NO Uraian Pekerjaan Satuan Kontrak: Realisasi

Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

NO URAIAN PEKERJAAN SATUAN VOLUME

KONTRAK REALISASI
1 2 3 4 4

I. PEKERJAAN PERSIAPAN

1 Penyediaan Direksi Keet, Gudang dan Barak Kerja ls ‐


2 Papan nama proyek , papan lokasi , papan jadwal ( 1 set= 3 papan) set ‐
3 Mobilisasi dan demobilisasi alat kerja pondasi lokasi 2,00 2,00
4 Pekerjaan pembersihan lokasi tower lokasi 1,00 1,00
5 Recheck Survey km ‐ ‐
6 Survey Reroute  km ‐ ‐
7 Sondir  ( kedalaman  15 meter/  qc  mak.= 200 kg/cm2 ) ttk                  2,00                    2,00 

II. PEKERJAAN PONDASI TOWER

  PONDASI TOWER TYPE 4DD2/ 4DRD2

1 Pondasi tower 4DRD2 set 2,00 2,00


2 Borepile W / Cap & Beam Type L 10M ‐ 64 BT set 2,00 2,00

JUMLAH 2,00 2,00

III. PEKERJAAN PENGADAAN TOWER

A PENGADAAN STUB TOWER 4 SIRKUIT
1 Tower Type 4DD / 4DDR set 2,00 2,00

2,00 2,00

1 Tower Type 4 DRD2  + 0 set 1,00


2 Tower Type  4DDR4 + 12 set 1,00
3 Pengadaan Arm tower set ‐ 8

1,00

C PENGADAAN ACCESSORIES TOWER

1 Anti Climbing Guard ( 1 set = 4 kaki per tower ) set 2,00


2 Number Plate & phase plate ( 1 set = 2 lbr. per tower ) set 2,00
3 Danger Plate ( 1 set = 2 lbr. per tower ) set 2,00
4 Peralatan sistem pentanahan ( 2 set per tower ) set 4,00

 JUMLAH   

IV. PEKERJAAN ERECTION , FINAL CHEK

A PEKERJAAN ERECTION TOWER
1 Tower Type  4DD4 + 0 set 1,00
2 Tower Type  4DDR4 + 12 set 1,00
3 Pembongkaran Arm tower set 8,00
4 Pemasangan Arm Tower set 8,00

1,00

B EREKSION ACCESSORIES TOWER

1 Anti Climbing Guard ( 1 set = 4 kaki per tower ) Set 2,00


2 Number Plate & phase plate ( 1 set = 2 lbr. per tower ) Set 2,00
3 Danger Plate ( 1 set = 2 lbr. per tower ) Set 2,00
4 Peralatan sistem pentanahan ( 2 set per tower ) set 4,00

C EREKSION STUB TOWER 4 SIRKUIT

1 Tower Type 4 DD2 / DRD2 set 2,00

     
JUMLAH  A+B+C 

NO URAIAN PEKERJAAN SATUAN VOLUME


KONTRAK TAMBAH
1 2 3 4 5

V PENGADAAN KONDUKTOR,GSW DAN OPGW


1 Pengadaan ACSR 240/40 mm² m ‐
2 Pengadaan GSW 55 mm² m 3.654
3 Pengadaan ADSS 12 core m 2.000
4 One Earthwire OPGW 70mm² 12 Pair m                         ‐ 
JUMLAH
VI PENGADAAN INSULATOR SET + HARDWARE, ACCSESSORIES + FITTING
A Pengadaan Accsessories + Hardware
 
1 Single suspension set Incl.Clamp,horn and disk insolator 120 kN set ‐
2 Double suspension set Incl.Clamp,horn and disk insolator 120 kN set ‐
3 Single tension set Incl.Clamp,horn and disk insolator 210 kN set 18 18
4 Double tension set Incl.Clamp,horn and disk insolator 210 kN set 6 6
5 Inverted single tension set Incl.Clamp,horn and disk insolator 210 kN set 12 12
6 Jumper set Incl.Clamp,horn and disk insolator 120 kN set 30
Jumlah  A

