G SM PPLT Pip 805
G SM PPLT Pip 805
G SM PPLT Pip 805
SON
REV. DATE DESCRIPTION DSGN CHKD APPD
FOR APPROVAL
OWNER :
PROJECT TITLE :
Engineering, Procurement, Construction, Operation and Maintenance of
Combined Cycle Gas Turbine Project at
Sabiya Power Station
CONTRACT NO : MEW/C/4010-2009/2010
CONTRACTOR : SUBCONTRACTOR FOR POWER :
JEONGWOO INDUSTRIAL
MACHINE CO., LTD.
DESIGNED BY DATE
W.H.LEE Jun. 22, 2010
CHECKED BY DATE Inspection and Test Procedure
S.W.PYUN Jun. 22, 2010 (Strainer)
APPROVED BY DATE
I.G.SON Jun. 22, 2010
SCALE NONE DOCUMENT NUMBER REV.
G/SM/PPLT-PIP/805 0
DOCUMENT NO. G/SM/PPLT-PIP/805
INSPECTION & TEST PAGE 2 OF 12
PROCEDURE REV. NO. 0
1.1. SCOPE
This procedure describes the requirements of inspection and tests for STRAINER of
Sabiya CCGT Project
(1) The inspector shall examine the material test report or certificate of compliance and shall
determine that it represents the material and meets shall sign on it.
(2) Materials shall be inspected for the purpose of detecting imperfections, surface cracks,
requirement of specification and approved drawings.
(3) Material identification shall be performed in accordance with ASME B16.5 and material
control chart. Mark transferring shall be carried out by marking method such as only
stamping, painting, tagging, and other suitable methods.
(4) JIMC will check the following items of mill sheet for pressure retaining parts in
accordance with applicable specification or standards, prior to fabrication of the strainer.
JEONGWOO INDUSTRIAL MACHINE CO., LTD.
DOCUMENT NO. G/SM/PPLT-PIP/805
INSPECTION & TEST PAGE 4 OF 12
PROCEDURE REV. NO. 0
① Chemical composition
② Mechanical properties
③ Heat No. (or Charge No.)
④ Other items specified in the applicable codes and standards
(1) GENERAL
Joint Categories
Section Thickness, in.
A B, C, & D
Up 1/2 to inch. 1/4t 1/4t
Over 1/2 to 3/4 inch. 1/3in. 1/4t
Over 3/4 to 1 1/2 inch. 1/8in. 3/16t
Over 1 1/2 to 2 inch. 1/8in. 1/8t
Over 2 Lesser of 1/16t or 3/8in. Lesser of 1/8t or 3/4in.
① Butt welded joints shall have complete penetration and full fusion. The surface of
welds shall be sufficiently free from coarse ripples, grooves, overlaps, and abrupt
ridges and valleys.
② Reduction in thickness due to the welding process is acceptable provided all of the
following conditions are met.
a. The reduction in thickness shall not reduce the minimum required thickness.
b. The reduction in thickness shall not exceed 0.8mm or 10% of the nominal
thickness of the adjoining surface, which is less.
③ The weld grooves are completely filled so that the surface of the weld metal at any
point does not fall below the surface of the adjoining base material.
Weld metal may be added as reinforcement on each face of the weld, the thickness
of the weld reinforcement on each face shall not exceed the fellows.
① Radiography test shall be performed with 100% for welded butt joint only.
Welded joints shall be radiography in accordance with the approved procedure. If any
defect was found on the welded joint, the Radiography test shall be performed again
after repair welding is completed using a acceptable methods to the inspector.
② All of casting and forging shall be testing R.T or U.T
ALLOW
DIMENSION REMARK
TOLERANCE
30 mm under ± 1.0 mm
30 mm over 120 mm under ± 2.0 mm
120 mm over 315 mm under ± 3.0 mm
315 mm over 1000 mm under ± 5.0 mm
1000 mm over 2000 mm under ± 5.0 mm
① Deformation
② Material surface
③ Marking & Name plate description
④ Internal cleaning
⑤ All surface and cutting edge shall be smooth and free from oil, grease, scale and
weld spatter
② After the successful completion of the hydrostatic test, the bolting used during testing
shall be replaced. Service bolts, nuts and gaskets furnished by the vendor shall not
be used for testing.
The hydrostatic test pressure shall be as shown on the fabrication drawing approved by
purchasers.
(1) GENERAL
No. Item Description Design Pressure Hydro. Test Pressure Holding Time Remark
No. Item Description Design Pressure Hydro. Test Pressure Holding Time Remark
(1) Applicable code and standard : - SSPC - STEEL STRUCTURE PAINTING COUNCIL
① Surface preparation is very important for effective painting and shall be done as
followings :
a. According to SSPC SP-1, oil grease, crayon and etc shall be cleaned
b. Scale weld spatter, excess weld metal, sharp points and edge shall be removed
c. Cleaning
(a) Blast shall be done according to SSPC SP-10
(b) Acid Cleaning shall be done according to SSPC SP-8(Stainless Steel)
(c) After blast cleaning the surface shall be cleaned by air
② Painting condition
a. Humidity is sensitive to dryness of painting. When the humidity is high,
evaporation of solvent is delayed. The most effective humidity for painting is
40% ~ 80%.
③ Painting procedure
a. Preparation
When the painting material is multi-mixture, it must be mixed well enough
according to maker's instruction such as mixture rate. If it needs a solvent,
only designated solvent shall be used. Mixture rate of paint and solvent will be
controlled by painting condition. Mixing of paint shall be done before painting
and if mixed with hardening material it shall be used within effective time.
b. Painting method
(a) All painting shall be performed by standard painting system.
(b) Paint shall be sprayed or brushed uniformity on the surface, and sage and
drip is not acceptable.
(c) Spray-gun shall be operated at a adopt distance with the surface and
vertical.
(d) To obtain a equal thickness on all surface, stripe coat on weld seam and
edge is needed
(e) Bolting area and areas to be welded shall be protected before painting.
(f) Additional painting shall be done after pre-painted surface was dried well.
(g) Dry-film thickness shall be checked by coating thickness gauge and the
area under specified thickness shall be painted additionally.
c. Repair and touchup paint
Damaged surface shall be repaired by proper method and touch-up painted.
After repair painting the final painting shall be done.
d. Inspection
(a) The inspector shall witness and inspect the painting work, and use the
following equipment.
-Air Temperature Gauge
-Steel Surface Temperature Gauge
-Dry Film Thickness Gauge
(b) All surface and cutting edge shall be smooth and free from oil, weld spatter.
(c) Surface condition painting material any dry-film thickness are as follows :
-Surface Preparation : AS PER DWG. or painting procedure
(1) The requirements for packaging of products protection against corrosion, physical
Damage, contamination, or any effect that would lower the quality or cause the product
to deteriorate during the time they are shipped, handled, and stored.
(2) The product shall be protected from physical and mechanical damage. The product just
before packaging, shall have been inspected for cleanness, dirt, oil residue, metal
chip, or other forms of contamination shall have been removed.
(3) Box markings shall appear on a minimum of two sides of a box, markings shall be
included the following information :
- Contract Number or p.o no.
- Package Number & Weights
- Manufacturer Name
- Size (length X width X high = volume)