Solutions Manual: Ch03-Flow & Batch-S: Review Questions
Solutions Manual: Ch03-Flow & Batch-S: Review Questions
Review Questions
3.1 What does sequential operations mean?
Answer: As defined in the text, sequential operations are a work system in which multiple
processing steps are accomplished in order to complete a work unit, and the processing
steps are performed sequentially (rather than simultaneously).
3.2 What is a precedence constraint in sequential operations?
Answer: A precedence constraint is a restriction on the order in which the sequence of
operations must be performed. Certain operations must be accomplished before other
operations can be started. The example given in the text is drilling and tapping. A hole
must be drilled before it can be tapped.
3.3 What is the difference between pure sequential work flow and mixed sequential work
flow?
Answer: Pure sequential means that all work units flow through the same exact sequence
of workstations and operations. There is no variation in the processing sequence. Mixed
sequential means that there are variations in the work flow for different work units.
Different work units are processed through different stations.
3.4 Name and define the four types of part moves between workstations in sequential
operations.
Answer: The four types of part moves identified in the text are: (1) in-sequence move, in
which the work unit moves forward from the current operation to the neighboring
operation immediately downstream; (2) bypassing move, which is a forward move beyond
the neighboring workstation by two or more stations ahead of the current station; (3)
backflow move, in which the work unit moves in the backward direction by one or more
stations; and (4) repeat operation, in which the operation is repeated at the same
workstation and the part does not move between stations.
3.5 What is a From-To chart?
Answer: A From-To chart is a tabular chart that is used to indicate various quantitative
relationships between operations or workstations in a multi-station work system. Typical
quantities displayed in a From-To chart include quantities between stations, flow rates of
parts between stations, and distances between stations.
3.6 What is a bottleneck in sequential operations?
Answer: The bottleneck operation is the slowest operation in the sequence. It is the
operation that ultimately limits the production rate of the sequence.
3.7 What do the terms starving and blocking mean in terms of sequential operations?
Answer: Blocking means that the production rate(s) of one or more upstream operations
are limited by the rate of a downstream operation. The upstream operations are blocked by
the slower rate of the downstream station. Starving means that the production rate(s) of one
or more downstream operations are limited by the rate of an upstream operation (e.g., the
1
Work Systems and the Methods, Measurement, and Management of Work
by Mikell P. Groover. ISBN 0-13-140650-7.
© 2007 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
Solutions Manual: Ch03-Flow & Batch-s
bottleneck). The downstream operations can work no faster than the rate at which the
bottleneck feeds work units to them.
3.8 What does the term batch processing mean?
Answer: As defined in the text, the term batch processing refers to the processing of work
units in finite quantities or amounts.
3.9 What are some of the disadvantages of batch processing?
Answer: The disadvantages of batch processing include the following: (1) batch
processing is discontinuous, which means there are periods in which the equipment is not
producing; (2) delays occur between processing steps when batch processing is used in
conjunction with sequential operations; (3) queues of work units form in front of
operations, resulting in high work-in-process inventories; and (4) long lead times occur due
to accumulation of work-in-process.
3.10 Given the disadvantages of batch production, what are the reasons why it is so widely used
in industry?
Answer: The reasons given in the text are (1) work unit differences that require
changeovers in processing equipment, (2) equipment limitations such as the capacity of
equipment, and (3) material limitations, in which the material must be processed as a unit
of material.
3.11 What are the two cost terms in the economic order quantity model?
Answer: The two cost terms in the economic order quantity model are (1) setup or
changeover cost and (2) inventory holding cost.
3.12 Write the equation that describes the relationship between the starting quantity of work
units Qo, the completed quantity Q, and the fraction defect rate q of the operation
processing the work units.
Answer: The equation is Q = Qo(1 – q)
3.13 What is a work cell?
Answer: As defined in the text, a work cell is a group of workstations dedicated to the
processing of a range of work units within a given type.
3.14 What is a worker team?
Answer: A worker team is a collection of workers who are brought together to achieve a
common objective or solve a common problem.
