NO Uraian Pekerjaan Satuan Kontrak: Realisasi
NO Uraian Pekerjaan Satuan Kontrak: Realisasi
NO Uraian Pekerjaan Satuan Kontrak: Realisasi
KONTRAK REALISASI
1 2 3 4 4
I. PEKERJAAN PERSIAPAN
A PENGADAAN STUB TOWER 4 SIRKUIT
1 Tower Type 4DD / 4DDR set 2,00 2,00
2,00 2,00
1,00
C PENGADAAN ACCESSORIES TOWER
JUMLAH
A PEKERJAAN ERECTION TOWER
1 Tower Type 4DD4 + 0 set 1,00
2 Tower Type 4DDR4 + 12 set 1,00
3 Pembongkaran Arm tower set 8,00
4 Pemasangan Arm Tower set 8,00
1,00
B EREKSION ACCESSORIES TOWER
C EREKSION STUB TOWER 4 SIRKUIT
JUMLAH A+B+C
B Pengadaan Accsessories + Fitting
1 Suspension set for GSW55 mm² set ‐
2 Tension Set for GSW 55 mm² set 8
3 Damper for GSW 55 mm² bh 8
4 Jointing ACSR 240/40 mm² bh 30
5 Jointing GSW 55 mm² bh ‐
6 Armour for GSW bh ‐
7 Armour for ACSR bh ‐
8 Repair Sleeve for ACSR 240/40 mm² bh 12
9 Spacer damper for ACSR 240/40 mm² (dual function) bh 48 12
10 Spacer jumper bh 60
11 PRESS CONDUCTOR BH 60
Jumlah B
1 Armour rod for ADSS 12 core bh 6
2 Vibration dumper for ADSS 12 core bh 12 2
3 Suspension set for ADSS 12 core set ‐
4 Tension set for ADSS 12 core set 12 4
Jumlah C
1 Gantry Box (GB) 12 core set 2
2 Stain Steel Join box complete with fixing device,fixing clamps and bh 2
necessary accessories (per haspel 4000 m)
Jumlah D
JUMLAH A+B+C+D
NO URAIAN PEKERJAAN SATUAN VOLUME
KONTRAK REALISASI
1 2 3 4 5
VII PENARIKAN KONDUKTOR, GSW DAN OPGW
A Pekerjaan persiapan
1 Mobilisasi Demobilisasi lot 1,00
2 Barak Kerja Unit 1,00
3 Pembuatan Steger Tarikan 1,00
4 Penebangan Pohon Span 2,00
5 Pembuatan Backstay Unit 1,00
Jumlah A
C Pemasangan Accsessories +Hardwere
1 Single suspension set Incl.Clamp,horn and disk insolator 120 kN set ‐ ‐
2 Double suspension set Incl.Clamp,horn and disk insolator 120 kN set ‐ ‐
3 Single tension set Incl.Clamp,horn and disk insolator 210 kN set 18 18
4 Double tension set Incl.Clamp,horn and disk insolator 210 kN set 6 6
5 Inverted single tension set Incl.Clamp,horn and disk insolator 210 kN set 12 12
6 Jumper set Incl.Clamp,horn and disk insolator 120 kN set 30 30
7 Suspension set for GSW55 mm² set ‐ ‐
8 Tension Set for GSW 55 mm² set 8 8
9 Damper for GSW 55 mm² bh 8 8
10 Jointing ACSR 240/40 mm² bh 30 30
11 Jointing GSW 55 mm² bh ‐ ‐
12 Armour for GSW bh ‐ ‐
13 Armour for ACSR bh ‐ ‐
14 Spacer damper bh 48 48
15 Spacer jumper bh 60 60
16 Repair Sleeve for ACSR 240/40 mm² bh 12 12
17 Armour Rod for ADSS bh 6 6
18 Vibration damper for ADSS bh 6 6
19 Suspension set for ADSS set ‐ ‐
20 Tension Set for ADSS set 6 6
21 Jointing ADSS dan Pemasangan Joint Box set 2 2
Jumlah C
D Saging adan Clamping
1 Penyetelan Saging adan Clamping km 0,71 0,71
Jumlah D
JUMLAH A+B+C+D
VIII PEKERJAAN COMMISIONING
A Pengujian pentanahan
1 Pengujian petanahan Tower Set 2
Jumlah A
B Pengujian OTDR
1 Pengujian OTDR Telekomunikasi Ls 1
Jumlah A
JUMLAH A+B
IX PEKERJAAN PEMBONGKARAN T.31