Process Validation Update: Jerry Holatko Pharmeng Technology Inc
Process Validation Update: Jerry Holatko Pharmeng Technology Inc
Jerry Holatko
PharmEng Technology Inc.
October 6, 2006
1
Regulatory Requirements
• Canada – Food and Drugs Act
2
Regulatory Authorities
have duty to ensure products are safe and effective
3
Manufacturer’s Responsibility
4
US Requirements
• The FDA defines process validation as follows:
Process validation is establishing documented
evidence which provides a high degree of
assurance that a specific process will
consistently produce a product meeting its pre-
determined specifications and quality
characteristics.
5
Canadian Requirements
• Health Canada defines Validation as:
The action taken to demonstrate, and to
provide documented evidence that a process
will, with a high degree of assurance,
consistently achieve the desired and intended
results.
6
VALIDATION OBJECTIVES
7
Canadian Guidance on Responsibilities for
Cdn. fabricators, packagers/labellers or
testors
8
Master Plan
The purpose of a Master Plan is:
9
Master Validation Plan Contents
• Responsibilities of various departments
• Recognized validation approaches
• Conditions for using approach
• Compliance requirements for worst case and
reproducibility
• Revalidation criteria
• Documentation format requirements
• Review and approval requirements
• Change control system
10
MASTER PLAN FOCUS
• cGMP PROGRAMS
• OPERATIONS PROGRAM
• RESOURCE REQUIREMENTS
• SCHEDULE
11
Life Cycle
• The life cycle concept of validation is a recurring
theme throughout a Master Plan. Paramount is the
establishment of the infrastructure to ensure that a
facility will be supported by sufficient documentation
throughout its conceptual and functional lifetime.
13
Validation Program
Validation Program is a second level validation document. It is
a detailed document and outlines the following as examples;
· Definitions
· Format for validation protocols and reports
· Protocols review and approval
· Protocol number assignment
· Procedures for initiation, execution and reporting validation
activities
· Protocol Change Control
14
Validation Program (cont’d)
Impact Assessment on product quality
• System/Process Changes and its Impact
Assessment on the validation status and the
quality/efficacy of the product
• Methodology of handling non-conformance
• Revalidation
• Retention time, location and archiving of
validation record and reports
15
Validation Program (cont’d)
• There can be more than one program (i.e
Cleaning Validation Program, Computer
Validation Program.....etc.).
16
Components of Validation
• Facility Qualification
• Equipment Qualification
• Processing Equipment
• Utility Systems
• Testing Equipment
• Cleaning Validation
• Process Validation
• Computer Validation
• Methods Validation
• Revalidation
17
Validation SOP’s
• A detailed step-by-step procedure required to
be followed to accomplish a task (i.e. SOP for
sampling, testing...etc)
18
Establishing Methodology for Impact
Assessment and Validation Rational
19
Establishing Methodology for Impact
Assessment and Validation Rational
(cont’d)
20
Key elements for successful
validation activities
• Timely planning and scheduling
• Impact assessment
• Validation/Qualification rational
• Good Documentation Practice
• Active participation of QA
• End-user participation and ownership
• Pre-determined acceptance criteria
• Additional checks, tests and verifications
• Methodology for handling non-conformance and changes
21
FACILITY CERTIFICATION
(OVERALL SCHEDULE)
• MASTER PLAN PREPARATION
• PROTOCOL PREPARATION & APPROVAL
• DQ/IQ/OQ
• REGULATORY LIAISON
• CERTIFICATION
• FACILITY TURNOVER
22
Facility/Equipment/Utility
Qualification
• Design Qualification (Review)
The following are some critical items to be considered for
successful Design Qualification
• Compliance with cGMP and all regulatory requirements
• Satisfy User/Functional Requirements Specification
(URS/FRS)
• Facility design layout, construction, air flow, differential
pressure, process flow and personnel flow to minimize
cross contamination
23
Facility/Equipment/Utility
Qualification (cont’d)
• Material of construction and cleaning
• Capacity and Efficiency
• Accessibility for maintenance and cleaning
• Commissioning, start-up and shut-down
process
• Safety and environmental requirements and
regulations
• Supporting documentations
24
Factory Acceptance Testing (FAT)
25
Site Acceptance Test (SAT) and
Commissioning
When appropriate, the equipment shall be
tested/challenged on site prior to qualification by the user
to simulate actual production conditions. SAT allows
troubleshooting prior to qualification and provides
confidence that the system will meet the FRS and URS.
26
Installation Qualification
29
GENERAL PRINCIPLES
• VALIDATION STUDIES ARE CONDUCTED AS PER
WRITTEN PROTOCOL
30
GENERAL PRINCIPLES (Cont)
• ALL CRITICAL SYSTEMS, EQUIPMENT AND
PROCESSES REQUIRE VALIDATION
“CRITICAL” – HAVING A POTENTIAL TO
IMPACT PRODUCT CONFORMANCE TO
QUALITY SPECIFICATIONS
31
MAINTAINING VALIDATED STATE
OF THE SYSTEM
• CALIBRATION
– CRITICAL INSTRUMENTS ARE CALIBRATED AS PER
DETERMINED SCHEDULE
• TRAINING
– TRAINING PROGRAM IS IN PLACE
– TRAINING IS DOCUMENTED
• PM AND CHANGE CONTROL
– NO EQUIPMENT MODIFICATION WITHOUT CHANGE
CONTROL
32
Validation Schedule
• Establish target dates
33
THANK YOU !
Jerry Holatko
[email protected]
34