian Development Bank. It has been stated in the Environmental
Assessment Guidelines that “determining appropriate environmental standards for ADB
projects, ADB will follow the standards and approaches laid out in the World Bank’s Pollution
Prevention and Abatement Handbook (PPAH)”. Presently, PPHA is used as reference
document. The World Banks “Environmental, Health and Safety General Directives, 2007
(EHS)” is functional instead of PPAH. EHS stipulates that noise at any activity shall not exceed
the levels given in the table below for given receptors, nor shall they result in a greater increase
of ambient noise than 3 dB at the nearest receiving area outside the site.
Industrial; commercial 70 70
The nearest receptor to the Amu Bukhara 1 New Pump Station (ABISRP 01) Construction site
is the settlement area (houses) which has been located approximately 250 m northwest.
The desert and steppe landforms that comprise the region influence the sharply continental,
arid character of the climate. This continental climate is characterized by cold winters and hot,
dry summers. During the summers there are strong winds that carry sand and dust.
Average air temperature in January is 8°С in the north, and 2°С in the south. Summer is long,
hot and dry; average air temperature in July of 28°С. The annual average air temperature is
16.0°С. The average monthly minimum temperature of the coldest month is -3.0°С, and the
average monthly maximum temperature of the hottest month is 37.2°С.
There is high solar radiation up to 150 kcal and more is characteristic of this region. The
average number of sunny days per year is 300.
There are 217 frost-free days per year. The annual precipitation is 125 mm to 175 mm.
AIII-3
15 July 2020
Winds from the north and north northwest (23.6% and 19.8% respectively) predominate in the
city of Bukhara. Usually there are winds with the speed of 2-3 m/s and 4-5 m/s, their probability
of occurrence is 37.6% and 33.1%. The probability that light breezes (0-1 m/s) occur is 11.5%
of the time. The low probability of light breezes occurring is beneficial for stronger winds
promote the dispersion of air pollutants. The relative humidity data according to the closest
available data measured was in Samarkand meteorological station. Based on the observations
made between 1961-1990 the relative average humidity value is 58,58%.
AIII-4
15 July 2020
The sound levels of equipment have been calculated according to table given at the Directive
2005/88/EC of The European Parliament and of the Council of 14 December 2005 Amending
Directive 2000/14/EC on The Approximation of the Laws of The Member States Relating to the
Noise Emission in the Environment by Equipment for Use Outdoors. This table is provided
Table 4.
The sound level of the equipment that will be used in the construction have been calculated as
shown below.
Trucked Excavator: The power of the engine that will be used in both of the project areas has
been considered as 350 HP. This engine power makes approximately P=261 kW. Based on
the information provided Table 4 since P =261 kW > 55 kW the permissible sound level of the
trucked excavators used in site calculated by using the formula below.
Lw = 84 + 11 log P;
Truck: The power of the engine that will be used in both of the project areas has been
considered as 250 HP. This engine power makes approximately P=186 kW. Based on the
information provided Table 4 since P =186 kW > 55 kW the permissible sound level of the
trucks used in site calculated by using the formula below.
Lw = 82 + 11 log P;
Wheeled Loader: The power of the engine that will be used in both of the project areas has
been considered as 200 HP. This engine power makes approximately P=149 kW. Based on
the information provided Table 4 since P =149 kW > 55 kW the permissible sound level of the
wheeled loaders used in site calculated by using the formula below.
Lw = 82 + 11 log P;
The type and number of the construction site the vehicles and equipment that create sound
have been listed at the following together with their sound characteristics. All equipment listed
here will be used at open areas.
AIII-5
15 July 2020
The difference in the sound power level of any equipment by the number of the same
equipment used has been calculated by the following formula.
∆ = 10 log
Table 5. The Number of Vehicles and Equipment and their Sound Levels at Amu
Bukhara 1 New Pump Station Construction Site
Based on the information provided the information above the Table 5 the sound level difference
the sound level of the equipment is given four (4) octave at Table 6.
Table 6. Sound Pressure Level at all Directions Originated from at Amu Bukhara 1 New
Pumping Station Construction Site
Sound level at a specified “r” distance calculated by the formula and given at Table 7.
AIII-6
15 July 2020
Sound Level : = + 10 .where
Q : Directivity factor is equal to “1” since the project area which is a free field and have no
ceilings.
Table 7. Sound Pressure Level at all Directions Originated from at Amu Bukhara 1 New
Pumping Station Construction Site
Sound Pressure Levels, which are in dB, calculated has been corrected by using the correction
factors provided at Table 8 and corrected sound pressure levels have been listed at Table 9.
Table 8. Correction Factors for db(A) for the Frequencies between 500 Hz and 4000 H
Frequency Correction
Factor
500 Hz -3,2
1000 Hz 0,0
2000 Hz 1,2
4000 Hz 1,0
AIII-7
15 July 2020
Table 9. Corrected Sound Power Level at at Amu Bukhara 1 New Pumping Station
Construction Site
Atmospheric absorption values have been calculated using the following formula.
The atmospheric absorption values for 4 (four) octaves have been calculated and given at
Table 10.
AIII-8
15 July 2020
The atmospheric absorption values have been subtracted from the Corrected Sound Power
Levels given at
The total sound levels given at the Table 11 have been calculated by the following formula.
Where:
Table 11. Total Sound Level at Amu Bukhara 1 New Pumping Station Construction Site
After that all equivalent sound levels which combines all the equipment and vehicle sounds
have been calculated by using formula for a given distance.
/0 = 10 log)* + 10,1⁄)*
Where:
Sound Level at a given distance Leq dBA
AIII-9
15 July 2020
Total Sound Level LT dBA
The results of calculation for equivalent Sound Level data is given at Table 12 and graphically
shown at Figure 1
Table 12. Equivalent Sound Levels at Amu Bukhara 1 New Pumping Station
Construction Site
Distance
Leq (dBA)
(m)
50 69
100 62
250 53
500 46
1000 39
2000 31
Figure 1. Equivalent Sound Level (Leq) Variation Versus Distance at Amu Bukhara 1
New Pumping Station Construction Site
AIII-10
15 July 2020
3.4 Comparison of Results with Existing Legislation
As indicated the nearest location to the Amu Bukhara 1 New Pump Station (ABISRP 03.1)
construction site is settlement area (houses) which has been located approximately 250 m
northwest.
The equivalent sound level at this location has been calculated as 53 dBA which is already
below according to the national and international standards. (See Table 13)
Table 13. Comparison of Equivalent Sound Levels with the National and International
Standards.
AIII-11
15 July 2020