Well Completion: Assoc. Prof. Issham Ismail

This document discusses well completion, which involves preparing an oil or gas well after drilling so it can produce in a controlled manner. It describes the key types of well completions like open hole, liner, perforated casing, and tubingless. Open hole completions have advantages like minimizing formation damage but risks water/gas control. Liner and perforated casing completions allow selective stimulation but reduce borehole size. Factors influencing completion selection include reservoir properties, potential production rates, and future workover needs. The document outlines principles of single, multiple, horizontal, and multilateral well completions.

Uploaded by

KAORU Amane
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
70 views36 pages

Well Completion: Assoc. Prof. Issham Ismail

This document discusses well completion, which involves preparing an oil or gas well after drilling so it can produce in a controlled manner. It describes the key types of well completions like open hole, liner, perforated casing, and tubingless. Open hole completions have advantages like minimizing formation damage but risks water/gas control. Liner and perforated casing completions allow selective stimulation but reduce borehole size. Factors influencing completion selection include reservoir properties, potential production rates, and future workover needs. The document outlines principles of single, multiple, horizontal, and multilateral well completions.

Uploaded by

KAORU Amane
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 36

WELL COMPLETION

Assoc. Prof. Issham Ismail


School of Chemical & Energy Engineering,
Universiti Teknologi Malaysia,
Johor Bahru, Malaysia.

.
WHAT IS WELL COMPLETION?

 An important phase in well construction.

 Is an important sub-discipline of petroleum


engineering.

 A series of activities to prepare an oil well or


a gas well, so that the well can be flowed in a
controlled manner. All wells have to be
completed.

 Cannot operate alone - must joint effort with


other sub-disciplines such as production
engineering and reservoir engineering.
TYPES OF WELL COMPLETIONS
Four basic categories:
 Open hole completions - Production casing to be set
above the zone of interests and prior to drilling same.
 Liner completion:
(1) Screen liner - Casing is set above the producing
zone, and an uncemented screen and liner
assembly is installed across the pay zone.
(2) Perforated liner completion - Casing is set above
the producing zone, the pay is drilled, and liner
casing is cemented in place. The liner is then
perforated selectively for production.
 Perforated casing completions - Production casing is
cemented through the producing zone and the pay
section is selectively perforated.
 Tubingless or reduced diameter completions -
Production tubing is cemented and perforated for
production.
OPEN HOLE COMPLETIONS
 Advantages:
(1) Mud wt & chemistry can be controlled to minimize formation
damage within the zone of interest.
(2) No perforation expenses.
(3) Log interpretation is not critical.
(4) Max. diameter opposite pay zone.
(5) Easy to deepen the well.
(6) Easy to convert to screen liner completions.
 Disadvantages:
(1) Excessive water or gas production is difficult to control.
(2) More rig time is required to set production casing above the
production zone.
(3) Pay zone cannot be selectively stimulated.
(4) Open hole section may require frequent clean out.
OPEN HOLE COMPLETION

Production casing
LINER COMPLETIONS
 Two types, namely screen and liner completions, and perforated
liner completions.

Screen and Liner Completions


 Advantages:
(1) Fm damage minimized when drilling pay zone.
(2) No perforation expenses.
(3) Log interpretation is not critical.
(4) Adaptable to special sand control techniques.
(5) Clean out problems avoided.
 Disadvantages:
(1) Excessive water or gas production is difficult to control.
(2) Production casing set before drilling the production zone. rig time.
(3) Pay zone cannot be selectively stimulated.
(4) Well is not easy to deepen.
(5) Diameter across the pay reduced.
SCREEN AND LINER COMPLETION

Production casing

Screen and liner assembly


OPEN HOLE &
SCREEN LINER COMPLETIONS
LINER COMPLETIONS
Perforated Liner Completions

 Advantages:
(1) Fm damage minimized when drilling pay zone.
(2) Excessive water or gas production can be controlled.
(3) Pay zone can be selectively stimulated.
(4) Adaptable to additional special sand control techniques.
(5) Well can be easily deepened.
 Disadvantages:
(1) Smaller wellbore diameter across the pay.
(2) Good quality liner cement jobs is more difficult to obtained
than primary casing cement jobs.
(3) Log interpretation is critical.
(4) Additional costs to cover perforation, cementing, and rig time.
PERFORATED LINER COMPLETION

