DETAILS OF ROAD PROJECTS IN ANDHRA PRADESH
Projects Inaugurated:
Sanctioned
Sr. Length
Name of the Project Cost Status
No. (Km)
(Rs in Cr)
(A) Projects through NHAI
1 4-laning of Kadapa-Mydukur-Kurnool Section of NH 40 188.75 2075 Project completed on 28.07.2019
4-laning of Vijayawada – Machilipatnam Section of NH-
2 64.611 1470 Project completed on 13.11.2019
65including Benz Circle Flyover on NH 16
4-laning of Nalagampalli to AP/Karnataka Border
3 47.687 1100 Project completed on 31.07.2019
Section of NH 4
6-laning of Ranasthalam–Anandapuram section of NH-
4 47.00 1470 Project substantially completed.
16
Sub Total 348 6115
(B) Projects through R&B
Rehabilitation and Up-gradation of Eepurpalem- Ongole
5 Section from km195+00 to 254+500 of NH- 57.87 574.19 Project completed on 28.07.2019
214A(NH216) to two lane with paved shoulders.
6 Rehabilitation and Upgradation of new NH-544DD (Old 56.00 294.12 Project completed on 17.10.2019
SH-30) from design Chainage Km 0.000 to 56.000 (Ex.
Sanctioned
Sr. Length
Name of the Project Cost Status
No. (Km)
(Rs in Cr)
Km 0.460 to Ex. Km 58.344) of Ananthapuramu–
Kalyandurg section to two lane with paved shoulders.
Rehabilitation and Upgradation of NH67 from km
7 424.650 to 487.693 of Gooty- Tadipatri section to two 63.013 378.24 Project completed on 19.01.2020
lane with paved shoulders
Construction of 4-Lane ROB and its approaches in lien
8 of existing level crossing No.18A/SPL class @ Km 7.800 1.34 66.08 Project completed on 31.08.2019
of NH 18.
Four laning of 5.122 km of NH9( New NH 65) from km
269.900( Design ch0.0 ) to km 275/622( Design Ch
5.122) i.e, connecting NH9(1.40km) with NH5(3.60km)
9 5.3 501.00 Likely to be completed by 31.08. 2020
including 6 lane elevated Kanakadurga Flyover from
Bhavanipuram to Kanakaghudhamma Vardhi Junction in
Vijayawada City limits
Construction of 4-Lane ROB and its approaches in lien
10 of existing level crossing No.23/SPL class @ Km 3.600 1.125 78.59 Recently completed
of NH 18
Sub Total 185 1892
Total 533 8007
Sanctioned
Sr. Length
Name of the Project Cost Status
No. (Km)
(Rs in Cr)
Grand Total 1411 15592
Foundation Stone Laid for Projects:
Sanctioned
Sr. Length
Name of the Project Cost Status
No. (Km)
(Rs in Cr)
(A) Projects through NHAI
6-lane bypass from Km 0.000 (Chinna Avutupalli) to Km
Project awarded and agreement
1 30.000 (Gollapudi) as a part of Vijayawada Bypass Section 30.00 1225
signed. Appointed Date being fixed.
of NH-16 (Pkg-III)
6-lane bypass from Km 30.000 (Gollapudi) to Km 47.880
2 Project awarded and agreement
(Chinnakakani) including Major Bridge across river Krishna 17.88 1600
signed. Appointed Date being fixed.
as a part of Vijayawada Bypass Section of NH-16 (Pkg-IV)
3 Project sanctioned. Bids finalised.
6 laning of Renigunta- Naidupeta section of NH-71 57.05 2225
LOA under issue.
Construction of 3-lane flyover from Jyothi Mahal Junction Project sanctioned. Bids received
4 to Ramesh Hospital Junction on the west side of the Median 2.47 100
and under evaluation.
Between Main Carriageway and Service Road on NH-16
Sanctioned
Sr. Length
Name of the Project Cost Status
No. (Km)
(Rs in Cr)
crossing Benz Circle, Nirmala Convent Junction & Ramesh
Hospital Junction.
