Inspection and Maintenance Report
Inspection and Maintenance Report
Inspection and Maintenance Report
Failure Cause ▪ Full inspection of the Engine by opening it, the oil nozzle failure - the injection nozzles
(corroded), so that Incorrect quantity of injected fuel to increase the combustion, therefore
the heating rises up.
▪ hence, the liner sleeve stuck and damage the cylinder.
▪ Replace the engine with the new one, at 20 Feb.21.
▪ Running the DEG No.3 for 30 minutes without load at 11:30 Pm 20/02/2021.
Final Performance The test run found the DEG no.3 in good performance and can back to the operation and supply
the power.
Evidences:
Internal inspection for the Engine of DEG No.3 Oil Jet broke of DEG No.3
Internal inspection for the Engine of DEG No.5 liner sleeves stuck
The new engine of DEG No.5 The new engine of DEG No.5 (Temp. record)
The new engine of DEG No.3 The new engine of DEG No.3 ((Temp. record))