Using MonteCarlo Simulation To Mitigate The Risk of Project Cost Overruns
Using MonteCarlo Simulation To Mitigate The Risk of Project Cost Overruns
Using MonteCarlo Simulation To Mitigate The Risk of Project Cost Overruns
Zakia Bouayed, Int. J. of Safety and Security Eng., Vol. 6, No. 2 (2016) 293–300
ABSTRACT
Cost overruns are common on government and commercial projects. This paper proposes a cost risk
estimating method that provides more accurate estimates of total project cost and answers the following
important questions: (1) What is the most likely cost? (2) How likely is the baseline cost estimate to be
overrun? (3) How much contingency is required on the project to guarantee that the total project cost is
not to be exceeded, with a certain confidence level? The proposed method is based on the Monte Carlo
simulation. It helps gain better information than traditional cost estimating methods, mainly because it
recognizes that project costs are uncertain. A fictitious case study was developed to provide a structured
way to provide the contingency value of a project in order to avoid cost overruns. Data were collected
on low, most likely and high possible costs and the @Risk software from the Palisade Corporation was
used to run the Monte Carlo simulations. Using a simplified cost case study, this paper demonstrates
how Monte Carlo simulation can assist project managers in estimating the contingency to be allocated
to their project, and contribute to fostering and bolstering the credibility of risk analysis results.
Keywords: contingency, cost estimating, cost overruns, monte carlo simulation, risk analysis.
1 INTRODUCTION
Cost overruns have been shown to occur in a significant number of Defence projects. Auger
[1] noted that despite the introduction of defence procurement reforms in recent years, Can-
ada, and its allies continue to face cost overruns and delays with the delivery of major weapon
systems and military equipment. The problem is not unique to the Canadian Defence sector.
It affects all kinds of projects in different sectors of the economy, in Canada and worldwide.
New research by Flyvbjerg [2] found that cost overruns occurred on nine out of ten megapro-
jects and concluded that ‘overruns of up to 50 percent in real terms are common, over
50 percent not uncommon’. Notorious examples of project cost overruns from all over the
World were reported in Flyvbjerg’s research work. Among them, one can find the disastrous
project for the construction of the Montreal Summer Olympics in Canada, which ended-up
costing 13 times its original price estimate.
Cost overruns are problematic. They don’t necessarily lead to project failure, but they do
create budgeting problems and take money from other priority projects. In the public sector,
cost overruns also translate into a loss of public confidence in the way the government man-
ages taxpayers’ money.
What causes such cost overruns? In the Defence world, Younossi et al. [3] identified the
complexity of technology, the scale of the program and the over-optimism of program man-
agers who overlook certain problems as the main reasons for cost overruns. Other factors
This paper is part of the Proceedings of the 10th International Conference on Risk Analysis
(RISK 2016)
www.witconferences.com
found on the internet as to why project cost overruns may occur include: design errors; fre-
quent changes in the project scope; escalation of costs associated with a project (labour,
materials, equipment, administration, etc.) due to unforeseen events; unexpected project
delays that automatically translate into more time and money; and poor management.
While these causes are valid in some cases, the main cause for cost overruns, as Flybjvberg
et al. [4] indicates is cost underestimation. ‘Projects promotors routinely ignore, hide, or
otherwise leave out project costs and risks in order to make total costs appear low’. In other
words, artificially low costs are presented to gain initial project approval, and then, once pro-
jects get underway, costs are revised upward. The cure for this is of course transparency and
accountability, but also better cost estimating methods to account for risks and uncertainties
over the life cycle of a project.
This paper proposes a simple and sound cost risk estimating method to apply to any type
of project, in order to mitigate the risk of cost overruns. It should be noted that better cost
estimates would not necessarily save any money; however, they would provide decision mak-
ers with a better basis for deciding whether to pursue a given program, thus avoiding potential
project cost overruns.
