P20202 - Testing & Commissioning Plan
P20202 - Testing & Commissioning Plan
THIS MANUAL DOES NOT AND SHOULD NOT BE CONSTRUED TO MODIFY THE
CONTRACT OF SALE FOR THE BIOAIR EQUIPMENT ("CONTRACT"). WITHOUT
LIMITING THE GENERALITY OF THE FOREGOING, THIS MANUAL DOES NOT
CREATE ANY NEW AND/OR MODIFY ANY WARRANTY, LIMITATION OF REMEDY OR
LIMITATION OF LIABILITY PROVISION CONTAINED IN THE CONTRACT.
1. Introduction 4
2. Reference Documents 4
4. Commissioning Team 4
5. Commissioning Overview 4
5.3 Pre-Commissioning 5
5.4 Commissioning 5
The purpose of this commissioning plan is to provide instructions on the steps to follow the
successful installation of the odour control system. Below are the details, reference documents for
the proper procedures, tools necessary, personnel, and deliverables relevant to startup of the odour
control system. All commissioning = will be outlined in this document & its attachment.
BioAir without question will make sure all commissioning and testing follows the site’s and BioAir’s
health and safety requirements.
BioAir welcomes the customer/client to perform their own audit of the commissioning and submit
feedback or concerns to BioAir for review and execution.
2. REFERENCE DOCUMENTS
Once system has been inspected and deemed properly installed, BioAir will issue a certificate
stating that the system has been installed per the instructions and guidelines and is ready for full
startup and operations.
4. COMMISSIONING TEAM
BioAir’s commissioning team will consist of the following roles:
• Project Manager
• Commissioning Engineer
• Startup Supervisor
5. COMMISSIONING OVERVIEW
BioAir will deliver all required equipment to the job site for the mechanical and electrical
installation. Following the installation BioAir will be able to properly startup, performance
test, and turnover the new biological odour control equipment to the end customer to
successfully operate.
5.2 Commissioning Goals and Objectives
The goal of the commissioning process is to ensure the system as a whole has been
installed correctly and that it is ready to be put into full service. The main objectives are as
follows:
• Ensure system has been installed per manufacturer’s instructions and all features are
defect-free and ready for use.
• Ensure system operates properly after startup with no errors or issues
• Ensure system meets project requirements and specifications
5.3 Pre-Commissioning
This step verifies all equipment has been installed per design documentation, is free from
all marks or damage, and is ready to be put into operation.
5.4 Commissioning
Once the Pre-Commissioning has been completed, and the equipment has been inspected
and deemed properly installed by BioAir, the Commissioning will follow BioAir’s startup
operation process.
Commissioning will be completed when BioAir has deemed the system’s biological process
is fully acclimated and the system is ready to begin the performance proving period.
6. TOOLS AND EQUIPMENTS
The commissioning process covers the following process associated with the Odor Control system.
OP.
ITEM PART NO. QTY. DESCRIPTION WT.
