Master Plan FOR Drainage of Storm Water Drainage of The Najafgarh Basin IN Union Territory of Delhi
Master Plan FOR Drainage of Storm Water Drainage of The Najafgarh Basin IN Union Territory of Delhi
Master Plan FOR Drainage of Storm Water Drainage of The Najafgarh Basin IN Union Territory of Delhi
MASTER PLAN
FOR
IN
1976
1
MASTER PLAN -NAJAFGARH BASIN
2
MASTER PLAN -NAJAFGARH BASIN
ANNEXURE-II.
G.S.I Report on Ground Water Conditions Around Najafgarh Jheel 52-56
10. Summary of Master Plan Report on Najafgarh Basin.
(1) Najafgarh Drain 54
(2) Mungeshpur Drain 54-55
(3) Palam Drain 55
(4) Palam Link Drain 55
(5) Nasirpur Link Drain 55
(6) Mundela Khurd Scheme 55-56
3
MASTER PLAN -NAJAFGARH BASIN
considerable area from Haryana & Kanjhawala basin is also draining into the
Najafgarh sub-basin from the North West & North directions. The basin
contains Approximately 76 villages with a population of about 1.30 Lacs. The
drainage zone of the sub-basin as explained above is very extensive and consists
of Najafgarh block, part of Urban areas of Cantonment Board, part of Mehrauli
& Kanjhawala Block & and adjacent areas of Haryana. A plan showing the present
population in the villages as per 1971 census and the projected population in
1981, 1991 & 2001 is enclosed as Appendix-III.
Haryana side, the Jheel is still under submersion, which covers an area of 6.5
sq.kms.
The sub-soil water in the block is generally saline and varies from 0.2 m.
to 9 m. below G.L. Two Plans showing the minimum and the maximum water tables
are enclosed as appendix IV & V. The water table is generally high around the
Najafgarh Jheel area and low towards south-east corner of the block.
All the 76 villages of the Najafgarh block are covered by the drainage
zone of this sub-basin and its total population was 1.31 Lacs in 1971 (vide
appendix-I). Out of the total area of 332 sq.km., only a negligible portion on the
south eastern boundary has been included for development under the Master
Plan Programme for urbanization of U.T. of Delhi and the remaining areas are
rural. Accordingly to the National Capital Region Plan, there is a proposal of
radial arteries being developed all around the Central Core of the urban Delhi.
One of the arteries will be Delhi-Gurgaon Road, passing through the Najafgarh
block. However, as per the N.C.R. report, no major development has Been
envisaged in the surrounding rural area of Delhi and it has been mentioned that
due to over congestion of the city of Delhi, a green belt should be left in the
immediate surrounding regions and the excess population to be diverted to
satellite towns beyond the border of U.T. of Delhi. Emphasis has been laid by
the N.C.R. on the development of rural areas. Accordingly, rural centres have
been classified into the following three categories to make the planning more
effective, realistic and disperse the population uniformly:-
6
MASTER PLAN -NAJAFGARH BASIN
1.Growth Centres: These will serve an around 200-300 sq.km. and 1.2 Lacs to 2
Lacs projected Population in 1981. These centers would have activities mainly
non-agricultural in nature with all centralized amenities and facilities in nature
with all centralized amenities and facilities in the field of education, medical,
public health, better whole-sale and retail shoppings, civic, cultural and
recreational centres etc.
2. Central Place villages: These will Serve a radius of 3 to 5 Kms. and serve an
area of about 30 to 80 sq.kms. and a projected population range of 20,000 to
40,000 in 1981. All such village will also have a predominantly agricultural
economy and will provide central service facilities for all the villages in the
cluster.
3.Basic Villages: Will serve their own existing Abadies. Amongst the important
villages in this Basin, Najafgarh has got a population of 10,009 Palam 16,800
Brijwasan 5800, Gumanhera 2050 and Ujwas 2400 according to 1971 census. Out
of the above villages, Najafgarh will be developed as Growth centre and
Brijwasan, Guman hera, Ujwas and Palam will be developed as central place
villages and hence may be facing internal drainage problem unless planned in
advance.
1:3 RAINFALLS:-
The Najafgarh sub-basin which falls under the Category of rural areas of
U.T. of Delhi covers an Area of about 332.0 sq.m. The net work of rain gauge
within Delhi Territory was limited till recently to only two stations i.e. Palam and
Safdarjung, for which long term rainfall records are available. The storm rainfall
analysis carried out from these data by the Reddy Committee during the 1958,
found that the rainfall in Delhi Territory was quite erratic and the existing
stations were considered inadequate for detail analysis of rainfall. According to
the recommendation of this committee, 14 self-recoding rain gauge stations had
been installed throughout the Delhi Territory during 1973.
7
MASTER PLAN -NAJAFGARH BASIN
However for the rainfall study for Najafgarh Sub-basins, none of the 14
self-recording R.G. Stations recently set up can be utilized, since the data for
only 3 years is available.
Hence only the rainfall data from Palam, R.G. Station has been considered
for this catchment. The actual Rainfall Analysis is enclosed as per Appendix
No.VI.
Urban drains:
The maximum hourly rainfall data of Palam rain-gauge station is available
for a period of 9 years i.e. 1966 to 1974 and the same has been put to frequency
analysis. The hourly maximum rainfall corresponding to 1 year, 2 years, 5years,
10 years and 25 years frequency comes to 1.28”, 1.72”, 2.29”, 2.73” and 3.30”
respectively vide Annexure-II.