2 CONTINGENCY DEFINITION
The objective of contingency allocation is to cover for items of cost which are not known
exactly at the time the estimate is developed. This could be because of incomplete engineer-
ing, lack of time to get definitive pricing, minor errors and omissions and minor changes,
within the scope. The Association for the Advancement of Cost Engineering (AACE) defines
contingency as, ‘An amount added to the estimate to (1) achieve a specific confidence level,
or (2) allow for changes that experience shows will likely be required.’ [5]. Contingency is
described in many different ways across the industry, but the common purpose for determin-
ing contingency is to account for the uncertainty or unexpected.
MOTI Project Cost Estimating Guidelines [6] indicate that cost estimates should always
include contingency to cover for certain uncertainties and risks. Contingency is an item in a
cost estimate like any other. It should be presented as a separate line to have it clearly identi-
fied. It is not ‘padding’ and it is expected to be spent during the life of the project. By no
means, should it be considered as a reserve fund to compensate for inaccurate estimating,
changes of scope or ‘nice-to-haves’. In addition, it should not provide for costs associated
with external influences (i.e. those not under the control of the project manager or estimator),
such as strikes or work stoppages; changes in government policies and regulations; natural
disasters, major accidents, catastrophes or significantly abnormal weather; management
reserves; and escalation and currency effects.
Last, but not least, the amount of contingency required should be determined very care-
fully. Remember a cost estimate, which does not contain enough contingency may jeopardize
the success of the project and could lead to cost overruns. Equally as important, placing too
much contingency in a cost estimate could impact in a negative way the project ‘go/no-go’
decision. It should also be noted that too much contingency represents money which cannot
be used on other projects.
and fails to explicitly acknowledge the underlying project risks that drive the need for contin-
gency in the first place and therefore exposes the organization to either overcompensating for
risk or underestimating risk.
A slightly better method consists of calculating a contingency percentage for each major
cost element, which at least acknowledges that some parts of the project may have greater
uncertainty than others. According to Mak et al. [8], this is still insufficient, because a sin-
gle-figure prediction of estimated costs implies a degree of certainty that is not justified.
The weaknesses of the traditional percentage addition approach for calculating contingen-
cies had led for a search for more robust approaches. Baccarini [9] conducted a literature
review of these methods. Monte Carlo simulation was found to be the most widely accepted
method for estimating the required cost contingency as project cost estimators become more
aware of its improved effectiveness over the traditional percentage approach. The Project
Management Body of Knowledge (PMBOK) [10] advocates its use for performing quantita-
tive risk analysis.
4 DATA COLLECTION
A fictitious case study, based on a typical capital transportation construction project, was
developed to provide a structured way to estimate the contingency value using Monte Carlo
simulation. The first step for estimating the required cost contingency consists of dividing the
project into manageable cost elements. Depending on the type of project, generic Cost Esti-
mating Structures (CES) or Work breakdown structures (WBS), which consist of the major
categories of work that make up the project, could be used.
The vast majority of capital transportation construction projects entail the same fundamen-
tal cost elements (see Table 1). MOTI Appendix 1 – Cost elements for Transportation
Projects [6], provides a detailed description of each of these cost elements and the methods
used to estimate them, depending on the maturity of the project. Note that the estimation
figures used to derive the total project cost of $280 M (base estimate) are arbitrary and do not
represent real costs.
Once the cost elements of the project are well defined, the next step consists of determining
for each cost element, the Most Likely Cost, High Cost and Low Cost to represent the uncer-
tainty that each cost element presents. According to MOTI [6], during early stages of a
project, the amount of uncertainty can be quite high (30% to 40%). As the project progresses,
the uncertainty decreases (5% to 10%).
It is recommended to use the AACE Cost Estimate Classification system [11] to determine
how the costs are distributed between the Low Cost and the High Cost and what methodology
to use to estimate the Most Likely cost, depending on the maturity of the project. Our case
study was based on Class 3 estimate, which corresponds to a pre-tender cost estimate a waiting
budget authorization. The uncertainty of each cost element can then be examined using prob-
ability distributions. For illustration purposes and to keep things simple, the triangular
distribution was used to represent the Low Cost, Most Likely Cost and High Cost, since its
shape can be described by three-point estimates.
