Precommissioning Activities Reinstatement Checklist

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 1

Reinstatement Check list

STATE COMPANY
FOR OIL PROJECT PRECOMMISSIONING ACTIVITIES

REINSTATEMENT CHECKLIST

Unit No. System No.

Sub-system No. Package No.

Task No.
NO Check Point COMMENTS

1 Draining and air blowing of line is successfully completed and accepted YES □ NO □ N/A □

All the temporary items, blinds, supports and spools installed for the purpose of
2 YES □ NO □ N/A □
testing is removed.
All the flange joints which have been opened after test are fitted with new
3 YES □ NO □ N/A □
permanent service gasket and bolts.

4 Vents and drain valves closed after draining, and provided end cap or blind flange. YES □ NO □ N/A □

5 Wherever applicable vent / drain caps are seal welded and required NDE is done. YES □ NO □ N/A □

All the process blinds, spades and spectacle blinds are correctly installed as
6 YES □ NO □ N/A □
indicated in P&ID.
All the valves, Relief valves, check valves, orifice plate are installed and functioning
7 YES □ NO □ N/A □
properly.
Wherever required extended spindles, chain wheels and locking devices installed
8 YES □ NO □ N/A □
for vales, and working properly.
All the inline instruments, equipments, gauges and steam tracing / electric tracing
9 YES □ NO □ N/A □
are installed.
Flow direction correct for strainers, traps, orifice plate, globe valves, control valves,
10 YES □ NO □ N/A □
check valves etc..

11 Welding and NDE of Tie-in joints are completed and accepted. YES □ NO □ N/A □

Provided all permanent pipe supports, anchors and guides. Cold setting done for
12 YES □ NO □ N/A □
Spring support.
Painting/coating/insulation of line, including weld joints and damaged area is
13 YES □ NO □ N/A □
completed and accepted.

14 Check for proper slope where required. YES □ NO □ N/A □

Remarks

CONSTRUCTION HDGSK JV QC EMPLOYER