0% found this document useful (0 votes)
112 views1 page

Activity Preceding Duration ES EF LS LF Total Float Free Float

The document provides instructions for a critical path method (CPM) quiz, including: 1) Drawing the network diagram for the given activities. 2) Identifying the critical path of activities A-D-E-F in red. 3) Calculating the early start (ES), early finish (EF), late start (LS), late finish (LF), total float (TF), and free float (FF) for each activity.

Uploaded by

Abigail
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
112 views1 page

Activity Preceding Duration ES EF LS LF Total Float Free Float

The document provides instructions for a critical path method (CPM) quiz, including: 1) Drawing the network diagram for the given activities. 2) Identifying the critical path of activities A-D-E-F in red. 3) Calculating the early start (ES), early finish (EF), late start (LS), late finish (LF), total float (TF), and free float (FF) for each activity.

Uploaded by

Abigail
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Jeruneo Gem C.

Yongca May 7, 2021

3CE-1 Engr. Elmer M. Mujar

CE 521/CE 326-18 - Construction Methods & Project Management

Quiz No. 2: Critical Path Method

1. Draw the Network Diagram

2. Determine the critical path: A-D-E-F *mark as red lines in network diagram*

3. For each task or activity, determine the ES, EF, LS, LF, TF, FF

Activity Preceding Duration ES EF LS LF Total Free


Float Float

A --- 2 0 2 0 2 0 0

B A 4 2 6 10 14 8 0

C I, B 3 3 6 14 17 11 11

D A 3 2 5 2 5 0 0

E D 12 5 17 5 17 0 0

F C, E 8 17 25 17 25 0 9

G E 5 17 22 20 25 3 12

H E 3 17 20 22 25 5 14

I --- 3 0 3 14 17 11 0