3.15 Define teamwork.
Answer: Teamwork refers to the cumulative efforts of the team members to achieve a
result that is greater than the sum of their individual efforts. It requires the subordination of
the members’ individual goals in favor of the team’s goals.
3.16 What is the difference between a work-unit team and a self-managed work team?
Answer: A work-unit team is one that consists of all the workers employed in a
department or unit. It is basically an extension of the regular organizational structure,
2
Work Systems and the Methods, Measurement, and Management of Work
by Mikell P. Groover. ISBN 0-13-140650-7.
© 2007 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
Solutions Manual: Ch03-Flow & Batch-s
except that the management of the organization is attempting to instill a spirit of teamwork
among the work-unit members. A self-managed work team operates like a separate
business unit in the organization. It elects its own leaders, and plans and manages its own
activities. Management provides the resources necessary for a self-managed team to
operate, but the team basically runs itself.
3.17 What is cross-training and what is its value in a worker team?
Answer: Cross-training means workers become trained in more than one job in the work
unit or cell. Although each individual brings unique knowledge, skills, and abilities to the
team’s activities, having more than one team member know each job mitigates problems of
absences and allows for job rotations to increase work variety and employee satisfaction.
3.18 Name some examples of cross-functional teams.
Answer: Examples given in the text are: (1) concurrent engineering teams, who work on
product design projects; (2) task forces, which are usually assembled to deal with a
significant organizational problem or exploit a commercial opportunity; and (3) crisis
management teams, which are designed to cope with a crisis or disaster that occurs.
Problems
Workflow Structures
3.1 Four parts (A, B, C, and D) are processed through a sequence of four operations (1, 2, 3,
and 4). Not all parts are processed in all operations. Part A, which has weekly quantities of
70 units, is processed through operations 1, 2, and 3 in that order. Part B, which has
weekly quantities of 90 units, is processed through operations 2, 4, and 1 in that order. Part
C, which has weekly quantities of 65 units, is processed through operations 3, 2, and 4 in
that order. Finally, part D, which has weekly quantities of 100 units, is processed through
operations 2, 1, and 4 in that order. (a) Draw the network diagram and (b) prepare the
From-To table for this work system.
Solution: (a) Network diagram.
100
70
1 2
65
90
70
100 90+65
4 3
3
Work Systems and the Methods, Measurement, and Management of Work
by Mikell P. Groover. ISBN 0-13-140650-7.
© 2007 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
Solutions Manual: Ch03-Flow & Batch-s
3.2 Five parts (A, B, C, D, and E) are processed through a sequence of five operations (1, 2, 3,
4, and 5). Not all parts are processed in all operations. Part A, which has daily quantities of
50 units, is processed through operations 1, 3, 5, and 1 in that order. Part B, which has
daily quantities of 70 units, is processed through operations 2, 4, and 5 in that order. Part
C, which has daily quantities of 25 units, is processed through operations 3, 2, and 4 in that
order. Part D, which has daily quantities of 10 units, is processed through operations 1, 2,
4, and 5 in that order. Finally, part E, which has daily quantities of 15 units, is processed
through operations 3, 1, and 2 in that order. (a) Draw the network diagram and (b) prepare
the From-To table for this work system.
Solution: (a) Network diagram
10+15 2
25
1
50
50 15 3
50
5 70+25+10
70+10
4
during a 40-hour week, in printed and indented blanks/week. Assumptions: (i) steady state
operation and (ii) there is work-in-process between operations 1 and 2 and between 2 and 3,
so that blocking and starving of operations is negligible.
Solution: Operation 1: cutting: Batch time TB = 25 + 4000(0.03) = 145 min
Production rate Rp = 4000/145 = 27.58 pc/min = 1655.2 pc/hr
Operation 2: indenting: TB = 30 + 2000(2.5/60) = 113.33 min
Rp = 2000/113.33 = 17.65 pc/min = 1058.8 pc/hr
Operation 3: printing: TB = 40 + 2000/30 = 106.67 min
Rp = 2000/106.67 = 18.75 pc/min = 1125 pc/hr
Bottleneck is Operation 2: indenting. The slowest operation sets the pace for the sequence.
