Protection of MV Closed-Loop Distribution Networks
Protection of MV Closed-Loop Distribution Networks
fully edited. Content may change prior to final publication. Citation information: DOI
10.1109/ACCESS.2019.2952934, IEEE Access
Date of publication xxxx 00, 0000, date of current version xxxx 00, 0000.
Digital Object Identifier 00.0000/ACCESS.2019.DOI
Protection of MV Closed-Loop
Distribution Networks with Bi-Directional
Overcurrent Relays and GOOSE
Communications
BOŠTJAN POLAJŽER1 , (Member, IEEE), MATEJ PINTARIČ1 , MIRAN ROŠER2 , and
GORAZD ŠTUMBERGER.1 , (Member, IEEE)
1 Faculty of Electrical Engineering and Computer Science, University of Maribor, Koroška 46, 2000 Maribor, Slovenia
2 Elektro Celje, d.d., Vrunčeva 2a, 3000 Celje, Slovenia
Corresponding author: Boštjan Polajžer (e-mail: [email protected]).
This work was supported by ARRS under projects: P2-0115, L2-5489, L2-7556. A part of the smart-grid project is financed by a
partnership between the Japanese agency NEDO and the Slovenian transmission system operator ELES.
ABSTRACT This paper proposes measures to improve the protection of MV distribution networks
operating with feeders in a closed-loop arrangement. Bi-directional overcurrent relays (OCRs) are discussed,
the selectivity of which is achieved through the timing coordination of their operation. The classic approach
is formulated as a minimization of the operating times of all the OCRs. The proposed approach enhances the
selectivity by considering the maximum operating time of substation OCRs and the unwanted trips of in-
loop OCRs. Moreover, the sensitivity is also increased by introducing an objective function that minimizes
the pickup-current settings of all the OCRs together with their operating times. Furthermore, to fulfill
the demanding requirements for operating times, variable penalties are introduced. Thus, the optimization
procedure is forced towards the region with viable solutions for the optimization problem. Two variants of
self-adaptive differential evolution have been used that both show better convergence when compared to the
classic differential evolution. Moreover, ten mutation strategies were tested, where “rand/1/bin” showed the
best results. A comparison with other methods for timing coordination shows that the proposed optimization
results in a comparable value for the OCRs’ operating times. In order to further reduce the operating times,
GOOSE communications between the OCRs are adopted. The proposed measures for improved protection
operation are fully confirmed through dynamic simulations of the faults in the discussed 20-kV network.
Moreover, the proposed protection design is already implemented and permanently operates in a 20-kV
network with more than 5000 customers, whereas the field results show selective and reliable protection
operation.
VOLUME 4, 2016 1
This work is licensed under a Creative Commons Attribution 4.0 License. For more information, see https://creativecommons.org/licenses/by/4.0/.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI
10.1109/ACCESS.2019.2952934, IEEE Access
B. Polajžer et al.: Protection of MV Closed-Loop Distribution Networks with Bi-Directional Overcurrent Relays and GOOSE ...
This work is licensed under a Creative Commons Attribution 4.0 License. For more information, see https://creativecommons.org/licenses/by/4.0/.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI
10.1109/ACCESS.2019.2952934, IEEE Access
B. Polajžer et al.: Protection of MV Closed-Loop Distribution Networks with Bi-Directional Overcurrent Relays and GOOSE ...
This work is licensed under a Creative Commons Attribution 4.0 License. For more information, see https://creativecommons.org/licenses/by/4.0/.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI
10.1109/ACCESS.2019.2952934, IEEE Access
B. Polajžer et al.: Protection of MV Closed-Loop Distribution Networks with Bi-Directional Overcurrent Relays and GOOSE ...
This work is licensed under a Creative Commons Attribution 4.0 License. For more information, see https://creativecommons.org/licenses/by/4.0/.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI
10.1109/ACCESS.2019.2952934, IEEE Access
B. Polajžer et al.: Protection of MV Closed-Loop Distribution Networks with Bi-Directional Overcurrent Relays and GOOSE ...
and CR is a problem-dependent task. Therefore, self-adaptive mechanism. This allows, e.g., the OCR to deliver the infor-
differential evolution (SADE) has been used, where F and mation simultaneously to a predefined group of destination
CR are adapted as proposed in [29]. Note that when using a OCRs.