(KG)
1 RA063100_P20202 1 ECOFILTER EF63 REACTOR ASSEMBLY, FRP 4500
2 EB071000_P20202 1 ECOCARB EB07S, REACTOR ASSEMBLY, FRP 3750
3 NA121500_P20202 1 DN600, PS15-69, NOZZLE ASSEMBLY, FRP 45
4 ST124800_P20202 1 DN300 x 1219H, PS15-69, OUTLET STACK, FRP 25
5 DV122000 2 DN300, PS15-69, BACKDRAFT DAMPER VALVE, FRP 13
6 DV122100 9 DN300, PS15-69, ISOLATION-LEVER DAMPER VALVE, FRP 13
7 FC120000 8 DN300, PS15-69, FLEX CONNECTOR, EPDM 15
8 BT121600_P20202 4 DN300, PS15-69, BLOWER INLET TRANSITION PIECE, FRP 10
9 CHP-10 2 VERANTIS CHP-10, CW, UB, ARRG. 4, FRP 150
10 DW120000_P20202 1 DN300, PS15-69, INTERCONNECTING DUCTWORK, FRP 100
11 DW120001_P20202 1 DN300, PS15-69, INTERCONNECTING DUCTWORK, FRP 100
12 DW120002_P20202 1 DN300, PS15-69, INTERCONNECTING DUCTWORK, FRP 50
13 DW120003_P20202 1 DN300, PS15-69, INTERCONNECTING DUCTWORK, FRP 150
14 DW120004_P20202 1 DN300, PS15-69, INTERCONNECTING DUCTWORK, FRP 20
15 DW120005_P20202 1 DN300, PS15-69, INTERCONNECTING DUCTWORK, FRP 150
16 DW120006_P20202 1 DN300, PS15-69, INTERCONNECTING DUCTWORK, FRP 100
17 RS000750_P20202 1 DN40, ANSI 150, STARTUP SYSTEM, PVC-U 55
18 MW075150 1 DN20, SCH80, MAKE-UP WATER ASSEMBLY, PVC-U 4
19 WP151010_P20202 1 DN40, ANSI 150, WATER PANEL, FRP 60
20 NB100000_P20202 1 378 LITER (100 GAL), NUTRIENT TANK, POLYEHTYLENE 200
21 PS343300_P20202 1 WATER PANEL STAND, 316SS 60
22 PS100000_P20202 1 ELECTRICAL PANEL STAND, 316SS 60
23 SS000100_P20202 1 WATER PANEL STAND SUNSHIELD, 316SS 15
24 SW000100_P19203 2 DIFFERENTIAL PRESSURE GAUGE MOUNTING BRACKET, 316SS 1
25 SW000101_P20202 3 INSTRUMENT MOUNTING BRACKET, 316SS 3
26 732.15.160 2 WIKA DIFFERENTIAL PRESSURE GAUGE 1
27 8344123 / 6809710 2 DRAGER POLYTRON 5100, INLET H2S TRANSMITTER / SENSOR, 0-1000PPM 2
28 8344123 / 6810435 1 DRAGER POLYTRON 5100, OUTLET H2S TRANSMITTER / SENSOR, 0-5PPM 2
29 6810536 3 CALIBRATION ADAPTER, VITON 1
30 58P 3 ؼ", FNPT, 58P SAMPLE FILTER, PC 1
31 FR2A12SVVT 3 0.04 - 0.5 LPM ROTAMETER 1
32 AF1-S-123000 1 MCDONNELL & MILLER AIR FLOW SWITCH 1
33 CD20202 1 ELECTRICAL CONTROL PANEL, FRP 75
When EcoFilter system (OCU) is initially started up, it operates in startup operating mode for the
first 4 weeks. This involves the recirculation of drain water through the EcoFilter system in order to
aid in growth of the biology and its adherence to the EcoBase media.
In startup mode, the irrigation settings will be set to standard times by the BioAir’s commissioning
team in order to control the moisture and pH levels in the media of the BioFilter.
After 1-4 weeks, the biology is well established in the media and the system can be converted to
normal operation, then allowed to acclimate to normal operating conditions.
During this period, system H2S removal performance should be monitored as advised by BioAir
personnel. Inlet and Outlet H2S levels can be monitored via HMI. Readings can be logged along
with other system data on BioAir’s Process Data Recording Sheet.
After startup, the system should be operated, monitored and maintained in accordance with BioAir’s
Operator Handbook on Section 2.5 of the O&M Manual.
Once the pH of the process drain water reaches ≈ 2.0, the system can be converted from startup
mode to normal operation. Please follow these steps to complete conversion for EcoFilter.
• At the electric control panel (ECP), turn Irrigation Switch (SW5) to CLOSED and the
Startup Pump Switch (SW3) to OFF. Turn nutrient pump switch (SW4) to OFF as well.