Weekly plant production rate Rp = 40(1058.8) = 42,353 pc/wk
3.4 Solve the previous problem except that the reliability of the cutting machine is 80%
(availability or uptime proportion = 80%), the reliability of the indenting machine = 95%,
and the reliability of the printing machine = 85%. These reliability factors apply only when
the machines are producing, not during setup or changeovers.
Solution: Operation 1: cutting: Batch time TB = 25 + 4000(0.03)/0.80 = 175 min
Production rate Rp = 4000/175 = 22.86 pc/min = 1371.4 pc/hr
Operation 2: indenting: TB = 30 + 2000(2.5/60)/0.95 = 117.72 min
Rp = 2000/117.72 = 16.99 pc/min = 1019.4 pc/hr
Operation 3: printing: TB = 40 + (2000/30)/0.85 = 118.43 min
Rp = 2000/118.43 = 16.89 pc/min = 1013.2 pc/hr
Bottleneck is Operation 3: printing. The slowest operation sets the pace for the sequence.
Weekly plant production rate Rp = 40(1013.2) = 40,530 pc/wk
3.5 A factory produces one product. One unit of raw material is required for each unit of
product. Two processes are required to produce the product, process 1, which feeds into
process 2. A total of five identical machines are available in the plant that can be set up to
perform either process. Once set up, each machine will be dedicated to perform that process.
For each machine that is set up for process 1, production rate = 12 units per hour. For each
machine that is set up for process 2, production rate = 18 units per hour. Both processes
produce 100% good units (fraction defect rate = 0). A work-in-process buffer is provided
between the two processes to avoid starving and blocking of machines. The factory operates
40 hours per week. (a) In order to maximize factory production, how many machines should
be set up for process 1, and how many machines should be set up for process 2? (b) What is
the factory’s maximum possible weekly production rate of good product units?
Solution: (a) Rp1 = 12 pc/hr, Rp2 = 18 pc/hr
n1 = (18/12)n2 = 1.5 n2
n1 + n2 = 1.5n2 + n2 = 2.5n2 = 5 machines total
n2 = 2 machines, n1 = 5 – 2 = 3 machines
(b) For the two operation sequence, Rp = 2(18 pc/hr)(40 hr/wk) = 1440 pc/wk
Check: Rp = 3(12 pc/hr)(40 hr/wk) = 1440 pc/wk
5
Work Systems and the Methods, Measurement, and Management of Work
by Mikell P. Groover. ISBN 0-13-140650-7.
© 2007 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
Solutions Manual: Ch03-Flow & Batch-s
3.6 A factory is dedicated to the production of one product. One unit of raw material is required
for each unit of product. Two processes are required to produce the product, process 1,
which feeds into process 2. A total of eight identical machines are available in the plant that
can be set up to perform either process. Once set up, each machine will be dedicated to that
process. For each machine that is set up for process 1, production rate = 10 units per hour.
For each machine that is set up for process 2, production rate = 6 units per hour. Both
processes produce 100% good units (fraction defect rate = 0). A work-in-process buffer is
provided between the two processes to avoid starving and blocking of machines. The factory
operates 40 hours per week. (a) In order to maximize factory production, how many
machines should be set up for process 1, and how many machines should be set up for
process 2? (b) What is the factory’s maximum possible weekly production rate of good
product units?
Solution: (a) Rp1 = 10 pc/hr, Rp2 = 6 pc/hr
n1 = (6/10)n2 = 0.60 n2
n1 + n2 = 0.60n2 + n2 = 1.60n2 = 8 machines total
n2 = 5 machines, n1 = 8 – 5 = 3 machines
(b) For the two operation sequence, Rp = 3(10 pc/hr)(40 hr/wk) = 1200 pc/wk
Check: Rp = 5(6 pc/hr)(40 hr/wk) = 1200 pc/wk
3.7 There are 20 automatic turning machines in the lathe department. Batches of parts are
machined in the department. Each batch consists of setup and run. Batch size = 100 parts.