Sub Total 107 5150
(B) Projects through R&B Department
Construction of 2-Lane ROB and subway in lieu of LC no.
88 at Railway km 136/5-6 between Kurbalakota &
5 1.40 36.24 Work recently started
Madanapalli Section on Dharmavaram - Pakala Section at
km 56/100 of NH-340
Construction of 2L RoB in lieu of LC no. 104 E-SPL at Km.
6 97/06-07 between Cherukuwada and Undi Station of Project sanctioned and awarded.
1.35 90.99
Gudivada – Bhimavaram Section at Km. 170/400 of NH 165 Appointed Date being fixed.
Construction of 4L RoB in lieu of LC no. 93 at Km. 84/4-5
7 between Akiveedu – Pallevada Station on Gudivada – Project sanctioned and awarded.
1.68 87.74
Dharmavaram Section at Km. 183.700 of NH 165 Appointed Date being fixed.
Construction of Bypass to Salur town from Km 486/831 to
8 Km 491/420 of Raipur – Vishakhapatnam section of NH-26 Project sanctioned and awarded.
5.92 70.81
on EPC mode Appointed Date being fixed.
Sanctioned
Sr. Length
Name of the Project Cost Status
No. (Km)
(Rs in Cr)
Rehabilitation and Strengthening of NH 516 D from Km
9 0.000 to 20.000 Devarapalli - Jeelugumilli road on NH 20.00 95.51 Work recently started
516D
Rehabilitation and upgradation from two to four lane from
10 5.40 96.63 Work recently started
Km 0 to 5/4 of Anantapur-Guntur road of NH 544D
11 Construction of 4-Lane Fly-Over at Km 742/600 at LOA issued on 16-06-2020.
0.81 41.88
Muthukur Road Junction) in Nellore District of NH 67 Appointed date being fixed
Project sanctioned.
12 Construction of two lane with paved shoulder Kadari bypass
12.58 220.66 Bids invited with bid due date
from km 0/0 to 11/078 and km 0/0 to 1/500 of NH 42
27.08.2020
13 Two laning with paved shoulders from Km 491/000 to Km Project sanctioned. Bids are under
32.03 221.40
525/200 of NH-26 (Saluru to Gajapatinagram Section). evaluation for award of work.
14 Two laning with paved shoulders from Bowdara to Project sanctioned. Bids finalised.
26.94 159.51
Vizianageram Section of NH 516E LOA under issue.
15 Two laning with paved shoulders of Paderu to Gundiguda to Project sanctioned. Bids are under
49.37 571.77
Araku Section of NH 516E evaluation for award of work.
14 Nos of works awarded and
16 Improvement of 36 Nos of stretches on State Roads under
613.52 741.54 agreement concluded & 22 Nos of
CRIF Scheme
works recently started
Sub Total 771 2435
Sanctioned
Sr. Length
Name of the Project Cost Status
No. (Km)
(Rs in Cr)
878 7585
Total
Projects likely to be completed during current FY 2020-21:
Total length: 637 Km
Total Cost: Rs.8306 Cr.
