Daily Dredging Report
Daily Dredging Report
DREDGER DAILY REPORT
Location: Designation #
Project: Master
INTRO.
Client: Chief Mate
Proj. Start Date: Project Calendar Day: 2nd Officer
Weather: Chief Engineer
2nd Engineer
Shift Shift dur. 3rd Engineer
CREW
DAILY ACTIVITY DESC.
TOTAL: 0
Visitor 1, Eng Rep.
Grand
Σ PRODUCTION
VISITORS
Visitor 3, Owner Rep.
Est. Volume Dredged Visitor 4, Ship Mng.
Est. TDS Visitor 5, Other
Linear Meters TOTAL: 0
Reclamation GRAND TOTAL: 0
CODES
Time
Chainage / Location 1 DREDGING
Start Finish Code Oper. Idle 2 PIPELINE HANDLING
3 PIPELINE FLUSHING/CLEARANCE
4 CUTTER / SUCTION HEAD CLEANING
5 WAITING FOR ATTENDANT PLANT
6 TO/FROM ANCHORAGE
7 WORK LOCATION CHANGE
DAILY LOG
8 LOSS DUE TO NATURAL MATERIAL
9 LOSS DUE TO UNNATURAL MATERIAL
10 THIRD PARTY WORKS
11 MINOR OPERATING REPAIRS
12 TOW PREPARATION
13 MARINE TRAFFIC STOPPAGES
14 BREAKDOWN
15 SUNDAY/HOLIDAY
16 END OF SHIFT
0 0 17 MISCELLANEOUS
CONSUMPTION & L
NOTES
m3 m3 m3 m3
MGO
OIL
FW