Production casing

Liner

Perforation
PERFORATED CASING COMPLETIONS
 Most commonly used especially in Malaysia.
 Advantages:
(1) Excessive water or gas production can be controlled easily.
(2) Pay zone can be selectively stimulated.
(3) Improved primary cementing (compared to liner cementing).
(4) Full diameter through pay zone.
(5) Easy to deepen the well.
(6) Easy to adapt to special sand control techniques.
(7) Requires log assistance to set casing.
(8) Adaptable to all types of multiple completions configurations.
(9) Minimum rig time required.
 Disadvantages:
(1) Log interpretation is critical.
(2) Significant perforation expenses.
(3) May damage severely the pay section.
PERFORATED CASING COMPLETION

Production casing

Perforation
CASED HOLE COMPLETIONS
TUBINGLESS COMPLETIONS
 Advantages:
(1) Reduced completion cost.
(2) Multiple completions less difficult to install.
(3) Wells can be worked over selectively.
 Disadvantages:
(1) Lower maximum potential productivity.
(2) Lower maximum potential stimulation rate.
(3) Paraffin, scale, and corrosion problems are more
critical.
(4) May be difficult to get primary cementing job.
FACTORS INFLUENCING THE WELL
COMPLETION SELECTION/DESIGN

 Natural occurrences of the field.


 Potential of oil production and the planning of
tertiary recovery.
 Limitations within the operation and the field.
NATURAL OCCURRENCES OF THE FIELD
 Location of the oil field.
In remote area, use simple well completion configurations.
 Depth of the reservoir.
Cementing of liner may face difficulties.
 Physical condition of the reservoir.
Consider the thickness and no. of layers. Are they
connected?
 Reservoir pressure.
Does the well requires artificial lift? Separate flow paths?
 Drives mechanism.
Relate with the perforation!
 Fluid properties.
Can be commingled? Production from different zones
 simultaneously through different conduits!
 Rock properties.
Is it a consolidated formation? Homogeneous formation?
POTENTIAL OF OIL PRODUCTION AND THE
PLANNING OF TERTIARY RECOVERY
 Production rates.
 Need to predict as accurate as possible. Do not exceed critical flowrate!
 Type of production.
 Uses primary drive mechanism…or artificial lift.
 Future workover.
 Should be able to predict what type of workover!
 Stimulation jobs.
 If stimulation required in the future, consider the material used. Avoid
using screen and liner completions.
 Secondary recovery.
 Producer can be converted to injector at minimum cost.
 Tertiary recovery.
 Materials used in the well can resist chemical attack.
 Termal recovery.
 Give attention to the temperature rating of the equipment.
LIMITATIONS WITHIN THE OPERATION AND THE FIELD
 Subsurface equipment.
 Selection of completion depends on the type and number of
subsurface equipment used, i.e. single tubing to dual tubing strings.
 Quality of primary cementing.
 Cementing in screen and liner completions is more critical than primary
cementing.
 Deviation of the hole.
 Minimize the number of subsurface equipment used in the well.
 Water or gas coning.
 Perforated casing or perforated liner completions could be used to face
this problem.
 Formation damage.
 Perforated casing or perforated liner completions may cause serious
formation…should exercise extra precaution!
Mechanical Considerations

(1) Simplicity
(2) Reliability
(3) Safety
(4) Anticipation of operating
conditions
(5) Economic
TYPES OF FLOW
Three types of flow, namely casing flow, tubing and annulus
flow, and tubing flow.

(1) Casing flow


Large flowrate. No tubing is required. Used in Middle East.
(2) Tubing and annulus flow
Large flowrate. Flow segregation.
(3) Tubing flow
Used widely especially in Malaysia. Due to safety. May use one
tubing string or more.

Our future discussion will be based on the tubing flow only in a


perforated cased hole completion.
SINGLE COMPLETION
MULTIPLE COMPLETIONS
Advantages of Multiple Completions

(1) Segregating production flow from


several zones in the wellbore.
(2) Higher producing rates and faster
payouts.
(3) Separating different types of
reservoirs.
(4) Proper reservoir controlled.
HORIZONTAL COMPLETION
MULTILATERAL WELLS
A MULTILATERAL WELL

Rapid Connect Multilateral


Completion
COMPLETION INTERVAL AND
PERFORATING PRACTICE
INTERVAL SELECTION

 Referred to the pay zones that need to be perforated to allow


oil/gas to flow into the well.
 Underbalance perforation.
 Factors influencing interval selection (to be perforated):
• Types of drive mechanism available.
• The predetermined oil rates.
• Heterogeneity characteristics.
• Completion efficiency considerations: partial penetration and
coning effects
• Summation of pressure drops effect
• Future stimulation!
• Future workover!
• Economic considerations.
WELLHEAD ASSEMBLIES

 Comprise x-mas tree, casing head, and tubing head.


Wellhead is referred to casing head and tubing head.

 X-mas tree is installed on top of the wellhead.

 Tubing head in located above the casing head.


THANK YOU