Section 2-Type of Flow Testing
Section 2-Type of Flow Testing
Section 2-Type of Flow Testing
Section 2
Table of Contents
Introduction ...........……………………………………………………………… 2 - 2
Objectives………………………………………………………………………… 2 - 2
Testing Procedures................................……………………………………… 2 - 3
Clean up...................................................................................................... 2 - 4
Types of Well test………………………………………………………………...2-11
Drawdown Test.........………………………………………………………....... 2 -11
Buildup Test............…………………………………………………………….. 2- 11
Multiple Rate Tests.............................………………………………………… 2 -12
Deliverability................................................................................................. 2 -12
Other types of test………………………………………………………………..2-13
Injectivity test……….……………………………………………………………..2-13
Fall off test………………….……………………………………………………..2-13
Figures………………….……………………………………………………..…..2-14
Sources of Pre-Test Data.............................................................................2 -15
Well Test Manual 2
Introduction
The section contains information on the Types of Flow Test you will encounter.
Objectives
After completing this section, you should be able to
Testing Procedures
In general, wells in the high productivity range tend to clean up faster than those at the other end of the
scale. Economic and practical reasons sometimes determine how long the clean up period can be
allowed to be carried out.
It is important to ensure that the well has cleaned up effectively to avoid further cleaning up during
designated flow periods as this may invalidate the data and make interpretation of results difficult.
An important factor in cleaning up gas wells is to ensure that the velocity in the tubing is sufficient to lift
liquids, if possible the flow rate should be adjusted to give the following minimum velocities
• Velocity of 5-10 ft/sec for hydrocarbon liquids
• Velocity of 10-20 ft/sec for water
Velocity may be calculated using the formula
The well flow should initially be directed to a tank or overboard through the gas flare line. Gas well
cleaning up can be continued through the flare as the gas volume increases. In the case of an oil well,
the flow should be directed to the burner once it is apparent oil has reached surface.
The cleaning up operation should be carried out with great care, bearing in mind the possibility of serious
damage to equipment by abrasion (sand, mud, perforating debris, etc. brought up with the well fluids). It
is advisable to use the choke manifold near the wellhead and to bypass all testing equipment (heater &
separator).
The best solution from a technical point of view is to install a direct separate clean up line, but this may
not be possible.
Clean up strategy is largely governed by the type of well (Oil or Gas), the perforating system and mainly
the cushion fluid/well contents prior to commencing the clean up.
The factors that require balancing are:-
The red area shows where drilling mud has penetrated into the formation from the Well Bore.
What does MPD entail? This is where when drilling the well at the Formation the pressure is kept as
close to the reservoir pressure (Pore Pressure) as possible. This in turn minimizes the risk of Skin
Damage.
Introduction
Acid treatments have been applied to wells in oil and gas bearing rock formations for many years.
Acidizing is probably the most widely used work-over and stimulation practice in the oil industry.
By dissolving acid soluble components within underground rock formations, or removing material at
the wellbore face, the rate of flow of oil or gas out of production wells or the rate of flow of oil-
displacing fluids into injection wells may be increased.
A number of different acids are used in conventional acidizing treatments, the most common are:
• Hydrochloric, HCl
• Hydrofluoric, HF
• Acetic, CH3COOH
• Formic, HCOOH
These acids differ in their characteristics. Choice of the acid and any additives for a given situation
depends on the underground reservoir characteristics and the specific intention of the treatment, for
example near well bore damage removal, dissolution of scale in fractures, etc.
It is imperative that caution be taken for both personal and environmental protection.
Procedures should be followed at all times.
Equipment Layout
Storage Storage
Matrix Stimulation Tank : 30m
3 3
Storage Tank Tank : 30m
3
: 30m 15% HCL 15% HCL
To the Well ACID
Head Bleed Off Injection / ACID
Displacement
Water
Data
Acquisitio
n
System
SCAN III Chemical
Injection P.
Pressure
Transducer Batch
Mixer Centrifugal Pump
Check
Data
4” Suction Hose
Acquisi Flow
tion
Meter
3” High Pressure
Hydraulic fracturing treatments create conductive cracks or fractures in producing zones. These very
deep-penetrating, high-permeability pathways help reservoir fluids enter wellbores by changing
formation flow from radial to linear. Fluids including proppant are pumped at pressures significantly
above minimum is situ principal rock stress actually split formations apart.
Temporary, artificially high pressures cause target zones to separate along maximum stress planes.
The resulting opposing fracture "wings" propagate away from wellbores perpendicular to the minimum
stress axis.
Propping agents (proppants), including naturally occurring sand, man-made intermediate and high-
strength ceramics (sintered bauxite) and resin-coated sand, added to fluid systems as sandstone
formations are treated, prevent induced fractures from closing completely after pressure is released at
the end of a job. Proppants are not needed in limestones or dolomites if these formation types can be
differentially etched by acid fracturing treatments.