The standard time to set up a machine for each batch is 5.0 hours. Four setup workers
perform the setups. They each work 40 hours per week. Once a machine is set up, it runs
automatically, with no worker attention until the batch is completed. Cycle time to machine
each part = 9.0 min; thus, it takes 15 hours of run time to produce a batch. Assume all
machines are perfectly reliable. (a) What is the production output of the lathe department in
40 hours of operation per week? (b) How many machines are idle (not in use or being set up
between production runs) on average at any moment?
Solution: (a) Compare machine output capacity and setup output capacity.
Machine capacity: Batch time TB = 5.0 + 100(9/60) = 20 hr/batch
In a 40 hr week, each machine produces 2 batches = 2(100) = 200 pc/wk
For 20 machines, Q = 20(200) = 4000 pc/wk
Setup worker capacity: With Tsu = 5.0 hr, in 40 hr, each setup worker can set up 40/5 = 8
setups/wk. With 4 setup workers, number of setups = 4(8) = 32 setups = 32 batches
Output is limited by setup worker capacity to Q = 32(100) = 3200 pc/wk
(b) Number of machines idle because of only 4 setup workers = (4000 – 3200)/4000
= 800/4000 = 0.20 = 20% of the 20 machines = 0.20(20) = 4 machines with no work.
In addition, with 4 setup workers doing setups, there will be 4 machines idle due to setups.
Thus, the total number of idle machines = 4 + 4 = 8 machines.
Batch Processing and Economic Order Quantities
3.8 The annual demand for a certain item = 22,500 pc/yr. One unit of the product costs $35.00,
and the holding cost rate = 15%/yr. Setup time to produce a batch = 3.25 hr. The cost of
6
Work Systems and the Methods, Measurement, and Management of Work
by Mikell P. Groover. ISBN 0-13-140650-7.
© 2007 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
Solutions Manual: Ch03-Flow & Batch-s
equipment downtime during setup plus associated labor = $200/hr. Determine the economic
order quantity and the total inventory cost for this case.
Solution: (a) Csu = 200(3.25) = $650, Ch = 0.15(35) = $5.25
2( 22 ,500) ( 650)
EOQ = = 2360 pc
5.25
(b) TIC = (2360/2)(5.25) + (22,500/2360)(650) = 6195 + 6197 = $12,392
3.9 A stamping plant supplies sheet metal parts to a final assembly plant in the automotive
industry. Annual demand for a typical part = 150,000 pc. Average cost per piece = $20;
holding cost = 25%; changeover (setup) time for the presses = 5 hours; and cost of
downtime for changing over a press = $200/hr. Compute the economic batch size and the
total annual inventory cost for the data.
Solution: (a) Csu = 200(5) = $1000, Ch = 0.25(20) = $5.00
2( 150 ,000) ( 1000)
EOQ = = 7746 pc
5.00
(b) TIC = (7746 /2)(5.00) + (150,000/7746)(1,000) = 19,365 + 19,365 = $38,730
3.10 Demand for a certain product is 25,000 units/yr. Unit cost = $10.00. Holding cost rate =
30%/yr. Changeover (setup) time between products = 10.0 hr, and downtime cost during
changeover = $150/hr. Determine (a) economic order quantity, (b) total inventory costs, and
(c) total inventory cost per year as a proportion of total production costs.
2( 25,000 )( 150 x10 )
Solution: (a) EOQ = = 25,000 ,000 = 5000 pc
( 0.30 x10 )
7
Work Systems and the Methods, Measurement, and Management of Work
by Mikell P. Groover. ISBN 0-13-140650-7.
© 2007 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
Solutions Manual: Ch03-Flow & Batch-s
8
Work Systems and the Methods, Measurement, and Management of Work
by Mikell P. Groover. ISBN 0-13-140650-7.