classic DE, then approximately one million iterations were In the given case the pick-up GOOSE messages will be
needed for the case study discussed in this paper, whereas sent between the RSCs and the substation OCRs. However,
when using SADE the number of iterations was considerably an instantaneous trip will be enabled only when the OCR
reduced. receives the message and when the condition given by a
logical equation is fulfilled. Thus, e.g., the instantaneous trip
2) Variable Penalties of R3 and R4 shown in Fig. 1 should be enabled only when
A very important part of the performed optimization is the they receive a pick-up message from each other, and when
penalties p in the objective function (4). Note that when using they do not receive a pick-up message from R7 . In this way
fixed penalties the optimization process was not converging the faults on the line between R3 and R4 can be cleared faster,
for the case study discussed in this paper. Therefore, the whereas for the faults on the side branch only R7 will operate
penalties were introduced in such a way that they force according to the set time-current characteristic.
the optimization procedure towards the region with viable
IV. METHODOLOGY FOR THE PARAMETERIZATION OF
solutions of the optimization problem. This means that the
OCRS
penalties are dependent on the difference between the actual
This section summarizes the proposed measures for improv-
values of the individual parameters, and their minimum- or
ing the OCRs’ operation in MV distribution networks. Thus,
maximum-allowed values, thus ensuring the convergence of
a methodology for the parameterization of OCRs is given by
the optimization procedure.
the following steps:
The penalties are calculated for ∆tr ≤ CTIr (typical CTI
value is within the range 100 to 300 ms), t ∗j,k ≥ 300 ms, Step 1:Relay points are determined that require bi-
TD j < TD j min , IP j < IP j min and IP j > IP j max . For all the afore- directional OCRs. In cases where larger DGs are
mentioned parameters (∆tr ,t ∗j,k , TD j , IP j ), the values for which connected, the short-circuit calculations are needed
V are bounded with the minimum Vmin and the maximum to check their impact on the current directions (R9
Vmax allowed values, the variable penalties pV are introduced in Fig. 1).
according to the pseudo code: Step 2:Short-circuit calculations are performed for Ph-Ph
faults at all the relay points, as well as at the ends of
if V < Vmin then
all the lines. For all the in-loop relays, short-circuit
pV = ((|Vmin −V | + 1)K1 )K2
calculations should be performed for two different
end if
states (Section III-B2).
if V > Vmax then
Step 3:Pickup-current limits are determined for all the
pV = ((|V −Vmax | + 1)K1 )K2
OCRs (Section II-C).
end if
Step 4:Pickup-current settings and time-dial settings are
where K1 = 10 and K2 = 4 are the constants, the values of determined through the minimization of the pro-
which were determined based on experiences. The values of posed objective function using the SADE algo-
all the penalties pV determined in this way for all relay pairs rithm and the mutation strategy “rand/1/bin” (Sec-
are summed up and added as a penalty p in (4). The described tions III-A and III-C).
procedure forces (4) to fulfill all the optimization bounds Step 5:Communications are applied according to the
before the actual operating times and pickup-current settings GOOSE model, where a release communication
are minimized. The authors are not aware of a publication scheme is adopted for all the in-loop OCRs (Sec-
where the proposed approach is applied to the operating-time tions II-E and III-D).
minimization of OCRs that provides the required selectivity The proposed timing coordination is validated for a three-
and sensitivity in a MV closed-loop distribution network. bus system through a comparison with the MINLP using
a standard branch-and-bound (SBB) and a seeker algo-
D. PEER-TO-PEER COMMUNICATIONS rithm [5], and through the comparison with the QCQP-
The IEC standard 61850 [22] enables peer-to-peer commu- based algorithm [6]. To make a clear comparison the same
nications between different devices. Protection applications assumptions and limits were used as in [5], [6], i.e., IP j and
require high-speed peer-to-peer-communications that should TD j were limited to the minimum values of 1.5 A (secondary)
guarantee the total transfer time below the order of a quarter and 100 ms, respectively, whereas the IEC standard inverse
of a cycle. GOOSE messages have the shortest maximum- characteristic was used. Furthermore, one-directional OCRs
allowed transfer time among all the IEC 61850 messages, were used, and thus the relay pairs were defined as in Fig. 4.
corresponding to the required 3 ms. They can be sent over Note that timing coordination with the protection relays of
TCP/IP or substation local area networks using high-speed the generators G1 , G2 and G3 was not considered. Moreover,
switched Ethernet. Furthermore, the exchange of GOOSE CTIr = 0.2 s was used when comparing the results with [5],
messages between devices is based on a publisher-subscriber whereas CTIr = 0.3 s was used when comparing the results
VOLUME 4, 2016 5
This work is licensed under a Creative Commons Attribution 4.0 License. For more information, see https://creativecommons.org/licenses/by/4.0/.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI
10.1109/ACCESS.2019.2952934, IEEE Access
B. Polajžer et al.: Protection of MV Closed-Loop Distribution Networks with Bi-Directional Overcurrent Relays and GOOSE ...