• Open the water retention valve on the startup piping assembly and allow all water to
drain out of each vessel system. This will take some time (likely 1+ hour)
• Close the ball valves in the Ø2” pipe that connects the startup piping assembly from the
recirculation tank and the leading to the water panels. Open the ball valves that will
redirect the drains to the common site drain.
After the following items have been achieved, BioAir will issue a Certificate of Proper Installation:
• Installed in accordance with BioAir Solutions project documents
• Inspected, checked and adjusted (if required)
• Serviced with proper initial lubricants
• Electrical and Mechanical connections meet quality and safety standards
• All applicable safety equipment has been properly installed
• Functional Tests performed
• Mechanically & Electrically Started Up
• Biologically Started Up
Training
Operator training will be conducted to monitor and service equipment when needed, as well as
adjust parameters to keep system removal at optimal levels.
This includes both site training with the equipment and classroom training for in-depth transfer
of knowledge on system functions and operation. Training will be coordinated with SBG to
accommodate shift schedules of operations staff.
On site:
Cycle = _____
Irrigation time = _________
Nutrient time = _________
Water flow rate ( lpm) = ___________
Pressure gauge above WP (PSI/bar) = ____
DP gauge of Blower (mbar) = _____
DP gauge of Reactor (mbar) = _____
Verify valves open/close correctly
Verify nutrient dosing OK, keeps prime, fittings tightened
Nutrients remaining in barrel = _____ gal / nutrient level = _____ cm
Record active alarms & alarm history including dates/times
Total Airflow = _____ (record measurement details in notebook)
pH @ time: ____ @ ____ : ___@ ___ : :____ @ ___
H2S (Inlet) @ time: ___@____ : : ___@___ : : ___ @___
H2S (Outlet) @ time: ___ @___ : : ___ @___ : : ___ @ ___
9. Appendix - Installation, Verification and Commissioning Checklists
Note – The personnel who are commissioning the system and filling out the checklists below may
be required to print out additional copies to guarantee all installed equipment has been inspected.
Signed: ____________________________
Appendix 2 – Installing Contractor Checklist
BioAir will assure the installing Contractor(s) complete the following items prior to the BioAir
Commissioning Team traveling to the site for startup of the odor control equipment.
Reactor(s) placed the appropriate location and fully assembled with all vessel sections,
roof, nozzle assemblies, etc. installed.
Pressure gauge and nozzle installed on nozzle assembly.
Construction or shipping-related smudges or stains, shipping notices, and tape removed
from vessels.
All drain lines completed including reactor to site drain.
All anchoring devices installed and tightened to appropriate tension.
Water and other instrument panels mounted on odour control pad.
Recirculation tank placed in appropriate location and all piping and wiring completed.
Confirm nutrient barrel and EcoGrow nutrients are present on site.
All water supply lines completed per P&ID, including:
1) TSE Tanks effluent water supply to water panel(s) flange.
2) TSE effluent water supply to vessel bottom (make-up water supply).
3) Recirculation pump (on startup system) discharge to water panel flange.
4) Water panel to spray nozzle(s) connection on each reactor assembly.
All drain water lines completed, including:
1) Reactor drain(s) to startup system.
2) Startup system piped to site drain.
All Sampling Couplings are closed out with a threaded NPT PVC plug.
All water sources are connected and ready for delivery to system.
All ductwork, dampers, and blowers connected to source foul air streams and reactor
inlet flanges per Contract Drawings and BioAir P&ID, GA, and Installation drawings.
All instruments mounted and connected as necessary and as given in Contract Drawings
and BioAir P&ID drawings.
Review Offloading and Installation Manual and ensure all items are completed in
accordance with these instructions.
Appendix 3 – Commissioning Equipment Checklist
Note – Safety is the top priority on site, and all local safety regulations shall be followed without
exception. Below is a checklist of equipment needed for commissioning of the system. Note
additional equipment may be required due to the site conditions. Some Items listed below will not
require a Model No.