© 2007 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
Solutions Manual: Ch03-Flow & Batch-s
made in batches of 1000 units for shipment each month to the wholesale distributor. (a)
Determine the total annual inventory cost for this product in batch sizes of 1000 units. (b)
Determine the economic batch quantity for this product. (c) How often would shipments be
made using this EOQ? (d) How much would the company save in annual inventory costs,
if it produced batches equal to the EOQ rather than 1000 units?
Solution: (a) Csu = 500(6.0) = $3000
7.00( 1000) ( 3000) ( 12 ,000)
At Q = 1000, TIC = + = 3500 + 36,000 = $39,500/yr
2 1000
2( 12 ,000) ( 3000)
(b) EOQ = = 10 ,285 ,714 = 3207 pc
7.00
(c) Using this EOQ, number of batches per year = 12,000/3207 = 3.74
Cycle time per batch = 12/3.74 = 3.207 mo
7.00( 3207) 3000( 12 ,000)
(d) At EOQ = 3,207, TIC = + = 11,225.50 + 11,225.44
2 3207
= $22,450.94/yr
The savings would be 39,500 – 22,451 = $17,049
Fraction Defect Rate
3.16 A starting batch of 5000 work units is processed through 8 sequential operations, each of
which has a fraction defect rate of 3%. (a) How many good parts and (b) defects are in the
final batch, and (c) what is the yield of the operation sequence?
Solution: (a) Qf = 5000(1 – 0.03)8 = 5,000(0.97)8 = 5,000(0.7837) = 3919 pc
(b) Df = 5000(1 – 0.7838) = 1081 defects
(c) Y = 0.7837 = 78.37%
3.17 A starting batch of 10,000 parts is processed through 6 sequential operations. Operations 1
and 2 each have a fraction defect rate of 4%, operations 3, 4, and 5 each have a fraction
defect rate of 6%, and operation 6 has a fraction defect rate of 10%. (a) How many good
parts and (b) defects are in the final batch, and (c) what is the yield of the operation
sequence?
Solution: (a) Qf = 10,000(1 – 0.04)2(1 – 0.06)3(1 – 0.10)
= 10,000(0.9216)(0.8306)(0.90) = 6889 pc
(b) Df = 10,000 – 6889 = 3111 defects
(c) Y = 0.6889 = 68.9%
3.18 A total of 1000 good units must be produced by a sequence of 10 operations, each of
which has fraction defect rate of 6%. (a) How many units must be in the starting batch in
order to produce this required quantity? (b) What is the yield of the operation sequence?
Solution: (a) Qf = 1000 = Qo(1 – 0.06)10 = Qo(0.94)10 = Qo(0.5386)
Qo = 1000/0.5386 = 1857 pc
(b) Y = 0.5386 = 53.9%
9
Work Systems and the Methods, Measurement, and Management of Work
by Mikell P. Groover. ISBN 0-13-140650-7.
© 2007 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
Solutions Manual: Ch03-Flow & Batch-s
3.19 A starting batch of 20,000 work units is processed through 7 sequential operations.
Operations 1, 2, and 3 each have a fraction defect rate of 5%, operations 4, 5, and 6 each
have a fraction defect rate of 4%, and the fraction defect rate of operation 7 is unknown. If
a final batch contains a total of 5,328 defects, determine the fraction defect rate of
operation 7.
Solution: Qf = 20,000 – 5328 = 14,672 pc
Y = 14,672/20,000 = 0.7336 = (1 – 0.05)3(1 – 0.04)3(1 – q7)
0.7336 = (0.8574)(0.8847)(1 – q7) = (0.75855)(1 – q7)
(1 – q7) = 0.7336/0.75855 = 0.9671
q7 = 1 – 0.9671 = 0.0329
3.20 Three sequential operations are required for a certain automotive component. Operation 1
has a defect rate = 4%. Operation 2 has a defect rate = 5%. Operation 3 has a defect rate =
10%. Operations 2 and 3 can be performed on units that are already defective. If 25,000
starting parts are processed through the sequence, (a) how many units are expected to be
defect-free, (b) how many units are expected to have exactly one defect, and (c) how many
units are expected to have all three defects?