TABLE 1. Relay settings for the three-bus system – IEC Standard Inverse (A = 0.14, B = 0.02, C = 0).
feeder 2
feeder 3
feeder 1
R2 R4
G1 G2 loop 1 loop 2
R5 R6
G3
a) b) c)
Relay pairs (primary, back-up): (R1,R5)1,
(R2,R3)2, (R3,R6)3, (R4,R1)4, (R5,R4)5, (R6,R2)6 FIGURE 5. Discussed topologies of a 20-kV network: Loop 1 (a), Loop 2 (b),
and Radial (c), where RMU is a Ring Main Unit.
FIGURE 4. The three-bus system with relay pairs.
Source
with [6]. The objective function (4) was minimized, where RTR
α = 0.3, β = 0.7 and tEV = 0.3 s. The obtained settings of the 110/20 kV
OCRs are given in Table 1 together with the value of T . Note 31.5 MVA
that these settings cannot be applied. Therefore, the value of
T 0 is also given for the settings rounded to 10 mA (secondary) FL13
R8
FL10
R6
FL1
R1 FL
14
A. DISCUSSED NETWORK TOPOLOGIES DGs are micro solar power plants and are not considered
Fig. 5 shows three network topologies, i.e., Loop 1, Loop 2 because of their negligible contribution to the fault currents.
and Radial, that will be further discussed. The entire 20-kV Relay pairs, fault locations, as well as communication pairs
network is shown in Fig. 6. Only a small hydro-power plant are given in this section for all three network topologies.
with a synchronous generator (SG) is shown, whereas other
6 VOLUME 4, 2016
This work is licensed under a Creative Commons Attribution 4.0 License. For more information, see https://creativecommons.org/licenses/by/4.0/.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI
10.1109/ACCESS.2019.2952934, IEEE Access
B. Polajžer et al.: Protection of MV Closed-Loop Distribution Networks with Bi-Directional Overcurrent Relays and GOOSE ...
TABLE 2. Relay pairs (∗ denotes substation OCR) for all three network TABLE 4. Relays for all three network topologies with fault locations used for
topologies with fault locations used for timing coordination. the determination of the pickup-current limits.
2) Fault Locations
In order to perform the timing coordination of the OCRs, the 3) GOOSE-based Communications
fault locations were determined according to the rule given Table 5 shows the subscriptions of all the OCRs to the
in Section II-D. They are given in Table 2, together with the GOOSE messages sent by the other OCRs. The logical
relay pairs. Furthermore, in order to determine the maximum equations that should be fulfilled for starting an instantaneous
pickup-current limits, the fault locations were determined trip that is based on received pick-up GOOSE messages xi
according to the rule given in Section II-C. They are given and the local pick-up y j are also given. Pick-up GOOSE
in Table 4, where FLx,y denotes two possible fault locations, messages are sent between the neighboring in-loop OCRs,
i.e., FLx and FLy . In such cases only a fault location that while the OCRs on the side branches are also included to
results in a smaller current measured by the corresponding achieve selectivity, e.g., R1 is subscribed to the messages sent
OCR is considered. However, the considered current value by R20 and R9 . For the discussed case the instantaneous trip
should be larger than the maximum load current. of R1 is possible when receiving a pick-up message from R20
and not receiving it from R9 , which is denoted in Table 5 as
VOLUME 4, 2016 7
This work is licensed under a Creative Commons Attribution 4.0 License. For more information, see https://creativecommons.org/licenses/by/4.0/.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI
10.1109/ACCESS.2019.2952934, IEEE Access
B. Polajžer et al.: Protection of MV Closed-Loop Distribution Networks with Bi-Directional Overcurrent Relays and GOOSE ...
RB
B. MODELING a) neighboring DisCo b) cable
The model of the discussed 20-kV network and the FIGURE 7. Field testing on a section between relays R19 and R2 : test location
model of a bi-directional RSC were both built for MAT- (a) and a Ph-Ph fault (b).
LAB/Simulink/Simscape Power Systems. It should be
pointed out that they were verified through extensive labo-
simulation measurement
ratory and field testing. 1000
ISC [A]
500
1) Network Model
A 110-kV source was modeled as a constant impedance 0
1 2, 20 3, 19 4, 18 5, 17 6
with a maximum short-circuit capacity of 6.679 kA. Further- relay no.
more, the discussed 20-kV network incorporates π models
FIGURE 8. Measured and simulated rms values of short-circuit currents
of underground cables and overhead lines, as well as generic during a Ph-Ph test for relays in Loop 1, where bi-directional relays are
models of transformers and a SG. According to the measured denoted by two numbers.
