Capital-Budgeting-Practice Questions
Capital-Budgeting-Practice Questions
Question 1
Messer’s Ltd is considering two potential projects that are Turbine and Wind
flow. The forecasted after-tax cash flows are as below:
i) Payback period
ii) Net present value
iii) Which project should be chosen and why.
Question 2
Oman LLC is considering two potential projects that are Real Corp and Next
Corp. The cost of capital is 8%. The annual cash flows are as below:
Year Real Next
Corp Corp
(OMR) (OMR)
0 (90,000) (90,000)
1 25000 15000
2 25000 20000
3 25000 35000
4 25000 30000
5 25000 35000
i. Payback period
Year 0 1 2 3 4
Cash inflows
Machine X (20000) 8000 6000 9000 4450
Machine Y (20000) 6240 8000 4000 7000
Question 4
Which project will be selected under NPV and IRR? Cost of capital is 12%.
Question 5
Al Taqdeer LLC is considering two mutually exclusive projects Tango and Silver
Star. Project Tango costs OMR 30000 and Project Silver Star OMR 36000. You
have been given below the net present value probability distribution for each
project:
ii. Compute the risk attached to each project, i.e., Standard Deviation of each
probability distribution.
i) Compute the expected net present value of Projects Foster and Edison.
Question 7
Mr. A is considering two mutually exclusive investment projects, from following
information select the Project on the basis of NPV and the risk attached to each
project.
Project I Project II
RO 15000 RO 15000