Solution: (a) Number of defect-free units = 25,000(1 – 0.04)(1 – 0.05)(1 – 0.10)
= 25,000(0.96)(0.95)(0.90) = 25,000(0.8208) = 20,520 pc
(b) Number of units with one defect
D1 = 25,000(0.04)(1 – 0.05)(1 – 0.10) = 855 pc
D2 = 25,000(1 – 0.04)(0.05)(1 – 0.10) = 1080 pc
D3 = 25,000(1 – 0.04)(1 – 0.05)(0.10) = 2280 pc
D1 + D2 + D3 = 4215 pc
(c) Number of units with all three defects D123 = 25,000(0.04)(0.05)(0.10) = 5 pc
3.21 Solve Problem 3.3 except that there is a 10% scrap rate in printing (operation 3).
Solution: Operation 1: cutting: Batch time TB = 25 + 4000(0.03) = 145 min
Production rate Rp = 4000/145 = 27.58 pc/min = 1655.2 pc/hr
Operation 2: indenting: TB = 30 + 2000(2.5/60) = 113.33 min
Rp = 2000/113.33 = 17.65 pc/min = 1058.8 pc/hr
Operation 3: printing: TB = 40 + 2000/30 = 106.67 min
Although the batch time is less than for operation 2, operation 3 is limited by the slower
input rate from operation 2. Thus, Rp = 1058.8(1 – 0.10) = 952.9 pc/hr
Weekly plant production rate Rp = 40(952.9) = 38,117 pc/wk
3.22 A starting batch of 10,000 workparts are processed through three sequential operations: 1
then 2 then 3. Operation 1 sometimes produces parts with defect type 1 at a rate = 5%.
Operation 2 sometimes produces parts with defect type 2 at a rate = 8%. And operation 3
sometimes produces parts with defect type 3 at a rate = 10%. The defects occur randomly. If
all 10,000 parts are processed through all three operations, (a) how many are expected to be
defect free, (b) how many are expected to have all three defects, and (c) how many are
expected to have exactly one defect?
Solution: (a) Number of defect-free units = 10,000(1 – 0.05)(1 – 0.08)(1 – 0.10)
10
Work Systems and the Methods, Measurement, and Management of Work
by Mikell P. Groover. ISBN 0-13-140650-7.
© 2007 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
Solutions Manual: Ch03-Flow & Batch-s
11
Work Systems and the Methods, Measurement, and Management of Work
by Mikell P. Groover. ISBN 0-13-140650-7.
© 2007 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
Solutions Manual: Ch03-Flow & Batch-s
q = 0.05 q = 0.15
Q6= 100,000
5 6
q = 0.13 q = 0.08
Qo (B)
3 4
q = 0.10 q = 0.20
Q6 = Q5(1 – 0.08), Q5 = 100,000/(0.92) = 108,696 pc
With q5 = 0.13, input to Q5 = 108,696/(1 – 0.13) = 124,938 pc
Starting quantity Qo(A) = Qo(B) = 124,938/{(1-0.05)(1-0.15)(1-0.10)(1-0.20)}
= 124,938/0.5814 = 214,891 pc of A and 214,891 pc of B
3.25 Two subassemblies, A and B, are processed separately, each requiring two finishing
operations. A is routed through operations 1 and 2, and B is routed through operations 3 and
4. The two subassemblies are then joined in an assembly operation (operation 5). The five
operations have the following fraction defect rates: q1 = 0.03, q2 = 0.08, q3 = 0.05, q4 = 0.09,
q5 = 0.01. If the desired final quantity of completed assemblies is 10,000 units, how many
starting units of A and B will be required? There is no inspection or separation of defective
units until after the final operation, so defective units and good units are processed together
through all processing and assembly steps.
