Project Control Process Unit 5
Project Control Process Unit 5
189
Notes
relating to duration is derived from the work breakdown structure (WBS)
database; and time-sequence data are derived from the network and resource
scheduling decisions. The WBS defines the work in discrete work packages
that are tied to deliverables and organization units. In addition, each work
package defines the work, duration, and budget. From the WBS, the project
network schedule is used to phase all work, resources, and budgets into a
baseline plan.
190
Notes
Key Programme/Project Monitors, Controls and Reports
d) Stage Plan: Provides detail of how and when the objectives for the
stage are to be met by showing the deliverables, activities and
resources required. The Stage Plan provides a baseline against which
stage progress will be measured and is used as the basis of
management control throughout the stage.
e) Work Package: Sets out all information needed to deliver one or
more specialist products. The necessary information is collated by
the Project Manager and used to formally pass responsibility for
work or delivery to a team leader or member.
f) Change Control Strategy: The Strategy documents the procedure to
ensure that the processing of all Project Issues is controlled,
including the submission, analysis and decision making.
191
Notes
g) Highlight Reports: The highlight reports are used to provide the
Project Board (and possibly other stakeholders) with a summary of
the stage status at intervals defined by them and to monitor stage and
project progress. The Project Manager also uses it to advise the
Project Board of any potential problems or areas where the Project
Board could help.
i) Project Issue Log: A project issue is a generic term for any mat-ter
that has to be brought to the attention of the Project Team and
requires an answer. An issue can have a negative or positive impact
on the project and includes items such as requests for change, off-
specifications (this is an item not included in the original specifica-
tion or errors or omissions found in work already completed which
would result in the agreed specification or acceptance criteria not
being met), questions and statements of concern.
l) End Project Report: A report sent from the Project Manager to the
Project Board, which confirms the hand-over of all deliverables,
provides an updated business case, and an assessment of how well
the project has done against its Project Initiation Document.
192
Notes
approved by the Project Board then held centrally for the benefit of
future projects. If the project is one of a number attached to a
programme this document will also be used as input to the
programme review.
Gantt Charts
Gantt and control charts serve well as a means for tracking and
trending schedule performance. Their easy-to-understand visual formats
make them favorite tools for communicating project schedule status-
especially to top management who do not usually have time for details.
Adding actual and revised time estimates to the Gantt chart gives a quick
overview of project status on the report date. The following figure shows
the sample of multi-color Gantt chart.
Control Charts
193
Notes