Gantt Chart Activity

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Ira Grace B. De Castro.

ACN1 | CAED101

Management Science:

Using the following data:

Activity Immediate Time


Predecessor
A ---- 5
B ---- 3
C A,B 7
D C 6
E C 7
F E 3
G C 8
H D,F,G 10
I D,F 9
J H 7
K I,J 8

Required:

A. Prepare a Gantt chart.


B. Prepare an activity schedule

Earliest Start Latest Start Earliest Latest Slack Critical


Activity
(ES) (LS) Finish (EF) Finish (LF) (LS-ES) Path?

A 0 0 5 5 0 Yes
B 0 2 3 5 2
C 5 5 12 12 0 Yes
D 12 16 18 22 4
E 12 12 19 19 0 Yes
F 19 19 22 22 0 Yes
G 12 14 20 22 2
H 22 22 32 32 0 Yes
I 22 30 31 39 8
J 32 32 39 39 0 Yes
K 39 39 47 47 0 Yes

E(T) = tA + tC + tE + tF + tH + tJ + tK
= 5 + 7 + 7 + 3 + 10 + 7 + 8
= 47 units of time