0% found this document useful (0 votes)
62 views

Example Project Management

1. The document provides a schedule for activities A through K with immediate predecessors, normal and crash durations in weeks, and normal and crash costs in dollars. 2. It asks to construct a network, determine the critical path, EST, EFT, LST, LFT and slack for each activity, and the probability of finishing in 70 days. 3. It also provides a schedule for activities A through J with predecessors, normal and crash durations in days, and normal and crash costs in dollars and asks for the project completion time, total cost, and how to crash the project to finish in 28 days.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
62 views

Example Project Management

1. The document provides a schedule for activities A through K with immediate predecessors, normal and crash durations in weeks, and normal and crash costs in dollars. 2. It asks to construct a network, determine the critical path, EST, EFT, LST, LFT and slack for each activity, and the probability of finishing in 70 days. 3. It also provides a schedule for activities A through J with predecessors, normal and crash durations in days, and normal and crash costs in dollars and asks for the project completion time, total cost, and how to crash the project to finish in 28 days.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Activity Immediate Week

Predecessors a m b
A - 4 7 10
B - 3 4 5
C A, B 2 5 8
D C 16 19 28
E C 6 9 24
F E 1 7 13
G C 4 10 28
H D, F, G 2 5 14
I G, F 5 8 17
J H 2 5 8
K I, J 17 19 45

a) Construct a network for this problem.


b) Determine EST, EFT, LST, LFT and slack for each activity.
c) Determine the critical path and project completion time.
d) Determine the probability that the project will be finished in 70 days or less.
Activity Immediate Day Cost ($)
Predecessors Normal Crash Normal Crash
A - 5 4 8,000 12,000
B A 8 6 6,000 9,000
C A 7 6 10,000 12,000
D A 6 5 9,000 11,000
E B, C 10 7 7,000 19,000
F B, C 10 8 10,000 15,000
G C, D 7 4 22,000 28,000
H E, F 7 6 15,000 18,000
I F, G 8 6 12,000 18,000
J G 4 3 14,000 15,000

a) What is the project completion time and total cost of this project?
b) Please crashing the project to reach the deadline at 28 days

You might also like