A. NHAI Projects
Sr.No. Cost
Name of the project Length (Km) Date of completion
(Rs in cr)
1 47 1,262 Completed in September,
6-laning of Ranasthalam - Anandapuram Section of NH-16
2020
2 Construction of Grade Separator from H7 area to Port
Connectivity road bypassing convent junction in the State of 1 57 November, 2020
Andhra Pradesh through EPC Mode
3 6-laning of Nandigama & Kanchikacherla bypass on NH-65 14 425 November,2020
4 Development of Emergency Landing Facility on 5 79 December, 2020
Chilakaluripet - Nellore Section (ELF-1)
5 Development of Emergency Landing Facility on 4 84 December,2020
Chilakaluripet - Nellore Section (ELF-2)
6 Four Laning of AP/TN border (Shantipuram) to 37 685 December,2020
Nalagampalli section of NH-4
7 February,
6-laning of Kalaparru to Chinna Avutupalli of NH-16 28 695
2021
8 March,
Capacity Augmentation of the existing 4 - lane stretch from 14 563
Ichapuram to Narasannapeta of NH-16 (Old NH-5) 2021
Total 150 3,850
B. MoRTH Projects
Sr. No. Cost
Name of the project Length (Km) Date of completion
(Rs in cr)
1 Construction of 4-Lane ROB and its approaches in lieu of existing level Completed in August,
1 79
crossing No.23/SPL class at Km 3.600 ( Murkumbattu) of NH 18. 2020
2 Four laning of 5.122 km of NH9( New NH- 65) connecting NH9 with
5 501 Completed in
NH5 including 6-lane elevated Flyover from Bhavanipuram to
September, 2020
Kanakaghudhamma Vardhi Junction in Vijayawada City
3 Construction of 4-Lane ROB and its approaches in lieu of existing level 2 69 November,2020
crossing No. 75 at (Railway Chainage 121/470) on NH - 205
4 Two-lane with paved shoulders of Chintakunta -Adoni Section of NH- 59 290 November, 2020
167
5 Two-lane with paved shoulders of Palamaneru to Krishnagiri Border 82 272 December, 2020
Section of NH-219
6 Two - lane with paved shoulders Madanapalli-Punganuru-Palamaneru 55 373 December, 2020
road section of NH-42
7 Two-lane with paved shoulders of Mangalore-Tiruvannamalai section 18 148 December, 2020
of NH-75
8 Two -Lane with Paved Shoulders of Gurajanapalli to Polekuru Section 50 349 December, 2020
and Komagiri to Pasarlapudi section of NH-216
9 December,
Construction of 4-Lane ROB and its approaches in lieu of existing level 3 88
crossing No. 95/SPL at Railway Chainage 93/17-19 on NH- 205 2020
10 December,
Construction of 4-lane bypass to Vijayanagaram Town on NH- 26 17 430
2020
January,
Two-Lane with Paved Shoulders of Kodikonda – Madakasira section 57 504
of NH-544E 2021
11 January,
Two-Lane with Paved Shoulders of Dindi - Digamarru section and 42 386
Digamarru-Losari section of NH-216 2021
12 February,
Construction of 4-Lane ROB and its approaches in lieu of existing level 1 139
crossing No. 102/3E at Km 281.200 (Tirupati) of NH 205 2021
13 February,
Two-lane with paved shoulders of Kalyandurg - Molakalmuru section 46 290
of NH-544DD 2021
14 March,
Construction of 4-Lane ROB at railway chainage km 44/679 between 2 67
Putalapattu and RVS Nagar station on NH-18 2021
15 March,
Two - lane with paved Shoulders of Odisha border to Narasannapeta 39 229
section of NH - 326A 2021
16 March,
Construction of 4-Lane ROB and its approaches in lieu of existing level 2 64
crossing No. 67 on NH-205 2021
17 March,
Construction of 4-Lane ROB and its approaches in lieu of existing level 2 57
crossing No. 30/E at Railway Chainage 42.858, on NH - 205 2021
18 March,
Construction of 4-Lane ROB and its approaches in lieu of existing level 2 64
crossing No. 67 at Railway Chainage 109/3-4 on NH-205 2021
19 Construction of 4-Lane ROB and its approaches in lieu of existing level March,
2 57
crossing No. 30/E at Railway Chainage 42.858 on NH-205 2021
Total 487 4456
Grand Total (NHAI + MoRTH) 637 8306
Projects to be awarded during current FY 2020-21:
Total length:535 Km
Total Cost: Rs. 11,712 Cr.