Signed: ____________________________
Appendix 4 – Instrumentation Commissioning Checklist
Tag No. Function Wired and Installed per P&ID
Signed: ____________________________
Appendix 5 – EcoFilter Startup Inspection Checklist
&200,66,21,1*&+(&./,67(&2),/7(5()BBB9(66(/
9(66(/,1)250$7,21
7DJ1R /RFDWLRQ
6HULDO1R 0RGHO1R
,1,7,$/,163(&7,21 67$786
(TXLSPHQWLVFOHDQDQGXQGDPDJHG RN QRWRN
$UHDLVFOHDQDQGIUHHRIGHEULV RN QRWRN
$OOPDQZD\VDUHVHDOHGZLWKJDVNHWVDQGEROWVWLJKWHQHGWRSURSHUWRUTXH RN QRWRN
3ODWIRUPLVLQVWDOOHGFRUUHFWO\DQGIUHHIURPGDPDJH RN QRWRN
(TXLSPHQWLVIUHHIURPLQVWDOODWLRQPDUNVRUJXLGHV RN QRWRN
,17(5&211(&7,21,163(&7,21 67$786
,QOHWGXFWZRUNLVFRQQHFWHGSURSHUO\SHU3 ,'DQG&RQVWUXFWLRQ'UDZLQJV RN QRWRN
,QOHWGXFWZRUNFRQQHFWLRQVDUHWLJKWDQGDOOEROWVSUHVHQW RN QRWRN
$OOGXFWFRQQHFWLRQVFRQWDLQJDVNHWVZKHUHDSSOLFDEOH RN QRWRN
,QOHW'DPSHUYDOYHEODGHPRYHVIUHHO\ZLWKRXWLQWHUIHUHQFH RN QRWRN
2XWOHWGXFWZRUNLVSURSHUO\DOLJQHGDQGLQVWDOOHGZLWKRXWLQWHUIHUHQFH RN QRWRN
$OOXQXVHGFRQQHFWLRQSRUWVVHDOHGZLWKWKUHDGHGSOXJ RN QRWRN
3,3,1*,163(&7,21 67$786
$OOYHVVHOSLSLQJFRQQHFWLRQVPDWFK3 ,'DQG*$ RN QRWRN
'UDLQLVWRFRPPRQGUDLQOLQHDQGVHDOHG RN QRWRN
$OOIODQJHFRQQHFWLRQVDUHVHDOHGZLWKJDVNHWVDQGEROWVWLJKWHQHGWRSURSHUWRUTXH RN QRWRN
&200,66,21,1*5(68/7
3DVVHG&DQ3URFHHGZ6\VWHP&RPPLVVLRQLQJ
3DVVHGZ&RPPHQWV&DQ3URFHHGZ6\VWHP&RPPLVVLRQLQJ8SRQ&RPSOLDQFHRI5HPDUNV
)DLOHG5HFRPPLVVLRQLQJ5HTXLUHG
&21),50$7,21,I5HTXLUHGE\%LR$LU
%LR$LU &RQWUDFWRU &XVWRPHU
1DPH
'DWH
6LJQDWXUH
(67,0$7('7,0(72&203/(7(0,1
1/1
Appendix 6 – Damper Valve Commissioning Checklist
&200,66,21,1*&+(&./,67'$03(59$/9(6
,QVWUXPHQW&RPPLVVLRQLQJ&KHFNOLVW1R
