Project: Proposed Construction of A Residential Building in Plot - D

This document provides an abstract estimate for the proposed construction of a residential building with a ground floor and first floor in Manapakkam Village, Kanchipuram District, Tamil Nadu. The estimate includes 18 line items for construction activities and materials like earthwork, brickwork, concrete work, plastering, flooring, doors and windows, painting, roofing, plumbing, electrification, staircase, compound wall, and unforeseen costs. The total estimated cost for the project is 55,00,000 Indian rupees.

Uploaded by

ArDaveAnand
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
601 views2 pages

Project: Proposed Construction of A Residential Building in Plot - D

This document provides an abstract estimate for the proposed construction of a residential building with a ground floor and first floor in Manapakkam Village, Kanchipuram District, Tamil Nadu. The estimate includes 18 line items for construction activities and materials like earthwork, brickwork, concrete work, plastering, flooring, doors and windows, painting, roofing, plumbing, electrification, staircase, compound wall, and unforeseen costs. The total estimated cost for the project is 55,00,000 Indian rupees.

Uploaded by

ArDaveAnand
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

________________________________________________________________________________

PROJECT : PROPOSED CONSTRUCTION OF A RESIDENTIAL BUILDING In PLOT - D,


R.S.No - 328 / 1, OF MANAPAKKAM VILLAGE, AT LAKSHMI NAGAR FIRST CROSS STREET,
SRIPERUMBATHUR TALUK, KUNDRATHUR PANCHAYAT UNION, KANCHIPURAM DISTRICT.
________________________________________________________________________________

TITLE: ABSTRACT ESTIMATE FLOOR: GROUND FLOOR & FIRST FLOOR


________________________________________________________________________________

SI.no. UNIT DESCRIPTION OF ITEMS RATE QTY AMOUNT


Rs./P
________________________________________________________________________________

1 C.ft Earth Work excavation for foundation 15.00 1536.00 23040.00


trenches.

2 C.ft Sand filling in foundation with river Sand 60.00 7624.00 457440.00

3 C.ft Laying Plain cement concrete in


pits in 1:4:8 mix using (1.5" jelly)
40mm granite metal. 105.00 1064.00 111720.00

4 S.ft Brickwork in C.M.1:6 using first class


chamber bricks for basement and
superstructure.(9" thick walls) 140.00 6566.00 919240.00

5 C.ft Reinforced cement concrete in mix


1:2:4 using 3/4"metal and providing
necessary reinforcements including
shuttering,curing,etc.,complete.
R.C.C.Roof, Lintels & Roof Beam 180.00 2713.50 488430.00

6 S.ft Plastering with cm 1:5 mix 1.5" tk


with cost of scoffolding work. 45.00 17710.25 796961.25

7 S.ft Flooring with 2'X2' of Tile in CM 1:5


including laying, polishing and etc., 210.00 3363.00 706230.00
complete.

8 S.ft Supplying and fixing of Teak wood doors


and windows using well seasoned wood
including polishing fixing in position with
necessary fittings, etc., complete. 945.00 408.00 385560.00

9 S.ft White washing with lime coating over a


coat of primer for inner, outer Walls and
Ceiling. 16.00 15167.00 242672.00

10 S.ft Colour Washing with MATT two coats


over a coat of primer for outer walls 20.00 4044.00 80880.00

Page 1 of 2
11 S.ft Colour Washing with Distember two coats
over a coat of primer for Inner walls 20.00 8684.00 173680.00

________________________________________________________________________________

SI.no. UNIT DESCRIPTION OF ITEMS RATE QTY AMOUNT


Rs./P
________________________________________________________________________________

12 S.ft Weathering course with brick jelly concrete


over roof slab including labours, materials
etc., complete. 65.00 1681.50 109297.50

13 S.ft Finishing the top roof with one course of


machine pressed tiles in C.M.1:3 mixed
with water proofing compound including
labours, materials,etc.,complete. 35.00 1681.50 58852.50

14 L.S Provisions for Water supply, Sump, OHT, ---------- L.S ---------- 320000.00
& sanitary arrangements

15 L.S Provision for Electrification installations. ---------- L.S ---------- 275000.00

16 L.S Provision for Staircase ---------- L.S ---------- 115000.00

17 L.S Provisions for 9" Compound wall upto 5'0" ---------- L.S ---------- 220000.00
Height & Gate arrangements

18 L.S Unforseen Items ---------- L.S ---------- 15996.75

TOTAL = 5500000.00
55,00,000-00

RUPEES FIFTY FIVE LAKHS ONLY