Finally, data on correlation between the cost elements should also be collected, since cor-
relation has an impact on the contingency value. Historical data and expert judgement can be
used to determine how cost elements are correlated between each other.
6 RESULTS
Figure 1 and 2 show the simulation results, based on 10,000 iterations. Typically, 5,000 iter-
ations and more are used for most project risk analyses. Three important results can be noted:
• First, the most likely cost for the project, represented by the mean, was estimated to be
approximately $289.33 M.
•• Second, the base estimate, as shown in Figure 2, is about 20% likely to be $280 M or less
and 80% likely to be overrun.
• Third, the total project cost at the 90th percentile is approximately: $303.46 M.
Figure 1: Probability distribution graph for the total project cost.
Zakia Bouayed, Int. J. of Safety and Security Eng., Vol. 6, No. 2 (2016) 297
So, how much contingency is required on the project to guarantee that the total project cost
is not to be exceeded at a certain confidence level? To answer this question, Let us assume
that the Ministry of Transportation and Infrastructure is very conservative and will not accept
to bid a project that has a likelihood of overrunning that is greater than 10%. Since the con-
tingency is ‘An amount added to the estimate to achieve a specific confidence level’, this
means that the difference between the base estimate and the total project cost at the 90th
percentile is the amount of contingency that would be necessary to provide the company with
the assurance that the estimated total project cost will not exceed the level of acceptable risk
of 10%. Therefore, the required amount of contingency for the current case study at the 90%
confidence level is $23.46 M ($303.46 M–$280 M). In terms of percentage, this represents a
contingency of 8.4%. This result is consistent with what the literature says about the percent-
age of contingency required for a typical pre-tender estimate (5% to 10%). Note that at a
higher confidence level (95% and above), the amount of contingency required would be
slightly greater.
7 SENSITIVITY ANALYSIS
In order to reduce the amount of contingency, a sensitivity analysis can be conducted to
detect the key cost elements affecting the total project cost. The bars in Fig. 3 show the cost
elements which contribute the most risk to the total project. The length of the bars is the
amount of change in the output due to a +1 standard deviation change in the input. As shown
in Fig. 3, Construction and Property Acquisition proved to be the most contributing factor to
the risk of the total project cost. Particular efforts should then be directed towards these cost
elements, in order to reduce the impact of risk events and uncertainties to the total project
cost, as well as the amount of contingency required.
8 CORRELATION ANALYSIS
Correlation between cost elements also has an impact on the contingency value. To demon-
strate the potential effects of correlation, an analysis of a hypothetical case was conducted
assuming that each cost element is positively correlated with Construction and the correlation
factor is 0.8.
Figure 2: Cumulative distribution chart for the total project cost.
298 Zakia Bouayed, Int. J. of Safety and Security Eng., Vol. 6, No. 2 (2016)
Figure 3: Bar chart showing the contribution of the cost elements to the risk in the project.
Table 2: Comparison of statistics for the total project cost without correlation and with cor-
relation.
Statistics No Correlation Correlation
Minimum $260 684 $256 875
Maximum $326 007 $329 126
Mean $289 333 $289 333
Mode $289 263 $281 371
Median $288 817 $288 295
Std Dev $10 471 $13 213
Tables 2 and 3 below display the simulation results without and with correlation. By com-
paring the statistics of both scenarios, one can see that the mean is the same but the standard
deviation and the range width (measures of dispersion) have increased in the case of the
scenario with correlation. Comparing the percentiles shows that the contingency value needs
to be slightly greater at higher levels of confidence when a positive correlation exists between
the project cost elements, based on the assumptions. As highlighted in the table, the presence
of a positive correlation between the project cost elements, as specified, would slightly raise
the risk of cost overruns at the 60th percentile level and higher.