'$03(59$/9(,1)250$7,21
7DJ1R /RFDWLRQ
6HULDO1R 0RGHO1R
,1,7,$/,163(&7,21 67$786
(TXLSPHQWLVFOHDQDQGXQGDPDJHG RN QRWRN
$UHDLVFOHDQDQGIUHHRIGHEULV RN QRWRN
$OOIODQJHVDUHVHDOHGZLWKJDVNHWVDQGEROWVWLJKWHQHGWRSURSHUWRUTXH RN QRWRN
'DPSHU9DOYH/HYHU$UPLVDEOHWRPRYHIHHO\ RN QRWRN
(TXLSPHQWLVIUHHIURPLQVWDOODWLRQPDUNVRUJXLGHV RN QRWRN
'DPSHU9DOYHOHDNWHVWKDVEHHQSHUIRUPHGDQGSDVVHG RN QRWRN
,17(5&211(&7,21,163(&7,21 67$786
'DPSHU9DOYHLVFRQQHFWHGSURSHUO\SHU3 ,'DQG&RQVWUXFWLRQ'UDZLQJV RN QRWRN
'DPSHU9DOYHFRQQHFWLRQVDUHWLJKWDQGDOOEROWVSUHVHQW RN QRWRN
$OOGXFWFRQQHFWLRQVFRQWDLQJDVNHWVZKHUHDSSOLFDEOH RN QRWRN
'DPSHUYDOYHEODGHPRYHVIUHHO\ZLWKRXWLQWHUIHUHQFH RN QRWRN
6SHWLFDO)ODQJHLVDEOHWRURWDWHIUHHO\DERXWFHQWHUKROH RN QRWRN
'DPSHU9DOYHLVDEOHWREHVHWEDVHGRQV\VWHPUHTXLUHPHQWV RN QRWRN
'DPSHU9DOYH
V$FWXDWRUKDVSURSHUSURFHVVFRQQHFWLRQDLUFKDLQHFW RN QRWRN
'DPSHU9DOYH
V$FWXDWRULVLQVWDOOHGSURSHUO\ RN QRWRN
'DPSHU9DOYH
V$FWXDWRULVDEOHWRPRYHEODGHWRUHTXLUHGRSHQFORVHGSRVLWLRQ RN QRWRN
&+$,1,163(&7,21 67$786
,I'DPSHU9DOYHKDVDFKDLQ&KDLQLVVHFXUHGDQGFDQEHXVHGWRFKDQJHYDOYHVSRVLWLRQ RN QRWRN
'DPSHU9DOYH&KDLQLVIUHHIURPWDQJOHV RN QRWRN
$OOIODQJHFRQQHFWLRQVDUHVHDOHGZLWKJDVNHWVDQGEROWVWLJKWHQHGWRSURSHUWRUTXH RN QRWRN
&200,66,21,1*5(68/7
3DVVHG&DQ3URFHHGZ6\VWHP&RPPLVVLRQLQJ
3DVVHGZ&RPPHQWV&DQ3URFHHGZ6\VWHP&RPPLVVLRQLQJ8SRQ&RPSOLDQFHRI5HPDUNV
)DLOHG5HFRPPLVVLRQLQJ5HTXLUHG
&21),50$7,21,IUHTXLUHGE\%LR$LU
%LR$LU &RQWUDFWRU &XVWRPHU
1DPH
'DWH
6LJQDWXUH
ϭͬϭ
Appendix 7 – Startup System(s) Commissioning Checklist
Signed: ____________________________
Appendix 8 – Flex Connector Commissioning Checklist