There are only 3 semi urban drains in the basin for which an hourly
intensity of 1.72” is adopted, which is of two years frequency.
8
MASTER PLAN -NAJAFGARH BASIN
9
MASTER PLAN -NAJAFGARH BASIN
Annexure-I
10
MASTER PLAN -NAJAFGARH BASIN
11
MASTER PLAN -NAJAFGARH BASIN
Annexure-1A
Y = EY = 3774.98 = 157
N 24
12
MASTER PLAN -NAJAFGARH BASIN
X = EX = 9.227 = 0.384
24
(X)2 = 0.1475
B = EXY-NXY
EX2 –N(X)2
= 185
- -
A = Y - B X = 157 -185 x 0.384
= 157-71 = 86
= 86 + 185 x 0.6990
= 86 + 130
= 216 M.M
= 8.5 inches.
Annexure-II
Maximum hourly rainfall of Palam rain gauge station for the years from
1966 to 1974 N= 9 years.
13
MASTER PLAN -NAJAFGARH BASIN
Annexure-11 a
CALCULATION:
Y = EY = 405.30 = 45.03
N 9
14
MASTER PLAN -NAJAFGARH BASIN
X = EX = 3.0245 = 0.3361
N 9
(X) 2 = 0.1130
= 164.8709-136.2114 = 28.6595
1.7989.1.170 0.7819
= 36.65
A=Y-BX = 45.03-36.65x0.3361
= 45.03-12.32
= 32.71
15
MASTER PLAN -NAJAFGARH BASIN
Region Report the rural centres have been classified into the following three
categories viz.
The internal drainage of these villages has not been properly taken care
of. The responsibility of the internal drainage of these villages lies with the
M.C.D. Even the other smaller villages within the Laldora are being looked after
by the M.C.D. It is found that in a number of villages the internal drainage
system has not been properly maintained.
16
MASTER PLAN -NAJAFGARH BASIN
(c) Villages which are liable to flooding normally must be provided with
permanent or mobile pumping sets in draining out water to the nearest available
link of the main drain. Development charges will be levied on the villagers for
installing such pumps.
(B ) Growth Centers:-
The drains in the rural fields are being looked after by the FCD, Delhi
Administration. It has been observed during inspection that annual maintenance
of a number of drains has been neglected all together. In some cases no regular
banks are there, whereas at certain places cart tracks are crossing the drains,
thus obstructing the natural flow. There is a lot of weed growth in certain
reaches of the drains and more over, sections of the drains are not uniform.
Farmers are using the bed of the drains for cultivation purposes at a number of
places. Such practices are to be checked completely and constant vigil by the
17
MASTER PLAN -NAJAFGARH BASIN
field staff of the FCD is required to stop any unauthorized blocking of the drain
anytime during the year. The blockings are sometime due to crossing of
irrigation channels, which is to be totally discouraged. Crossing if any, shall be
with pipes allowing proper water way for the drain to pass unobstructed. The
field staff of FCD of Delhi Administration has to submit a report of all
obstructions created along the drainage channels every fortnight and these are
to be cleared before the next three days positively. Before the start of
monsoon, silt clearance of the drains must be taken up every year and sections
to be restored to designed sizes. Cultivators blocking the drain or cultivating in
the beds of the drains, to be legally punished. Sectional officer allowing such
practices are to be dismissed. Villagers causing blockage to drains shall be
punished under law. Relevant acts shall be made known to the villagers for strict
compliance.
It is also observed that the irrigation channels in the basin coming from
Haryana State often over flow near their tail ends in the monsoon season, there
being no surplusing arrangements. This inundates the neighboring low lying areas.
Problem in sometimes created by small breaches in the Bank or by seepage.
Constant watch therefore should be kept by FCD and such breaches must be
immediately brought to the notice of the Haryana Government for immediate
remedial measures. The Haryana Government must take up construction of
surplusing arrangements and connecting them to the regular drains.
18
MASTER PLAN -NAJAFGARH BASIN
8.5” An areal distribution factor of 90% has also been taken into Account as
discussed vide 1:3.
According to the recommendations of the expert Committee, a runoff co-
efficient of 15% and 30% for the rural plan & semi hilly rural drains has been
adopted. After applying the run off factor of 15% and ADF of 90% to the
rainfall intensity of 8.5”, the discharge for the rural drains works out to 10
cusecs/Sq.miles as under:-
Run off from 8.5” of rainfall
Thus the discharge for semi hilly drain will be Rs.20 cusecs/sq.miles. Say 10
cusecs/sq. miles.
2.1:2 Urban drains. The drains in the Najafgarh basin coming from the urban
areas have been designed for a rainfall intensity of 1.72”. This is the maximum
rain-fall intensity for a return period of two years according to the Palam rain
gauge station (vide para 1:3 above). An aerial distribution factor of 90% and run
off 35% have been adopted for arriving at The actual run off as discussed for
arriving at the actual run off as discussed in the outlines of the master plan.
= 1815 cft/hour/acre
= 1815cusecs/acre = ½ cusecs/acre
60x60
19
MASTER PLAN -NAJAFGARH BASIN
2.2 Design section: The sections of the drains have been designed with
Manning’s formula for open channels for uniform flow.
