Standard: ISO 22000:2005, clause 4.2.2; SANS 10049:2011, clause 5: SANS 10330:2007, clause 3
Purpose: To define the methods and responsibilities for controlling documents used
to provide work direction or set policy; and to define methods for
document revision, approval and distribution.
Scope: This procedure applies to all documents required by the Food Safety
Management System. Documents of internal or external origin are
included.
The Food Safety Team is responsible for reviewing all procedures and
instructions at least annually to ensure documents remain current.
Procedure:
2.1 For many reasons, temporary changes to the Food Safety Management System
may be needed. Temporary changes must be defined and controlled.
3.1 The Food Safety Team Leader is responsible for coordinating with Department
Mangers to review all procedures and instruction at least annually and update
them, as required, to ensure documents remain current.
3.2 Anyone may submit a new document or changes to an existing document, as
necessary. To submit a change, the requestor shall print a copy of the document
and mark (“redline”) the requested changes on the copy. If changes are
extensive, a new document may be typed and submitted with a copy of the
original. The requestor shall clearly identify, initial and date all such changes.
3.3 The requestor shall submit changes to his/her Department Manager for review.
The Department Manager, after reviewing the requested change(s), shall
complete a FS1000-1 – REQUEST FOR DOCUMENT CHANGE (RDC), indicating the
nature and reason for the change. He/she shall submit the FS1000-1 with the
changed document to the Food Safety Team Leader for review.
3.4 The Food Safety Team leader shall review the change request to ensure
ISO22000 compliance.
If the request for change is not in compliance with the standard, the Food
Safety Team Leader shall notify the requestor of the reason for the denial
and explain the changes needed to bring the request into compliance.
If the request is ISO 22000 compliant, the FSTL shall determine who else
needs to review the change and submit the change and the FS1000-1 form
Top Management to review.
3.5 The Top Management shall consider the change and the reason for it and
determine if the change is warranted.
If Top Management approves the requested changes, the FSTL shall update
the document, index the revision, update the document status and update
the revision history on the document.
3.6 When Top Management has approved the changes/documents, the FSTL shall
circulate the final document(s) to obtain signatures.
3.7 FSTL shall make sufficient copies for distribution to all locations indicated on
FS1000-2 – DOCUMENT CONTROL DATABASE.
Document Control shall pull the master copy of the previous revision, mark it
“Obsolete”, and file it in the historical files (archives).
Because the electronic version will not show signatures, the current Master
Copy is maintained as evidence of review and approval.
4.1 Flow diagrams and other technical diagrams are distributed by the responsible
department via hard copy. Obsolete drawings and other technical documents
are to be returned to the responsible department when revisions are distributed.
4.2 Document Control shall maintain a database of all controlled documents
(FS1000-2 – DOCUMENT CONTROL DATABASE). Documents of internal origin
and external origin shall be maintained in separate lists or databases.
Document Number;
Document Title;
Current Revision number or ID;
Revision Date;
Responsible Department; and
Document Location
4.3 Document control shall distribute hardcopy documents only to the locations
shown on the database and shall remove and destroy any previous versions of
procedures or work instructions.
Document Control shall distribute electronic versions of documents by
moving old revisions to the OBSOLETE folder, moving the new revisions to
the RELEASED folder, and notifying affected parties in a timely manner.
All electronic documents moved to the OBSOLETE folder shall be assigned
expiration dates. When a document’s expiration date is reached, it shall be
permanently removed from electronic storage.
4.4 External documents are controlled only for distribution. All external standards
should be purchased through Document Control, to ensure they are added to
the External Document list and are properly controlled and distributed.
The Food Safety Team Leader shall review the document control process on a regular
basis (annually, at a minimum) with Document Control, to ensure that all food-safety-
related documents are being controlled effectively and that the process continues to
meet Company, statutory/regulatory, and standards-based requirement.
Effectiveness Criteria:
References:
Records:
Revision History:
Originator:_____________________________________________________________________
Comments:____________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
Department supervisor approval:___________________________________________________
Recommended solution to problem or postponement/dissolution of request (attach all
necessary documentation to support response:_______________________________________
Approved By FSTL:______________________________ Date:_________________________