&200,66,21,1*&+(&./,676,1*/($5&+)/(;&211(&725
(TXLSPHQW&RPPLVVLRQLQJ&KHFNOLVW1R
)/(;,%/(&211(&725,1)250$7,21
7DJ1R /RFDWLRQ
6HULDO1R 0RGHO1R
,1,7,$/,163(&7,21 67$786
)OH[&RQQHFWRULVFOHDQDQGXQGDPDJHG RN QRWRN
$UHDLVFOHDQDQGIUHHRIGHEULV RN QRWRN
$OO%DFNLQJ5LQJVDUHVHDOHGZLWKKDUGZDUHDQGZDVKDQGEROWVWLJKWHQHGWRSURSHUWRUTXH RN QRWRN
$OO)OH[&RQQHFWRUVDUHVHDWHGSURSHUO\LQGXFWZRUNZLWKRXWVHULRXVPLVDOLJQPHQW RN QRWRN
(TXLSPHQWLVIUHHIURPLQVWDOODWLRQPDUNVRUJXLGHV RN QRWRN
)OH[&RQQHFWRUV'XFWOHDNDJHWHVWKDVEHHQSHUIRUPHGDQGSDVVHG RN QRWRN
,17(5&211(&7,21,163(&7,21 67$786
)OH[&RQQHFWRUVLVFRQQHFWHGSURSHUO\SHU3 ,'DQG&RQVWUXFWLRQ'UDZLQJV RN QRWRN
$OO)OH[&RQQHFWRUVFRQQHFWLRQVDUHWLJKWDQGDOOEROWVSUHVHQW RN QRWRN
$OO)OH[&RQQHFWRUVFRQWDLQEDFNLQJULQJVZKHUHDSSOLFDEOH RN QRWRN
&RQQHFWLQJ'DPSHUYDOYHEODGHPRYHVIUHHO\ZLWKRXWLQWHUIHUHQFHZLWK)OH[&RQQHFWRUVDQG
RN QRWRN
*53'XFWZRUN
$OOXQXVHGFRQQHFWLRQSRUWVVHDOHGZLWKWKUHDGHGSOXJ RN QRWRN
2WKHU RN QRWRN
3,3,1*,163(&7,21 67$786
$OOSLSLQJFRQQHFWLRQVPDWFK3 ,'DQG*$ RN QRWRN
'UDLQLVWRFRPPRQGUDLQOLQHDQGVHDOHG RN QRWRN
$OOIODQJHFRQQHFWLRQVDUHVHDOHGZLWKJDVNHWVDQGEROWVWLJKWHQHGWRSURSHUWRUTXH RN QRWRN
$OO-RLQWV)ODQJHVDQG&RXSOLQJ&RQQHFWLRQVKDYHEHHQVRDS\EXEEOHWHVWHGIRUOHDNVIRU
RN QRWRN
ERWK6\VWHPVGXULQJWKH,Q3URFHVVFRQGLWLRQV
&200,66,21,1*5(68/7
3DVVHG&DQ3URFHHGZ6\VWHP&RPPLVVLRQLQJ
3DVVHGZ&RPPHQWV&DQ3URFHHGZ6\VWHP&RPPLVVLRQLQJ8SRQ&RPSOLDQFHRI5HPDUNV
)DLOHG5HFRPPLVVLRQLQJ5HTXLUHG
&21),50$7,21,IUHTXLUHGE\%LR$LU
%LR$LU &RQWUDFWRU &XVWRPHU
1DPH
'DWH
6LJQDWXUH
ϭͬϭ
Appendix 9 – GRP Ductwork Commissioning Checklist
&200,66,21,1*&+(&./,67*53'8&7:25.