2.2.2 Bed Slope: - The Bed slopes drain the drains have generally been kept
with the following consideration:-
(a) To limit the velocities in the drains within none silting
and non-securing values.
(b) To avoid falls in the drains as far as possible.
(c) To maintain the existing sections of bridges and
culverts. Generally the Bed slopes vary from 1 in 1000 to 1 in 7000. But in
exceptional cases they have been kept flatter or steeper, where the levels
of the main drains do not permit it otherwise.
2.2.3 Velocities: - Velocities in the drains have been Kept within the following
limits:-
Unlined sections 0.45 to 1.50 meters/Sec.
Lined Sections (Brick lining or Rubble Masonry) 1.50 to 3.0 meters/Sec.
However, in exceptional cases, velocities upto 0.3 meters per second has
also been allowed in the drains where discharge are very low, of the order of 5
to 10 cusecs, with the following considerations:-
20
MASTER PLAN -NAJAFGARH BASIN
2.3 Bridges.
2.3.1 Waterway: Water way for the bridges and culverts has been provided for
the full design discharge, limiting the afflux between 15 & 25 Cms.
The water logging and drainage problems in the Najafgarh block are
mainly categorized as below:-
The area to the South-East of Najafgarh Block has got very few regular
drains for draining the discharges from its own catchment and also that
coming from the hilly areas of the Cantonment and Mehrauli block. Moreover,
two soil conservation bunds namely Mahipalpur bund and Brijwasan bund in the
Mehrauli block and Najafgarh block have also not been connected by regular
drains to drain off the surplus water. With the result, the fields and the
surrounding villages of the area namely Brijwasan, Kapashera, Shahabad,
Mohammadpur, Barthal and Bagrola are affected badly in rainy season, due to
stagnation.
During the 1967 monsoon there was about 4 to 5 feet of water in the
village and the necessity of constructing a drain was very much felt during that
period. Accordingly a scheme to drain out the water from this area was framed,
investigated and approved, but was not taken up for execution. The same should
be implemented early. The alignment of the proposed drain has been marked on
the drawing. The L-section and cross sections of the drain along with the
relevant details are also enclosed at Appendix-VII.
During the monsoon, a large quantity of water flow from the Haryana
Territory through a culvert in Delhi-Gurgaon Road Near village Kapashera. A
small drain is already existing from the culvert and is ending abruptly at village
at village Brijwasan without any surplusing or out falling arrangements. Due to
inadequate capacity of the drain and due to the fact that this drain is not
22
MASTER PLAN -NAJAFGARH BASIN
connected to any other drain, village Brijwasan and Kapashera are flooded every
year causing crop-damage. The Delhi-Rewari Railway. Line is also affected.
Sometimes Flooding is caused even on Najafgarh Brijwasan Road. To solve this
problem, a drain is proposed to be ‘Constructed from the culvert of Delhi-
Gurgaon Road to the Najafgarh drain utilizing the existing drain on the way. At
the first instance, the drain should be constructed only upto culvert No.44 of
the Delhi-Rewari Railway line, thus allowing the water to accumulate in the low
lying area of Brijwasan Bund. This will help in recharging the sub-soil water table
in the surrounding areas of the bund. The surplus water if, will over flow from
the weir of the bund and will automatically flow to Najafgarh drain through the
natural drainage path already existing. The above natural drainage path should
be converted into the regular drain at a later date if necessary. The L-section
and cross-section of the drain along with other necessary details are enclosed
herewith at Appendix-XI.
A few villages are having their ponds in their neigh bourhood where all the
storm water collects during the monsoon. These ponds are to be connected to
regular N-23 drains as otherwise they get flooded in updating the hutments and
the roads. The major problems in this category are in the following villages:-
There is a pond behind the Govt. Girls Higher secondary School, which
gets filled up and over flow during monsoon, submerging the nearby houses and
part of the Delhi-Najafgarh Road near the bus stop. The problem becomes
worse with the local sullage of the area collecting in the ponds in the midst of
houses. M.C.D. who is responsible for the maintenance of internal drainage of the
area has to resort to pumping every year. Flood Control Department of Delhi
Administration has carried out detailed survey of the area. A link drains of a
capacity of 30 cusecs, off taking from the pond and out falling into Najafgarh
Drain U/s. of Kakrola regulator, where an inlet is already available can solve the
problem permanently. The bus stop connected to the pond, for draining the area
one the other sides of the road. The road level also needs rising above the
present eyelevel by 2’. The alignment of the drain has been marked on the plan
23
MASTER PLAN -NAJAFGARH BASIN
and its L-section is shown at appendix XI. The above measures are urgently
necessary to remedy the serious drainage problem.
3.2.2. Chhawala Village: - A similar problem also exists in the Chhawala village
where three local ponds in the abadies get filled up during the monsoon and
submerge the neighboring houses. It is therefore, recommended that all the
three ponds may be connected to N-24 each other by link and ultimately
connected to the Najafgarh drain U/s. of Chhawala Bridge. The alignment of the
drain and its sections are shown at appendix XII.
3.2:3 Brijwasan Village: A pond near the Brijwasan village gets filled up during
the monsoon thus inundating the surrounding houses. A link drain off taking from
the pond and out falling into the area surrounded by Brijwasan Bund through the
culvert No.43 (Delhi-Gurgaon Railway Line) is proposed to be constructed to
drain off the Surplus water. The alignment of the drain is marked on the
drawing enclosed at appendix I & II. The L-section and its cross section along
with other relevant details are also enclosed at appendix-XIII.
3.2:4 Malikpur Pond Scheme: There is a big pond near the village Malikpur
situated near Dhansa. In certain years when the rainfall is high this pond gets
inundated causing great hardship to the villagers. In addition to the problem
caused to the villagers. In addition to the problem caused to the village on
agricultural area of about 100 acres also gets submerged. In this area water
stands to a depth 2-3 feet. Earlier a scheme was prepared for draining the area
by a link drain connecting this village to Najafgarh Drain U/s. of Rawta Bridge.
It has now been proposed to construct a small drain off taking from the pond in
the Malikpur village and out falling into the proposed Mundela Khurd drain vide
para 3.4:1. The scheme should be implemented very urgently. The alignment of
the drain is revised to avoid hardship of villages as marked on the plan enclosed
a appendix. Its L-section & cross-section with other relevant details are
enclosed at appendix XIV
in about 100 acres of land. If a drain is constructed connecting this area to the
Palam drain, the problem can be solved permanently. The alignment of the drain
is marked on plan enclosed at appendix I & II. The L-section and cross-section
is also enclosed at appendix -XV.
3.2:6 Palam Pond Scheme: There are a few constructions near the Palam
Airport where lot of water gets accumulated during monsoon period. During
heavy rains, even the road gets/submerged causing inconvenience to the public.
The water stands in the field to a depth of about 1 foot in an area of about 100
acres causing damage to the crops. A link drain is therefore suggested to be
constructed off taking from the said area and out falling into Nasirpur drain
flowing at a distance of hardly 500 meters. The alignment of the drain is marked
on the plan enclosed at appendix I & II. The L-section and cross section along
with other relevant details is also enclosed at Appendix XVI.
There are two irrigation channels namely Dhansa Minor and Surkhpur
minor flowing through this block. Both of them are having their tail ends in this
block. Dhansa minor is having its tail end near the village Gummanhera whereas
Surakhpur minor near Jafarpur. None of them is having surplusing arrangement
near their tail ends. During the rainy season, when water is not needed for
cultivation purposes, farmers plug the outlets of the minors near the tail end.
With the result, minors start overflowing and inundate the surrounding low lying
areas. Sometimes, seepage water from the above minors also create problem.
The major problem of drainage congestion due to overflow of minors occurred in
1975 in the village Kair which is situated near the left bank of Surakhpur minor
and is built up in a low lying area. The whole village got submerged for about
twenty days due to chocking of the siphon across the minor near the village
resulting in overflowing of the minor. The water was standing in the village and in
the surrounding field nearly to a depth of about 2 ft. in an approx. area of 50
acres, thus causing inconvenience to the people as well as damage to the crops.
The following measures are therefore suggested to overcome the above problem
permanently.
25
MASTER PLAN -NAJAFGARH BASIN
3.3:2 Surakhpur Minor: Surakhpur Minor and sub-Minor area having their tail
ends near Zafarpur and Mitraon villages respectively. At present there is no
surplusing arrangement for the minors. As a result, the surplus irrigation water
used to spread out in the open fields between Zafarpur Kalan and Sorada.
(a) The syphon across the Surakhpur minor under the Kair-Mitraon road
must be immediately silt cleared and repaired.
26
MASTER PLAN -NAJAFGARH BASIN
In addition to above, drains which have their origin in the other states and
carry discharges into the U.T. of Delhi are mainly the West Jua drain, and
Thanekurd drain which are not capable of carrying their full discharge due to
their limited capacity. They therefore overflow and cause flooding in the low
Lying areas of their States as well as the areas of the U.T. of Delhi. A major
problem of drainage had occurred in 1975 in the villages Mundela Khurd and
Mundela Kalan.
27
MASTER PLAN -NAJAFGARH BASIN
has been observed in 1975 that Haryana Government was sending drainage water
through minors during the monsoons. The discharge in the different reaches
have been calculated at the rate of 10 cusecs per sq.miules of the catchment
area as per design criteria laid down for rural area of Delhi. While designing the
28
MASTER PLAN -NAJAFGARH BASIN
above drain, it has been observed that the FSL of the proposed drain at the
outfall point is slightly lower than the FSL of the Najafgarh Drain which cannot
be avoided even after keeping the water surface slope to the minimum. Gradient
possible, considering the topographically conditions of the area. In this reach
the FSL of the Najafgarh Drain is slightly above the natural surface level.
Hence chances of back flow from Najafgarh Drain at the time of its
running in full capacity into the above drain cannot be ruled out. It is therefore
suggested that:
1. Mundela Khurd link drain should be provided with a gated regulator at the
outfall point so that gates could be operated only when the conditions are N/32
favorable. However it has been examined that the Najafgarh drain will not be
running for more than 10 days above the design outfall level of the proposed
drain.
The L-section and cross section of the Mundela Khurd Link drain along with
the other relevant details are enclosed herewith.
29
MASTER PLAN -NAJAFGARH BASIN
The following committees had examined the drainage problem of Delhi and
dealt with the remodeling of the Najafgarh drain and its tributaries which is the
main drain age system of the entire U.T. of Delhi.
4.1:1 Urban drains may be designed for the rainfall intensity of 1.67”/Hr. with
a runoff factor of 0.30 i.e. ½” net runoff.
