0% found this document useful (0 votes)
95 views1 page

PBU PPVC MAS Flowchart New Application Renewal

The document outlines the process and requirements for obtaining and renewing a PBU/PPVC MAS certification. For new applications, manufacturers must first obtain a valid Precaster Accreditation Scheme Certificate and then submit documents for a Documentation Audit. If documentation is approved, a Plant Audit will be scheduled. For renewals, current certificate holders can submit a renewal application for a Documentation Audit only or apply if their certificate is still valid. The audit process involves assessing conformance, with corrective actions or re-audits required for non-conformities.

Uploaded by

Nicky Lim
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
95 views1 page

PBU PPVC MAS Flowchart New Application Renewal

The document outlines the process and requirements for obtaining and renewing a PBU/PPVC MAS certification. For new applications, manufacturers must first obtain a valid Precaster Accreditation Scheme Certificate and then submit documents for a Documentation Audit. If documentation is approved, a Plant Audit will be scheduled. For renewals, current certificate holders can submit a renewal application for a Documentation Audit only or apply if their certificate is still valid. The audit process involves assessing conformance, with corrective actions or re-audits required for non-conformities.

Uploaded by

Nicky Lim
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

NEW APPLICATION RENEWAL

To retain the current PBU/PPVC MAS certification,


Does the PBU/PPVC
the Manufacturer :
manufacturer has a valid Does the previously certified

Pre-requisite Precast Acreditation No PBU/PPVC manufacturer must obtain a valid PBU/PPVC manufacturer has a No
Precaster Accreditation Scheme Certificate before • To submit application for renewal before expiry
Certificate? project and is ready to start fit-
applying for MAS of certificate,
(PBU - GS1 Product) out operation?
• Proceed with Documentation Audit only (no site
(PPVC - PPVC Product)
audit),
• will receive Provisional Certificate

NOTE:
Yes Yes
There are 2 parts to the MAS.

Part 1: Documentation Audit


Download Application Form from • required for new application
www.SCinst.org.sg • if Applicant is currently not manufacturing, Applicant can opt to proceed with
Part 1 audit only, and be issued with a Provisional Certificate.
• Applicant can proceed with Part 2 audit only when manufacturing is in No The Applicant will have to apply for Documentation
Is the current PBU/PPVC
progress. MAS Certificate still valid? Audit first, followed by the Fit-Out audit.

Part 2: Plant Audit


- After clearance from Part 1
Submit completed Application
form and required documents to Yes
[email protected]
Note:
Download Application Form from Applicant can apply for Part 2: Plant audit.
www.SCinst.org.sg
Part 1: Documentation Audit NOT required if the
MAS certificate is still valid at the time of
application.

Application Application documents


complete?
No
Refer Application form Reject, Applicant to resubmit Submit completed Application
Annex 2 form and required documents to
[email protected]

Yes
Application

Schedule and conduct audit

Application documents
No
complete?
Refer Application form Reject, Applicant to resubmit
Annex 2

No Minor or Major Yes


Meet Audit criteria? Non-Award, re-audit required

Site Audit
Major Non-Conformity

Schedule and conduct audit

Yes Minor

Submit corrective ction until


Award of Accreditation
Auditor's clearance obtained
No Minor or Major
Site Audit Meet Audit criteria?
Major Non-Conformity
Non-Award, re-audit required

Yes Minor

Award / Renewal of Submit corrective ction until


Accreditation Auditor's clearance obtained