Macalinao, Joshua M.
BSCPE 2-2 ENGS32 A- Engineering Management
TIME SCALED EVENT NETWORK
For items 1 and 2:
From the following network diagram, draw the unscaled activity Bar Type based on
A. Early Start
B. Late Start
PROBLEM 7-1
(PROBLEM1) 9 19
12 17
5 2 8 27
2 4 6
4
4 17
19
8
7 17
1 7
4
10 15
13
7 9 9 22
7 6
0 3 5 18
Critical path: 1 – 3 – 4 – 6
ACTIVITY TIME ES EF LS LF
1-2 4 0 4 8 12
1-3 7 0 7 0 7
2-4 5 4 9 12 17
3-4 10 7 17 7 17
3-5 6 7 13 9 15
4-6 2 17 19 17 19
5-6 4 13 17 15 19
5-7 9 13 22 18 27
6-7 8 19 27 19 27
Macalinao, Joshua M.
BSCPE 2-2 ENGS32 A- Engineering Management
PROBLEM 7-2
9
(PROBLEM2)
7 18
5 E-4 G-9 days
2 5 11
5 days
C-2 days
20 6
7
1 13 13
J-0 days
6
5 19
20
3
I-6 days
5
3 D-5 days 4 6
8 19
8 14
Critical path: 1 – 2 – 4 – 7
ACTIVITY TIME ES EF LS LF
1-2 5 0 5 0 5
1-3 3 0 3 5 8
2-3 2 5 7 6 8
2-4 8 5 13 5 13
2-5 4 5 9 7 11
3-4 5 3 8 8 13
4-6 6 13 19 14 20
4-7 7 13 20 13 20
5-7 9 9 18 11 20
6-7 0 19 19 20 20
Macalinao, Joshua M.
BSCPE 2-2 ENGS32 A- Engineering Management
For items 3-4:
From the following two table of information;
a. Draw the precedence diagram;
b. What is the probability that the project can be completed in 24 days or less? In 21 days or less?
3. Solution:
ACTIVITY PRECEDES TIME IN DAYS
OPTIMISTIC MOST LIKELY PESSOMISTIC
TIME TIME TIME
A C 5 6 7
B H 8 9 11
C E 6 9 11
D F 9 12 15
E end 5 7 10
F G 5 6 7
G end 3 4 7
H I 4 4 5
I end 5 7 8
𝑇𝑜 + 4𝑇𝑚 + 𝑇𝑝
𝑇𝐸 =
6
𝑇0 = optimistic time; 𝑇𝑀 = most likely time; 𝑇𝑃 = pessimistic time; 𝑇𝐸 = exp duration
Tm = most likely time
Tp = pessimistic time
ACTIVITY PRECEDES TIME IN EXPECTED SD VARIANCE
DAYS DURATION
Optimistic Most Pessimistic
Time Likely Time
Time
A C 5 6 7 6 0.33 0.11
B H 8 9 11 9.17 0.5 0.25
C E 6 9 11 8.83 0.83 0.69
D F 9 12 15 12 1 1
E end 5 7 10 7.17 0.83 0.69
F G 5 6 7 6 0.33 0.11
G end 3 4 7 4.33 0.66 0.44
H I 4 4 5 4.17 0.17 0.03
Macalinao, Joshua M.
BSCPE 2-2 ENGS32 A- Engineering Management
I end 5 7 8 6.83 0.5 0.25
PATH PROJECT DURATION (IN DAYS)
G-F-D 4.33 + 6.0 + 12.0 22.33
E-C-A 7.17 + 8.83 + 6.0 22
I-H-B 6.83 + 4.17 + 9.17 1.66
∴ Critical Path is G-F-D
a. Draw the precedence diagram:
G F D
E C A
I H B
b. What is the probability that the project can be completed in 24 days or less? In 21 days or less?
Formula: z = x-µ
σ
σ = standard deviation
where: =√Total Variance of Critical Path x
= expected duration = √0.44+0.11+1
µ = project duration = 22.33 σ = 1.24
Probability for 24 days or less: Probability for 21 days or less:
z= = 1.35 = 0.9115 = 91.15% z= = -1.07 = 0.1423 = 14.23%
4. Solution:
ACTIVITY PRECEDES TIME IN DAYS
OPTIMISTIC MOST LIKELY PESSOMISTIC
TIME TIME TIME
A D,F 2 4 6
D E 6 8 10
E H 7 9 11
H end 2 3 5
F G 3 4 8
G end 5 7 9
B I 2 2 3
Macalinao, Joshua M.
BSCPE 2-2 ENGS32 A- Engineering Management
I J 2 3 6
J K 3 4 5
K end 4 5 8
C M 5 8 12
M N 1 1 1
N O 6 7 11
O end 8 9 13
6
where: To = optimistic time
Tm = most likely time
Tp = pessimistic time
ACTIVITY PRECEDES TIME IN EXPECTED SD VARIANCE
WEEKS DURATION
Optimistic Most Pessimistic
Time Likely Time
Time
A D, F 2 4 6 4 0.66 0.44
D E 6 8 10 8 0.66 0.44
E H 7 9 11 9 0.66 0.44
H end 2 3 5 3.17 0.5 0.25
F G 3 4 8 4.5 0.83 0.69
G end 5 7 9 7 0.66 0.44
B I 2 2 3 2.17 0.17 0.03
I J 2 3 6 3.33 0.66 0.44
J K 3 4 5 4 0.33 0.11
K end 4 5 8 5.33 0.66 0.44
C M 5 8 12 8.17 1.17 1.36
M N 1 1 1 1 0 0
N O 6 7 11 7.5 0.83 0.69
O end 8 9 13 9.5 0.83 0.69
PATH PROJECT DURATION (IN
WEEKS)
A-D-E-H 4 + 8 + 9 + 3.17 24.17
A-F-G 4 + 4.5 + 7 15.5
B-I-J-K 2.17 + 3.33 + 4 + 5.33 14.83
C-M-N-O 8.17 + 1 + 7.5 + 9.5 26.17
∴ Critical Path is C-M-N-O
c. Draw the precedence diagram;
D E H
F G
Macalinao, Joshua M.
BSCPE 2-2 ENGS32 A- Engineering Management
B I J K
C M N O
d. What is the probability that the project can be completed in 24 weeks or less? In 21 weeks or less?
Formula: z = x-µ
σ
where: σ = standard deviation
x = expected duration
µ = project duration = 26.17 weeks
1.36 + 0 + 0.69 + 0.69 σ = 1.66
Probability for 24 weeks or less: Probability for 21 weeks or less: z
= = -1.31 = 0.0951 = 9.51% z= = -3.11 = 0.00094 = 0.094 %
5. From the table of information of problem 4, the project manager will receive a bonus P20 000; and
if the project is finished within 28 weeks of its start, the bonus is only P10 000. Find the probability
of each bonus.
Bonus: P20 000 Bonus P10 000
In problem 4, x = 24: If x = 28:
z=x -µ
z = x-µ
= =
z = -1.31 = 0.0951 = 9.51% z = 1.10 = 0.8643 = 86.43%