Solution: Required: output of Q5 = 10,000 pc
Qo (A)
1 2
q = 0.03 q = 0.08
Q5 = 10,000
5
q = 0.01
Qo (B)
3 4
q = 0.05 q = 0.09
With q5 = 0.01, input to Q5 = 10,000/(1 – 0.01) = 10,101 pc
Starting quantity Qo(A) = Qo(B) = 10,101/{(1-0.03)(1-0.08)(1-0.05)(1-0.09)}
= 10,101/0.7715 = 13,093 pc of A and 13,093 pc of B
Work Cells and Worker Teams
3.26 For Problem 3.1, (a) use the Hollier algorithm to determine the most logical in-line
sequence of workstations in the work system, and (b) compute the percentage of in-
sequence moves, backflow moves, and by-passing moves for the sequence.
Solution: (a) Hollier Method
From\To 1 2 3 4 “From” sums From/To ratio
12
Work Systems and the Methods, Measurement, and Management of Work
by Mikell P. Groover. ISBN 0-13-140650-7.
© 2007 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
Solutions Manual: Ch03-Flow & Batch-s
70 100
100 70
2 1 3 4
65
155
15 80
2 3 1 4 5
25 50
25 50
13
Work Systems and the Methods, Measurement, and Management of Work
by Mikell P. Groover. ISBN 0-13-140650-7.
© 2007 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
Solutions Manual: Ch03-Flow & Batch-s
3.28 Four workstations (1, 2, 3, and 4) used to produce a family of similar parts are to be
arranged into an in-line layout. The daily flow of parts between workstations is as follows:
10 parts from stations 1 to 2, 40 parts from stations 1 to 4, 50 parts from stations 3 to 1, 20
parts from stations 3 to 4, and 50 parts from stations 4 to 2. (a) Use the Hollier algorithm
described to determine the most logical sequence of stations in the work system. (b) Draw
the network diagram for the system. (c) Compute the percentage of in-sequence moves, by-
passing moves, and backflow moves for the sequence.
Solution: (a) Hollier Method
From\To 1 2 3 4 “From” sums From/To ratio
1 10 40 50 1.0
2 0 0
3 50 20 70
4 50 50 0.83
“To” sums 50 60 0 60 170
Arranging operations in descending order of From/To ratio, we have the following
sequence: 3 – 1 – 4 – 2
(b) Network diagram
20 10
3 50 1 40 4 50 2
14
Work Systems and the Methods, Measurement, and Management of Work
by Mikell P. Groover. ISBN 0-13-140650-7.
© 2007 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.
Solutions Manual: Ch03-Flow & Batch-s
20 60 35
4 3 2 1
15
10
30 20
25 35
1 5 3 4 2
from stations 1 to 4, 60 parts from 3 to 2, 15 parts from stations 2 to 5, and 30 parts from
stations 4 to 2. (a) Use the Hollier algorithm described to determine the most logical
sequence of stations in the work system. (b) Draw the network diagram for the system. (c)
Compute the percentage of in-sequence moves, by-passing moves, and backflow moves for
the sequence.
Solution: (a) Hollier Method
From\To 1 2 3 4 5 “From” sums From/To ratio
1 25 25 1.25
2 15 15 0.115
3 20 60 80 2.29
4 30 30 1.2
5 40 35 75 5.0
“To” sums 20 130 35 25 15 225
Arranging operations in descending order of From/To ratio, we have the following
sequence: 5 – 3 – 1 – 4 – 2
(b) Network diagram.
40
60
35 20 25 30
5 3 1 4 2
15
w2 = 45/0.9 = 50
w = 50 = 7.07 rounded down to 7 workers
Check: Try w = 7 workers: Tc = 45/7 + 0.9(7) = 12.73 min
Rp = 60/12.73 = 4.71 units/hr
Try w = 8 workers: Tc = 45/8 + 0.9(8) = 12.83 min
Rp = 60/12.83 = 4.68 units/hr
Use a work team of 7 workers to maximize production rate.
17
Work Systems and the Methods, Measurement, and Management of Work
by Mikell P. Groover. ISBN 0-13-140650-7.
© 2007 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved.