NO Informations/Issues Witon (Bogor) Remarks A List of Documents & Drawing From Customer

The document contains a list of questions about a factory site in Bogor, Indonesia that is being considered for a solar PV installation. It requests information in four key areas: documents and drawings of the electrical systems and roof structure, details about the roof and any issues, operation of the factory and any power quality concerns, and an overview of the factory site and available space. The questions aim to gather technical specifications and assess the suitability and any constraints of installing a solar PV system on the factory rooftop.

Uploaded by

indrasyifai
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
57 views

NO Informations/Issues Witon (Bogor) Remarks A List of Documents & Drawing From Customer

The document contains a list of questions about a factory site in Bogor, Indonesia that is being considered for a solar PV installation. It requests information in four key areas: documents and drawings of the electrical systems and roof structure, details about the roof and any issues, operation of the factory and any power quality concerns, and an overview of the factory site and available space. The questions aim to gather technical specifications and assess the suitability and any constraints of installing a solar PV system on the factory rooftop.

Uploaded by

indrasyifai
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

WITON (BOGOR)

NO INFORMATIONS/ISSUES
REMARKS
A List of Documents & Drawing from Customer
1 Plant/ Factory Layout - General Arrangement (GA) Drawing
Electrical Single Line Diagram (SLD); verify all electrical ratings, capacities
2
and spare circuit breakers/locations

Electrical Layout of the Facility (including cable route/layout and


3 electrical switchgear layout); location of switchgear and electrical
connection points must be checked during site visit.
4 Roof Structure & Roof Layout and Elevation Drawing including roof
specification and dimension (see Sheet roof dimension)
5 Load profile/energy consumption per month within one year, or PLN
billing if the Customer is willing to share

B Roof Overview
6 Height of Building from ground (m)
7 Number of available roofs/buildings
8 Roof material type
9 Roof thickness (mm)
10 Tilt angle of roof (deg)
11 Size of roof in each building factory (m2)
12 Is there any area of the roof that is subject to dust/soiling because of
close proximity to a stack emitting blakish smoke?
13 Is there any skylight on the roof area? How much is the size of the
skylight on the roof area?
Are there any hot spots indicated or detected on the roof area of the
14 factory? What equipment or other items that are causing the hot spots
(boiler,stack,etc.)?
15 Is there any roof maintenance schedule?
Perform a visual inspection of the topside and underside of the roof area.
16 What is the general condition of the roof? Are there any observed issues
with the roof structure?

C Operation of Factory
17 Are there any seasonal/weekly/daily variations of load consumptions?
18 Is there any sudden load consumption during starting/ramping up of any
equipment that may impact the frequency/voltage fluctuation?
19 Is there any critical equipment in the factory that has a large electricity
consumptions and must be carefully managed?
Are there any power quality issues (power factor, reactive power,
20 harmonic issue, etc) tahat should or must be maintained by the existing
power supply (PLN/own genset) and future power supply (from PV)?
21 How often do you experience black outs? (Are there cases that have
brown outs on specific parts of the factory)
22 What is the duration of those blackoouts? (or brown outs)
23 What is the annual shutdown and maintenance schedule of the factory?

D Factory Site Overview


24 Is there any available are for laydown and storage during construction
and testing? (Secure laydown and storage)
25 Is there any available water source for PV Cleaning purposes?
26 Are there any environmental characteristic that may affect performance
of the PV plant (dust, trees, etc.)?
Are there any high buildings or structures surrounding or near factory
27 that will cause shading on the rooftop and which may impact PV panel
yield?
28 Availability of area/space for inverter? (Confined/Covered Place)
29 Availability of space cubicles in electrical distribution panels?
30 Availability area for adding additional electrical cubicles?
31 Availability area for adding transformer? (Outdoor or indoor)
32 Availability and structural integrity of roof access and deliveries?
(Security of the facility)
33 Availability of a passenger or freight elevator? (Or crane access if the
facility is not supportive)

34 Any special requirements that the contractor needs to know about


(installation requirements, operating hours, prohibition of activities, etc)