Vipros 358 King User Pre-Installation Guide
Vipros 358 King User Pre-Installation Guide
Vipros 358 King User Pre-Installation Guide
Warning
Qualified personnel must complete all work.
Do not apply power to the Vipros 358 King until an A.E.S.I. (Amada
Engineering and Service Incorporated) Engineer is present and has
instructed you to do so.
Contents
Contents ....................................................................................................................................................3
Introduction ...............................................................................................................................................5
Motion Package Specifications.................................................................................................................6
Punching System Specifications...............................................................................................................7
58 Station - 4 Auto-Index Turret Configuration ...................................................................................8
Fanuc O4PC CNC Controller....................................................................................................................9
Supply Requirements..............................................................................................................................10
Installing the Electrical Power Supply ...............................................................................................11
Installing the Air Supply.....................................................................................................................12
Planning the Location of the Vipros 358 King.........................................................................................13
Lifting the Machine ............................................................................................................................14
Machine Dimensions - Plan View......................................................................................................15
Machine Dimensions - Elevation View..............................................................................................16
Machine Dimensions - End View ......................................................................................................17
Maintenance Areas ...........................................................................................................................18
The Chiller...............................................................................................................................................19
Chiller Placement ..............................................................................................................................20
Connections.......................................................................................................................................21
Foundation Requirements.......................................................................................................................22
Machine Anchoring Requirements..........................................................................................................23
Introduction
This manual describes the tasks that the purchaser of a Vipros 358 King must complete before calling the service
organization to complete the installation and operator training.
An overview of the preparations is as follows:
Plan the location of the Vipros 358 King in the shop, taking into account all the maintenance areas indicated
on the floor plan.
Uncrate the Vipros 358 King and Fanuc O4PC control and place them on the floor.
Remove the protective coating from the surface of the Vipros 358 King.
Anchor the Machine to the floor or foundation using the apropriate method described in this document
Note: It is the purchaser’s responsibility to install any safety devices to ensure the safety area.
319
314 216 321
311 115 218
213
A/I 117 323
309 112 120
110 325
307 122
108
124 227
204 106 328
305 126
103
229
202
1200mm disk
58 STATION 230
A/I 4 AUTO INDEX A/I
201 VIPROS 358 KING VIPROS 368 KING
VIPROS 558 VIPROS 568 Number of
PEGA 358S Maximum Stations
231 Size Round
258 (Keyed)
132
155 334
357 135 233 ½" (12.7mm) 24 (16)
256 153 A
137 336 1¼" (31.7mm) 24 (24)
151 B
354 139
149 141 C 2" (50.8mm) 4 (4)
146 144 338
352
247 A/I 242 340 D 3½" (88.9mm) 2 (2)
350 245 343 B 1¼" (31.7mm) 2 (2)
348 Auto Index
E 4½" (114.3mm) 2 (2)
Supply Requirements
Electrical Power Supply Vipros 358 King 230 / 460 3ph ±10%, 28 kVA
SBC-5.5 Chiller* 230 or 460 3ph ±10%, 15 kVA
The Vipros 358 King electrical inlet is 60" above floor level inside the magnetic enclosure located to the rear of
the Fanuc O4PC control.
The SBC-5.5 chiller electrical inlet is 48" above floor level at the end of the chiller.
Vipros King SBC 5.5 Chiller
No obstacles are allowed in the worksheet travel area and the ceiling must be at least 40" above the top of
the Vipros 358 King.
All of the maintenance areas recommended should be used, but at a minimum you must ensure that the
doors of the Fanuc O4PC CNC unit can be opened.
The Vipros 358 King, Fanuc O4PC control, and SBC-5.5 chiller must be protected from direct sunlight or
other heat sources.
The floor must be of sufficent quailty to addiquitly support the wieght of the machine. See Floor Mounting
Procedure for details.
VIPROS 358
KING
Y Axis Zero
Turret Center Punch Center
45.5"
CNC Unit
Hydraulic
96.5" Unit
63.0"
55.2"
Material
Pass 39.6" 38.3" 8.3"
Line
7.1"
1.3"
103.1"
179.1"
1.2"
Maintenance Areas
81.1"
The Chiller
The Chiller Unit is very important to the reliable operation of the Vipros 358 King.
The position of the Chiller is flexible. The Vipros 358 King is supplied with two (2) fifteen-foot lengths of
hose to connect the Chiller to the Hydraulic Unit. The customer may supply a longer length of hose if
required.
Under normal operating conditions the Chiller may be placed against walls as shown. However for
maintenance purposes access to all sides of the Chiller may be required.
