MEETING OF CITY LEVEL COMMITTEE

HEARTIEST WELCOME TO ALL

DISTRICT COLLECTOR PROJECT DIRECTOR


BARMER RUIDP, JAIPUR

1
(UNDER RUIDP Phase-IV)

2
Barmer
3
Ward Division of Barmer
4
Demographic View
S. No. Particular BARMER
1. Wards 55
2. Area 1465 Ha.

Year Stage Population Projection

BARMER TOWN (55 WARDS)

2011 Census 96225

2021 Base Year 109670

Intermediate
2036 129640
Year

2051 Ultimate Year 149360

5
RUIDP Phase-IV
Work To be consider in this work Approach

• Project with external funding ▪ 100% coverage with the sewer


from ADB to improve the system..
Sewerage system of the identify ▪ Single Contract for water supply
towns of Rajasthan considered and sewerage works
under the RUIDP Phase-IV Project.
▪ Synchronized laying of sewerage &
water supply lines.
• 100 % coverage of municipal area
of Barmer town with piped ▪ Road restoration.
Sewerage System. ▪ Digitization of Network
▪ Work Contract embedded with
long term O&M provision

6
DETAIL PROJECT REPORT
OF
SEWERAGE
FOR
BARMER TOWN

7
POPULATION & SEWAGE GENERATION

Per Capita
Sewerage Load Sewerage Load
Year Pop Sewage Flow
KLD MLD
(LPCD)

2021 109670 113.4 12436.578 12.5

2036 129640 113.4 14701.176 14.8

2051 149360 113.4 16937.424 17.0

8
DETAIL PROJECT REPORT OF
SEWERAGE FOR BARMER TOWN

Cost
S. No. Particular
(Rs. Crores)

1 Estimated Cost of Works 138.23

2 Contingencies@2% of Cost of works 2.77

3 O&M for 10 years 9.99

4 Total Project Cost 150.99

9
Details of Sewer Lines Laid By RUIDP

Ward No.
02, 03, 04, 16, 27, 30, 31, 32, 33, 34, 35, 47, 48, 49,
50, 51, 52, 53 and 54
Total: 19 Wards Covered

Existing Sewer Length covered = 27 km.

10
Details of Sewer Lines Laid By TCIL

Ward No.
42, 44, 45 & 46
Total: 4 Wards Covered

Existing Sewer Length covered = 10 km (approx.)

11
Details of Sewer Lines Laid By NF Infra

Ward No.
17, 18, 20, 22, 25 & 26
Total: 6 Wards Covered

Existing Sewer Length covered = 20 km (approx.)

12
EXISTING SEWERAGE LAYOUT PLAN

13
Details of Sewer Lines Covered Under new Proposal

Ward No.
1, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 19, 21, 23,
24,28, 29, 36, 37, 38, 39, 40,
41, 43 & 45
Total: 26 Wards Covered under the proposal

Proposed Total Sewer Length including Trunk Mains


110.10 km

14
PROPOSED SEWRAGE LAYOUT PLAN

15
DETAIL PROJECT REPORT OF SEWERAGE FOR
BARMER TOWN

COVERAGE OF WARDS
Under RUIDP Under
S. No. Particulars By TCIL By NF Infra Total
Ph-II New Proposal

No. of Wards
1 covered in Barmer 19 4 6 26 55
Town (Nos.)

Sewer Length in
2 27 10 20 110 167
Barmer Town (Km)

16
PROPOSED SEWERAGE WORKS

DETAILS OF PROPOSED SEWER NETWORK

DWC Pipe dia. 200 to 300 mm* : 94.75 Km

HDPE Pipe dia. 200 to 630 mm* : 4.07 Km


(Trenchless)
RCC NP4 Pipe* : 11.28 Km

Sewer Network* : 110.10 km

* The Lengths are including the length occupied by the Manholes

17
PROPOSED SEWERAGE WORKS
DWC PIPE ABSTRACT
Total
DWC Pipe Dia
(M)

200 mm 86942.00

250 mm 6607.00

300 mm 1209.00

Total 94758.00

SAY 94.76 KM
18
PROPOSED SEWERAGE WORKS
HDPE PIPE ABSTRACT

Total
HDPE PIPE DETAILS
(M)
250 mm dia HDPE pipe 1268.00
315 mm dia HDPE pipe 452.00
400 mm dia HDPE pipe 853.00
500 mm dia HDPE pipe 552.00
630 mm dia HDPE pipe 952.00
TOTAL 4077.00
SAY 4.07 KM 19
PROPOSED SEWERAGE WORKS
RCC PIPE ABSTRACT

Total
RCC PIPE DETAILS
(M)
350 mm Dia 816.00
400 mm Dia 1480.00
450 mm Dia 1647.00
500 mm Dia 169.00
600 mm Dia 7177.00
Total 11289.00
SAY 11.28 KM
20
Sewerage Treatment Plant

➢ The Sewerage Treatment Plant Design has been proposed for


Intermediate Stage year 2036.

➢ The total Sewerage load for year 2036 is 14.8 MLD.

➢ Hence the total required capacity is 14.8 MLD.

➢ The Capacity of Existing STP is 10 MLD.

➢ Hence balance capacity of STP required is 4.8 MLD.

➢ STP (SBR Technology) of 4.8 MLD capacity is proposed near to


Existing 10 MLD STP on Sindhari Road, Barmer

21
Location of STP

(10 MLD EXISTING)


(4.8 MLD PROPOSED)

25°44'53.7"N, 71°28'20.4"E

(STP SITE IS LOCATED 6.0 KM FROM


SINDHARI CHORAHA ON SINDHARI
ROAD)
22
Location Map of STP

(4.8 MLD PROPOSED)


STP-1 (10 MLD EXISTING)

23
Sewerage Treatment

Quality parameters of Raw sewerage and Treated Effluent.


S. no. Parameter Raw Sewage Treated Effluent
Parameter Parameter
1. pH 6.5-7.5 mg/l 6.5-9.0 mg/l
2. BOD at 20°C 300mg/l <10mg/l
3. COD 600mg/l <50mg/l
4. TSS 600mg/l <50mg/l
5. Total Phosphorus 6mg/l <2mg/l

The treated effluent may be used for irrigation/ horticulture / Fire


Fighting /In Public Utilities/ Cleaning of Sewer Lines / wetting of
playgrounds, meeting ground and roads in summer/ washing of
railway platforms etc.
24
SALIENT FEATURES
S. No. Particulars Quantity

1 Total Pipe Line Length proposed 110.10 Kms.

2 Sewerage Treatment Plant 1 Nos. of 4.8 MLD Capacity

3 Type of Treatment Proposed SBR Technology

4 Railway Line Crossings 2 Nos.

5 National Highway Crossings 2 Nos.

6 Electrical Load Extension at STP 1 Nos at Existing STP

25
ABSTRACT OF COST
General Abstract of Cost
Amount
S. No. Description
in Lakhs
1.0 Sewer Network 10744.32
2.0 Sewage Treatment Plant 1139.00
3.0 House Sewer Connections 1633.39
4.0 Provisional Sum 306.00
Total Project Cost of works 13822.71
5.0 Add Contingencies@ 2% of Project Cost 276.57
Operation and Maintenance Cost for 10 years
6.0 999.93
period in Lakhs
Total Project Cost Including O&M & Contingencies 15099.21
In Rs. Cr. 150.99
26
THANK YOU

27