load and generating profiles for a period of 15 months a max-
imum load was determined for all the MV/LV transformer
locations. Thus, a constant power-load model was incorpo- All the relays in the Loop 1 picked-up without operation
rated on the LV side of each corresponding transformer. The and recorded the time responses of the line currents. Note
developed 20-kV network model can be used for static short- that the directional criterion was not activated during the
circuit calculations as well as for dynamic simulations of the test. Furthermore, the distance between the test location and
relay operation. The step size for the dynamic simulations R19 is 0.6 km. Since the length of the section between R19
was set to 0.0625 ms, whereas a step size of 2.5 ms was used and R2 is 10.9 km, the fault location FL4 was assumed
for the calculation of the phasors. when comparing the field testing and simulation results. The
Field testing was performed to verify the discussed MV comparison of the measured and simulated rms values of the
network model. A Ph-Ph fault was generated in a controlled currents is shown in Fig. 8, where the simulated values agree
way, where special care was taken not to disconnect any cus- with the measured ones within a range of ±3%.
tomers. The fault was located near R19 , i.e., at the beginning
of a line that can be used to connect the discussed network 2) Bi-Directional RSC Model
to a network of the neighboring DisCo, as shown in Fig. 7a. A generic model of a switch gear was used with a specified
During normal operation this line is only connected from side time delay of 50 ms. Furthermore, a dynamic model of a bi-
A; however, it can be connected from both sides in cases of directional overcurrent function was built according to the
a total power loss in one of the DisCos. Note that an OCR specifications given by the manufacturer [36]. It is composed
is located on both sides of the line, i.e., RA and RB . During of the following units. The model of the input unit incorpo-
the test, the discussed line was connected only from side A. rates filtering and sampling. The line currents and voltages
No special equipment was needed to perform the test, except are filtered by low-pass, second-order Butterworth filters with
a cable used for the Ph-Ph connection, as shown in Fig. 7b. a cut-off frequency of 1.6 kHz, while the sampling frequency
Only the Loop-1 topology was tested, while the following is 3.2 kHz. Next, a discrete Fourier filtering is applied using
procedure was followed: a full-cycle data-window. The resulting phasors are refreshed
Step 1:All the in-loop relays were set only to pick-up every 2.5 ms. The model of the main unit describes the
without operation, whereas the relay RA was set to overcurrent function with IEC inverse-time pickup character-
pick-up and operate with no delay. istics and additional definite-time reset characteristics. Fur-
Step 2:Switch gear Q1 was closed first, then the closed thermore, a bi-directional functionality was modeled with a
poles were visually inspected. standard directional criterion, which is based on the angle
Step 3:Switch gear Q0 was closed next to generate a Ph-Ph between the current phasor and the line-voltage phasor. The
fault. model of the logic unit provides the pickup and trip signals.
Step 4:Relay RA operated, and Q0 was opened after ap- Moreover, a GOOSE model was used [23], where a transfer
proximately 60 ms. Note that none of the customers time of 5 ms was considered. Note, that the same dynamic
were disconnected. model was used for all the discussed relay locations.
8 VOLUME 4, 2016
This work is licensed under a Creative Commons Attribution 4.0 License. For more information, see https://creativecommons.org/licenses/by/4.0/.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI
10.1109/ACCESS.2019.2952934, IEEE Access
B. Polajžer et al.: Protection of MV Closed-Loop Distribution Networks with Bi-Directional Overcurrent Relays and GOOSE ...
TABLE 6. Minimum, mean and standard deviation (Std. Dev.) of best q values
Schneider controller for 50 independent runs – radial network topology.
ADVC3
Omicron CMC 256-6
SADE1 SADE2
Secondary current Strategy Min Mean Std. Dev. Min Mean Std. Dev.
injection test set best/1/exp 1.051 1.144 0.117 1.033 1.117 0.069
rand/1/exp 1.028 1.039 0.003 1.023 1.038 0.009
rand-to-best/1/exp 1.024 1.057 0.042 1.029 1.053 0.025
best/2/exp 1.028 1.053 0.026 1.025 1.052 0.019
rand/2/exp 1.036 1.048 0.018 1.054 1.139 0.035
best/1/bin 1.034 1.187 0.131 1.027 1.133 0.083
Secondary voltage
rand/1/bin 1.018 1.021 0.004 1.018 1.027 0.005
injection interface set rand-to-best/1/bin 1.027 1.059 0.084 1.021 1.056 0.016
best/2/bin 1.020 1.052 0.025 1.027 1.053 0.032
FIGURE 9. Laboratory set-up for secondary testing of a protection unit rand/2/bin 1.042 1.074 0.026 1.105 1.151 0.023
(Schneider controller ADVC3).
