0% found this document useful (0 votes)
87 views2 pages

EOT 02 Status

This document provides a status update on EOT-02 and outlines the procedure for EOT-03. It notes that the original EOT-02 submission included duration for the Sheratala proposed tunnel but this was revised per the employer's direction to exclude that duration. The engineer determined EOT-02 to extend to September 26, 2021. Continuing delay events will be claimed in the upcoming EOT-03 submission, including late drawings, suspensions, land issues, and the Sheratala tunnel timeline if approved.

Uploaded by

taimur ahmad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
87 views2 pages

EOT 02 Status

This document provides a status update on EOT-02 and outlines the procedure for EOT-03. It notes that the original EOT-02 submission included duration for the Sheratala proposed tunnel but this was revised per the employer's direction to exclude that duration. The engineer determined EOT-02 to extend to September 26, 2021. Continuing delay events will be claimed in the upcoming EOT-03 submission, including late drawings, suspensions, land issues, and the Sheratala tunnel timeline if approved.

Uploaded by

taimur ahmad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

EOT-02 Status

Sr No Item Cut-off date Duration Completed date


1 EOT-02 1st submission 15-Aug-19 1712 days 22-Apr-24

2 EOT-02 2nd Submission 15-Aug-19 1070 days 20-Jul-22

3 15-Aug-19 780 3-Oct-21

EOT-02 3rd Submissio


Engineer's determination

4 15-Aug-19 773 26-Sep-21


EOT-02 3rd Submissio
Procedure for EOT-03

5 EOT-03
EOT-02 Status
Remarks
in this submission, Contractor JV included the duration of Sheratala proposed tunnel
due to which 1712 days were claimed

A revised submission has been made as per directions by the Employer, Engineer in
which they have directed us to exclude Proposed tunnel duration & directed to
include in EOT-03

A meeting was held in Feb-20 in which Contractor's submission was thoroughly


discussed & it was finalized that only the delaying events which have been finished
would be compensated it this claim. Continuing delaying events (like additional
quantum, varied works) would be cliamed in EOT-03
Engineer's determination

the Engineer determined the EOT-02 till 26 Sep 2021 with cut-off date of 15-Aug-19.
Procedure for EOT-03

After approval of EOT-02 by the WAPDA, EOT-03 would be prepared and claimed.
Continuing delaying events would be claimed in EOT-03 Like:
1) Late issuance of PH-IV foundation IFC drawings.
2) Partial suspension
3) late finalization of Outlet Portal location
4) land issues
5) Timeline of STC proposed tunnel, if VO approved by WAPDA. etc

You might also like