4:1:2 The storm water drains in the rural area shall be designed so as not to
allow storm water to stand in the fields for more than 3 days and shall be for
worst condition, occurring once in 5 years with a runoff factor of 0.15. The
maximum 3 days rainfall occurring once in five years is 8.2” which works out to
runoff of about 10 cusecs/sq.mile of catchment area. Similarly runoff for hilly
area is 20 cusecs /sq,miles of catchment area.
4:1:3 An immediate interim relief by regarding the Najafgarh drain above the
reach which has already been regarded will even up the existing bed slope and
local humps between Kakrola bridge and Basaidarapur bridge and relief about
2900 acres for Rabi cultivation by bringing down the level of Jheel to
R.D.690.00.
If the rain water is prevented from flooding the area for a long duration
and the same is drained away within three to four days after rainfall. This will
relieve an area of 14400 acres within the Jheel. Works necessary to achieve
the objects are:-
4:2:1 The capacity of the Najafgarh drain should be increased to 3000 cusecs
throughout as soon as possible. It should be further increased to 10,000
cusecs in tail reaches to suit present as well as urban development according to
Delhi Master Plan.
4:2:3:-The Chhawala bridge should also have a capacity to pass 3000 cusecs
without submerging the area.
4:2:4:- A ring bund about 6’ high should be constructed all round the Najafgarh
Jheel with its bottom on the 690 contour. The work should be completed only
after the remodeling of the Najafgarh drain is complete.
4:2:6:- The Dhansa bund and the Najafgarh Jheel should be connected by a
drain so that the water released from the regulator may flow down without
submerging the country side.
4:2:7:- The capacity of the regulators in the Dhansa bund should be increased
to 3000 cusecs in all with a drop in head of 1 foot.
31
MASTER PLAN -NAJAFGARH BASIN
4:2:9:- A new drain with a capacity of 3000 cusecs should be constructed from
a place above Dhansa bund upto the river Yamuna. It may be taken through
Gurgaon district and may join the Yamuna north of Faridabad. The existing
Shainten Nalla may be used in tail reaches.
4:2:10:-The capacity of the link drain is between the Jahazgarh and Dhansa
bund should be increased to suit the dia mentions of the new drain above bund
and it should have a regulator at RD-12,000. This work should however be
started only after the new drain taking off above Dhansa bund is completed.
4:2:12:- The Project estimate for a dam across the Sahibi nadi proposed by
the Rajasthan Govt. at Ajmeripura may be approved and work commenced as
early as possible.
32
MASTER PLAN -NAJAFGARH BASIN
4:3:2:- It is essential that the work of preparing a Master Plan for drainage of
Delhi is taken up without further delay and completed as early as possible so
that no difficulty may be experienced later on, either in constructing new drains
or remodeling the existing areas within the urbanized limits.
4:3:3:- The capacity of Najafgarh drain from Jhatikera upto Kakrola regulator
at R.D. 65000 should be increased to 3000 cusecs as early as possible.
4:3:4:- The old regulator at Kakrola should be remodeled so as to have its erect
at same level of 681.00 as that of new regulator. This will improve the
discharging capacity of the drain at this point and will help in passing discharges
upto 4000 cusecs through the two regulators in times of need.
4.3.5:- The Najafgarh drain below Kakrola regulator upto Basaidarapur Bridge
at RD 1, 14859 should be regarded to a slope of 1 in 9000. this will increase the
capacity of the drain to 3600 cusecs.
4:3:6:- The capacity of the drain connecting Dhansa bund with the Najafgarh
Jheel and the latter with the Najafgarh drain should be increased to 3000
cusecs as early as possible.
4.3.7:- For reducing the inflow into Najafgarh Jheel from its own catchment
areas, possibility of constructing bund on the hill stream coming down from
rocky areas on the north east of Gurgaon district and storing water for
Irrigation and Water supply in addition to the existing bund should be
investigated and those found economically feasible should be constructed.
4:3:8:- In order to deal effectively with the water coming down from the rural
and urban areas of Delhi State itself. A supplementary drain of the capacity
very in from 4000 cusecs at head to 4500 cusecs at the tailed which will take
off from the Najafgarh drain from its lefts bank near RD 88000 opposite to the
outfall of the proposed Pankha Road or the cantonments drain and run in a north
easterly direction for about 7 miles and then take a turn towards east until it
33
MASTER PLAN -NAJAFGARH BASIN
meets the Shahalam bund which will form its bank and fall into Najafgarh drain
below its tail regulator should be constructed now or later as may be found
feasible. However, necessary steps to acquire the land required for constructing
the drain which will be 15 to 18 miles and will have a bed slope of 1 in 8000
should be taken up as early as possible, as the acquisition proceedings take a long
time.
4.3.11:- Lower down, either a few check dams or low diversion weirs with short
channels taking off from them may be constructed across Sahibi Nadi on either
side of Rewari-Sohana road crossing the Haryana state for See page irrigation.
34
MASTER PLAN -NAJAFGARH BASIN
4.4.3 :- Since the present Master Plan indicates the areas likely to be urbanized
upto 1981, studies were also carried out by rational method to find out the
discharge if the balance areas are urbanized at later data, which revealed that
even if these areas are urbanized there will not be significant differences in
outfall discharges on account of larger time concentration.