A. NHAI Projects
Sr. No. Length
Name of the Project Cost (Rs in cr) Likely date of award
(Km)
1 3 - lane elevated flyover from Jyothi Mahal Junction - 3 100 Awarded in August, 2020
Ramesh Hospital Junction
2 6 - laning of Renigunta – Naidupeta section of NH-71 57 2225 December, 2020
3 Bangalore - Chennai Expressway 85 5175 March, 2021
4 4 - laning of Khammam-Devarapalli Section 72 1571 March, 2021
Total 217 9071
B. MoRTH Projects
Sr. No. Length Cost (Rs in
Name of the Project Likely date of award
(Km) cr)
1 Two - laning with paved shoulders of Bowdara to Vizianageram Sectionof
27 128 Awarded in September, 2020
NH 516E
2 Two-laning with paved shoulders of Paderu to Gundiguda section of NH -
Awarded in September, 2020
516E 25 223
3 Two - laning with paved shoulders of Gondiguda to Araku (upto
24 297 Awarded in September, 2020
Bhallaguda) section of NH-516E
4 Widening and strengthening to two - lane with paved shoulders of (Saluru
34 221 October, 2020
to gajpatinagaram section) of NH-26
5 Widening to two-lane with paved shoulders of Pamarru to Akiveedu section
61 529.54 November, 2020
of NH-165
6 Construction of Kadiri Bypass on NH-42 13 221 November, 2020
7 Two - laning with paved shoulders of Lambasingi to Paderusection of NH-
48 361 March, 2021
516E
8 Two -laning with paved shoulders of Chaprathipalem to Lambasingi 311 March, 2021
40
Section of NH-516E
Sr. No. Length Cost (Rs in
Name of the Project Likely date of award
(Km) cr)
9 Two - laning with paved shoulders of Koyyuru to Chaprathipalem section 349 March, 2021
46
of NH - 516E
Total 318 2641
Grand Total (NHAI + MoRT&H) 535 11712
DPR projects:
Total length:2371 Km
Total Cost: Rs. 34,133 Cr.
A. NHAI Projects
Sr. No. Cost
Name of stretch Length (Km) Remarks
Rs in Cr)
1 DPR Completed
121 3,304
Kadapa - Renigunta Section of NH-716
(Bharatmala corridor)
2 DPR of 2 Packages Completed
85 5,175
Bangalore – Chennai Expressway
(Bharatmala corridor)
3 FFR submitted.
Madanapalle to Pileru Section of NH-71 56 1,243
(Bharatmala corridor)
4 DFR submitted
Pileru to Cherlopalli section of NH-71 42 909
(Bharatmala corridor)
5 FFR approved
Odisha-A.P Border (Ondarangi) to Sabbavaram Section of 100 2,993
NH-130CD (Raipur – Visakhapatnam) (Bharatmala corridor)
6 45 778 FFR submitted
Mydukur–Badvel Section of NH-67
(Bharatmala corridor)
7 KA/AP Border – Chintakunta – Adoni – KA/AP Border 84 FFR in progress
1,812
section of NH- 167 (Bharatmala corridor)
8 Badvel – Nellore Section 108 1,774
9 Khammam – Devarapalle section of NH-365BG 36 708 FFR submitted
(Telangana/AP Border to Borrampalem village) Pkg-3 (Bharatmala corridor)
10 Khammam – Devarapalle section of NH-365BG 36 863
(Borrampalem village to Devarapalli Village) Pkg-4
Total 713 19,559
B. PC Projects
Sr.