101
SADE1, rand/1/exp
q (mean best)
SADE1, rand/1/bin
The developed model of a bi-directional overcurrent pro- SADE2, rand/1/exp
tection was verified with extensive laboratory testing using SADE2, rand/1/bin
3000 radial
approximately 25 ms. However, the obtained time delay of
the tested model and the actual unit were different within 2000
VI. RESULTS FIGURE 11. Maximum-load currents and minimum short-circuit currents for all
three network topologies.
A. BEST OBJECTIVE FUNCTION VALUE AND
CONVERGENCE
SADE was extensively tested for the case with the radial B. PICKUP-CURRENT LIMITS AND OCR SETTINGS
network topology. Self-adaptation was applied in two differ- The obtained maximum-load currents I j,L max and the mini-
ent ways, i.e., for the entire population, as well as for each mum short-circuit currents I j,SC min are shown in Fig. 11. Note
population member. This is denoted as SADE1 and SADE2, that equal values of I j,L max were used for all three network
respectively. Furthermore, ten different mutation strategies topologies. The values I j,SC min were determined according to
were considered. Table 6 shows the minimum, mean and the fault locations given in Table 4 and show considerable
standard deviations of the best values of the objective func- impacts of the network topology. Pickup-current limits were
tion q for 50 independent runs, where α = 0.3, β = 0.7 determined using (2), where eCT% = 10% and KSC =KL = 1.1
and tEV = 0.3 s. The convergence was also tested for the were considered. Furthermore, at several relays the value of
mutation strategies “rand/1/bin” and “rand/1/exp”. Fig. 10 I j,L max is very small. In such cases IP j min was set to the
shows that for approximately the first 135 iterations the estimated value of 50 A, which corresponds to a possible
obtained values were penalized, whereas the minimum value increase in demand over time.
was reached before 2500 iterations. The typical computation The CTIs for the relay pairs between individual RSCs were
time for a single run of our implementation in Matlab on 100 ms, while the CTIs for the relay pairs with substation re-
a 3-GHz Intel Core i5-7400 with 8 GB of RAM was less lays R1 , R6 and R8 were 150 ms. Furthermore, the minimum
than 2 min. Furthermore, the results were also qualitatively time-dial setting was TD j min = 10 ms. Minimization of the
the same for other network topologies, as well as when objective function (4), where α = 0.3, β = 0.7, tEV = 0.3 s,
testing the objective function T . Based on the obtained results was performed using SADE1 and “rand/1/bin”. The results
given in Table 6 and Fig. 10, the SADE1 variant and the are given in Table 7, where the obtained time-dial settings
“rand/1/bin” strategy were found to be the most suitable for were rounded to 10 ms, whereas the obtained pickup-current
the discussed optimization problem. settings were rounded to 1 A.
VOLUME 4, 2016 9
This work is licensed under a Creative Commons Attribution 4.0 License. For more information, see https://creativecommons.org/licenses/by/4.0/.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI
10.1109/ACCESS.2019.2952934, IEEE Access
B. Polajžer et al.: Protection of MV Closed-Loop Distribution Networks with Bi-Directional Overcurrent Relays and GOOSE ...
tr [s]
IP j [A] TD j [ms] IP j [A] TD j [ms] IP j [A] TD j [ms] CTI CTI*
0.2
R1 676 50 493 110 460 80
R2 254 90 98 50 120 60 0.1
R3 217 40 – – – –
0
R4 105 100 – – – – 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
R5 118 40 – – – – relay pair no.
R6 390 60 204 80 286 70
R7 74 60 136 60 95 130 0.5 primary
R8 555 30 291 70 353 70
tr [s]
0.2 CTI CTI*
TABLE 8. Operating times of substation OCRs for a fault at the beginning of a
feeder.
0.1
Loop 1 Loop 2 Radial
t ∗j,k [ms] t ∗j,k [ms] t ∗j,k [ms] 0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
R1 FL1 70 80 51
relay pair no.
R6 FL10 28 10 18 primary
R8 FL13 28 18 26 0.3 back-up
t(p,r), t(b,r) [s]
0.2
C. SELECTIVITY TESTING AND OPERATING TIMES
0.1
1) Theoretical Calculations
The operating times of the primary and back-up OCRs, 0
i.e., t(p,r) and t(b,r) , were calculated using (1) for the fault 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
relay pair no.
locations given in Table 2, while using the optimum settings.
