Pressure Testing 5K Choke - Choke Tested Inside GY Base Well - Workshop Foreman and

Download as pdf or txt
Download as pdf or txt
You are on page 1of 15

Pressure testing incident

Summary

• Pressure testing 5K choke


manifold TX 54-10
• Choke tested inside GY base well
test pressure test bay
• Workshop Foreman and
Technician inside test bay to
inspect for leaks
• Thermowell (3/4” NPT) failed
• Hit Workshop Technician in leg,
resulting in serious injury to right
knee
Pressure testing incident
Summary

WARNING

The following slide may cause


distress

A picture of the incident scene will


now be shown
Pressure testing incident
Summary
Incident Scene
Pressure testing incident
Summary

The injury was caused


when the Technician was
struck by a thermowell
ejected from a 3/4” NPT
female tapping in a 5K
choke manifold during a
pressure test.
Thermowell
tapping
Thermowell
Pressure testing incident
Summary

3/4” NPT Thermowell

The thermowell is
about 9 ins long and
weighs approx 1 kg.

It struck the
Technician on his
knee from approx
0.5 metres. Thermowell
Pressure testing incident
Summary

Severe corrosion had


affected the mechanical
integrity of the female
thread.

The forces generated


by the 5000 psi test
pressure overcame
the mechanical strength
of the corroded thread
and caused the
thermowell to be Corroded thread
ejected.
Pressure testing incident
Forces

Pressure = Stored Energy

When pressure acts upon an area,


a force is generated

Pressure is measured in Pounds


per Square Inch (psi)
Expro Separator - Pressure Containing Device

1 psi = 0.0689 bar


1 psi = 6.895 kPa
Pressure testing incident
Forces
The higher The larger
the pressure OR THE GREATER
the area
ie 10,000psi ie 400 barrel tank THE FORCE

Calculating the force acting upon the thermowell

Force = Pressure x Area

Test pressure = 5000 psi

Affected area = 0.785 sq ins

Force = 1 3/4 tons


Pressure testing incident
Forces

When the NPT


… the stored energy was
thread failed...
released and propelled...

=
...the thermowell
at a velocity of
42 metres/ sec
or

94 MPH
Pressure testing incident
Underlying causes
• Procedural failure

Pressure retaining threads and tappings should have been inspected


for wear and corrosion during the maintenance of the choke manifold.
See the photographs and answer the question, had they been?

Calibrated thread gauges are to be used for checking the condition


of the threads. The gauges were specified in the procedures but had
not been used.

A review of the risk assessment for pressure testing had not been
conducted prior to starting the test.

Two maintenance technicians entered the test bay to investigate leaks


from the choke manifold assembly. It was not known if the pressure
had stabilised prior to the technicians entering the bay. Actual
pressure on the assembly was not know/recorded.
Pressure testing incident
Underlying causes
• Procedural ineffectiveness

The procedures were found to be outdated with several cross-


references to memos, some 5 years old.

Pressure tests had not been recorded on charts, although calibrated


gauges were routinely used.

Job cards were not being completed as the maintenance work


was progressed.

The technician was working under the supervision of the


workshop foreman during the re-build and testing of the choke
manifold.
Pressure testing incident
Underlying causes

• Facilities

The test bays were built to contain the failure of equipment during
pressure testing. However, the bay walls and doors were not fitted
with viewing ports or any other means to identify the source of leaks.

Normal practice was to apply the test pressure and wait for pressure
stabilisation before entering the test bay to visually inspect for leaks.
Pressure testing incident
Actions

Dismantle and inspect ALL pressure retaining threads on Yarmouth


Base equipment using calibrated thread gauges. Ensure condition of
threads are established and deficient components are scrapped and
replaced as required prior to any further pressure testing activity.

Action: Closed

Investigate alternative materials and options for pressure retaining


threads for Expro owned equipment with a view to adopting same.

Action: Region Technical Manager/SES BS

Issue an alert to all Expro bases and clients upon completion of the
investigation (Interim alert already issued).

Action: Region HSEQC Manager


Pressure testing incident
Actions

Review and revise the procedures for the maintenance and inspection
of pressure retaining equipment (particularly threads and threaded
fittings). Revise the pressure testing procedures for all equipment.

Action: Region Technical Manager/SES BS

Train staff in the application of these new procedures and ensure that
the training is recorded.

Action: Region Manager(s)

Review and report upon the Region’s pressure testing facilities against
industry best practice with a view to implementing best practice.

Action: Region Technical Manager


Pressure testing incident
Actions

Disseminate and roll out the investigation findings to workshop and


operations staff involved in maintenance and pressure testing
activities.

Action: Region Manager(s)

Perform an audit of all the actions arising from this incident to verify
that they are effective and have been consistently applied throughout
the Region.

Action: Region HSEQC Manager

You might also like