No. Cost
Length
Name of stretch (Km) Rs in Cr)
1
30 450
2 to 4 laning of road connecting Kakinada port to NH 16 at Rajanogaram on NH-16 to
Samalkota
2
2 to 4 laning of road connecting Kakinada port from Samalkota to Rajanogaram on NH-16 in 13 195
Godavari District
3
Greenfield road connecting north and south industrial cluster of Khandaleru Creek near 22 462.7
Krishnapatnam port
4 4 laning of road from Nellore city to Krishnapatnam port to NH 5 24 360
5 Up grading of existing Road from Chilakaru cross-NH-16 to Power Plants 26 374
6
39 704
4 lane road to Krishnapatnam Port from Naidupeta in AP
7 4 laning of Kakinada Anchorage Port Uppada beach road connecting NH-16 in East Godavari
43 733
District
8 Road Connectivity From Outer Harbour To Port Connectivity Junction (B) at Vizag port 5 75
9 Development of Fly over bridge from Sea-horses junction area to dock area at Vizag Port 3 45
10 Greenfield bypass road connecting Gangavaram part in Visakhapatnam District: Lanes to be
11 165
specified
11 4 to 6 laning of road connecting to NH16 at Gajuwaka to Gangavaram Port 14 210
12
14 549
Development of adequate road connectivity from Vizag Port - connectivity from Sheela nagar
junction to Anakapalli - Sabbavaram / Pendurti - Anandapuram road i.e. NH-16
13 Improvement works for Visakhapatnam Port Road 13 195
14 Port connectivty road (four lane) from East Break Water to Convent Junction 10 150
15
17 456
4-laning of Varagali Road from Chilakur cross to Chintawaram Package - II km 0 to km 16.45
16 20 300
Development of outer ring road from East Breakwater to Sheelanagar
17 3 45
Construction of flyover bridge at Nathayyapalem (Mindi) on NH- 16
18
Construction of flyover / under pass at Vizag airport junction to ensure flow of container 5 75
trailers to/from MMLP setup at NH-16
19
Improvement/upgradation of four lane road to six lane road for the port connectivity road from 15 225
East Breakwater to Sheela Junction
20
Four lane Beach Read connecting Gangavaram Port to the SEZ proposed at Achuthapuram in 30 450
Visakhapatnam District
21 Development of Four lane green field road from Machilipatnam South Port to NH-9 in the
State of Andhra Pradesh
20 300
22 Development of Four Lane green field road from Machilipatnam North Port to NH-SH-46 in
the State of Andhra Pradesh
10 150
23 Upgrading of Manginapudi Beach Road to a 4 lane road to connect to cater to Machilipatnam
10 195
24 Development of 7.2 Km green field road connecting NH 65 to Machilipatnam Port in the
State of Andhra Pradesh. 7 140
Total
404 7004
C. MoRTH Projects
Sr. No. Cost
Name of stretch Length (Km) Remarks
Rs in Cr)
1 Akividu - Digamarru section of NH – 165 46 450 DPR finalized (NIP )
2 Muddanur on NH 67, Kadapa on NH-40 (Part of NH – 716) 51 180 DPR finalized (NIP )
3 Porumamilla – CS Puramu 56 525 DPR finalised(NIP )
4 CS Puramu – Singarayakonda 90 872 DPR finalized (NIP )
5 Bhadrachalam (on NH-30) in TS - TS/AP Border –Jeelugumilli
– Jangareddygudem – Devarapalli – Upto Rajhamundry (on NH 38 204 DPR finalized (NIP )
-16) 516D
6 Rampachodawaram to Koyyuru 74 264 DPR finalized (NIP )
7 Suryapet (on NH-65) – Khammam – Ashwaraopet-Kovvur (on 85 302 DPR finalized (NIP )
NH-16) section of NH – 365BB
8 Vijayawada-Jagadalpur (NH-30) 64 235 DPR finalized (NIP )
9 Near Davulapalli reserve forest 21 200 DPR finalized (NIP )
10 Nagarjuna sagar Dam to Davulapally 47 259 DPR finalized (NIP )
11 Kavali – Udayagiri – Seetharamapuram 104 468 DPR to be taken up (NIP )
12 Araku – Bowdara section of NH-516E 43 220 DPR to be taken up (NIP )
13 Improvement to hair pin bends on Hyderabad – Srisailam – 38 230 DPR to be taken up (NIP )
Dornala – Tokapalli road of NH- 765
14 Mydukur to Pormamilla section of NH – 167B 43 210 DPR to be taken up (NIP )
15 47 225 DPR to be taken up (NIP )
Molakalacheruvu to Madanapalle, section of NH-42
16 DPR to be taken up
Construction of Tunnel and realignment to avoid Hair Pin 6 250
Bends in Ghat portion of NH-40
17 Bypass road to Lepakshi on NH-544E 5 40 DPR to be taken up
18 Chintoor to Motu, section of NH 326 9 100 DPR to be taken up
19 Bestavaripeta – Ongole section (In principle NH) 107 642 DPR under preparation(NIP)
20 Malkangiri – Sabbavaram section (In principle NH) 280 1680 DPR under preparation (NIP)
Total 1254 7570
Grand Total (NHAI+PC+ MoRTH) 2371 34133
EXPRESSWAYS
Bangalore - Chennai Expressway:
This project shall facilitate better connectivity between Karnataka, Andhra Pradesh and Tamil Nadu States.