B Pengadaan Accsessories + Fitting
1   Suspension set  for GSW55 mm² set ‐
2 Tension Set for GSW 55 mm² set 8
3 Damper for GSW 55 mm² bh 8
4 Jointing ACSR 240/40 mm² bh 30
5 Jointing GSW 55 mm² bh ‐
6 Armour for GSW bh ‐
7 Armour for ACSR bh ‐
8 Repair Sleeve for ACSR 240/40 mm² bh 12
9 Spacer damper  for ACSR 240/40 mm² (dual function) bh 48 12
10 Spacer jumper    bh 60
11 PRESS CONDUCTOR BH 60
Jumlah  B

C Pengadaan Accsessories + Fitting (ADSS)

1 Armour rod for ADSS 12 core bh 6
2 Vibration dumper  for ADSS 12 core bh 12 2
3 Suspension set  for ADSS 12 core set ‐
4 Tension set for ADSS 12 core set 12 4
Jumlah  C

D Pengadaan Perlengkapan Fasilitas Sistem Telekomunikasi FO

1 Gantry Box (GB) 12 core set 2
2 Stain Steel Join box complete with fixing device,fixing clamps and bh 2
necessary accessories (per haspel 4000 m)
Jumlah  D
     JUMLAH   A+B+C+D 
NO URAIAN PEKERJAAN SATUAN VOLUME
KONTRAK REALISASI
1 2 3 4 5
VII PENARIKAN KONDUKTOR, GSW DAN OPGW

 A  Pekerjaan persiapan
1 Mobilisasi Demobilisasi lot 1,00
2 Barak Kerja Unit 1,00
3 Pembuatan Steger Tarikan 1,00
4 Penebangan Pohon Span 2,00
5 Pembuatan Backstay Unit 1,00
Jumlah A

B PENARIKAN KONDUKTOR,GSW DAN OPGW


1 Penarikan ACSR 240/40 mm² Km 8,49
2 Penarikan GSW 55 mm² Km 0,71
3 Penarikan ADSS 12 core Km 0,71
Jumlah B

C Pemasangan Accsessories +Hardwere
1 Single suspension set Incl.Clamp,horn and disk insolator 120 kN set ‐ ‐
2 Double suspension set Incl.Clamp,horn and disk insolator 120 kN set ‐ ‐
3 Single tension set Incl.Clamp,horn and disk insolator 210 kN set 18 18
4 Double tension set Incl.Clamp,horn and disk insolator 210 kN set 6 6
5 Inverted single tension set Incl.Clamp,horn and disk insolator 210 kN set 12 12
6 Jumper set Incl.Clamp,horn and disk insolator 120 kN set 30 30
7 Suspension set  for GSW55 mm² set ‐ ‐
8 Tension Set for GSW 55 mm² set 8 8
9 Damper for GSW 55 mm² bh 8 8
10 Jointing ACSR 240/40 mm² bh 30 30
11 Jointing GSW 55 mm² bh ‐ ‐
12 Armour for GSW bh ‐ ‐
13 Armour for ACSR bh ‐ ‐
14 Spacer damper    bh 48 48
15 Spacer jumper    bh 60 60
16 Repair Sleeve for ACSR 240/40 mm² bh 12 12
17 Armour Rod for ADSS bh 6 6
18 Vibration damper  for ADSS bh 6 6
19 Suspension set  for ADSS set ‐ ‐
20 Tension Set for ADSS set 6 6
21 Jointing ADSS dan Pemasangan Joint Box set 2 2
Jumlah C

D Saging adan Clamping
1 Penyetelan Saging adan Clamping km 0,71 0,71
Jumlah  D
JUMLAH A+B+C+D

VIII PEKERJAAN COMMISIONING

A Pengujian pentanahan
1 Pengujian petanahan Tower Set 2
Jumlah A

B Pengujian OTDR
1 Pengujian OTDR Telekomunikasi Ls 1
Jumlah  A
JUMLAH A+B

IX PEKERJAAN PEMBONGKARAN T.31

1 Pembongkaran tower T.31 Eksisting SUTT 150 kV Set 1


2 Pembongkaran Material Insulator T.31 Eksisting Set 6 6
3 Pembongkaran konduktor kawat tanah GSW km 0,71
4 Pengiriman dan unloading ke gudang PLN Set 1 1
5 Pembongkaran konduktor ACSR km 8,49
6 Pembongkaran Arm Tower set 6
JUMLAH