The results are shown in Figs. 12–14, together with the ∆tr FIGURE 13. ∆tr values and operating times of primary and back-up OCRs –
Loop-2 topology, where (•)∗ denotes the relay pairs with substation OCRs.
values. Note that the results denoted as (•)∗ are given for
relay pairs with substation OCRs (R1 , R6 and R8 ). Selectivity
is achieved for all the relay pairs since ∆tr > CTIr . Moreover, 0.4
selectivity is also assured for the substation OCRs, since 0.3
tr [s]
0.1
2) Dynamic Simulations
0
The models proposed in Section V-B were used, while 1 2 3 4 5 6 7 8 9 10 11 12
using the optimum settings given in Table 7. The Ph-Ph relay pair no.
faults were simulated for all possible fault locations. The
0.4 primary
simulations were performed for the RSCs with and without
t(p,r), t(b,r) [s]
back-up
the GOOSE communications. The resulting clearing times 0.3
This work is licensed under a Creative Commons Attribution 4.0 License. For more information, see https://creativecommons.org/licenses/by/4.0/.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI
10.1109/ACCESS.2019.2952934, IEEE Access
B. Polajžer et al.: Protection of MV Closed-Loop Distribution Networks with Bi-Directional Overcurrent Relays and GOOSE ...
TABLE 9. Results of dynamic simulations for all the fault locations and all the topologies, where the clearing times include the operation of the RSCs (relay and
switch gear) and communication transfer times.
up. The same situation was observed for the fault at FL10 operation of the RSCs is due to the closed-loop operation and
and the operation of R5 and R6 . Obviously, communications an appropriate protection design.
could not be activated for the discussed fault locations FL1
and FL10 , which was confirmed with the obtained results. VII. CONCLUSION
A similar result was also noticed for the Loop-2 topology This paper proposes measures that improve the operation
for the fault locations FL10 and FL13 . Based on the obtained of OCRs in MV closed-loop distribution networks. The se-
results it can be concluded that the operating times of the lectivity of the substation OCRs is achieved by considering
communication-assisted RSCs were significantly reduced. the required maximum operating time (300 ms), while the
unwanted trips of the in-loop OCRs are avoided by a simple
D. IMPLEMENTATION procedure for short-circuit calculations. The proposed timing
The proposed protection design is already implemented in a coordination of the OCRs’ operation minimizes the operating
20-kV network of DisCo Elektro Celje using compact RSCs. times and increases the sensitivity of all the relays, i.e., RSCs
Even though the GOOSE communications are not yet estab- and substation OCRs. Preliminary results showed that, when
lished, the field results are promising. During two recent Ph- using the classic DE in combination with fixed penalties, the
Ph faults in the section between R3 and R18 (Loop 1) and one optimization process was not converging for the discussed
Ph-Ph fault in the end branch near R15 the protection operated case study. Therefore, variable penalties were introduced that
in a reliable and selective way. Fig. 15 shows photographs of force the optimization procedure towards the region with
the discussed Ph-Ph faults that were all on overhead lines due the viable solutions of the optimization problem. Further-
to falling trees. Note that before modernization, the discussed more, SADE was used, which showed considerably better
network operated in a radial arrangement of feeders, using convergence than the classic DE. Two variants of SADE
only the substation relays R1 , R6 and R8 . Consequently, were extensively tested together with ten mutation strategies.
these Ph-Ph faults would have resulted in an outage of 2124 Based on the obtained results the strategy “rand/1/bin” was
customers. However, according to the data obtained from chosen together with a SADE variant that is based on the self-
DisCo Elektro Celje, only 49 customers were out of power adaptation of the control parameters for the entire population.
during faults in the section between R3 and R18 , while for The resulting operating times of the OCRs are comparable
a fault in the end branch near R15 only 26 customers were with the operating times determined using methods known in
disconnected. It should be emphasized, that the resulting the literature. Moreover, adopting the GOOSE communica-
VOLUME 4, 2016 11
This work is licensed under a Creative Commons Attribution 4.0 License. For more information, see https://creativecommons.org/licenses/by/4.0/.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI
10.1109/ACCESS.2019.2952934, IEEE Access
B. Polajžer et al.: Protection of MV Closed-Loop Distribution Networks with Bi-Directional Overcurrent Relays and GOOSE ...
tions reduces the operating times, which was fully confirmed [11] F. B. Bottura, W. M.S. Bernardes, M. Oleskovicz, et al., “Setting di-
through the dynamic simulations of the Ph-Ph faults in the rectional overcurrent protection parameters using hybrid GA optimizer,”
Elect. Power Syst. Res., vol. 143, pp. 400–408, Feb. 2017.
discussed 20-kV network. The discussed protection design [12] A. A. Kida, and L. A. Gallego, “A high-performance hybrid algorithm to
with compact RSCs is already implemented and operates solve the optimal coordination of overcurrent relays in radial distribution
permanently in a 20-kV network of DisCo Elektro Celje networks considering several curve shapes,” Elect. Power Syst. Res.,
vol. 140, pp. 464–472, Nov. 2016.
