MS Project Guide Objectives:: FIT2002 Project Management Monash University
MS Project Guide Objectives:: FIT2002 Project Management Monash University
MS Project Guide
Objectives:
• Understand
the
different
tools
of
MS
Project
2013
(or
2010)
in
order
to
construct
a
Work
Breakdown
Structure
(WBS)
The tutorial goal is to enter the following WBS into MSP:
3-‐ Now
change
the
start
date
to
1/08/2015.
Page
1
of
4
FIT2002
Project
Management
Monash
University
4-‐ Enter
the
name
of
the
activities
in
Task
Name
section
5-‐ Select
all
activities
and
change
the
task
mode
from
manually
schedule
to
auto
schedule
Note:
All
activities
are
set
to
the
start
of
the
project
in
the
Gant
Chart
(1st
of
August)
Page
2
of
4
FIT2002
Project
Management
Monash
University
6-‐ Use
indent
to
differentiate
the
WBS
levels
Note:
Your
entry
table
should
look
like
this
now
7-‐ Don’t
worry
about
durations
and
predecessors,
you
will
learn
about
them
later
on.
Let’s
assume
the
duration
of
each
activity
is
3
days
(don’t
set
any
duration
to
summary
tasks).
Enter
3
days
duration
for
all
activities
except
0.0,
1.0
and
1.2
(summary
tasks).
8-‐ Let’s
assume
the
predecessors
are
linear
(For
example,
1.1
is
the
predecessor
of
1.2.1)
a. To
set
predecessors,
you
need
to
double
click
on
the
activity,
go
to
the
predecessor
tab
to
set
it,
or
you
can
simply
use
the
row
number
from
the
table.
b. You
shouldn’t
use
summary
tasks
as
predecessors
Note: Look at the duration of summary tasks that are automatically calculated.
Page
3
of
4
FIT2002
Project
Management
Monash
University
9-‐ You
can
see
the
Chart
on
right
side
of
your
screen
Note:
look
at
the
result
of
the
linear
relationships
Page
4
of
4