,QVWUXPHQW&RPPLVVLRQLQJ&KHFNOLVW1R
*53'8&7:25.,1)250$7,21
7DJ1R /RFDWLRQ
6HULDO1R 0RGHO1R
,1,7,$/,163(&7,21 67$786
*533LSHLVFOHDQDQGXQGDPDJHG RN QRWRN
$UHDLVFOHDQDQGIUHHRIGHEULV RN QRWRN
$OOPDQZD\VDUHVHDOHGZLWKJDVNHWVDQGEROWVWLJKWHQHGWRSURSHUWRUTXH RN QRWRN
$OO'XFWZRUNLVVHDWHGSURSHUO\LQGXFWVXSSRUWV RN QRWRN
(TXLSPHQWLVIUHHIURPLQVWDOODWLRQPDUNVRUJXLGHV RN QRWRN
*53'XFWOHDNDJHWHVWKDVEHHQSHUIRUPHGDQGSDVVHG RN QRWRN
,17(5&211(&7,21,163(&7,21 67$786
'XFWZRUNLVFRQQHFWHGSURSHUO\SHU3 ,'DQG&RQVWUXFWLRQ'UDZLQJV RN QRWRN
$OO'XFWZRUNFRQQHFWLRQVDUHWLJKWDQGDOOEROWVSUHVHQW RN QRWRN
$OOGXFWFRQQHFWLRQVFRQWDLQJDVNHWVZKHUHDSSOLFDEOH RN QRWRN
&RQQHFWLQJ'DPSHUYDOYHEODGHPRYHVIUHHO\ZLWKRXWLQWHUIHUHQFHZLWK*53'XFWZRUN RN QRWRN
$OOGUDLQVDUHSURSHUO\LQVWDOOHGWR*53'XFWZRUN RN QRWRN
$OOXQXVHGFRQQHFWLRQSRUWVVHDOHGZLWKWKUHDGHGSOXJ RN QRWRN
3,3,1*,163(&7,21 67$786
$OOSLSLQJFRQQHFWLRQVPDWFK3 ,'DQG*$ RN QRWRN
'UDLQLVWRFRPPRQGUDLQOLQHDQGVHDOHG RN QRWRN
$OOIODQJHFRQQHFWLRQVDUHVHDOHGZLWKJDVNHWVDQGEROWVWLJKWHQHGWRSURSHUWRUTXH RN QRWRN
$OO-RLQWV)ODQJHVDQG&RXSOLQJ&RQQHFWLRQVKDYHEHHQVRDS\EXEEOHWHVWHGIRUOHDNVIRUERWK
RN QRWRN
6\VWHPVGXULQJWKH,Q3URFHVVFRQGLWLRQV
&200,66,21,1*5(68/7
3DVVHG&DQ3URFHHGZ6\VWHP&RPPLVVLRQLQJ
3DVVHGZ&RPPHQWV&DQ3URFHHGZ6\VWHP&RPPLVVLRQLQJ8SRQ&RPSOLDQFHRI5HPDUNV
)DLOHG5HFRPPLVVLRQLQJ5HTXLUHG
&21),50$7,21,IUHTXLUHGE\%LR$LU
%LR$LU 6RULPD 9H%HV
1DPH
'DWH
6LJQDWXUH
ϭͬϭ
Appendix 10 – Water Panel Commissioning Checklist
Item #: Description / Task STATUS
1. Verify Water Panel ball valves are in the proper positions - OK - NOT OK
1. Rinse gun shutoff valve (BV-04) CLOSED
2. Water release valve (BV-03) CLOSED
3. Startup water supply shutoff valve (BV-01) OPEN
4. TSE supply shutoff valve (BV-02) OPEN
5. Common line shutoff valve (BV-02) OPEN
6. Verify no leaks at full pressure for 10 minutes - OK - NOT OK
Signed: ____________________________
Appendix 11 – Blower Commissioning Checklist
&RQVWUXFWLRQ&RPSOHWLRQ
%/2:(5 )81&7,21$/7(67
)RUP1R 1RRI3DJHV
'UDZLQJ5HIHUHQFH5HY
(48,30(17 ,1)250$7,21
'HVFULSWLRQ /RFDWLRQ
7DJ1R 0RGHO1R
0DNH 6HULDO1R
3XQFK/LVW
)81&7,21$/7(67 5HVXOWV 5HPDUNV
<1
9HULI\SURSHUDOLJQPHQWRIWKHPRWRUIDQVKDIW DQG EHOWGULYH
&KHFNWKH)LHOG,VRODWRU3RVLWLRQDQGPDNHLW21
9HULI\WKH&RQWUROVXSSO\WR6RIW6WDUWHU
7XUQ+$1'2))$8726ZLWFKWR+$1'