It is extremely important that Well Test Operations are aware of the consequences during flow back of
these solids.
Special equipment has been developed to counteract the problems in performing Frac Flowbacks.
Some of this equipment includes:
Filters
Sand Cyclones
Sand Separators
Four Phase Separators
Sand Busters
Rock Catchers.
The most important fact is, DO NOT FLOW THROUGH HEATERS, SEPARATORS ETC if there are
solids flowing back.
In the majority of well tests the measured reservoir response is the pressure transient resulting from
or in response to changes in production or injection of fluids. In modern pressure transient reservoir
interpretation, a mathematical model is used to relate the pressure response to flow rate history and
subsequently rock, fluid and well properties can be determined. If the main test objective is the
determination of reservoir characteristics, a single flow is recommended as the simplest procedure to
yield this data. However, if well performance data is required, multiple flow rate tests will be required.
Drawdown
A drawdown test requires flowing the well and analysing the pressure response as the reservoir is
drawn down, or reduced, below its original pressure. The objectives of a drawdown test usually
includes estimates of productivity, permeability, skin factor, reservoir volume and the collection of
reservoir samples.
Pressure Drawdown tests are particularly suitable for new wells, wells that have been shut in for
sufficiently long periods to allow pressure stabilisation in the reservoir and wells in which the loss of
revenue incurred in a build-up test would be difficult to accept. Lengthy Drawdown Tests are
performed on exploration wells with the objective of determining reservoir limits and boundaries.
Analysis is possible of a test where reservoir fluids into flow to surface; this is the original definition of
a Drill Stem Test (DST). However, it is not normal nowadays to plan a test on this basis.
It is normal to conduct a build-up test after a drawdown test. The drawdown data will be analysed in
conjunction with the build-up test results.
Build Up
After a drawdown Test, the well is closed in and the pressure increases back to or near to the original
reservoir pressure; this is the pressure build-up (PBU). This is the normal type of test performed on
an oil well and can be analysed using the Horner or superposition plot methods. From this the
reservoir permeability-thickness (kh) and wellbore skin damage can be determined.
On low production rate gas wells, where is a rate dependent skin factor, a simple form of test to
determine this rate dependent skill factor, is to conduct a second flow at a different rate ant then a
PBU. This type of test constitutes a simple form of deliverability test.
Deliverability
A deliverability test will be performed to determine a well’s inflow performance relation (IPR) and, in
the case of gas wells, the Absolute Open Flow Potential (AOFP) and the rate dependent skin factor; a
simple test for a gas well was described above. The AOFP is the theoretical rate at which produced
fluid of the reservoir sandface was at atmospheric pressure. This calculated rate is only of importance
where governmental bodies set the maximum rate at which a well may be produced as a proportion of
this flow.
Conducting a Flow-After Flow Test requires flowing a well at a set rate until the flowing pressure
stabilises and then repeating the test at several different flow rates; See Figure 3.2a. Flow rates are
usually increased at each step. In such tests, the pressure transient data provides estimations of
productivity, permeability, skin effect and reservoir pressure. This type of test is applicable to high
rate gas testing which would be followed by a single PBU.
An Isochronal Test consists of a series of flowrates, each of equal duration and separated by a
pressure build-up long enough to reach a stabilised reservoir pressure: See Figure 3.2b. The final
flow period is usually followed by an extended build-up. Isochronal tests are usually performed to
establish a deliverabililty relationship for a low permeability gas well without flowing the well for long
enough to achieve stabilised flowing conditions. Flow rates are usually increased at each step.
A Modified Isochronal Test is performed on tight formations where it would take too long for shut-in
pressures to stabilise; See Figure 3.2c. Flow rates are usually increase at each step. The flow and
shut-in periods are of the same duration, except the final flow period, which is also extended as on an
Isochronal Test.
NOTE: Isochronal Tests are based on rigorous mathematical theory. Modified Isochronal tests use
approximations to this theory. Modified Isochronal Tests are used widely since they save time and
money, and have proved to be excellent approximations to true Isochronal Tests.
Two rate tests are usually performed on wells which cannot be shut in for economic reasons.
Pressure-flow schedules for such tests are also shown in Figure 3.2. It is common to follow a
drawdown with a pressure build-up and the difference in pressure between the initial reservoir
pressure and the pressure to which the reservoir returns is termed “depletion”. The reservoir volume
may be estimated directly from this depletion, the volume of produced fluids and he effective
isothermal compressibility of the reservoir system. The volume produced must be sufficient to give a
measurable pressure difference on downhole pressure gauges. These gauges must be high
resolution gauges with negligible drift.
Injectivity Test
In such a test, fluid (usually seawater offshore) is injected into the reservoir to establish the
formation’s injection potential and possibly its fracture pressure; these can be determined with a step
rate test. Very high surface injection pressures may be required to fracture the formation
The object of testing an injection well is to determine a wells ability to accept fluid uniformly over a
period of time in tertiary recovery projects.