that supplies more than 5000 customers. Field results are [13] D. Saha, A. Datta, and P. Das, “Optimal coordination of directional
promising; even though the GOOSE communications are not overcurrent relays in power systems using symbiotic organism search
yet established, the RSCs have selectively operated during optimisation technique,” IET Gener., Transm., Distrib., vol. 10, no. 11,
pp. 2681–2688, Aug. 2016.
recent Ph-Ph faults. Thus, we can expect that the SAIDI
[14] M. Singh, B. Panigrahi, and A. Abhyankar, “Optimal coordination of
and SAIFI will be improved in the future. There are natural directional over-current relays using teaching learning-based optimization
extensions for the work presented in this paper, especially (TLBO) algorithm,” Int. J. Elect. Power Energy Syst. Res., vol. 50, pp. 33–
41, Sep. 2013.
the adaptation of the proposed measures for the improved
[15] H. H. Zeineldin, E. F. El-Saadany, and M. M. A. Salama, “Optimal coordi-
operation of ground fault-protection relays in MV closed- nation of overcurrent relays using a modified particle swarm optimization,”
loop distribution networks. Elect. Power Syst. Res., vol. 76, no. 11, pp. 988–995, Jul. 2006.
[16] M. Y. Shih, C. A. C. Salazar, and A. C. Enriquez, “Adaptive directional
overcurrent relay coordination using ant colony optimisation,” IET Gener.
REFERENCES Transm. Distrib., vol. 9, no. 4, pp. 2040–2049, Nov. 2015.
[1] D. P. Le, D. M. Bui, C. C. Ngo, et al., “FLISR approach for smart [17] A. Wadood, T. Khurshaid, S. G. Farkoush, et al., “Nature-inspired whale
distribution networks using E-Terra software–A case study,” Energies, optimization algorithm for optimal coordination of directional overcurrent
vol. 11, no. 12, art. no. 3333, Dec. 2018. relays in power systems,” Energies, vol. 12, no. 12, art. no. 229, Jun. 2019.
[2] Definitions for Power Switchgear, IEEE Standard C37.100-1992 (R2001), [18] H. H. Zeineldin, H. M. Sharaf, D. K. Ibrahim, et al., “Optimal protection
2001. coordination for meshed distribution systems with DG using dual setting
[3] J. Sykes et al., “Reliability fundamentals of system protection,” NERC, directional over-current relays,” IEEE Trans. Smart Grid, vol. 6, no. 1,
Princeton, NJ, USA, Report for the Planning Committee, 2010. pp. 115–123, Jan. 2015.
[4] A. S. Noghabi, H. R. Mashhadi, and J. Sadeh, “Optimal coordination [19] L. Huchel, and H. H. Zeineldin, “Planning the coordination of directional
of directional overcurrent relays considering different network topologies overcurrent relays for distribution systems considering DG,” IEEE Trans.
using interval linear programming,” IEEE Trans. Power Del., vol. 25, no. 3, Smart Grid, vol. 7, no. 3, pp. 1642–1649, May 2016.
pp. 1348–1354, Jul. 2010. [20] K. Pereira, B. R. Pereira, J. Contreras, et al., “A multiobjective optimiza-
[5] T. Amraee, “Coordination of directional overcurrent relays using seeker tion technique to develop protection systems of distribution networks with
algorithm,” IEEE Trans. Power Del., vol. 27, no. 3, pp. 1415–1422, Jul. distributed generation,” IEEE Trans. Power Syst., vol. 33, no. 6, pp. 7064–
2012. 7075, Nov. 2018.
[6] V. A. Papaspiliotopoulos, G. N. Korres, and N. G. Maratos, “A novel [21] S. Katyara, L. Staszewski, and Z. Leonowicz, “Protection coordination of
quadratically constrained quadratic programming method for optimal co- properly sized and placed distributed generations-methods, applications
ordination of directional overcurrent relays,” IEEE Trans. Power Del., and future scope,” Energies, vol. 11, no. 10, art. no. 2627, Oct. 2018.
vol. 32, no. 1, pp. 3–10, Feb. 2017. [22] Communication Networks and Systems for Power Utility Automation, 2.0,
[7] D. L. A. Negrão, and J. C. M. Vieira, “The local fit method for coordinating Standard IEC 61850, 2013.
directional overcurrent relays,” IEEE Trans. Power Del., vol. 31, no. 4, [23] A. Apostolov, “To GOOSE or not to GOOSE? - that is the question,” in
pp. 1464–1472, Aug. 2016. 68th Annual Conference for Protective Relay Engineers, College Stn, TX,
[8] M. Y. Shih, A. C. Enríquez, T.-Y. Hsiao, et al., “Enhanced differential USA, 2015, pp. 583–596.