1. Bharat Nagar
Bridge to Rajpur 8500 72 ft. 1:1 15:25 1 in 4000
Road bridge.
2. Rajpur Road to
Rifle range bridge. 9400 80 ft. 1:1 15.25 -do-
The capacity of the Najafgarh drain in the reaches U/S of Bharat Nagar
should be examined with reference to design discharge it will have to carry for
rainfall intensity of 1 in 5 years and with the progress of urbanization.
4:4:6:- At present there are only two main gauge stations in Delhi that is Palam
& Safdarjung. Since the area draining into Najafgarh drain is more than the
intensity of rainfall cannot be applied to entire areas 4000 acres. As now some
additional rain gauge stations are set, it is necessary to accurately observe and
analysis the rainfall from these stations to work out the correct intensity of
rainfall for the likely discharge in Najafgarh.
36
MASTER PLAN -NAJAFGARH BASIN
The discharge was calculated on the basis of the available rainfall data until
that date. A return Period of 5 years was adopted and the designed intensity of
hourly rainfall was taken as 2.17 inch. An aerial distribution factor of 70% was
assumed. The runoff co-efficient of 0.45 and 0.6 was assumed for the density
of 100-120 persons per acre and 150 persons per acre respectively. Only the
37
MASTER PLAN -NAJAFGARH BASIN
rainfall data from Palam rain gauge station was utilized. The rainfall data of
Safdarjung was not considered as it showed comparatively much less intensity.
The bed slope of the Nalla just downstream of Bharat Nagar bridge was
proposed as / 1 in 4000 and F.S.D. below Bharat Nagar was proposed as 15.75
feet.
It was also mentioned that the likely discharge from rural area
synchronizing with the urban discharge may be of the order of 500 cusecs.
Based on the recommendations of the above Committees a portion of drain upto
outfall of Nangloi drain (RD 98000) has already been remodeled for a capacity
of 3000 cusecs. The reach between the outfalls of Nangloi Drain and the
Bharat Nagar bridge has been redesigned in light of the recommendations of
Shri J. Tripathy. The portion of the Najafgarh drain below Bharat Nagar upto
its tail end has already been redesigned and the work of remodeling is in
progress. The revised L-section and the cross-section of the drain upto outfall
point are enclosed at Appendix-XXIII in three parts i.e. (a) from Dhansa to
Tilak Nagar(b) from Tilak Nagar to Bharat Bridge and (c) from Bharat Nagar to
outfall point.
38
MASTER PLAN -NAJAFGARH BASIN
from Rohtak Road bridge onward to Bharat Nagar. Proposed bed width are 120’
and 72’ against 95 & 65 ft. respectively in the above two reaches. The bed
slopes are also proposed to be regarded to 1 in 7800, 1 in 6000, 1 in 3000 from 1
in 12000 in the reaches between the outfall of Tilak Nagar drain to outfall of
Paschim Puri drain, outfall of Paschim Puri drain to Rohtak road bridge and
Rohtak road bridge to Bharat Nagar bridge respectively. Minimum free board of
2’ has been kept. Inspection road of 22’ have been provided on both sides of the
drain. While redesigning, special care has been taken to ensure that the min.
clearance of ………feet is there in the existing bridges and the afflux is also
within permissible limits. The following guidelines are also suggested for future
maintenance, possible remodeling and utilization of water of Najafgarh drain at
the future date.
(1) Najafgarh drain shall be desilted every year a few months before monsoon so
that the full cross section is available for utilization before the start of next
monsoon. An L-section of the drain from Dhansa to Kakrola as surveyed in past
1975 monsoon is enclosed. The design cross section is also super imposed. It may
be seen that on an average 3 feet of silting is there, which is to be immediately
cleared. It was noted in 1975 flood that at a number of places water stagnation
occurred due to this heavy siltation in upper reach of Najafgarh drain. The level
reached were that of nearly 3000 cusecs whereas the actual discharge passed
was nearly 1500 cusecs maximum. Pre-monsoon and post monsoon L-sections are
to be invariably taken every year and submitted to Chief Engineer for record.
Cross-sections at 100’ interval should also be taken for calculating desilting
proposal. Executive Engineers failing to take action on annual desilting and taking
L-sections should be suspended forthwith.
(3) Kakrola regulator shall be operated to control the discharges from the U/S
areas of the regulator only when the discharge D/S of it has been exceeded
39
MASTER PLAN -NAJAFGARH BASIN
3000 cusecs/ the water level has exceeded the safe limits in the Najafgarh
drain to cause overflow of its banks in any of the localities in the city reaches.
The Kakrola regulator gates should be lowered in the receding stage of the flood
when the water level in U/s. of the regulator is at RL-685. The water level U/s
of the Kakrola regulator is to be maintained at Rl-685 during the dry period for
recharging of water table.
(4) For Dhansa regulators, emergency should be declared when the water level in
the Najafgarh Jheel touches RL-690. The gates of the Dhansa Regulators may
be kept open as long as the level in Najafgarh Jheel is less than RL-690 the
discharge in Najafgarh drain in city reaches is less than 3000 cusecs/ the safe
level in the Najafgarh drain has not been exceeding to cause overflow of its
banks in city reaches. After the level reaches R.L.690 in Najafgarh Jheel or
3000 cusecs discharge is observed in Najafgarh drain, the safe level in the
Najafgarh drain has been exceeding, the gates shall be opened keeping in view
both the upstream and downstream conditions that would provide reasonable
relief to the areas in Haryana and Delhi.