The Chiller must have a minimum of 60" of clearance above the Chiller for proper airflow.
Chiller Placement
|||
zzz
,,
yy
{{
zzz
|||
,,
yy
{{
Print Date 11/05/97 Page 20 of 41
This document available on the World Wide Web at http://amada.com/support/pdf/v358kuig.pdf
Vipros 358 King User Pre-installation Guide Amada America Inc.
Connections
Hydraulic Unit Chiller
Foundation Requirements
The Vipros 358 King does not require a special foundation to perform as expected, however there are minimum
requirements that an existing floor must meet in order to assure machine reliability and tool life. If the existing floor
does not meet the following minimum requirements, plans for a recommended foundation are given in the section
Foundation Mounting Procedure
The minimum acceptable floor conditions to assure a successful installation are:
The area of the floor where the machine frame is to be located must be a single, homogeneous slab in good
condition. There must be no cracks or other signs of deterioration of the floor.
Machine Foot
5.0"
Floor Line
Supplied J-bolt
24.00"
7.0" 5."
15.75" 10.00"
Machine Foot
Floor Line
Supplied J-bolt
Foundation Line
Supplied J-bolt
24.00"
7.0" 5."
15.75" 10.00"
48."
Machine Centerline
96."
48."
zzzzzz
||||||
,,,,,,
yyyyyy
{{{{{{
yyyyyyyyyy
,,,,,,,,,,
,,,,,,,,,,
yyyyyyyyyy
Print Date 11/05/97 Page 31 of 41
This document available on the World Wide Web at http://amada.com/support/pdf/v358kuig.pdf
Vipros 358 King User Pre-installation Guide Amada America Inc.
Machine Leveling
Proper Machine leveling is critical to the Vipros 358 King performing as designed.
Materials and tools required:
Supplied with the machine:
Assorted thickness machine leveling shim stock
Anchor bolts
Supplied by AESI service:
Spirit level capable of reading 0.0005"/ft
One (1) 12 ton hydraulic bottle jack
Not supplied:
Additional shim stock of 0.005" thickness may be required to achieve a properly leveled machine.
Rocking Test
After the machine frame has been leveled the use of the following G-code is necessary to determine that the machine
frame is properly leveled and balanced.
Should the machine frame vibrate or move excessively during the rocking test the machine frame must be re-leveled
using the procedure in this manual.
Should the proper leveling technique not eliminate the excessive frame motion, consideration must be given to
relocation of the machine or replacement of the existing floor with an adequate foundation.
G92 X78.740 Y50.000
G06 A.100B0
N1
G91 X-.250 TTTT (Use any valid tool number)
X.250
M97 P1
G50
Under extreme conditions the use of half-shims may not Weight Bearing Point
Sloped Floor Half-shim
move the machine weight bearing points far enough from
the machine centerline to ensure the machine frame is
stable.
Leveling Procedure
1) Determine the high end of machine frame by placing the spirit
level on the turret to measure the level of the machine frame
in the y-axis.
.0005"/ft
2) Use the bottle jack to lift the low end of the machine frame.
Shim equally between both machine feet and the base plates
until the machine frame measures near level on the y-axis
with the turret end of the machine frame slightly higher than
Bottle
the carriage end. Jack
Shim Equaly Both Sides
3) Center the bottle jack under the carriage end of the machine
frame.
Lift the machine frame until all weight is off of the machine
feet at the carriage end of the machine frame.
Remove weight
of machine from Bottle
Lift the machine frame as little as possible to take the weight base plates Jack
off of the base plates.
.0
00
Measure and record the level of the turret in the x-axis
5"
/ft
direction.
6) With the bottle jack supporting the weight of the carriage end
of the machine monitor the level of the turret in the x-axis as
the bottle jack is slowly lowered to place the carriage end
machine feet in contact with the base plates.
Any change in the level indicates that the carriage end of the Remove weight
Bottle
of machine from
machine needs to be leveled. base plates Jack
8) With all of the machine feet setting on the shims and base
plates place the spirit level on the turret to measure and note
the level of the machine frame in the y-axis.
.0005"/ft
9) Using the bottle jack lift the low end of the machine frame and
shim equally under both machine feet to level the machine
frame in the y-axis.
10) Run the machine using the rocking test G-code to determine
that the machine frame is leveled adequately. Should
excessive movement of the machine frame be noticed check
for the conditions discussed in Floor Condition Crowning and
Floor Condition Slope.
11) Tighten the anchor bolt nuts to prevent the machine frame
from moving when in use. Monitor the machine level while
tightening the anchor bolts to assure the machine level is not
changed.
12) Lower and lock the outrigger weight support feet in place.