SCM 302 Ratcliffe - 03 - Project Management
SCM 302 Ratcliffe - 03 - Project Management
OPERATIONS
MANAGEMENT
Project Management
SCM 302 - Project Management
Ratcliffe 2
Ratcliffe 3
SCM 302 - Project Management
Ratcliffe 4
Industry Question
• Bechtel Project Management
• Largest project manager in US.
• $37.9 billion in revenue (2012)
• 53,000 workers on project in nearly 50 countries
• List of Projects
• Rail line from London to Chunnel ($4.6 billion)
• Oil pipeline Caspian Sea to Russia ($850 million); Thailand gas pipeline ($700 million)
• Dubai Airport ($600 million); Miami Airport ($2 billion)
• New subway for Athens, Greece ($2.6 billion)
Ratcliffe 5
Ratcliffe 6
Ratcliffe 7
What is a project?
Projects are Everywhere but Typically on a Much Smaller Scale
Ratcliffe 8
Planning
Budgets
Delayed activities report
Slack activities report
SCM 302 - Project Management
Ratcliffe 9
Project Planning
• Project organization: formed to ensure that programs
(projects) receive the proper management and attention.
• Often temporary. Permanent structure: matrix organization
• Work breakdown structure: specialists throughout company
• Headed by project manager, responsible for:
• Monitoring schedule and budget
• Meeting quality goals
• Directing employees
Ratcliffe 10
Human Quality
Resources Marketing Finance Design Production
Mgt
Figure 3.2
SCM 302 - Project Management
Ratcliffe 11
Compatible with
Activities Level 4
Windows 7 1.1.2.1
(Work packages)
Compatible with
1.1.2.2
Windows Vista
Ratcliffe 12
Project Scheduling
• Purposes of Project Scheduling
1. Show relationships between activities and with
whole project.
2. Identify precedence relationships among activities
3. Set realistic time and cost estimates for each
activity
4. Better utilize resources by identifying critical
bottlenecks
Ratcliffe 13
Ratcliffe 14
Project Controlling
• Closely monitor resources, costs,
quality, budgets
• Feedback: revise plan and shift
resources
• Reports from computerized tools
1. Detailed cost breakdowns for each task
2. Total program labor curves
3. Cost distribution tables
4. Functional cost and hour summaries
5. Raw materials and expenditure forecasts
6. Variance reports
7. Time analysis reports
8. Work status reports
SCM 302 - Project Management
Ratcliffe 15
Ratcliffe 16
Ratcliffe 17
Represent Projects
Activity-on-Node (AON)
Nodes represent activities
Arcs represent precedence relationship
A B C
Ratcliffe 18
Building a House
Activity Predecessor Duration
A Foundation - 14
B Steel work A 5
C 1st Floor B 6
D 2nd Floor B 4
E Roof B 6
F Exterior Walls C 12
G Interior partitions F, E, D 10
H Paint G 8
SCM 302 - Project Management
Ratcliffe 19
A B D G H
Ratcliffe 20
A B D G H
14 5 days 10 8 days
days days
E 6 days
Ratcliffe 21
A B D G H
14 5 days 4 10 8 days
days days days
Ratcliffe 22
A B D G H
14 5 days 10 8 days
days days
Ratcliffe 23
Ratcliffe 24
Ratcliffe 26
Building a House
Activity Predecessor Duration
A Foundation - 14
B Steel work A 5
C 1st Floor B 6
D 2nd Floor B 4
E Roof B 6
F Exterior Walls C 12
G Interior partitions F, E, D 10
H Paint G 8
SCM 302 - Project Management
Ratcliffe 27
Ratcliffe 28
Forward Pass
• Begin at starting event and work forward
• First activity:
• Earliest Start, ESActivity = 0
• Earliest Finish, EFActivity = ESActivity+ tActivity
Ratcliffe 29
A B D G H
14 5 days 4 days 10 8 days
days days
E 6 days
A B C D E F G H
Earliest Start 0 14 19 19 19 25 37 47
Earliest Finish 14 19 25 23 25 37 47 55
SCM 302 - Project Management
Ratcliffe 30
A B D G H
14 5 days 4 days 10 8 days
days days
E 6 days
A B C D E F G H
Latest Finish 14 19 25 37 37 37 47 55
Latest Start 0 14 19 33 31 25 37 47
SCM 302 - Project Management
Ratcliffe 31
Backward Pass
• Begin with the last event and work backwards
• Last activity
• Latest Finish, LFActivity = Earliest Finish
• Note: often will just have one final activity
• Latest Start, LSActivity = LFActivity- tActivity
Ratcliffe 32
Earliest Earliest
Start Finish
Time Time
ESj
ESi EFi
i j
LSi LF
LSj
i
Latest EF = ES +t Latest
Start Finish
Time LS = LF –t
Time
t = duration
SCM 302 - Project Management
Ratcliffe 33
A B D G H
14 5 4 days 10 8
days days days days
E 6 days
A B C D E F G H
Earliest Start 0 14 19 19 19 25 37 47
Earliest Finish 14 19 25 23 25 37 47 55
Latest Finish 14 19 25 37 37 37 47 55
Latest Start 0 14 19 33 31 25 37 47
Slack = LS-ES 0 0 0 14 12 0 0 0
SCM 302 - Project Management
Ratcliffe 34
A B D G H
D
G H
A B ES:19 EF:23
ES:37 EF:47 ES:47 EF:55
ES:0 EF:14 ES:14 EF:19 LS:33 LF:37
LS:37 LF:47 LS:47 LF:55
LS:0 LF:14 LS:14 LF:19
E
E
ES:19 EF:25
LS:31 LF:37
SCM 302 - Project Management
Ratcliffe 35
Activity Format
Activity Name
or Symbol
A Earliest
Earliest ES EF Finish
Start
Latest LS LF Latest
Start 2 Finish
Activity Duration
SCM 302 - Project Management
Ratcliffe 36
True or False?