The design flood level for Dhansa bund is R.L.698.0ft. Water overflows at
Dhansa Regulator above R.L. 695.5 since the top of the gates is R.L. 695.5 in the
closed position.
The combined discharge of new regulator and the existing regulator would
be 3000 cusecs with the U/s. water level of 694 and D/S water level of 693.
Proper regulation should be made when U/s. water level is 697.00 or D/S
water level is 690 so that higher differential head is not acting on the
structure.
40
MASTER PLAN -NAJAFGARH BASIN
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
+690. 170
0
41
MASTER PLAN -NAJAFGARH BASIN
+694. 1470 1470 1570 1560 1540 1510 1490 1280 920
0
+694. 1730 1780 1780 1770 1760 1750 1700 1610 1440 1040
5
+695. 1980 1980 1980 1970 1960 1940 1890 1770 1570 1160
0
+695. 220 220 220 2190 2180 2160 2140 2208 1970 1700 229
5 0 0 0 0 0
+696. 244 244 244 244 242 2410 240 2350 226 2130 1890 1420
0 0 0 0 0 0 0 0
+696. 268 268 268 268 267 267 265 2630 257 249 2310 205 1540
5 0 0 0 0 0 0 0 0 0 0
+697. 292 292 292 292 292 290 290 2840 283 278 268 250 225 169
0 0 0 0 0 0 0 0 0 0 0 0 0 0
STATEMENT SHOWING THE CAPACITY OF NAJAFGARH JHEEL BETWEEN R.L.695 AND R.L. 684 UPTO
KAKRAULA BRIDGE.
42
MASTER PLAN -NAJAFGARH BASIN
S.L.No. Areas submerged in acres. Total Area Capacity in acre Rate of absorption.
submerged feet.
Delhi Haryana Above Dhansa Below Dhansa
acres.
(in cusecs/day)
312.60
43
MASTER PLAN -NAJAFGARH BASIN
Discharge table for various u/s and /s water level for Kakrola Regulator.
Water way, 4 Spans of 15- 0’ each 677.85
Discharge Capacity in cusecs.
Water level D/S W.L.
688 688.5 689 689.5 690 690.5 691 691.5 692 692.5
693 693.5 694 594.5 695
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
+688 2160
+692 7360 7330 7250 7120 6900 6570 6150 5550 4290
44
MASTER PLAN -NAJAFGARH BASIN
+692.5 7900 7840 7750 7660 7540 7310 7000 6380 6540 4650
+693 8410 8390 8350 8270 8180 8040 7830 7490 6959 5800 4000
+693.5 9010 8990 8980 8900 8800 8700 8560 88760 8100 7600 6600 5180
+694 9620 9600 9520 9530 9490 9430 9290 9060 8740 8300 7700 6980 5500
+694.5 10160 10130 10100 10090 10080 10050 9900 9720 9500 9250 8800 8300 7550 5900
+695 10750 10700 10700 10650 10600 10600 103200 10200 9900 5650 9420 8680 7720 6120 6120
45
MASTER PLAN -NAJAFGARH BASIN
The present proportionate details of Thana Khurd Mandora & East Jua
drains in Haryana & Delhi are as given below:-
46
MASTER PLAN -NAJAFGARH BASIN
47
MASTER PLAN -NAJAFGARH BASIN
48
MASTER PLAN -NAJAFGARH BASIN
Palam drain rises from hilly areas of South Delhi and after running
through cantonment area in the north and North-west direction, joins Najafgarh
drain U/s. of Kakrola regulator. During the course it is joined by the following
link drains:-
2. Nasirpur drain.
It collects discharges from hilly, urban and rural areas and serves a total
catchment area of 20 Sq. miles at its outfall point (Urban 10.25 Sq. miles Hilly.
3.17 Sq. miles Rural 6.85 sqm. Miles). The total discharge as per design criteria
discussed vide para 2.0 above at the outfall point of Palm drain comes to 3410
cusecs, at the run off rates of 10 cusecs/sqm. Miles for rural: 320 cusecs/ sq.
miles for urban and 20 cusecs/sq. miles for/semi-hilly area, which seems to be
on the higher side. As the total catchment of this drain is more than 5000
acres the design discharge should have been calculated by rational method,
according to the recommendations of the expert Committee. In that case, the
design discharge would have considerably reduced taking the large time of
concentration. However the sections of the drain from 20200 RD to RD 0 outfall
point has already been remodeled for the discharge capacity of 3042 cusecs
capacity. The above discharge seems to be reasonable and hence the original
remodeled section in the above reach has been retained. The section of the
drain from 28000 RD upto 20200 should also be remodeled for 1840/ cusecs
discharge. It is further pointed out that there is no regular section of drains
U/S of 28000 RD. The drain U/s of 28000 RD therefore should be surveyed
and a regular section is provided at different reaches on the above basis. The
catchment area of its link drains also lie partly in rural and partly in urban areas
and hence been designed on the above basis (i.e. @ 10 cusecs/ sq,.miles for rural
and 32 cusecs for urban). The proposed sections of Palam drain along with its
link drains are enclosed at Appendix XXV to XXVIII. It is evident from the
L-Section that i) Palam Link drain is to be remodeled to B.W of 9’ and 15’ from 7’
and 10’ and to a bed slope of 1 in 1200 and 2000 from existing 1 in 1000 and 1 in
49
MASTER PLAN -NAJAFGARH BASIN
2000 in the reaches between the R.Ds 10400 to 5200 and 5200 to O
respectively. There is average of 5’ deepening throughout the length of the
drain. ii) Nasirpur drain is to be remodeled to a B.W. of 25’ from 8 ft and to a
bed slope of 1 in 2500 from 1 in 2000 with an average deepening of 6 feet.