Implementation of the project would result in development of basic infrastructure, industrial development and better connectivity
between Bangalore and Chennai, which would result into overall economic development of the region.
Out of total length of 262.100 Kms, 85 Kms length (Bethamangala to Gudipala Section) falls in Andhra Pradesh which is proposed
for 4-lane standards.
Salient Features:
Length 85 Km
Lane configuration 4 lane
Estimated Cost Rs.5174.50 Cr.
Major Bridges 18 Nos.
VOP 8 Nos.
Flyover 2 Nos.
Underpasses 46 Nos.
Amaravati - Ananthapuram Expressway:
Post bifurcation, the Govt of Andhra Pradesh plans to develop the Rayalaseema region by providing better infrastructure facilities
and thus making it a major potential hub for Industrial development.
Therefore, an access controlled Expressway has been planned for better connectivity of Capital region, Costal and Northern region
of Andhra Pradesh.
The proposed Expressway connects Amaravati, new capital city of Andhra Pradesh with Ananthapuram of Rayalaseema region.
It takes off from National Highway-44 near Maroor in Ananthapuram district and terminates at Chilakaluripeta Bypass (NH-16)
near Chilakaluripeta in Guntur district.
The proposed Expressway provides a major connectivity between NH-44 and NH-16 which are lifeline in the State of Andhra
Pradesh.
The Expressway passes through 4 districts (Ananthapuram, Kurnool, Prakasam & Guntur) of Andhra Pradesh.
Salient Features:
Length 335 Km
Lane configuration 4/6 lane
Estimated Cost Rs.19,877 Cr.(including LA cost of Rs.2,232 Cr.)
Tunnel 9.41 Km
Major Bridges 21 Nos
Underpasses 19 Nos.
Amaravati Outer Ring Road:
The proposed ring road runs around the proposed capital city of “Amaravati” and passes through the districts of Krishna & Guntur
and thus fast / better movement of through traffic.
This project decongests the traffic on NH-16 & 65 passing through Vijayawada city.
This ring road shall decongest the roads in Capital City.
Salient Features
189Km
Length (Eastern Side:78 Km, Western Side: 111 Km)
Lane configuration 6 lane
Estimated Cost
Rs. 17,961 Cr.
Tunnel 5.7 Km.
Major Bridges 14 Nos.
(including 2-Bridges across River Krishna)
Underpasses 78 Nos.
VOP 11 Nos.
CRIF works:
118 works completed: 1550 km and Rs 1,471 Crore
53 works in progress: 897 km and Rs 1054 Crore
36 works proposed for Bhumipoojan: 614 km and Rs 742 Crore
CRIF Status
Sr.
Description Rs. (in Crore)
No.
1. CRIF Sanction works till 2019-20 (177 nos.) 3103.59
2. CRIF Sanction work in 2020-21(35 nos.) 681.00
3. Total CRIF Sanction works till date (212 nos.) 3784.59
4. Total CRIF Accrual (till 2019-20) 1605.48
5. Accrual during for the year 2020-21 322.00
6. Total Accrual till Date 1927.48
7. Amount released till 2019-20 1605.48
8. Amount released during 2020-21 322.00
9. Total Released Till Date 1927.48
10. Utilization Certificate received (Up to June’ 2020) 1919.54
11. Amount available with State Govt. against UC submitted by State Government 7.94
12. BOS as on date (Total Sanction – Total Release) 1857.11
13. BOS ratio (BOS/Accrual) 5.76