Ratcliffe 37
Ratcliffe 38
Ratcliffe 39
Software Development
Activity Predecessor Normal Normal Crash Crash Crash Max
Time Cost Time Cost Cost Crash
Per Period Possible
A - 3 $14,000 3 $14,000
B A 6 $40,000 5 $50,000
C A 2 $20,000 2 $20,000
D B 6 $12,000 4 $15,000
E B,C 5 $8,600 3 $13,000
F B,C 3 $18,700 2 $21,000
G E 7 $20,000 2 $30,000
H E,F 5 $13,000 3 $18,000
I D,G,H 2 $9,000 2 $9,000
J I 6 $10,400 4 $18,800
SCM 302 - Project Management
Ratcliffe 40
Ratcliffe 41
A E G I J
3 weeks 7 weeks
5 weeks 2 weeks 6 weeks
C F H
2 weeks 3 weeks 5 weeks
A B C D E F G H I J
Earliest Start 0 3 3 9 9 9 14 14 21 23
Earliest Finish 3 9 5 15 14 12 21 19 23 29
Latest Finish 3 9 9 21 14 16 21 21 23 29
Latest Start 0 3 7 15 9 13 14 16 21 23
Slack = LS-ES 0 0 4 5 0 3 0 2 0 0
SCM 302 - Project Management
Ratcliffe 42
Ratcliffe 43
Ratcliffe 44
6 weeks B D
6 weeks
A E G I J
3 weeks 6 weeks
5 weeks 2 weeks 6 weeks
C F H
2 weeks 3 weeks 5 weeks
Ratcliffe 45
C F H
2 weeks 3 weeks 5 weeks
A B C D E F G H I J
Earliest Start 0 3 3 9 9 9 14 14 20 22
Earliest Finish 3 9 5 15 14 12 20 19 22 28
Latest Finish 3 9 9 20 14 15 20 20 22 28
Latest Start 0 3 7 14 9 12 14 15 20 22
Slack = LS-ES 0 0 4 5 0 3 0 1 0 0
Critical path:
A-B-E-G-I-J (3+6+5+6+2+6=28 weeks)
SCM 302 - Project Management
Ratcliffe 46
6 weeks B D
6 weeks
A E G I J
3 weeks 5 weeks
5 weeks 2 weeks 6 weeks
C F H
2 weeks 3 weeks 5 weeks
Ratcliffe 47
6 weeks
A E G I J
C F H
2 weeks 3 weeks 5 weeks
A B C D E F G H I J
Earliest Start 0 3 3 9 9 9 14 14 19 21
Earliest Finish 3 9 5 15 14 12 19 19 21 27
Latest Finish 3 9 9 19 14 14 19 19 21 27
Latest Start 0 3 7 13 9 11 14 14 19 21
Slack = LS-ES 0 0 4 4 0 2 0 0 0 0
Now we have two critical paths:
A-B-E-G-I-J (3+6+5+5+2+6=27 weeks)
A-B-E-H-I-J (3+6+5+5+2+6=27 weeks)
SCM 302 - Project Management
Ratcliffe 48
6 weeks
A E G I J
C F H
2 weeks 3 weeks 5 weeks
Ratcliffe 49
Ratcliffe 50
Ratcliffe 51
In-class Exercise #2
Activity Duration (in weeks) Immediate Predecessor(s)
A 2 -
B 8 A
C 4 A
D 5 A
E 2 C
F 3 C,D
G 1 E,F
H 2 B,G
a. Draw a Gantt chart for this project. Develop an AON network.
b. What are the ES, EF, LS, LF and slack for each activity?
c. What is the critical path?
d. What is the project completion time?
e. Which activities are non-critical? Explain why.
SCM 302 - Project Management
Ratcliffe 52