evolution algorithm for coordination of directional overcurrent relays,” [24] Y. Liu, H. Gao, W. Gao, et al., “Development of a substation-area backup
Elect. Power Syst. Res., vol. 143, pp. 365–375, Feb. 2017. protective relay for smart substation,” IEEE Trans. Smart Grid, vol. 8,
[9] M. H. Costa, R. R. Saldanha, M. G. Ravetti, et al., “Robust coordination of no. 6, pp. 2544–2553, Nov. 2017.
directional overcurrent relays using a matheuristic algorithm,” IET Gener., [25] S. Kumar, N. Das, and S. Islam, “High voltage substation automation
Transm., Distrib., vol. 11, no. 2, pp. 464–474, Jan. 2017. and protection system based on IEC 61850,” in AUPEC, Auckland, New
[10] F. Razavi, H. A. Abyaneh, M. Al-Dabbagh, et al., “A new comprehensive Zealand, 2018, pp. 1–6.
genetic algorithm method for optimal overcurrent relays coordination,” [26] M. A. Aftab, S. Roostaee, S. M. S. Hussain, et al., “Performance evaluation
Elect. Power Syst. Res., vol. 78, no. 4, pp. 713–720, Apr. 2008. of IEC 61850 GOOSE-based inter-substation communication for acceler-
12 VOLUME 4, 2016
This work is licensed under a Creative Commons Attribution 4.0 License. For more information, see https://creativecommons.org/licenses/by/4.0/.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI
10.1109/ACCESS.2019.2952934, IEEE Access
B. Polajžer et al.: Protection of MV Closed-Loop Distribution Networks with Bi-Directional Overcurrent Relays and GOOSE ...
ated distance protection scheme,” IET Gener., Transm., Distrib., vol. 12, MATEJ PINTARIČ received his M.Eng. degree in
no. 18, pp. 4089–4098, Oct. 2018. electrical engineering from the Faculty of Electri-
[27] A. Leal, and J. F. Botero, “Defining a reliable network topology in cal Engineering and Computer Science, University
software-defined power substations,” IEEE Access, vol. 7, pp. 14323– of Maribor, Maribor, Slovenia, in 2016. Since
14339, Feb. 2019. 2016 he has been an Assistant of Electrical En-
[28] S. M. Farooq, S. M. S. Hussain, and T. S. Ustun, “Performance evaluation gineering at the University of Maribor, Faculty of
and analysis of IEC 62351-6 probabilistic signature scheme for securing Electrical Engineering and Computer Science. His
GOOSE messages,” IEEE Access, vol. 7, pp. 32343–32351, Mar. 2019.
research interests include smart grids and energy
[29] J. Brest, S. Greiner, B. Bošković, et al., “Self-adapting control parameters
management.
in differential evolution: A comparative study on numerical benchmark
problems,” IEEE Trans. Evol. Computat., vol. 10, no. 6, pp. 646–657, Dec.
2006.
[30] K. Price, R. M. Storn, and J. A. Lampinen, “Differential evolution: A
practical approach to global optimization,” Berlin Heidelberg, Germany,
Springer-Verlag, 2005.
[31] M. Ojaghi, and R. Ghahremani, “Piece-wise linear characteristic for coor- MIRAN ROŠER graduated in 2004 from the
dinating numerical overcurrent relays,” IEEE Trans. Power Del., vol. 32, Department of FERI Technical Faculty of the
no. 1, pp. 145–151, Feb. 2017. University of Maribor. In 2014 he received his
[32] Measuring Relays and Protection Equipement-Part 151: Functional Re- Ph.D. from the Faculty of Electrical Engineering,
quirements for Over/Under Current Protection, Standard IEC 60255-151, Computer Science and Informatics in Maribor. He
2009. is employed by the company Elektro Celje, d. d.,
[33] Inverse-Time Characteristics Equations for Overcurrent Relays, IEEE where he deals with measurements and relay pro-
Standard C37.112-2018, 2018. tection systems as well as methods for managing
[34] Guide for Protective Relay Applications to Distribution Lines, IEEE
and analyzing the operation and development of
C37.230-2007, 2007.
the distribution network. He also deals with the
[35] V. C. Nikolaidis, E. Papanikolaou, and A. S. Safigianni, “A
communication-assisted overcurrent protection scheme for radial implementation of modern solutions within the framework of smart-grid
distribution systems with distributed generation,” IEEE Trans. Smart Grid, projects.
vol. 7, no. 1, pp. 114–123, Jan. 2016.
[36] ADVC Controller Range Operations Manual, R29, Schneider Electric,
Brisbane, QLD, Australia, 2018.
VOLUME 4, 2016 13
This work is licensed under a Creative Commons Attribution 4.0 License. For more information, see https://creativecommons.org/licenses/by/4.0/.