9 CONCLUSION
Based on a fictitious case study, this paper demonstrated how the Monte Carlo simulation can
assist project managers in estimating the contingency value to be allocated to their project, to
mitigate the risk of project cost overruns. The proposed methodology provided answers to the
following questions: (1) What is the most likely cost? (2) How likely is the baseline cost
estimate to be overrun? (3) How much contingency is required for the project to guarantee
that the total project cost is not to be exceeded at a certain confidence level? This involved
dividing the project into manageable cost elements and carefully collecting data on low, most
likely and high possible costs, as well as on correlation between the cost elements. The @
Zakia Bouayed, Int. J. of Safety and Security Eng., Vol. 6, No. 2 (2016) 299
Table 3: Comparison of statistics for the total project cost without correlation and with cor-
relation.
Percentile (%) No correlation Correlation
1 $267 680 $263 201
5 $273 151 $268 836
10 $276 077 $272 647
15 $278 248 $275 245
20 $280 095 $277 604
25 $281 662 $279 666
30 $283 076 $281 503
35 $284 503 $283 258
40 $286 040 $284 897
45 $287 400 $286 540
50 $288 817 $288 295
55 $290 289 $290 241
60 $291 729 $292 085
65 $293 185 $294 073
70 $294 719 $296 238
75 $296 459 $298 537
80 $298 470 $301 148
85 $300 814 $303 917
90 $303 461 $307 692
95 $307 238 $312 748
99 $314 172 $320 385
Risk tool from the Palisade Corporation was used to provide the power of the Monte Carlo
simulation. This paper also showed the importance of cost risk analysis to identify the major
key cost elements that contribute the most risk to the total project cost and where efforts
should be focused, in order to prevent cost overruns. It has also demonstrated how correlation
between cost elements could also affect the contingency value, thus providing a complete and
sound cost estimating and analysis approach that contribute to fostering and bolstering the
credibility of risk analysis results.
REFERENCES
[1] Auger, M., Procurement organizations: a global comparison, economics, resources and
international affairs division – parliamentary information and research service, publica-
tion N0. 2014-82-E, Ottawa, Canada, pp. 4–10, 2014.
[2] Flyvbjerg, B., What you should know about megaprojects and why: an overview.
Project Management Journal, 45(2), pp. 6–19, 2014.
http://dx.doi.org/10.1002/pmj.21409
300 Zakia Bouayed, Int. J. of Safety and Security Eng., Vol. 6, No. 2 (2016)
[3] Younossi, O., Arena, M.V., Leonard, R.S., Roll, C.R., Jain, A. & Sollinger, J.M., Is
Weapon System Cost Growth Increasing? A Quantitative Assessment of Completed and
Ongoing Programs, RAND: California, US, pp. 44–46, 2007.
[4] Flyvbjerg, B., Holm, M.S. & Buhl, S., Underestimating costs in public works projects:
error or lie? Journal of the American Planning Association, 68(3), pp. 279–295, 2002.
http://dx.doi.org/10.1080/01944360208976273
[5] AACE (American Association of Cost Engineers), AACE International’s risk manage-
ment dictionary. Cost Engineering, 42(4), pp. 28–31, 2000.
[6] Ministry of Transportation and Infrastructure (MOTI), Project cost estimating guide-
lines, Version 01.02, Victoria BC, pp. 8–10, 2013.
[7] Baccarini, D., Understanding project cost contingency – a survey, Cobra International
Construction Conference, Brisbane, 2005.
[8] Mak, S., Wong, J. & Picken, D., The effect on contingency allowances of using risk
analysis in capital cost estimating: a Hong Kong case study. Construction Management
and Economics, 16, pp. 615–619, 1998.
http://dx.doi.org/10.1080/014461998371917
[9] Baccarini, D., Estimating project cost contingency – beyond the 10% syndrome. Aus-
tralian Institute of Project Management Conference, Victoria: Australian Institute of
Project Management, 2005.
[10] Project Management Institute, A Guide to the Project Management Body of Knowledge
(PMBok), 4th edn., Project Management Institute: USA, 2008.
[11] ACCE International, Cost estimate classification system – as applied in engineering,
procurement, and construction for the process industries, Recommended Practice No.
18R-97, TCM Framework: 7.3 – Cost Estimating and Budgeting, 2011.