50
MASTER PLAN -NAJAFGARH BASIN
51
MASTER PLAN -NAJAFGARH BASIN
constructed as suggested in the plan enclosed to cover larger areas. CGWB also
has mentioned in their report on “Report on the Ground Water Condition Around
Najafgarh Jheel in parts of Delhi and Haryana State” that three factors namely
( a) continuous low rainfall (b) effective drainage of the Jheel area and (c)
increase in withdrawal from ground water reservoir are mainly the cause for the
decline in water levels of the area. It has been found by them that factor (b)
and (c) constitute the cause of decline of water table but the chief cause for
fall is rise in installation of tube well pumping sets. The extract of conclusions
and the recommendations of the report is enclosed as Annexure-II. (ii) Crops
such as sugarcane, paddy which needs more water and can stand standing water
for a few days should be sown in the area around the Jheel in post monsoon
season, in consultation with the Agricultural Department( iii) In winter season,
when the water table goes down the gates of the outfall structures of the
Najafgarh drain at Kakrola and Mungeshpur drains should be closed to allow the
water to stagnate in the drains as well as in the fields for automatic recharging
of the water table. Possibility of construction of gated structures in the
intermediate parts in the above drains as well as inlets to the bunds which can
be closed when necessary should also be explored.
On south east side of the Najafgarh block the water table is relatively
lower with an average depth of 6 to 9 meters below ground. This area being hilly,
irrigation by means of tube-wells is difficult. Presently, only the Surukhpur
minor coming from the Haryana Territory has its tail end upto Mitran villages.
It is suggested that this minor should be further extended upto Najafgarh
drain. Water from here can be stored at a higher place farther by pumping and
distributed for irrigating a larger area by means of gravity as marked in plan at
Appendix II.
52
MASTER PLAN -NAJAFGARH BASIN
53
MASTER PLAN -NAJAFGARH BASIN
ANNEXURE-II
Three factors namely (a) continuous low rainfall (b) effective drainage of
the Jheel area and (c) increase in withdrawal from ground water reservoir, were
considered for the decline in water levels of the area. It has been found that
factors (b) and (c) constitute the cause of decline of water table, Further the
contribution to decline of water table by the effective drainage from the Jheel
54
MASTER PLAN -NAJAFGARH BASIN
area has been found very low. The chief cause for the fall in the water table
could be attributed to a steep rise in the installation of tube wells/pumping sets,
with a consequent increase in the ground water withdrawal.
The trend of water levels in the area indicates possible over draft. To
precisely determine the extent of the over draft a more detailed ground water
balance survey would be required because the data collected during this short
term investigation is insufficient.
The relationship between water table and drain bed confirms discharge of
ground water through drain immediately after the monsoon period. To curtail or
minimize this loss, a proper regulation of the drain at Kakrola regulator is
55
MASTER PLAN -NAJAFGARH BASIN
essential. The regulation precise is very good as it keeps the depth of water in
the drain to such a level that the ground water flow is at its minimum.
The water logging conditions near Mundela and Kair need special attention.
A drain may be essential to link the depression to the Najafgarh drain so that
some areas could be reclaimed. The area around Kair may also be connected b y
the same drain. The effect of canal around Kair should also be examined and the
canal a should be lined if already not done.
c) The bridges culverts at R.D’s 15125, 43500. 75700 ft. should be remodeled
and one or two spans should be added or slight modification should be done in
the floor levels of the existing structures at R.D’s 8845, 29600,47090, 62100,
63900, 76815, 87300, 96800, 98100, 102375, 109700, 112100, 11435 and
120700 to send the proposed design discharge.
(3) Palam Drain: The reach between the R.D’s 20000 to 28800 should be
remodeled as per latest design requirements along with the structures.
(4) Palam Link Drain: - Palam Link drain should be widened to 9’ and 15’ from 7’
and 15’ and regarded to bed slope of 1 in 1200 and 1 in 2000 from 1 in 1000 and 1
in 2000 from 1 in 1000 and 1 in 2000 in the reaches between the R.D’s 10400 to
5200 and 5200 to O respectively. The culverts at R.D’s 5900 and 5200 should
also be remodeled.
(5) Nasirpur link drain:- Nasirpur link drain should be remodeled to a bed width
of 25’ from 5 ft. and regarded to bed slope of in 2500 from 1 in 2000. The
culverts at R.D’s 6000 and 750 should also be remodeled.
(6) Mundela Khurd Scheme:- A bund of about 6’ average heigh with top at R.L.
699 should be constructed along the Harayana and U.T. of Delhi boundary
between Dhansa minor and Bahadurgarh minor near the Mundela Khurd Village.
The above bund should be provided with gated regulators of 10 cusecs capacity
of R.L. 697 and the regulators should be connected to Najafgarh drain by means
of link drain called mundela khurd link drain.
57
MASTER PLAN -NAJAFGARH BASIN
58