%ORZHU6WDUW2SHUDWLRQ
3UHVV(PHUJHQF\6WRS
)DQVWRSVRSHUDWLRQ
2Q3/&+0,YHULI\WKH'XW\VWDQGE\5XQ+RXUVRI%ORZHU
6LJQDWXUH
3ULQW1DPH
'DWH
6KHHW
Appendix 12 – Pump Commissioning Checklist
&200,66,21,1*&+(&./,6738036
3803,1)250$7,21
7DJ1R /RFDWLRQ
6HULDO1R 0RGHO1R
(48,30(17,163(&7,21 67$786
(TXLSPHQWLVFOHDQDQGXQGDPDJHG RN QRWRN
$UHDLVFOHDQDQGIUHHRIGHEULV RN QRWRN
&RQILUPDOO3UHVHUYDWLRQPHDVXUHVKDYHEHHQUHPRYHG RN QRWRN
(QVXUHDOOYDOYHVDVVRFLDWHGZLWKWKHSXPSXQLWKDYHWKHLUFRUUHFWO\GHVLJQHGDFWXDWRURU
RN QRWRN
PDQXDORSHUDWRULQVWDOOHGDQGWKDWWKH\DUHIUHHWRPRYH&RQILUP9DOYH7DJJLQJLVFRPSOHWH
&KHFNWKDW9DOYHLQWHUORFNVDUHLQVWDOOHGLIDSSOLFDEOHDQGWKHV\VWHPRSHUDWHVDVGHVLJQHG
RN QRWRN
(QVXUHNH\VDUHVDIHO\ORFDWHG
&RQILUPZKHUHDSSOLFDEOH/XEH6HDORLOV\VWHPVIOXVKLQJLVFRPSOHWH
RN QRWRN
5XQOXEHVHDOSXPSVDQGFKHFN/XEH6HDORLOV\VWHPVIRUOHDNV
3,3,1*,163(&7,21 67$786
$OOYHVVHOSLSLQJFRQQHFWLRQVPDWFK3 ,'DQG*$ RN QRWRN
'UDLQLVWRFRPPRQGUDLQOLQHDQGVHDOHG RN QRWRN
$OOIODQJHFRQQHFWLRQVDUHVHDOHGZLWKJDVNHWVDQGEROWVWLJKWHQHGWRSURSHUWRUTXH RN QRWRN
1/2
&200,66,21,1*5(68/7
3DVVHG&DQ3URFHHGZ6\VWHP&RPPLVVLRQLQJ
3DVVHGZ&RPPHQWV&DQ3URFHHGZ6\VWHP&RPPLVVLRQLQJ8SRQ&RPSOLDQFHRI5HPDUNV
)DLOHG5HFRPPLVVLRQLQJ5HTXLUHG
&21),50$7,21,I5HTXLUHGE\%LR$LU
%LR$LU &RQWUDFWRU &XVWRPHU
1DPH
'DWH
6LJQDWXUH
(67,0$7('7,0(72&203/(7(0,1
2/2
Appendix 13 - Airflow Balancing Checklist
1. Using Hot-Top Anemometer, Verify Airflow at inlet of EcoFilter #1
2. Use Inlet Actuated Damper Valve to set airflow.
3. Record final Airflow Readings on Airflow Balancing Worksheet, Appendix 13.
4. Using Hot-Top Anemometer, Verify Airflow at inlet of EcoFilter #2
5. Use Inlet Actuated Damper Valve to set airflow
6. Record final Airflow Readings on Airflow Balancing Worksheet, Appendix 13.
7. Use Outlet Damper Valves to set airflow
8. Record final Airflow Readings on Airflow Balancing Worksheet, Appendix 13.
9. Use Outlet Damper Valves to set airflow
10. Record final Airflow Readings on Airflow Balancing Worksheet, Appendix 13.
Signed: ____________________________
APPENDIX 14: AIRFLOW BALANCING WORKSHEET
Airflow Balancing Chart note multiple sheets may be required to complete Appendix 13.
LOCATION # ________________________________
AIRFLOW # ________________________________
Signed: ____________________________