Borrow Area Summary PDF

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

SUMMARY OF BORROW AREA

Client Karnataka State Highway Improvement Project

Independent Engineer LEA Associates South Asia Private Ltd

Concessionaire Sadbhav Gadag Highways Private Ltd

EPC Contractor M/S. Sadbhav Engineering Ltd

GSA Atterberg Limit Proctor Test USED QTY


Proposed
Date of BALANCE
Sl.No BA No Location (Lead) FSI CBR Quantity REMARKS
sampling QTY (CUM)
Silt & (cum)
Gravel Sand LL PI MDD OMC (CUM)
Clay

Approved for
1 1 15-10-2020 179+370(LHS)@3.3Km 28.44 37.28 34.28 33.47 13.10 1.993 10.02 10.42 - 18000 18000.00 0
Embankment
Approved for
2 3 27-10-2020 161+850(RHS)@0.7Km 27.59 48.14 27.21 32.50 11.53 2.014 7.98 11.25 - 12000 3292.00 8708
Embankment
Approved for
3 3(A) 27-10-2020 161+850(RHS)@0.7Km 18.58 48.35 33.08 31.40 10.73 2.020 8.60 15.00 - 6000 0.00 6000
Embankment
Approved for
4 11 08-12-2020 179+370(LHS)@4.5Km 14.50 52.45 33.05 30.03 10.64 2.006 10.23 - 18000 0.00 18000
Embankment
Embankment &
5 12 14-12-2020 161+852(RHS)@0.7Km 17.54 49.73 32.80 23.39 NP 2.012 10.23 11.25 19.04 12000 6516.50 5484
Subgrade
Embankment &
6 20 30-12-2020 179+500(LHS)@3.3Km 16.15 50.26 33.59 30.73 11.29 2.044 8.15 15.00 19.29 24000 9649.34 14351
Subgrade
Approved for
7 24 01-02-2021 217+500(RHS)@3.0Km 34.26 47.60 18.14 30.15 11.63 2.056 10.28 13.75 - 18000 0.00 18000
Embankment
Approved for
8 30 17-02-2021 246+420(LHS)@0.5Km 35.58 46.77 17.28 28.65 9.41 2.096 9.28 13.13 - 12000 0.00 12000
Embankment

Remarks:

EPC Contractor
Representative

You might also like